AC 150/5360-13A Airport Terminal Planning
This AC provides information on the process of planning airport passenger terminal facilities. It combines and supersedes two previous FAA ACs on this topic: AC 150-5360-13, Planning and Design Guidelines for Airport Terminal Facilities, and AC 150/5360-9, Planning and Design Guidelines for Airport Terminal Facilities at Non-hub Locations. This AC does not create new requirements for airport terminal planning. Rather, it consolidates information from two separate ACs and includes updated information on terminal planning.
U.S. Department of Transportation Federal Aviation Administration
Advisory Circular
Subject: Airport Terminal Planning Date: 7/13/18 Initiated By: APP-400
AC No: 150/5360-13A
1 Purpose. This advisory circular (AC) provides updated guidance on the process of planning airport passenger terminal facilities. This update reflects changes that have occurred in the aviation industry and to planning practices for airport passenger terminal facilities since the Federal Aviation Administration (FAA) published AC 150/5360-13, Planning and Design Guidelines for Airport Terminal Facilities, and AC 150/5360-9, Planning and Design Guidelines for Airport Terminal Facilities at Non-hub Locations.
2 Distribution. This AC is available on the FAA Office of Airports website.
3 Cancellation. This AC cancels:
AC 150/5360-13, Planning and Design Guidelines for Airport Terminal Facilities, dated April 22, 1988; and
AC 150/5360-9, Planning and Design Guidelines for Airport Terminal Facilities at Non-hub Locations, dated April 4, 1980.
4 Application. This AC is a reference document and starting point for anyone planning airport passenger terminal facilities, during or after the master planning process. For more detailed information, there are references to relevant ACs, FAA orders, and industry guidance. For information on Airport Improvement Program (AIP) or Passenger Facility Charge (PFC) eligibility and justification, refer to FAA Order 5100.38, Airport Improvement Program Handbook, and FAA Order 5500.1, Passenger Facility Charge Handbook.
ii
5 Principal Changes. This AC:
1. Combines ACs 150/5360-13 and AC 150/5360-9. 2. Changes the title of the AC from Planning and Design Guidelines for Airport Terminal Facilities to Airport Terminal Planning. 3. Adds initial planning considerations before and during the terminal planning process. 4. Articulates a basic terminal planning process and key considerations for each step. 5. Provides a responsibilities matrix to clarify and streamline key coordination points between the airport owner/operator, airport consultant, and FAA. 6. Incorporates information on integrating sustainability into the planning process, and a chapter on the fundamentals of sustainability in terminal planning and design. 7. Includes references to relevant ACs, FAA orders, and other industry guidance and resources on terminal planning. 8. Incorporates requirements to provide Service Animal Relief Areas (SARA) in airport passenger terminals (Per 49 CFR § 27.71(h) and AC 5360-14, Access to Airports by Individuals with Disabilities.
6 Feedback on this AC. If you have suggestions for improving this AC, please use the Advisory Circular Feedback form at the end of the document.
Elliott Black Director, Office of Airport Planning and Programming
iii
CONTENTS Item Page
CHAPTER 1. USE OF THE ADVISORY CIRCULAR … 1-1
1.1 Intended Audience … 1-1 1.2 Organization and Use of this Advisory Circular (AC) … 1-1 1.3 Use of this Advisory Circular and Financial Assistance … 1-2 1.4 FAA Role in Passenger Terminal Planning … 1-2 1.5 Use of Other Industry Publications … 1-2
CHAPTER 2. INITIAL PLANNING CONSIDERATIONS … 2-1
2.1 General … 2-1 2.2 Situation Assessment and Strategic Planning … 2-1 2.3 Establishing Goals and Objectives … 2-2 2.4 Airport Master Plans … 2-2 2.5 Other Factors for Initial Consideration … 2-3 2.6 Terminal Planning Study Design … 2-4
CHAPTER 3. TERMINAL PLANNING PROCESS … 3-1
3.1 General … 3-1 3.2 Typical Terminal Planning Process … 3-1 3.3 Documentation … 3-10
CHAPTER 4. PLANNING METHODOLOGIES AND TOOLS … 4-1
4.1 General … 4-1 4.2 Demand Characteristics … 4-1 4.3 Analytical Tools … 4-4
CHAPTER 5. TERMINAL BUILDING SPACE PROGRAMMING … 5-1
5.1 General … 5-1 5.2 Level of Service … 5-1 5.3 Gross Terminal Area Estimates … 5-1 5.4 Terminal Building Space Allocation … 5-2 5.5 Trends and Innovations … 5-15
CHAPTER 6. FUNCTIONAL RELATIONSHIPS AND TERMINAL CONFIGURATION … 6-1
6.1 General … 6-1 6.2 Origin and Destination Versus Hub/Connecting Airport Terminals … 6-1 6.3 Terminal Components and Functional Relationships … 6-1 6.4 Terminal Siting Considerations … 6-5 6.5 Terminal Configurations … 6-9
CHAPTER 7. TERMINAL APRON AREAS … 7-1
7.1 General … 7-1 7.2 Aircraft Parking Gates … 7-2 7.3 Aircraft Parking Gate Requirements … 7-3
iv
7.4 Taxilanes and Aprons … 7-7 7.5 Apron Lighting … 7-8
CHAPTER 8. AIRPORT GROUND ACCESS AND CIRCULATION … 8-1
8.1 General … 8-1 8.2 Planning Studies … 8-1 8.3 Key Roadway and Parking Components … 8-1 8.4 Roadways … 8-3 8.5 Terminal Curbside … 8-5 8.6 Parking Facilities … 8-7 8.7 Public Transit and Automated People Movers … 8-9 8.8 Landside Signage and Wayfinding … 8-11
CHAPTER 9. SUSTAINABILITY IN TERMINAL PLANNING … 9-1
9.1 General … 9-1 9.2 Airport Sustainability Practice … 9-1 9.3 Airport Sustainability Planning … 9-4 9.4 Sustainability in Terminal Development … 9-5 9.5 Other Sustainability Considerations … 9-12
APPENDIX A. LIST OF ACRONYMS … A-1
APPENDIX B. RESPONSIBILITIES MATRIX … B-1
APPENDIX C. REFERENCE MATERIALS … C-1
1.2 Organization and Use of this Advisory Circular (AC). › 1.2.3 It should be noted that this document combines AC 150/5360-13,…
CHAPTER 1. USE OF THE ADVISORY CIRCULAR
1.1 Intended Audience. This document provides guidance for anyone initiating the planning and design of an airport passenger terminal facility, including (but not limited to) the following:
Airport operators
Airport leadership
Airport planning staff
Airport engineering staff
Airline representatives
FAA personnel
Public stakeholders
Consultants
Airport planners
Terminal planners
Architects
Engineers
1.2 Organization and Use of this Advisory Circular (AC).
1.2.1 The nine chapters in this AC are presented in 3 main parts: 1. Initial Planning Considerations (Chapter 2) – Identifies key topics to consider before any terminal planning project. 2. Terminal Planning Process (Chapter 3) – Articulates an approach to the planning process with an emphasis on flexibility. 3. Terminal Planning Methodologies and Tools (Chapters 4 through 9) a. Covers the three main functional elements of the terminal area (terminal building,
terminal apron, terminal landside). b. Provides considerations, applicable reference documents, and tools for each element. c. Discusses sustainability in terminal planning and design.
1.2.2 Using the terminal planning process presented in the following chapters, this AC gives the user a basic explanation of each key subject and functional area, then refers the user to more detailed resources.
1.2.3 It should be noted that this document combines AC 150/5360-13, Planning and Design Guidelines for Airport Terminal Facilities, and AC 150/5360-9, Planning and Design Guidelines for Airport Terminal Facilities at Non-hub Locations. The planning processes for hub and nonhub terminal facilities planning were found to be generally comparable and not warranting two separate discussions.
1.5 Use of Other Industry Publications. › 1.5.2 Please note that the FAA has included external reference…
1.3 Use of this Advisory Circular and Financial Assistance. This AC provides general guidance to assist end users with the process of planning terminal facilities. The material in this AC is independent from guidance on Airport Improvement Program (AIP) or Passenger Facility Charge (PFC) eligibility and justification. Use of this AC does not establish or ensure project eligibility or justification for AIP or PFC funding. For information on AIP or PFC eligibility and justification, refer to FAA Order 5100.38, Airport Improvement Program Handbook (Appendix N) and FAA Order 5500.1, Passenger Facility Charge Handbook.
1.4 FAA Role in Passenger Terminal Planning.
1.4.1 For airports in the National Plan of Integrated Airport Systems (NPIAS), early coordination with their local FAA Office of Airports Regional or Airports District Office is essential to facilitate review and coordination of proposed airport development (particularly if seeking financial assistance). In all cases, the FAA is involved to ensure that proposed airport development is safe, efficient, and sustainable, is reasonable, meets airport design standards, and follows environmental policy.
1.4.2 A responsibilities matrix is included in Appendix B to assist end users with the process of planning terminal facilities. The matrix identifies when FAA coordination and approval are required. For additional information, please coordinate with FAA Office of Airports Regional or Airports District Office staff.
1.5 Use of Other Industry Publications.
1.5.1 The focus of this AC is the process of planning airport passenger terminal facilities. It is also intended to be a starting point and reference document. There are other publications that provide greater detail on the quantitative elements of terminal planning and design for each respective discipline encountered within the terminal area. To avoid duplicative guidance and recognize the natural evolution of terminal planning practices, this AC provides references to other relevant resources. They can be found in the following sections and are summarized in Appendix C, Reference Materials.
1.5.2 Please note that the FAA has included external reference materials that are widely used in the airport industry. Some of these documents are proprietary and may require a subscription or payment to access. The FAA is only including these documents because they are commonly used references for terminal planning. The FAA is not endorsing any of these materials.
2.2 Situation Assessment and Strategic Planning. › 2.2.2 Documentation and communication of the outcomes of the situation…
CHAPTER 2. INITIAL PLANNING CONSIDERATIONS
2.1 General. This chapter discusses key considerations before and during the formal terminal planning process. Particular emphasis should be placed on this early stage of the planning process because its outcome will form the scope of work for the project, and the foundation for the rest of the terminal planning process.
2.2 Situation Assessment and Strategic Planning.
2.2.1 Before beginning the terminal planning process, airport operators should conduct a situation assessment to identify problems at the existing terminal facility (if applicable) and decide which problems the terminal project will address. A situation assessment can include answering the following questions:
What problem(s) needs to be solved in the existing terminal facility?
Has the existing terminal infrastructure (or components thereof) reached the end of its useful life?
Does the overall terminal complex (or any of its individual components) no longer meet current or evolving operational needs of the airport?
o Does it require renovation, expansion, or replacement?
o Is the terminal complex (or any of its components) simply too small or large to accommodate current or projected demand?
o Are there changes or expected changes in the operational fleet, or to airline tenants?
o Does the terminal need modernization or aesthetic improvements to meet changing user and community expectations?
What sustainability initiatives, practices, or measures are required to ensure the new, modernized or renovated terminal is sustainable?
What specific passenger or tenant complaints about the facility need to be addressed?
Are there multiple problems representing a combination of the above?
Has the terminal facility (or any of its components) suffered significant damage or closed due to storms, electrical outages, flooding, or other external factors?
Have previous planning studies (e.g. an Airport Master Plan or related planning study) explored the questions above or identified terminal related projects?
Are any environmental impacts anticipated as part of the project?
2.2.2 Documentation and communication of the outcomes of the situation assessment are important parts of the planning process. The documented outcome of this step will define the goals and objectives, and establish consensus among stakeholders and others who will play an integral role in the planning process.
2.4 Airport Master Plans. › 2.4.3 Airport master plans usually contain basic information useful to…
2.3 Establishing Goals and Objectives.
2.3.1 Once the situation assessment is completed, it is important to have a clear understanding of the goals and objectives of the terminal planning project in order to address the appropriate problems and issues. This should occur at the onset of the planning process. The goals and objectives should define the purpose of the terminal project and be prioritized to align with:
The airport operator’s overall vision and mission for the terminal facility and airport enterprise;
The airport operator’s funding capabilities;
The motivations and needs of primary stakeholders, such as governmental leadership, tenant(s), and users of the facility, and;
Airport sustainability practices.
2.3.2 Planners and designers should clearly state this vision in a written set of goals and objectives. Stating goals and objectives also provides an early coordination opportunity for stakeholders and others to agree that the project is needed, and provides a benchmark for evaluating alternatives. Evaluation criteria for the project should relate to, or draw from, the established goals and objectives.
2.3.3 Planners and designers, in coordination with environmental and other professionals, should ensure that the goals and objectives are stated in a manner that supports subsequent phases of the approval process. For example, projects being analyzed in accordance with the National Environmental Policy Act (NEPA) require a supportable “purpose and need statement.” This statement articulates what a proponent hopes to achieve and why the project is necessary. NEPA analyses also require criteria that will be used to screen out alternatives that do not achieve the project’s purpose and need. For additional information on NEPA purpose and need statements and alternatives analysis, see FAA Order 5050.4, National Environmental Policy Act (NEPA) Implementing Instructions for Airport Actions.
2.4 Airport Master Plans.
2.4.1 Airport master plans are studies that document and support the long-term development and use of an airport’s land and facilities. Master plans provide the framework for future airport development that will sustainably satisfy aviation demand in a cost-effective manner, and balance capacity of airport functions while considering potential safety, environmental, and socioeconomic impacts. AC 150/5070-6, Airport Master Plans, provides comprehensive guidance on this topic.
2.4.2 In general, an airport master plan should establish the context for more detailed terminal planning. In most cases, the terminal planning process should align with the broader framework and guidelines of the airport master plan.
2.4.3 Airport master plans usually contain basic information useful to the terminal planning process. This includes an inventory of existing airport facilities, aviation activity forecasts, capacity analyses, estimates of facility requirements, sustainability initiatives, environmental
2.5.3 Financial Considerations. › 2.5.3.1 Airports must address a number of financial considerations…
considerations, an airport layout plan set, and information on land use, terminal area, and intermodal surface access.
2.4.4 The terminal facility analysis contained in an airport master plan is usually limited to layouts and drawings delineating general location, overall area, and basic configuration of the terminal area development envelope. However, some airport operators develop master plans with a strong emphasis on terminal planning and may provide more detailed documentation on this subject.
2.5 Other Factors for Initial Consideration. Following are additional factors that contribute to a successful airport passenger terminal planning process.
2.5.1 Project Team. In the initial phase of the planning process, an airport should assemble a project team that will function for the duration of the planning process. This team typically includes the lead person for the planning effort for both the airport and the planning consultant team, and their key team members. The airport may or may not include stakeholders outside of airport staff on the project team. However, FAA encourages stakeholder involvement early in the planning process. Examples of key stakeholders include airlines, airport tenants, the consultant team, FAA (e.g., the Office of Airports and Air Traffic), other federal agencies such as the Transportation Security Administration (TSA), Department of Homeland Security (DHS), and Customs and Border Protection (CBP), other regulatory stakeholders, local government, local business groups, and community planning groups.
2.5.2 Consultant Selection. Airport operators typically hire a consultant to assist with passenger terminal planning studies. As a general rule, consultants provide subject matter expertise and additional labor to complete tasks within a given schedule. For information on the selection and engagement of architectural, engineering, and planning consultants, see AC 150/5100-14, Architectural, Engineering and Planning Consultant Services for Airport Grant Projects. Another useful reference is the Airport Consultants Council Contracting Toolkit.
2.5.3 Financial Considerations.
2.5.3.1 Airports must address a number of financial considerations early in the planning process. For example, airport operators should have a realistic sense of their funding capacity, as this is a key to determining what is affordable or feasible. The airport should give early consideration to overall capital costs and potential funding sources; annual debt service (if any portion of the funding is to come from bond proceeds); resulting operating and maintenance costs; forecast activity levels in terms of passengers and operations; ability to generate non-aeronautical revenue; cost recovery options; and facility management plans (including the plan for airline rates and charges). All of these factors should be considered when evaluating the financial feasibility of each option under consideration.
CHAPTER 2. Initial Planning Considerations › 2.6 Terminal Planning Study Design.
2.5.3.2 As stated earlier, neither this AC nor the use of this AC establishes project eligibility or justification for AIP or PFC funding. For information on AIP project eligibility and justification, please refer to FAA Order 5100.38, Airport Improvement Program Handbook. For information on the PFC program, please refer to the FAA Order 5500.1, Passenger Facility Charge Handbook.
2.5.4 Environmental Considerations. Early in the terminal planning process, airports should understand the level of environmental review that will be required for the project and potential projects emerging from the study. Underestimating the level of review (or assuming that no review is required) can have significant impacts on the trajectory of a project. Planners and environmental specialists should attempt to identify key environmental issues for the proposed project to ensure the planning project scope and budget provide enough resources to analyze them, there is enough analysis and documentation for any environmental review, and the overall schedule accounts for the time required to complete this review. For comprehensive information on NEPA requirements, see FAA Order 5050.4, National Environmental Policy Act (NEPA) Implementing Instructions for Airport Actions. For additional perspective on environmental considerations in the comparable context of master planning, see the Environmental Considerations chapter in AC 150/5070-6, Airport Master Plans. For airports in the NPIAS, operators should also coordinate with their local FAA Regional or Airports District Office for information on environmental review requirements.
2.6 Terminal Planning Study Design. A key output of these initial efforts should be a scope of work that is tailored to the project. The scope of work will articulate the types of analyses and level of effort needed to address key issues. For airports in the NPIAS, airport operators should coordinate with their local FAA Regional or Airports District Office to discuss the project, timeframe, basis for the project, key assumptions (e.g. the forecast of aviation activity used to define facility requirements), level of effort, NEPA considerations, and ultimately, to tailor the scope of the effort. The airport operator should develop a scope of work that is appropriate for the circumstances, and will achieve the identified goals and objectives.
3.2.2 Stakeholder Involvement. › 3.2.2.1 The process of planning an airport passenger terminal requires…
CHAPTER 3. TERMINAL PLANNING PROCESS
3.1 General. This chapter describes a typical terminal planning process with an emphasis on flexibility and adaptation. This approach commences following the completion of steps identified in Chapter 2 and the development of a scope of work. The output of this planning process is typically a report that documents each step in the process, and the final recommendations on the terminal project.
3.2 Typical Terminal Planning Process. Figure 3-1 depicts a typical terminal planning process. The following sections describe each step in this process diagram, and key considerations.
Figure 3-1 Conceptual Terminal Planning Process
3.2.1 Initial Planning Considerations. As discussed in Chapter 2 and depicted in Figure 3-1, an airport operator should complete a number of initial steps before formally initiating the terminal planning process. These steps include assessing the situation and identifying problems to be resolved, establishing goals and objectives, forming the project team, and developing a scope of work.
3.2.2 Stakeholder Involvement.
3.2.2.1 The process of planning an airport passenger terminal requires considerable coordination and input from a number of airport users, and other interested parties. Participants in such a process may include, but are not limited to:
Airport management and staff from key departments (landside/airside operations, finance, commercial development, airport fire department/local fire department/airport emergency response staff, airport police, etc.), as well as other airport departments and offices (environment/sustainability, etc.), which can provide valuable perspective and project support.
3.2.3 Existing Conditions. › 3.2.3.3 Additionally, the airport owner/operator or consultant should…
Tenant airlines, concessionaires, and other service providers and tenants.
The terminal planning consultant, and other consultants indirectly involved or working on other aspects of the facility.
FAA.
Other federal agencies such as the TSA, DHS, and CBP.
Relevant local governmental agencies, municipal planning offices, transportation departments, local business groups, community planning groups, etc.
3.2.2.2 Stakeholder involvement runs parallel to the planning process presented in this chapter. Airport operators should engage stakeholders - or the project advisory committee if an airport chooses to form one - to review terminal planning information and provide input at key project milestones. Airport operators should also engage the general public as part of the planning process. For specific information on public participation, see AC 150/5050-4, Citizen Participation in Airport Planning.
3.2.3 Existing Conditions.
3.2.3.1 A foundational step in the planning process is the documentation of existing conditions (also called an inventory). “Existing conditions” refers to the physical characteristics of the facility by functional element, as well as non-physical elements like operational activity and the current critical aircraft. For information and guidance on critical aircraft, see AC 150/5000-17, Critical Aircraft and Regular Use Determination.
3.2.3.2 The airport owner/operator or consultant (if applicable) conducting the study should assemble a base set of plans, documents, and photos to document existing conditions that are relevant to the terminal planning project and key issues identified in the situation assessment. When the project is terminal replacement or enhancement, the airport owner/operator or consultant should evaluate the physical characteristics of the existing facility. This process includes a walkthrough of the facility and reviewing the most recent Airport Layout Plan (ALP), airport master plan, related internal and external planning studies, and all existing conditions documents the airport has on file related to terminal facilities (e.g., electronic drawings of terminal plans, site surveys, utility drawings, and property maps).
3.2.3.3 Additionally, the airport owner/operator or consultant should gather any relevant operational data on functional elements in the terminal complex to document demand levels, processing rates, and any other applicable data. A wide range of data (passenger enplanements, aircraft operations, delay statistics, etc.) are available from the FAA Operations and Performance Data website. Among the available data, the FAA Terminal Area Forecast (TAF) provides aviation data users with historical and forecast statistics on passenger demand and aviation activity at U.S. airports. For the purposes of documenting existing conditions, historical
3.2.5 Facility Requirements. › 3.2.5.2 See Chapter 5, Terminal Building Space Programming, for an…
data are summarized by year for each facility. The TAF databases are available in zipped .dbf format through the “Download Data” links on the TAF website.
3.2.3.4 The airport owner/operator or consultant should document any deficiencies in information and reach consensus with the airport owner/operator on how to address them (e.g., will additional work be necessary to obtain basic data, or can assumptions be made to form the basis of the planning effort). Throughout the planning process, the airport owner/operator or consultant should document all assumptions and their underlying rationales.
3.2.4 Forecasts of Aviation Activity.
3.2.4.1 The forecast of aviation activity is a pivotal step in the terminal planning process. Aviation activity forecasts are estimates of demand expressed in passenger activity levels (enplanements and total passengers) and aircraft operations (including the forecast critical aircraft). Forecasts are completed during the master planning process or as part of a more focused terminal planning study. These projections are used to determine and substantiate the extent and type of development needed to accommodate expected traffic (i.e., facility requirements).
3.2.4.2 If the airport owner/operator is preparing a standalone terminal planning study or Terminal Area Narrative Report, and anticipates seeking federal financial assistance for any portion of terminal construction, the airport owner/operator must present a forecast of aviation activity. The local FAA Regional or Airports District Office must approve the forecast in these instances.
3.2.4.3 The forecast may be developed for the study’s planning period or be from a recent planning effort (i.e., a recent Airport Master Plan) if no significant changes to the forecast or its assumptions have occurred since that effort. For additional information, see the section on forecasts for planning or environmental projects in FAA Order 5100.38, Airport Improvement Program Handbook.
3.2.5 Facility Requirements.
3.2.5.1 Facility requirements translate the output from forecasts of aviation activity into requirements and programmatic input (or sizing) for the functional components of the terminal facility. Facility requirements and other planning recommendations should be linked to activity milestones (or triggers) defined in terms of planning activity levels. The connection to activity levels enables capital improvements to be accelerated or delayed as actual activity dictates. It is critical to view the planning process as dynamic and consider potential changes in the aviation industry (e.g., aircraft fleet mix, technology, airport and airline business models, and passenger needs). Flexibility to adapt to changing aviation industry conditions and the economy is one of the most important considerations in terminal planning efforts.
3.2.5.2 See Chapter 5, Terminal Building Space Programming, for an overview of terminal building space programming and key factors that drive the programming of major
3.2.6.1 Development and Evaluation of Initial Alternatives. › 3.2.6.1.1 The investigation of terminal alternatives should include a…
terminal components. The functional relationships between terminal components are described in Chapter 6, Functional Relationships and Terminal Configuration.
3.2.5.3 At the conclusion of the Forecast and Facility Requirements steps, it is critical for the airport owner/operator to establish consensus about the outcome and resulting recommendations with the project team and advisory committee before proceeding with the development of terminal alternatives.
3.2.6 Terminal Alternatives Development and Evaluation. The following sections describe methods for evaluating and selecting a preferred passenger terminal alternative.
3.2.6.1 Development and Evaluation of Initial Alternatives.
3.2.6.1.1 The investigation of terminal alternatives should include a high-level consideration of different terminal alternatives to accommodate forecast activity levels and resulting facility requirements (see Chapter 6, Functional Relationships and Terminal Configuration). The purpose of this step is to identify the full range of potential options, rather than explore alternatives in detail. For comparison, alternatives should be developed using consistent criteria including, but not limited to, aircraft fleet mix and wingtip spacing, terminal and concourse dimensions to meet gate requirements, relationship to the airfield, roadway network, and other support facilities, and sustainability considerations. Each alternative should be accompanied by a brief summary of the main points of consideration related to it. Alternatives at this stage in the planning process may be developed using criteria which could be revisited later and modified based upon input and discussions with stakeholders. Figure 3-2 shows a variety of common conceptual terminal redevelopment alternatives.
3.2.6.1 Development and Evaluation of Initial Alternatives. › 3.2.6.1.3 The score for each alternative is the sum of all factors…
Figure 3-2 Example of Initial Conceptual Terminal Alternatives
3.2.6.1.2 Airports can use the following three-step process to compare the alternatives,
and reduce the number of possible alternatives to a shortlist of alternatives warranting further refinement and evaluation: 1. Identify Evaluation Criteria. Develop evaluation criteria that represent the essential factors to consider when determining the preferred development alternative(s) for the airport. The criteria and definitions should be carefully tailored to match the goals, objectives, and other parameters established earlier in the project. Initial criteria may include economic viability, airside access, expansion flexibility, walking distances, landside access availability, operational flexibility, site availability, airspace impacts, Airport Traffic Control Tower (ATCT) line-of-sight, environmental issues, constructability, schedule, and order-of-magnitude costs. 2. Establish Weighting (if needed). Weighting factors may be assigned to each evaluation criterion according to relative importance. Airports should develop the weighting with input from stakeholders, and consider priorities in relation to goals and objectives identified earlier in the planning process. 3. Perform a Technical Ranking. Develop a matrix or other framework for ranking the alternatives against each criterion. The ranking should represent majority consensus among stakeholders. One possible ranking scheme utilizes rankings of positive, neutral, or negative for each criterion.
3.2.6.1.3 The score for each alternative is the sum of all factors identified for the criteria listed. This preliminary evaluation process can be repeated with second-tier
criteria in order to reduce a large number of potential alternatives to a more manageable number.
3.2.6.1.4 An evaluation matrix which includes generalized evaluation criteria and definitions used in the preliminary evaluation process is presented in Figure 3-3. In the example provided, positive, neutral, and negative rankings are notionally indicated by +, 0, and - rankings, respectively.
3.2.6.2 Shortlisted Alternatives. › 3.2.6.2.1 Following identification of shortlisted terminal…
Figure 3-3 Example Preliminary Evaluation Matrix
3.2.6.2 Shortlisted Alternatives.
3.2.6.2.1 Following identification of shortlisted terminal alternatives, the conceptual terminal plans should be redrawn at a larger scale (greater level of detail) and depict specific functional areas shown. This will allow for a more detailed evaluation of each alternative. See Figure 3-4 for examples of typical conceptual alternatives. This refinement is prudent because it:
Ensures each alternative conforms to the goals and objectives.
3.2.6.3 Refined Evaluation. › 3.2.6.3.1 For each of the shortlisted terminal alternatives that are…
Closely examines the ability of each alternative to satisfy demand, and the functional and operational requirements of airlines, passengers, tenants, automobiles, and other elements.
Ensures each alternative can be phased without causing significant disruption to airport operations.
Allows for the preparation of order-of-magnitude costs and financial feasibility assessments of each alternative.
3.2.6.2.2 The airport owner/operator or consultant should write brief narrative descriptions of each shortlisted terminal concept (and potential variations).
Figure 3-4 Examples of Prototypical Shortlisted Terminal Alternatives
Note: Conceptual drawings are shown for thematic purposes. Not to scale.
3.2.6.3 Refined Evaluation.
3.2.6.3.1 For each of the shortlisted terminal alternatives that are developed in greater detail, the initial evaluation criteria should be revisited and reassembled in a new matrix (potentially with new or refined criteria) to complete the evaluation. A scoring system may be used in this secondary alternative evaluation. The system could be simple (such as assigning positive, neutral, or negative (+, 0, -) labels to each alternative based on specific criteria) or more elaborate (such as allocating points to each alternative based on the criteria). Figure 3-5 shows an example of a secondary evaluation matrix.
3.2.6.5 Preferred Terminal Development Alternative. › 3.2.6.5.1 Once the airport owner/operator identifies the preferred…
Figure 3-5 Example Secondary Evaluation Matrix
3.2.6.3.2 The result of the evaluation process should be presented graphically so the recommended development alternative, phasing, schedule, and other key details can be readily understood. This is particularly important if the recommended approach combines different elements of the shortlisted alternatives.
3.2.6.4 Financial Feasibility. Using rough order of magnitude (ROM) cost estimates, the planning team should considerer financial planning factors to confirm the economic viability of terminal alternatives. An analysis of the financial feasibility of each investigated alternative in parallel with alternatives development and evaluation is a key factor in selecting the preferred alternative. As part of the evaluation process, a second round of financial feasibility should occur once the airport selects a preferred alternative.
3.2.6.5 Preferred Terminal Development Alternative.
3.2.6.5.1 Once the airport owner/operator identifies the preferred terminal development alternative, the layout should be clearly depicted in plans, cross-sections, perspectives, and descriptive narrative. This delineation should also address the original planning parameters, site constraints, and other criteria set out at the beginning of the study. A narrative prepared for the preferred terminal
3.2.7 Recommended Plan. › 3.2.7.1 Utilizing the preferred development alternative, this step in…
alternative should describe the alternative development and evaluation process, the resulting recommendation, and cover major points. These include:
Achieving balanced capacities (e.g., the passenger curbfront should support the number of passengers that the aircraft gates can accommodate).
Overall flexibility of space within the terminal building.
Revenue enhancement opportunities.
Operational flexibility for airlines and concessionaires.
Flexibility to adapt to industry changes and future considerations.
Ease of ground transportation access.
Phasing of terminal improvements.
3.2.6.5.2 The implementation of the preferred terminal alternative may need to be a multiphased development extending over a significant period of time. A multi-phased approach may be necessary for several important reasons, including, but not limited to:
The need to complete enabling projects.
The need to retain a minimum number of operational aircraft gates at all times during construction.
The need to maintain existing terminal building systems and equipment in operation during all phases.
The potential requirement to build a substantial portion of the new terminal on the same site as the existing terminal.
The need to preserve the safety of passengers, vehicles, personnel, and aircraft during all phases of construction.
Other factors related to cost, affordability, climate, and seasonal construction variables.
3.2.6.5.3 Finally, there are a number of elements which will continue to be evaluated as the planning evolves and projects move into design phase (e.g., plans for baggage processing, concessions, passenger processing, concourse phasing, aircraft parking, and departure holdrooms).
3.2.7 Recommended Plan.
3.2.7.1 Utilizing the preferred development alternative, this step in the process summarizes all of the proposed development at a high level. The outcome of this step is a chapter in the planning document that presents the airport’s development plan for the planning horizon. This plan is the precursor to postplanning processes (implementation) where individual projects undergo more detailed review and development towards project implementation. This is important to remember throughout the planning process.
3.3 Documentation. › 3.3.1 Document Organization.
3.2.7.2 This chapter in the report typically includes:
A supporting narrative that summarizes all the project recommendations.
A graphic that overlays the proposed development on a single scale graphic of the airport (typically in the form of linework overlaid on an aerial or vector base).
A tabular summary of proposed development with development triggers identified (levels of activity, facility condition, phasing, etc.).
A tabular program (if seeking federal financial assistance) of the proposed terminal development that quantifies the main functional program elements, and delineates public-use area verses non-public use areas. For the applicable definition of public-use area, please refer to FAA Order 5100.38, Airport Improvement Program Handbook.
Capital Improvement Plan.
An updated ALP set.
3.3 Documentation. Clear and concise documentation is critical to the success of the overall planning process, and ultimately to the successful transition to design and implementation phases. The outcome of the entire planning process is the project documentation, which is prepared in parallel with the terminal planning process steps.
3.3.1 Document Organization. Terminal planning documents are typically organized around the fundamental process steps discussed in this chapter, but also include introduction and recommended plan sections. Below is an example of chapters that are typically included. This is similar to the organization of a typical master plan document. See AC 150/5070-6, Airport Master Plans, Chapter 2, for additional information and coordinate the final document organization with FAA Regional or Airports District Office staff.
1. Introduction 2. Existing conditions 3. Forecasts of aviation activity 4. Facility requirements 5. Alternatives development and evaluation 6. Recommended plan
4.2.1 Annual Activity. › 4.2.1.1 Use annual activity to determine order-of-magnitude facility…
CHAPTER 4. PLANNING METHODOLOGIES AND TOOLS
4.1 General.
4.1.1 This chapter discusses methods and tools to support the terminal planning process, including demand characteristics and analytical tools.
4.1.2 Demand levels and characteristics provide basic data necessary for terminal planning or design. Therefore, they are usually researched and established early in the planning process. Analytical tools are used later in the planning process to determine terminal facility needs and sizing.
4.2 Demand Characteristics. Demand forecasts estimate future passenger activity and aircraft operations levels. Preparation of annual activity data and the conversion of demand forecasts into planning activity levels are addressed in Chapter 3, Terminal Planning Process. Facility requirements and other terminal space programs should be linked to annual “activity milestones” that are defined in terms of planning activity levels rather than future calendar years. Airport owners/operators or consultants develop terminal space programs based on peak demand levels (e.g., busiest day of the year, Peak Hour of the Average Day of the Peak Month). The following sections describe basic activity characteristics and traditional methodologies to determine those characteristics.
4.2.1 Annual Activity.
4.2.1.1 Use annual activity to determine order-of-magnitude facility requirements. Annual forecast data relevant to the terminal planning process includes:
Passenger enplanements – the annual number of departing passengers using a terminal facility. Enplanements can be subcategorized by domestic and international, originating or connecting, or any other category depending on project need. Annual enplanements can be used to derive design period enplanements needed to develop order-of-magnitude facility requirements.
Passenger deplanements – the annual number of arriving passengers using a terminal facility. Deplanements can be subcategorized by domestic and international, terminating or connecting, or other categories depending on the project need. Annual deplanements can be used to derive design period deplanements needed to develop order-of-magnitude facility requirements.
Aircraft operations – the annual number of arriving and departing aircraft that utilize the terminal facility. Aircraft operations can also be subcategorized by domestic and international, and wide-body versus narrowbody aircraft. Annual aircraft operations can be used to calculate order-ofmagnitude gate requirements.
Aircraft fleet mix – the specific types of aircraft serving an airport. Fleet mix is important because different aircraft have different passenger capacities
(i.e., number of seats). Aircraft fleet mix can be used to calculate order-ofmagnitude gate requirements and determine the flexibility of a proposed aircraft parking layout.
4.2 Demand Characteristics. › 4.2.6 Average Day of the Peak Month (ADPM) is a common methodology used…
Load factor – the percentage of seats utilized on an aircraft; this can be determined and expressed individually for specific airlines or type of operation (e.g., international or domestic), or as an average of all aircraft operations at an airport.
4.2.1.2 Annual forecasts are typically translated to peak daily and hourly demand.
4.2.2 Peak Activity.
4.2.3 Peak activity measures the highest projected level of passenger or operational activity in peak months, days, or hours. Terminal facility planning requires knowledge of peak activity because the terminal space programs are based on projected peak volumes of passengers. For example, the number of lanes required for a security screening checkpoint is based on the maximum throughput of an individual screening lane. If there are 300 passengers in the peak hour and each lane can process 150 passengers per hour, then a minimum of two screening lanes are needed.
4.2.4 Chapter 5, Terminal Building Space Program, describes the relationship of peak activity to building a space program for each terminal functional area. Depending on the level of analysis required, peak activity data can be prepared for passenger enplanements and deplanements (and associated sub classifications), and aircraft operations.
4.2.5 The following publications provide guidance on forecasting and peaking calculations:
FAA Guidelines, Forecasting Aviation Activity by Airport
Airport Cooperative Research Program (ACRP) Synthesis Report 2, Airport Aviation Activity Forecasting
ACRP Report 82, Preparing Peak Period and Operational Profiles—Guidebook
4.2.6 Average Day of the Peak Month (ADPM) is a common methodology used to identify existing and forecast future peak activity. The peak month is the month representing the highest percentage of total annual activity. ADPM is determined by dividing the peak month’s activity by the total number of days in that month. Future ADPM is determined by multiplying forecast annual activity by the historic percentage of total activity in the peak month, and again, dividing by the total number of days in that month. Figure 4-1 shows the method of determining existing and forecast ADPM.
4.2.7 Design Day Flight Schedules. › 4.2.7.3 Future peak hour volumes are determined by applying appropriate…
Figure 4-1 Determination of Average Day Peak Month Activity
4.2.7 Design Day Flight Schedules.
4.2.7.1 Another method used to determine future peak activity is through the development of a “design day” flight schedule. A design day flight schedule differs from a calculated peak activity number derived from annual activity in that it is based on a theoretical day, or rather, based on existing/current airline and passenger characteristics, such as:
Airline flights – scheduled commercial aviation activity, by each airline.
Airline fleet mix – aircraft types used by each airline.
Airline load factors –percentages of seats occupied, per each airline flight.
Passenger type – percentage of passenger types such as families, business travelers, leisure travelers, prescreened travelers, and passengers with airline status.
4.2.7.2 An existing design day flight schedule provides a distribution of passengers on an hourly basis throughout the design day. The peak hour can therefore be identified as the hour in the schedule that includes the highest passenger volumes for a given function, such as enplaning passengers, deplaning passengers, connecting passengers, and international passengers.
4.2.7.3 Future peak hour volumes are determined by applying appropriate growth rates to the existing design day flight schedule and increasing the activity levels to match forecast demand. This can be accomplished via a combination of “upgauging” (utilizing larger aircraft with higher numbers of seats per plane) aircraft types and the introduction of additional flights, depending on the strategies most likely to be deployed by the individual airlines at the airport. Coordinate with air carriers to validate and tailor assumptions used in the development of the future schedule.
4.3 Analytical Tools. › 4.3.3 Microscopic Methods.
4.2.7.4 Industry resources that provide additional information for determining annual and peak activity include:
ACRP Report 23, Airport Passenger-Related Processing Rates
ACRP Report 25, Airport Passenger Terminal Planning and Design
ACRP Report 163, Guidebook for Preparing and Using Airport Design Day Flight Schedules
4.3 Analytical Tools. A variety of analytical tools are available to assist in developing a terminal building space program. Three general levels of analysis – quick-estimation methods, macroscopic methods, and microsimulation methods – can be used to generate requirements. Each of these methods differs in terms of the level of effort to perform the analysis, the level of accuracy or reliability of the results, and the required level of user expertise. The following sections describe each method and when each should be applied.
4.3.1 Quick-Estimation Methods. Quick-estimation methods are best applied in early, conceptual stages of planning. They are used to develop a high-level terminal space program. A physical design is not needed at this low level of detail. Typically, the outputs are presented in tabular form. These methods are used as initial screening criteria to determine whether a terminal space program can be accommodated within the allowable development area, and therefore, if further analysis is warranted. The International Air Transport Association (IATA) Airport Development Reference Manual contains rules-of-thumb for the following facilities: check-in, passport control, centralized security check, gate area hold rooms, bag claim units, and arrival hall. ACRP Report 25, Airport Passenger Terminal Planning and Design, Volume 1, also contains gross area terminal planning factors. These factors are a useful tool when considering rough terminal sizing.
4.3.2 Macroscopic Methods. Macroscopic methods are used to understand overall passenger, baggage, and vehicular flows. This level of analysis typically requires a design or concept that can be represented in a model environment, along with logical assumptions assigned to passenger activities. Model outputs can include renderings of the simulation including passenger routes, flows at processing points, and numerical outputs. Macroscopic methods can be used to generate a reasonable planning or design-level space program. These methods are fairly sophisticated, but require less time and experience than microsimulation methods. Macroscopic methods are most useful during a terminal planning conceptual design phase when developing a comprehensive space program, as opposed to detailed focus on one specific functional area. ACRP Report 25, Airport Passenger Terminal Planning and Design – Volume 2 Spreadsheet Models and User’s Guide includes a spreadsheet model that is useful for this level of analysis, covering many of the functional terminal components.
4.3.3 Microscopic Methods. Microscopic methods use sophisticated computer software to simulate individual passenger, baggage, and vehicle movements, and their interaction with each other. This method
provides the most realistic passenger movement analysis and projects passenger interactions, detailed queuing/movements, and other passenger characteristics and behaviors. Outputs from this method include numerical outputs, three-dimensional visualization images, or videos for use in presentations. Due to their complexity, microscopic methods require the highest level of experience and maximum level of effort to produce results. These methods are most useful when analyzing and demonstrating micro-operational improvements, such as addressing security checkpoint congestion when it is impossible to expand beyond the building envelope.
PAGE INTENTIONALLY LEFT BLANK
5.3 Gross Terminal Area Estimates. › 5.3.2 Guidance for the above estimating techniques can be found in the…
CHAPTER 5. TERMINAL BUILDING SPACE PROGRAMMING
5.1 General. This chapter provides an overview of terminal building space programming. Programming defines the overall terminal size and the size of individual terminal components necessary to meet projected activity levels. Terminal space programs can be developed for a variety of project types, ranging from high-level strategic plans to more detailed design of new or expanded facilities.
5.2 Level of Service.
5.2.1 Level of Service (LOS) is defined as a qualitative and quantitative measurement of comfort experienced by passengers using the airport passenger terminal facility. LOS is a balance, or compromise, between customer service, cost, and available space. It is a key parameter to address at the onset of the spatial programming process. LOS is traditionally rated on a scale of A through F, excellent to unacceptable. This metric has evolved in recent years to simplify the categories “optimum, sub-optimum, under-provided, and over-design” (IATA Airport Development Reference Manual). Factors that are weighed to determine LOS vary by each terminal element, but can include factors such as processing time, level of crowding, walking distance, climate, etc.
5.2.2 Airport owners/operators are encouraged to design terminal projects to maintain a balanced LOS that results in an optimal (neither overbuilt nor underbuilt) and practical facility for the existing and planned activity levels.
5.2.3 Guidance on LOS can be found in the following resources:
ACRP Report 55, Passenger Level of Service and Spatial Planning for Airport Terminals ACRP Report 25, Airport Passenger Terminal Planning and Design IATA Airport Development Reference Manual
5.3 Gross Terminal Area Estimates.
5.3.1 Gross terminal area estimates are appropriate early in the planning process to determine orders of magnitude and sizing of key terminal components. Estimating generalized, gross terminal building sizes can be accomplished using the following methodologies:
Benchmarking other terminal facilities with similar functions, passenger activity levels, and passenger demographics (e.g., a high percentage of international or connecting passengers).
Calculating ratios based on demand and capacity (e.g., overall terminal area per required units, such as gates and passengers).
5.3.2 Guidance for the above estimating techniques can be found in the following resources:
ACRP Report 25, Airport Passenger Terminal Planning and Design IATA Airport Development Reference Manual
5.4.3 Check-in Lobby. › 5.4.3.3 The primary components of the check-in lobby are:
5.4 Terminal Building Space Allocation.
5.4.1 A planning level terminal building space program should focus on the individual functional areas and terminal components identified in Chapter 6, Functional Relationships and Terminal Concepts. It is important to consider inputs from a variety of stakeholders, including airlines and tenants, FAA (typically when receiving federal financial assistance), and other users.
5.4.2 The following sections describe major functional components, key variables, necessary inputs, and industry-accepted resources involved in calculating space requirements.
5.4.3 Check-in Lobby.
5.4.3.1 The check-in lobby is historically where departing passengers check-in for a flight, drop off checked baggage, and obtain boarding passes and other information for the flight. Traditionally, check-in lobbies were designed to be grand public spaces: the “front door” of an important public facility. Until around 2001, most check-in lobbies were long, linear spaces with large areas reserved for airline ticket counters, passenger queuing and waiting, airline ticket office space, and supporting areas such as restrooms and concessions.
5.4.3.2 Technology and evolved security requirements have significantly changed the way passengers and airlines use the check-in lobby. This has resulted in changes to space requirements. First, self-service check-in and baggage drop kiosks allow passengers to bypass the traditional check-in counters, and allow the check-in process to take place anywhere inside or outside the terminal building (such as at the curb or parking garage). In addition, computers and personal electronic devices allow passengers to check-in off-airport. These passengers interact with airline personnel only to drop off bags or to resolve problems. The result is a significant change in passenger and airline approaches to the check-in process. As the check-in process evolves, airline processes and airport policy are likely to create more options for the traveler. These options may reduce the building space allocated to the check-in lobby.
5.4.3.3 The primary components of the check-in lobby are:
Curbside check-in/baggage drop – a location outside of the terminal building, typically along the departure curbside, where passengers can check-in and drop baggage before entering the building.
Lobby check-in/baggage drop – a location inside the terminal building where passengers can check-in and drop baggage, either at a self-serve kiosk or traditional airline counter. The area can be a single consolidated space, or divided into segments by function (e.g., for boarding passes only or traditional check-in with an agent) or passenger classification (e.g., first class, economy, etc.). Typically, this area also includes airline office space.
Passenger queuing – areas designated for passengers waiting to check-in or check baggage, either at self-serve kiosks or traditional airline counters.
5.4.3 Check-in Lobby. › 5.4.3.5 Resources that provide in-depth explanations and tools to…
Public circulation – open areas from the entry vestibules to the check-in zones, and from the check-in zones to the security checkpoints that allow passengers and others to efficiently move throughout the lobby. This area also includes vertical circulation between levels and life safety egress.
Concessions –concessions space is warranted in the check-in lobby area to provide access for basic needs such as food and beverages and news/gifts for passengers who are delayed, have a long pre-security wait, or are spending time with well-wishers not allowed beyond security. Concessions also provide basic amenities to airport employees who do not have access to postsecurity areas.
Support areas – areas allocated for support functions such as restrooms, public seating, public information kiosks, and mechanical spaces.
5.4.3.4 Each airport and airline situation is different, but there are common variables which influence spatial requirements for the check-in lobby.
Passenger volumes – estimated passenger volumes, typically expressed in peak hour numbers, based on forecasted activity levels.
Patrons and passengers – factors such as the ratio between originating and connecting passengers, the characteristics and requirements of passengers who check-in and drop-off baggage (e.g., passengers requiring assistance, the number of well-wishers who see passengers off, earliness arrival profiles, etc.).
Processing rates objectives – acceptable processing rates, allowable wait times, maximum queuing lengths, etc. to meet established level of service parameters. Objectives need to be balanced against facility and equipment capacities.
Airport environment – are check-in lobby facilities (ticket counters or kiosks) for common use or preferential use? Is there a single dominant hub airline? Or are there multiple airlines?
Airline processes – the unique characteristics, equipment, processes, and special requirements of individual airline check-in and bag-drop policies.
5.4.3.5 Resources that provide in-depth explanations and tools to calculate check-in lobby space requirements include:
ACRP Report 25, Airport Passenger Terminal Planning and Design
ARCP Report 55, Passenger Level of Service and Spatial Planning for Airport Terminals
ACRP Report 10, Innovations for Airport Terminal Facilities
ACRP Report 23, Airport Passenger-Related Processing Rates
IATA Airport Development Reference Manual
5.4 Terminal Building Space Allocation. › 5.4.8 Individual airlines have different procedures to optimize their…
5.4.4 Outbound Baggage Processing.
5.4.5 Outbound baggage processing includes the area and equipment required to accommodate, sort, screen, and process checked baggage from the check-in lobby to the aircraft. Outbound baggage processing includes the following main components:
Baggage conveyance system – automated conveyor belts that sort and connect baggage from the check-in/drop-off point to the baggage security screening machines, and from the baggage screening machines to outbound baggage makeup devices.
Primary baggage screening area – the area that accommodates screening equipment where all bags are initially inspected; cleared bags proceed to outbound baggage make-up devices, and “alarmed” bags (e.g., bags that are determined to contain suspicious contents) are either rescreened or sent to secondary screening.
Secondary baggage screening area – the area that accommodates screening equipment where alarmed bags are manually screened a second time.
Outbound baggage devices – automated devices that circulate and sort cleared baggage in preparation to be transported to the aircraft. These devices range from simple flat-plate to sloped plate units.
Staff support areas – areas necessary to accommodate baggage screening personnel.
5.4.6 All checked and carry-on baggage must be screened by federal mandate. In many locations, terminals were renovated to meet federal guidelines. Given differing passenger volumes and the complexity of baggage processing infrastructure, airports and airport security have adopted the following three variations of the screening process:
Stand-alone screening – used for small airports where baggage is placed into screening machines and the outbound processing system by hand.
Mini-inline systems – used at small to medium-sized airports, or constrained terminals where one or more airlines share a single conveyor belt system that feeds a screening machine, and outbound baggage device.
Fully automated inline system – used at other airports where multiple conveyor belts feed outbound baggage into a consolidated screening area with multiple screening machines.
5.4.7 TSA’s Planning Guidelines and Design Standards for Checked Baggage Inspection Systems describes these screening processes in detail.
5.4.8 Individual airlines have different procedures to optimize their outbound baggage operations. Airport owners/operators should consult airlines about space requirements of outbound baggage systems before project design. Each airport is different, but some common variables influence space requirements for outbound baggage processing:
System type – the most appropriate screening process (stand-alone, mini-inline, fully automated inline) for a given airport.
Passenger baggage characteristics – data pertaining to the percentage of passengers checking bags. This includes average number of bags per passenger, average traveling party size, etc.
5.4.10 Security Screening. › 5.4.10.2 The primary components of security screening checkpoints in…
Processing rate objectives – acceptable conveyance system speeds, screening machines processing rates, etc., to meet established level of service parameters. Objectives should to be balanced against other facility and equipment capacities. Therefore, coordination between the airport, TSA, and airlines is paramount.
Design activity for equipment requirements – the passenger demand level that the baggage system and screening machines are designed to accommodate, and the equivalent estimated baggage demand.
Airline processes – individual airline outbound baggage makeup processes. This can be “stacked” cart staging (parked perpendicular to a baggage belt) or “linear” cart staging (parked parallel to a baggage belt).
Passenger and baggage volumes – estimated passenger and baggage volumes. These are typically expressed in peak numbers of bags per hour and based on forecast activity levels.
5.4.9 Resources that provide in-depth explanations and tools to calculate space requirements include:
TSA’s Planning Guidelines and Design Standards for Checked Baggage Inspection Systems ACRP Report 25, Airport Passenger Terminal Planning and Design
5.4.10 Security Screening.
5.4.10.1 Security screening checkpoints are where security personnel examine commercial airline passengers and carry-on baggage to ensure that prohibited or harmful items are not carried onto aircraft. Commercial airports began to vet passengers through a security screening process beginning in the late 1960s. The FAA mandated screening in 1973. The Federal government created the TSA to implement more rigorous screening procedures in 2001. Security screening procedures are complex and evolve to address new threats and requirements.
5.4.10.2 The primary components of security screening checkpoints in passenger terminals are:
Queuing area – area reserved for passengers waiting to enter the screening area. This is typically segregated into multiple zones, including the main line(s) for passengers (both with or without a status that warrants expedited screening), airport employees, and airline crew members.
Document check – location where TSA employees examine a passenger’s bonafides (boarding pass and government issued identification) to confirm authenticity and allow them to proceed to screening.
Divestiture area – zone where passengers must divest items such as metal objects, electronic devices, coats, belts, shoes, and baggage onto a conveyor belt for screening. This is also the area where passengers queue for screening.
Screening area – location where passengers pass through screening equipment (advanced imaging technology or magnetometers). Baggage is screened through advanced technology machines. Secondary baggage
5.4.10 Security Screening. › 5.4.10.4 Resources that provide in-depth explanations and tools to…
screening is located adjacent to the primary screening. Private, manual passenger screening is provided remotely.
Recomposure area – seating area or vacant space at the end of the screening checkpoint for passengers to gather and re-pack divested items.
Administrative space –areas within or adjacent to the security screening checkpoints where security operates and monitor the security screening equipment. Space for detention rooms, training rooms, break rooms, and other administrative functions can be located remotely from the screening checkpoint.
5.4.10.3 Each airport situation is different, but there are some common variables that influence security checkpoint space requirements:
Location – where the security screening process occurs within the terminal. This can be a single, centralized location or multiple checkpoints throughout the terminal(s).
Characteristics of airline passengers, employees, and tenants – the unique attributes and special requirements of individuals going through the checkpoint. This includes airport employees, airline crew, frequent-flyers versus less frequent passengers, passengers with disabilities or reduced mobility, passengers traveling with families, percentage of prescreened passengers, etc.
Policy and regulations – current TSA and/or additional local guidelines and procedures.
Processing rates objectives – acceptable processing rates, allowable wait times, maximum queuing lengths, etc., to meet established level of service parameters. Objectives need to be balanced against other facility and equipment capacities.
Passenger volumes – estimated passenger volumes; typically expressed in peak hour numbers and based on forecasted activity levels.
5.4.10.4 Resources that provide in-depth explanations and tools to calculate space requirements include:
TSA’s Checkpoint Design Guide
ACRP Report 10, Innovations for Airport Terminal Facilities
ACRP Report 23, Airport Passenger-Related Processing Rates
ACRP Report 25, Airport Passenger Terminal Planning and Design
ACRP Report 55, Level of Service and Spatial Planning for Airport Terminals
IATA Airport Development Reference Manual
5.4.11 Gate Holdrooms / Departure Lounge.
5.4.11 Gate Holdrooms / Departure Lounge. › 5.4.11.4 Resources that provide in-depth explanations and tools to…
5.4.11.1 A gate holdroom or departure lounge is where departing passengers wait for and ultimately board flights. Primary components of a holdroom include:
Waiting area – designated airline-specific space where passengers wait to board a flight. The area includes seating for passengers.
Airline gate podium and queuing – area where passengers queue and ultimately communicate with airline representatives.
Boarding and egress corridor – designated area near the gate used for queuing passengers to board the aircraft, and for passenger egress from the aircraft when it arrives at the gate. Individual airlines have differing boarding and egress procedures.
5.4.11.2 Holdrooms are typically sized according to the largest aircraft able to park at the gate being served. Not all passengers arrive and wait at the gate prior to boarding a flight, so requirements are calculated based on the percentage of total passengers who could be at the gate at a given time.
5.4.11.3 Common variables that influence spatial requirements for holdrooms include:
Passenger volume– estimated passenger volume. This is based on forecast activity levels or passenger loads from defined aircraft types serving the gate(s).
Passenger behavior – Another detail to consider in the space programming of holdrooms is the amount of baggage (personal items and carry-on) that passengers travel with. Since most airlines charging fees for checked bags, many passengers carry-on as much as possible. This results in more luggage in circulation space and seats adjacent to passengers in the holdroom. With increasingly high load factors on planes, gate agents commonly require passengers to gate check their carry-ons. This results in a potentially longer boarding process and longer passenger queue times. These factors (among others) have spatial impacts and need to be carefully considered.
Holdroom Seating – the ratio of seats in the holdroom area versus standing area. This is an important consideration that directly relates to anticipated passenger volumes at each gate.
Airport or airline characteristics – airport policy applications (e.g., designated versus common use gates) and unique boarding processes for the airlines projected to use the holdrooms, and the physical footprint of the terminal building relative to gate location.
Processing rates objectives – acceptable processing rates, allowable wait times, etc., to meet established level of service parameters.
5.4.11.4 Resources that provide in-depth explanations and tools to calculate space requirements include:
ACRP Report 25, Airport Passenger Terminal Planning and Design
5.4.12 Concessions. › 5.4.12.2 Although every airport situation is unique, some common…
IATA Airport Development Reference Manual
5.4.12 Concessions.
5.4.12.1 Airport concessions are an important component in terminal space programs. The following are primary concessions areas an airport should consider when developing space program requirements:
Leased space – areas operated by the concessionaire including: (a) the space where patrons consume food and beverages, or shop for retail items, (b) food and beverage serving space or retail shelf space, and (c) close-in, “back-ofhouse” preparation and/or storage space.
Duty free – retail areas exclusively for departing international passengers where passengers can purchase certain tax-exempt goods.
Decentralized in-terminal storage space – remote storage or food preparation areas leased by the concessionaires to serve the primary leased space. The area can be located throughout the terminal or near concessions nodes.
Centralized remote storage – a centralized commissary, usually away from the terminal, that receives and stores incoming goods, and delivers the goods to the terminal locations on a regularly scheduled basis. Third party logisticians typically lease and operate these areas.
Parking and access – employee conveyance, access, and parking to support concession operations.
Loading dock – area where concessions goods and other deliveries are unloaded from trucks. This area can be in-terminal or at a remote location such as the “centralized remote storage area” noted above.
Waste collection and removal – area dedicated to the collection and removal of trash, recycling, compost, etc. from tenant spaces or the collective concessions’ tenant location. This includes “back-of-house” private circulation to support this function.
5.4.12.2 Although every airport situation is unique, some common variables influence space requirements:
Passenger volumes – estimated passenger volumes based on forecast activity levels. This is typically expressed in annual or peak hour passengers. In general, higher passenger volumes can justify more diversity in offerings.
Terminal geometry – the terminal layout that dictates the general flow of passengers between the check-in lobby and holdrooms. Particular attention should be paid to location of the security checkpoint(s).
Split between pre- verses post-security – the allocation of concessions between pre-security and post-security areas (depending on the terminal layout and other airport and passenger characteristics).
5.4.13 Baggage Claim / Inbound Baggage Processing. › 5.4.13.2 There are baggage claim areas in both domestic and…
Patron types –passenger characteristics, including the numbers of business and leisure travelers, originating and connecting passengers, domestic and international passengers, etc.
Exposure – the physical location of concessions areas (e.g., directly adjacent to the security checkpoint[s], in a centralized concession node, or in a concourse among the holdrooms).
Concession types – the allocation of food and beverage concessions versus retail offerings, including specialty retail or duty free retail.
Centralized or decentralized storage – dependent on an airport’s business agreements with a single or multiple concessionaires, and policy regarding movement of goods through public verses private areas.
Support space allocation – amount of space required to support concession operations, including back-of-house non-public circulation to support this function. This can vary depending on centralized or decentralized location
5.4.12.3 Resources that provide in-depth explanations and tools to calculate concession space requirements include the following:
ACRP Report 25, Airport Passenger Terminal Planning and Design
ACRP Report 54, Resource Manual for Airport In-Terminal Concessions
IATA Airport Development Reference Manual
5.4.13 Baggage Claim / Inbound Baggage Processing.
5.4.13.1 Baggage claim, or inbound baggage processing, includes the facilities and area required for arriving passengers to reclaim checked baggage. Baggage claim is also typically the area reserved for “meeters and greeters,” and where most passengers end the flight/aviation portion of their journey. Therefore, in addition to baggage claim devices and airline offices, baggage claim areas traditionally include city and transportation information, rental car counters, concessions space, and support areas such as restrooms and mechanical spaces.
5.4.13.2 There are baggage claim areas in both domestic and international terminals. This section focuses on domestic baggage claim. International baggage claim is discussed in Section 5.4.14, Customs and Border Protection Facilities. Baggage claim and inbound baggage processing includes the following primary components:
Inbound baggage drop off – private areas where airline personnel place deplaned baggage onto conveyor belts that feed into the baggage claim devices.
Baggage claim hall – general term for the area encompassing baggage claim devices, circulation, and other support functions. These include public seating, baggage carts, ground transportation concessionaires, customer support, etc.
5.4 Terminal Building Space Allocation. › 5.4.14 Customs and Border Protection Facilities.
Baggage conveyance and delivery devices – devices that move and circulate deplaned passenger baggage for reclaiming.
Baggage service office – airline office space to assist passengers with lost baggage. Also an area where airlines store unclaimed bags.
5.4.13.3 Some common variables which influence space requirements for inbound baggage processing are:
Baggage claim device type – flat plate or sloped plate devices. The latter has more handling capacity and requires fewer carousels.
Baggage claim device usage/allocation – airline claim for device usage (e.g., preferential versus common use). The latter is more efficient because of sharing between airlines.
Passenger baggage characteristics – the percentage of passengers checking bags, average number of bags per passenger, and average traveling party size.
Processing rates objectives – acceptable conveyance system and claim device speeds, allowable wait times, etc., to meet established level of service parameters. Objectives should be balanced against other facility and equipment capacities.
Forecast activity levels for equipment requirements – baggage processing equipment/spatial requirements should be based on the forecast activity levels for the overall terminal design.
Passenger and baggage volumes – estimated passenger and baggage volumes. Typically expressed in peak period or numbers of bags per hour and based on forecast activity levels.
5.4.13.4 Resources that provide in-depth explanations and tools to calculate space requirements include:
ACRP Report 10, Innovations for Airport Terminal Facilities
ACRP Report 25, Airport Passenger Terminal Planning and Design
5.4.14 Customs and Border Protection Facilities. The U.S. CBP operates Federal Inspection Stations (FIS) where arriving international passengers and their baggage are inspected to allow entry into the United States. These facilities are commonly referred to as FIS facilities. They are only located in terminals that serve arriving international passengers. The U.S. CBP maintains guidance on the development of CBP processing facilities entitled Airport Technical Design Standards. This is the primary reference document for government agencies, airport owner/operators, airlines, architect/engineering consultants, and CBP personnel involved with the planning, design, development, and alteration of CBP processing facilities at airports. For additional information on this guidance, please contact the U.S. CBP’s Office of Facilities.
5.4.15 Restrooms. › 5.4.15.3 For more information on the topic, see the following:
5.4.15 Restrooms.
5.4.15.1 A space program for terminal restrooms and related restroom facilities (sometimes referred to as ancillary restroom facilities) must be developed per local building codes and Americans with Disabilities Act (ADA) standards. See 42 U.S.C. § 1201, et seq.
5.4.15.2 There are a number of airport-specific variables and related restroom facilities that should also be considered:
Passenger volumes – estimates of passenger volumes in specific terminal areas based on forecasted activity levels, fleet mix, arrival/departure frequency, etc. Typically expressed in the number of peak hour or peak period passengers.
Airport-specific passenger processing and layout – understanding airport specific variables that define restroom catchment zones. These include the location of the security screening area, concessions areas, and amount of space dedicated to holdrooms.
Sizing of restrooms and layout – programming adequate space to accommodate ambulatory travelers and travelers with disabilities (wheelchair-accessible) that have luggage. Consider out-swinging stall doors, open restroom entryways without doors, touch-free restroom environments, etc.
Restroom allocation – understanding the balance of demand for restrooms, and the number and types of bathroom fixtures needed.
Related restroom facilities – in addition to typical restrooms, airports are encouraged to program space for;
o Companion care and family restrooms with changing tables.
o Nursing rooms that are separate from restrooms.
o Lactation rooms that are separate from restrooms.
Service Animal Relief Areas (SARA). Per 49 CFR § 27.71(h)(2) and (3), airports with 10,000 or more annual enplanements shall cooperate with airlines to provide wheelchair accessible relief areas for service animals that accompany passengers departing, connecting, or arriving at the airport. See AC 150/5360-14, Access to Airports by Individuals with Disabilities, for additional information on the requirements and recommendations for SARA facilities.
5.4.15.3 For more information on the topic, see the following:
U.S Department of Justice Civil Rights Division, ADA Standards for Accessible Design
ACRP Report 130, Guidebook for Airport Terminal Restroom Planning and Design
5.4.17 Public Amenities. › 5.4.17.1 Public amenities are additional areas within the terminal…
ACRP Report 25, Airport Passenger Terminal Planning and Design, Volume 1: Guidebook
ACRP Synthesis Report 64, Issues Related to Accommodating Animals Traveling Through Airports
AC 150/5360-14, Access to Airports by Individuals with Disabilities
5.4.16 Support Areas.
5.4.16.1 Airline, tenant, and airport owners/operators require space to support general management and operations, emergency response, staff medical facilities, security offices, airport police, and similar functions. Other airport tenants, such as concessionaires and the TSA, may also need similar space depending on airport policy and facility layout. Input from airport management and other operators or tenants who might use such space is necessary in developing space requirements.
5.4.16.2 Airlines require office space for management personnel, flight crew facilities (lounge/rest areas), storage, and other support areas. Airline clubrooms are tenant spaces provided by airlines to cater to their frequent travelers and airline club members. Typically, clubrooms are found at hub airports or at an airport with large passenger volumes. At international airports, global airline alliances often provide common use clubs for all premium passengers within their alliance. Recently, some airports have been developing premium lounges, sponsored and operated by a third party, to cater to premium passengers who are not associated with an alliance but still want the lounge experience.
5.4.17 Public Amenities.
5.4.17.1 Public amenities are additional areas within the terminal building that facilitate passenger convenience and level of service objectives. These areas may include the following:
Information centers – locations where passengers can ask questions about the airport or local environs. These tend to be booths or kiosks in the baggage claim or check-in lobby.
Computer and phone recharging stations – areas where passengers can recharge electronic devices. Airports or third-party operators provide this amenity. They are typically located near holdrooms.
United Service Organizations (USO) facilities for military personnel.
Passenger sanctuaries – non-denominational or interfaith areas within the terminal complex for worship, meditation, or to offer passengers refuge.
Smoking facilities – contained indoor and sometimes outdoor areas for smoking.
Wheelchair storage – area where airport staff store wheelchairs for escorting passengers who need assistance in the terminal.
5.4.19 Signage and Wayfinding. › 5.4.19.2 The following are factors to consider when developing a…
Luggage carts – storage area for luggage carts. Usually in the check-in or baggage claim hall. Generally provided by a third-party operator.
5.4.17.2 The above are common among airports of various sizes and roles. However, the size and location should be determined on a case-by-case basis, and varies depending on terminal and environmental characteristics. Another resource to define space requirements for public amenities is ACRP Report 25, Airport Passenger Terminal Planning and Design.
5.4.18 Building Services.
5.4.18.1 A portion of all terminal buildings is allocated to building operations and equipment. Examples include:
Maintenance and storage – areas allocated to airport maintenance staff and storage of maintenance equipment.
Operations – space allocated to general airport operations, emergency response, staff medical facilities, security offices, and similar functions.
Mechanical system rooms– areas allocated to heating ventilation and air conditioning (HVAC) systems, and other infrastructure needed for the building to operate.
Utilities – areas allocated to operate or provide access to major airport utilities. This includes electrical, technology infrastructure, communications equipment, plumbing, and other systems needed for the building to operate.
Structural systems – areas allocated to the structural support of the building. This is usually 5% of the terminal’s total gross area.
Life safety egress – facilities for the egress or evacuation of passengers in the terminal building during an emergency.
5.4.18.2 The above areas are unique to each airport. Space should be allocated on a caseby-case basis. See ACRP Report 25, Airport Passenger Terminal Planning and Design, for information on defining building services spatial requirements.
5.4.19 Signage and Wayfinding.
5.4.19.1 Signage and wayfinding facilitates movement of departing passengers from the airport access roadway (or transit system) through the terminal to the holdroom, and vice-versa for arriving passengers. Passenger demographics are diverse and can include frequent business travelers, first time travelers, large numbers of families traveling with children, international passengers, and passengers with disabilities, reduced vision, or reduced mobility. Therefore, it is important that signage and wayfinding is consistent and reliable throughout the airport, and meets all local and national code compliance standards.
5.4.19.2 The following are factors to consider when developing a signage and wayfinding program:
5.4.20 Security Area Delineation and Control Systems. › 5.4.20.2 Security areas include:
Graphic standards – a uniform visual theme that complies with industry, international standards and local code. It should be consistent in appearance, concept, and location. Carefully consider font type, font size, character spacing, and signage illumination for a wide range of users. Note that it is good practice for temporary and tenant branded signage to be consistent with airport graphic standards.
Terminology/Diction – consistent and easy to understand wording.
Spacing – consistent frequency of signage and placement (considering building design and passenger flows).
Maintenance and fabrication – materials and site locations should minimize sign maintenance.
Code compliance – program should accommodate all special requirements, to include U.S Department of Justice ADA Standards for Accessible Design and local building codes.
5.4.19.3 Because of technological advances, signage and wayfinding have become more flexible, focused, and passenger friendly. Signage that used to be static can now be dynamic, and change based on owner/operator requirements. For example, security checkpoint wait times can be displayed at a central terminal location to better inform passengers. In addition, mobile technology such as smart phones and tablets provide passengers accessible indoor maps, and the capability to navigate through the entire airport. This technology will continue to evolve as a component of the terminal environment. Airport owners/operators should consider and incorporate new technology into the terminal program at the planning stage to maintain maximum flexibility, and adapt to changing needs/technological trends.
5.4.19.4 ACRP Report 52, Wayfinding and Signage Guidelines for Airport Terminals and Landside, provides detailed explanations and best practices for developing signage and wayfinding programs. For specific information on airport landside considerations for signage and wayfinding, see Section 8.8, Landside Signage and Wayfinding.
5.4.20 Security Area Delineation and Control Systems.
5.4.20.1 There are three distinct security zones within the terminal: public areas for passengers and non-passengers, sterile areas for screened passengers, and secure non-public areas for airport and airline employees. There are numerous FAA, TSA, local law enforcement regulation definitions, and equally as many sitespecific regulations for airports.
5.4.20.2 Security areas include:
Public area – the non-sterile area that is open to the general public, commonly referred to as “pre-security.”
5.5 Trends and Innovations. › 5.5.2 Passenger Demographics.
Sterile area – public area for passengers who have been screened by the TSA, commonly referred to as “post-security.”
Secured area – the areas located outside the terminal or concourse where only approved airport or airline employees are permitted (e.g., the aircraft parking apron).
Security Identification Display Area (SIDA) – designated areas where only approved airport or airline employees, contractors, concession employees, FAA personnel and others are permitted (e.g., “back-of-house” concessions circulation corridors).
FIS sterile area – controlled area for arriving international passengers before they have been cleared by CBP to enter the country (e.g., “sterile” corridors that connect the aircraft boarding gate to the FIS facility).
5.4.20.3 These areas have a variety of control systems to ensure the security of the terminal, including access controls and video surveillance. A key source of information on this topic is the National Safe Skies Alliance document, Recommended Security Guidelines for Airport Planning, Design and Construction. Additionally, an industry-recognized publication that provides extensive guidance is the Integrated Security System Standards for Airport Access Control (Radio Technical Commission for Aeronautics).
5.5 Trends and Innovations. Major events and developments that occurred around the turn of the 21st Century – such as terrorist attacks and technological advances (e.g., mobile devices, self-service kiosks, etc.) – have significantly changed how airports and airlines operate. These events and changing passenger demographics continue to impact the evolution of the terminal building, as well as terminal planning and space programing.
5.5.1 Flexible Space Planning. Given changing terminal building spatial and functional needs, it is important to build facilities that can adapt over time. The concept of “programmable design” allows for interior functional components to be moved around and adapted to new passenger flows driven by technology or other innovations. Column-free space is one design decision that makes a facility more flexible and reconfigurable without impacting major structural elements. The use of prefabricated, modular building elements can also be used to create environments that can be reconfigured and adapted to work as functions change.
5.5.2 Passenger Demographics. Airline passenger profiles are diverse, ranging from frequent business travelers to leisure or first-time travelers. In the past decade, the focus of the industry has shifted to frequent travelers who have an interest in self-service, and use personal electronic devices to move through check-in, screening, and boarding. There are demographic factors that should be considered, including:
5.5.4 Passenger Experience. › 5.5.4.1 Airport owners/operators are making a renewed effort to provide…
Aging population – an increasingly aging population requires specific accommodations in facility design. ACRP Synthesis Report 51, Impact of Aging Travelers on Airports, provides an in-depth explanation and best practices for addressing this.
Passengers without mobile technology – not all passengers will adapt to self-service or mobile technologies. A portion of the traveling public will continue to require personal interaction in the airport passenger terminal.
Language diversity – a growing number of domestic and international passengers require information to be available in multiple languages. The extent of language diversity varies geographically.
5.5.3 Self-Service Processing.
5.5.3.1 Airline passengers have come to expect that they will be able to transact or receive help with the assistance of technology in a variety of industries (e.g., banks, gas stations, grocery stores, video kiosks, etc.). This trend is being embraced in the airport environment with self-service kiosks and remote processing enabling passengers to check themselves in for a flight and in some cases, submit information for security or customs screening. For check-in, locating these devices outside the terminal building in parking garages, rental car facilities, and intermodal transportation centers allows passengers to bypass the ticket counter entirely and proceed directly to security screening. Self-service processing sometimes begins through web-based services before passengers arrive at the airport. Using other innovations, passengers are able to buy tickets on the internet, check-in for a flight, print baggage tags, and arrange other services in advance.
5.5.3.2 Inside the concourse, passengers can navigate to preferred concessions and holdroom locations using smart phone applications, which can enhance the passenger experience and improve passenger mobility in the terminal environment. Self-boarding is taking place at some international airports, and is being tested at some facilities in the United States. These trends will continue to evolve. It is important to consider these trends during the terminal planning process.
5.5.3.3 In an effort to expedite the processing of passengers entering the U.S, self-service processing is also available at some FIS facilities. Travelers use self-service kiosks or a mobile application to submit their customs declaration form and biographical information. Travelers using this program can experience shorter wait times, less congestion, and faster processing. For additional information, see the U.S. CBP website on Automated Passport Control.
5.5.4 Passenger Experience.
5.5.4.1 Airport owners/operators are making a renewed effort to provide a more positive passenger experience. This is occurring through some of the technological and self-serve advances noted above, and through architectural design and customer service improvements. Examples of these innovations are:
5.5.5 Cost Reduction and Revenue Enhancement. › 5.5.5.2 In conjunction with self-service processing and enhanced…
Improved restroom facilities – one of the first and last things passengers experience when arriving and departing airports are the restroom facilities. It often represents one of the most significant sources of customer complaints. Improving restrooms to meet current passenger expectations is a high priority for many airports.
Open lounge waiting areas – traditional holdrooms are being replaced by large open, light-filled spaces with Wi-Fi connectivity, televisions, comfortable lounge seating, easily accessible power connections, and concessions. The intent is to provide a place of convenience, comfort, and relaxation for aircraft passengers.
Performances and events – such activities can provide a sense of place and allows the airport to become a marketing tool for local tourism. Examples include free live music or theme events during the busiest travel periods, such as sidewalk sales and local product and food sampling.
Spa facilities and health clinics – to ease the burden of long layovers, some airports have concessions that offer massages, spa, sauna, and fitness facilities. Other offerings include pharmaceutical services and walk-in health clinics.
Art and culture–airports offer in-terminal art or museums to enhance the airport experience, including displays and other installations that describe or acknowledge local culture and history.
5.5.4.2 For additional information on the topic, see ACRP Report 157, Improving the Airport Customer Experience.
5.5.5 Cost Reduction and Revenue Enhancement.
5.5.5.1 Self-service processing and a renewed emphasis on the passenger experience are positive developments for the passenger, but they also benefit the airline operators. The 2008 financial crisis combined with rising fuel prices forced the airlines to seek cost reductions. Airlines turned to consolidation as one way to reduce costs. They are also increasing self-service processing. Recent and projected increases in self-service processing will lower airline staffing requirements. In some cases, staffing reductions may reduce or repurpose the space program for major functional elements and for back-of-house office space, thereby reducing capital expenditures for airport owners/operators.
5.5.5.2 In conjunction with self-service processing and enhanced passenger experiences, airports are increasing the size of concessions programs. This can include:
Relocating concessions from pre-security to post-security areas, and to locations where there is a high volume of passenger traffic.
Improving concessions quality by making local and high quality goods available.
PAGE INTENTIONALLY LEFT BLANK
CHAPTER 6. FUNCTIONAL RELATIONSHIPS AND TERMINAL CONFIGURATION
6.1 General. This chapter describes the difference between origin and destination (O&D) and hub/connecting airport terminals, passenger terminal components, their functional relationships, and planning considerations.
6.3 Terminal Components and Functional Relationships. › 6.3.2 The primary users of airport passenger terminals are airlines,…
6.2 Origin and Destination Versus Hub/Connecting Airport Terminals.
6.2.1 The difference between an O&D airport terminal and a hub/connecting airport terminal stems from the way airlines use or serve the facilities. An O&D airport terminal primarily serves passengers that start and end their trip at a given airport, with little to no connecting flights. A hub/connecting airport primarily functions as a connecting point for passengers who start and end their trip at other airports.
6.2.2 There are vast differences between a passenger terminal for O&D, and one that accommodates connecting or hub operations. One difference is the active or peak periods (both operationally and in terminal buildings). In the United States, domestic O&D markets typically experience two main peak-hour periods during the day. These vary across the country depending on geography and markets served. In contrast, airports with significant connecting or hubbing operations tend to experience sustained levels of passenger activity throughout the day.
6.3 Terminal Components and Functional Relationships.
6.3.1 As stated earlier, an airport passenger terminal is a building or complex of buildings that serve as the interface between aircraft, travelers, and landside transportation elements. These elements work cohesively to convey passengers to and from their origins and destinations. The terminal complex is typically divided into three primary components: airside, terminal building, and landside. Figure 6-1 shows the flow between the various components in a typical terminal complex, from curbside to parked aircraft. Not every terminal provides all of these functions or spatially aggregates these functions. For example, at low-activity airports, one general space may contain multiple functions, such as a lobby, ticket counters, and waiting lounge.
6.3.2 The primary users of airport passenger terminals are airlines, travelers, well-wishers, meeters/greeters, airline employees, concessionaires, government, airport owner/operator staff, and other airport tenants. While terminal facilities must accommodate all these users, the planning and design of a terminal facility is primarily influenced by the activities within the terminal building, which can be categorized into: (1) processing and servicing passengers; (2) handling and processing of belly cargo (including passenger baggage); (3) aircraft servicing; and (4) facility support and utility functions. Good terminal design requires a layout that locates the various components in a sequence or pattern that reflects the natural movement and services each function requires. Such a design minimizes passenger walking distances, airline servicing and processing times, and congestion that arises from the convergence of unrelated activities.
6.3.3 Airside Components. › 6.3.3.1 Airside terminal facilities (see Figure 6-1) primarily include…
Figure 6-1 Terminal Components
6.3.3 Airside Components.
6.3.3.1 Airside terminal facilities (see Figure 6-1) primarily include the area and facilities required to accommodate aircraft parking, and aircraft support and servicing operations:
Terminal gates or “contact“ parking positions – this portion of the apron is used for parking aircraft to enplane and deplane passengers via passenger boarding bridges (PBB), secure pedestrian walkways, or by walking to the aircraft.
Remote aircraft parking positions – used for parking aircraft to enplane and deplane passengers; passengers are transferred from the terminal to the aircraft (or vice versa) via bus or other passenger transport vehicle. These areas can also serve as remain overnight (RON) positions.