AC 150/5070-6B Airport Master Plans
Provides guidance for the preparation of airport master plans that range in size and function from small general aviation to large commercial service facilities. Appendix D of this AC cancels Chapter 1, Section 5; Appendix 6; and Appendix 7 of AC 150/5300-13, Airport Design. Consolidated file contains Changes 1 and 2.
Advisory Circular
U.S. Department of Transportation Federal Aviation Administration
Subject: Change 2 to Airport Master Plans Date: 1/27/2015 Initiated by: APP-400
AC No.: 150/5070-6B Change: 2
1. PURPOSE. This Change 2 incorporates additional guidance on passenger convenience, ground access, and access to airport facilities, as identified in Section 131 of Public Law 112-95, “FAA Modernization and Reform Act of 2012 (49 U.S.C. § 47101(g)(2)).” Additional provisions of Public Law 112-95 such as Section 132 (b) which amended the definition of airport planning to include plans for recycling and minimizing the generation of airport solid waste (49 U.S.C § 47102(b)(5)(C)), and Section 133 providing that master plans address issues related to solid waste recycling and waste minimization (49 U.S.C. § 47106(a)(6)(A)) have been addressed in separate FAA guidance. These and related considerations will be incorporated into a future change to this AC.
This change also incorporates relevant updates related to the recent changes to Advisory Circular (AC) 150/5300-13, Airport Design, and references to the new Standard Operating Procedures for preparation and submission of Airport Layout Plans.
2. PRINCIPAL CHANGES. Changed text is indicated by vertical bars in the margins. The primary revisions are contained in Chapters 8 and 10 and Appendix B of this AC. In addition, limited editorial and text revisions since the release of Change 1 to this AC in 2007 are incorporated throughout. A full revision to this AC is underway.
PAGE CONTROL CHART
Remove Pages Dated Insert Pages Dated
i-iii
iv
7-8
13
27
7/29/2005
5/1/2007
7/29/2005
7/29/2005
7/29/2005
i-iii
iv
7-8
13
27
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
AC 150/5070-6B Change 2 1/27/2015
Remove Pages Dated Insert Pages Dated
32-33
42
48-62
65
73
75-76
78
79-83
89
91
97-110
129-130
7/29/2005
7/29/2005
7/29/2005
7/29/2005
7/29/2005
7/29/2005
5/1/2007
7/29/2005
7/29/2005
7/29/2005
7/29/2005
7/29/2005
32-33
42
48-67
71
79
81-82
84
85-91
97
103
105-118
137-138
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
1/27/2015
Elliott Black Director, Office of Airport Planning and Programming
Advisory Circular
U.S. Department of Transportation Federal Aviation Administration
Subject: Airport Master Plans Date: July 29, 2005 Initiated by: APP-400
AC No.: 150/5070-6B Change:
1. PURPOSE. This Advisory Circular (AC) provides guidance for the preparation of master plans for airports that range in size and function from small general aviation to large commercial service facilities. The intent of this AC is to foster a flexible approach to master planning that directs attention and resources to critical issues. The scope of each master plan must be tailored to the individual airport under evaluation.
2. CANCELLATION. This publication cancels Advisory Circular 150/5070-6A, Airport Master Plans, dated June 1985. Chapter 10 and Appendix F of this document cancel Chapter 1, Section 5, Airport Layout Plan; Appendix 6, Section 2, Typical Airport Layout Plan; and Appendix 7, Airport Layout Plan Components and Preparation, of Advisory Circular 150/5300- 13, Airport Design, dated September 1989.
Dennis E. Roberts, Director Office of Airport Planning and Programming
Consolidated AC includes Changes 1 and 2
This page intentionally left blank.
1/27/2015 AC 150/5070-6B Change 2
i
Table of Contents
PART I: THE PROCESS OF PREPARING MASTER PLAN STUDIES … 1
CHAPTER 1 INTRODUCTION … 1 101. Purpose and Application … 1 102. Intended Users … 1 103. Need for New Guidance … 1 104. Function of Master Plan Studies … 1 105. Organization and Use of the Advisory Circular … 2
CHAPTER 2 CONTENT OF MASTER PLANNING STUDIES … 5 201. Tailoring Studies to the Needs of Individual Airports … 5 202. Types of Master Planning Studies … 5 203. Level of Study Detail … 7 204. Products of the Master Planning Process … 7 205. Master Plan Reviews by the FAA … 8
CHAPTER 3 PRE-PLANNING … 9 301. Initial Needs Determination … 9 302. Request for Qualifications and Consultant Selection … 9 303. Development of Study Design … 10 304. Negotiating Consultant Contracts … 12 305. Application for Federal Funding … 13
PART II: ELEMENTS OF MASTER PLAN STUDIES … 15
CHAPTER 4 PUBLIC INVOLVEMENT PROGRAM … 17 401. Timing … 17 402. Tools and Techniques … 18 403. Identify the Stakeholders … 20 404. Identify Key Issues … 20 405. Documentation Guidelines … 20
CHAPTER 5 ENVIRONMENTAL CONSIDERATIONS … 23 501. General … 23 502. Environmental Considerations in Master Planning Alternatives Analysis … 24 503. Further Guidance on Consideration of Environmental Factors in Airport Master Planning … 26 504. Documentation Guidelines … 26
AC 150/5070-6B Change 2 1/27/2015
ii
CHAPTER 6 EXISTING CONDITIONS … 27
601. General … 27 602. Background Section … 27 603. Inventory and Description of Existing Facilities … 27 604. Describe Regional Setting and Land Use … 30 605. Environmental Overview … 31 606. Develop Socioeconomic Data … 32 607. Assemble Historical Aviation Activity … 32 608. Financial Data … 33 609. Documentation Guidelines … 34
CHAPTER 7 AVIATION FORECASTS … 35 701. General … 35 702. Forecast Elements … 36 703. Factors Affecting Aviation Activity … 37 704. Steps in the Forecast Process … 39 705. Documentation … 43 706. Source Data … 43
CHAPTER 8 FACILITY REQUIREMENTS … 47 801. General … 47 802. Emerging Trends … 48 803. Design Hour Demand … 49 804. Security Considerations … 50 805. Airfield and Airspace Requirements … 50 806. Commercial Service Passenger Terminal Complex … 54 807. General Aviation Requirements … 60 808. Air Cargo Requirements … 61 809. Support Facilities … 62 810. Ground Access, Circulation, and Parking Requirements … 63 811. Utilities … 66 812. Other Requirements … 67 813. Documentation Guidelines … 67
CHAPTER 9 ALTERNATIVES DEVELOPMENT AND EVALUATION … 69 901. General … 69 902. Alternatives Analysis Process in Airport Master Planning … 71 903. Identification of Alternatives … 74 904. Evaluation of Alternatives … 76 905. Selection of a Recommended Alternative … 78 906. Airport Site Selection … 79 907. Documentation Guidelines … 79
CHAPTER 10 AIRPORT LAYOUT PLANS … 81
1001. General … 81 1002. Airport Layout Plan Drawing Set … 82 1003. Computer-Aided Design Standards … 85
1/27/2015 AC 150/5070-6B Change 2
iii
1004. Geographic Information Systems Applications … 85 1005. Base Mapping and Data Sources … 86 1006. Checklists … 87 1007. Approvals … 87 1008. Documentation Guidelines … 88
CHAPTER 11 FACILITIES IMPLEMENTATION PLAN … 91
1101. General … 91 1102. Formulation of the Capital Improvement Plan … 92 1103. Project Sequencing and the Comprehensive Master Schedule … 93 1104. Key Activities and Responsibilities … 94 1105. Documentation Guidelines … 95
CHAPTER 12 FINANCIAL FEASIBILITY ANALYSIS … 97
1201. General … 97 1202. Sources of Funding … 97 1203. Financial Feasibility … 99 1204. Revenue Enhancement … 102 1205. Benefit Cost Analysis … 103 1206. Documentation Guidelines … 103
APPENDIX A GLOSSARY … 105
APPENDIX B USEFUL REFERENCE MATERIALS … 111
1. FAA Advisory Circulars … 111 2. FAA Orders … 113 3. Federal Aviation Regulations … 114 4. Transportation Security Regulations … 114 5. Security-Related Publications … 115 6. FAA Reports … 115 7. General Airport Publications … 116 8. Airport Cooperative Research Program (ACRP) Reports … 117
APPENDIX C LIST OF POTENTIAL STAKEHOLDERS … 119
APPENDIX D CONSIDERATION OF ENVIRONMENTAL FACTORS IN AIRPORT MASTER PLANNING … 121
1. Introduction … 121 2. Practice and Process … 122 3. Tools … 127 4. NEPA Documents of Other Federal Agencies … 130 Attachment D-1 Environmental Overview for Master Plan Purposes … 131
APPENDIX E AIRPORT SITE SELECTION … 133
1. General … 133 2. Site Selection Process Overview … 133 3. Site Approval … 134
AC 150/5070-6B Change 2 1/27/2015
iv
APPENDIX F AIRPORT LAYOUT PLAN DRAWING SET … 137
1. Airport Layout Drawing … 137 2. Airport Airspace Drawing … 140 3. Inner Portion of the Approach Surface Drawing … 141 4. Terminal Area Drawing … 142 5. Land Use Drawing … 142 6. Runway Departure Surfaces Drawing … 143 7. Airport Property Map … 144
List of Figures
Figure 4-1: Public Meeting … 17
Figure 6-1: Timeline of Events … 28
Figure 7-1: Sample of FAA Forecast Graphs … 35
Figure 7-2: Aviation Demand Elements … 37
Figure 7-3: Sample Table from Terminal Area Forecast Summary Report … 44
Figure 9-1: Alternatives Analysis Process Example … 73
Figure 10-1: Airport Layout Plan Drawing … 84
Chapter 1 Introduction › 104. Function of Master Plan Studies
PART I: THE PROCESS OF PREPARING MASTER PLAN STUDIES
Chapter 1 Introduction
101. PURPOSE AND APPLICATION
This Advisory Circular (AC) provides guidance for the preparation of master plans for all airports. Its intent is to foster the development and adoption of a flexible approach to master planning that devotes resources and attention to critical issues. Planners should tailor an individual master plan to the unique conditions at the study airport. As a result, master plans for individual airports will vary in what elements they include and in the level of detail.
An airport master plan is a comprehensive study of an airport and usually describes the short-, medium-, and long-term development plans to meet future aviation demand. The category of study that includes master plans and master plan updates can therefore be thought of as a continuum that varies by level of detail and associated effort.
The elements of a master planning process will vary in complexity and level of detail, depending on the size, function, issues, and problems of the individual airport. The technical steps described in this AC are generally applicable, although each step should be undertaken only to the extent necessary to produce a meaningful product for a specific airport. However, study elements for large and/or complex airports may involve unique technical analyses beyond those detailed in this AC. The sponsor, the sponsor’s consultant, and FAA representatives must carefully prepare a scope of work that reflects the circumstances of the individual airport.
102. INTENDED USERS
This publication is intended primarily for use by members of the aviation community, especially those directly involved in preparing master plans: airport sponsors, airport staff, airport consultants, FAA representatives, and state aviation officials. It will also be useful to airport board members; municipal officials; state, regional, and local planning personnel; and the general public.
103. NEED FOR NEW GUIDANCE
Methods and techniques associated with airport master plan studies have evolved since the last version of this AC was published in 1985. This update incorporates current industry methods and procedures commonly employed in the preparation and documentation of master plan studies.
104. FUNCTION OF MASTER PLAN STUDIES
a. Airport master plans are prepared to support the modernization or expansion of existing
airports or the creation of a new airport. The master plan is the sponsor’s strategy for the development of the airport.
Chapter 1 Introduction › 105. Organization and Use of the Advisory Circular
b. The goal of a master plan is to provide the framework needed to guide future airport
development that will cost-effectively satisfy aviation demand, while considering potential environmental and socioeconomic impacts. The FAA strongly encourages that planners consider the possible environmental and socioeconomic costs associated with alternative development concepts, and the possible means of avoiding, minimizing, or mitigating impacts to sensitive resources at the appropriate level of detail for facilities planning.
c. Each master plan should meet the following objectives:
1) Document the issues that the proposed development will address.
2) Justify the proposed development through the technical, economic, and environmental investigation of concepts and alternatives.
3) Provide an effective graphic presentation of the development of the airport and anticipated land uses in the vicinity of the airport.
4) Establish a realistic schedule for the implementation of the development proposed in the plan, particularly the short-term capital improvement program.
5) Propose an achievable financial plan to support the implementation schedule.
6) Provide sufficient project definition and detail for subsequent environmental evaluations that may be required before the project is approved.
7) Present a plan that adequately addresses the issues and satisfies local, state, and Federal regulations.
8) Document policies and future aeronautical demand to support municipal or local deliberations on spending, debt, land use controls, and other policies necessary to preserve the integrity of the airport and its surroundings.
9) Set the stage and establish the framework for a continuing planning process. Such a process should monitor key conditions and permit changes in plan recommendations as required.
105. ORGANIZATION AND USE OF THE ADVISORY CIRCULAR
a. Structure of the Advisory Circular – The Advisory Circular is presented in two parts:
1) Part I – The Process of Preparing Master Plan Studies provides an introduction to the Advisory Circular, an overview of master plan studies, and a summary of the preplanning process.
2) Part II – Elements of Master Plan Studies provides a detailed discussion of the various elements of master plan studies, including the components of master plan technical reports and the plan drawings that accompany them.
b. As noted above, Part II of the AC details the individual elements of a master plan study.
Although they are presented in the order found in a typical master plan report, issues in some chapters may have a direct bearing on those in other chapters. Environmental and financial feasibility considerations, for example, must be considered throughout the process. These cross-linkages are explicitly identified in the relevant chapters of Part II.
c. The AC includes several appendices of supplemental materials. Appendix A presents a
glossary of terms that are commonly used in airport master planning. Appendix B provides a list of useful reference materials, including other advisory circulars, FAA orders, appropriate Code of Federal Regulations, Transportation Security Regulations, security-related publications, FAA reports, and general airport publications. Appendix C provides a listing of potential stakeholders in the public involvement program of the master planning process. Appendix D provides a discussion of environmental factors in airport master planning. Appendix E provides guidance on the site selection process. Appendix F shows the general guidelines in preparing the airport layout plan drawing set.
This page intentionally left blank.
Chapter 2 Content of Master Planning Studies › 202. Types of Master Planning Studies
Chapter 2 Content of Master Planning Studies
201. TAILORING STUDIES TO THE NEEDS OF INDIVIDUAL AIRPORTS
The guidance in this AC covers planning requirements for all airports, regardless of size, complexity, or role. However, each master plan study must focus on the specific needs of the airport for which a plan is being prepared and the scope of a study must be tailored to the individual airport. Therefore, in a given study certain master planning elements may be emphasized while others may not be considered at all. Although the FAA does not require airports to prepare master plans, it strongly recommends that they do so.
The intent of this AC is to foster a flexible approach in the preparation of airport master plans, enabling planners to focus their resources and effort on critical issues. As a scope of work is developed, the planners and airport sponsors must make decisions regarding two key questions: (1) what type of study should be conducted, and (2) what level of detail should be assigned to the individual elements of the study?
202. TYPES OF MASTER PLANNING STUDIES
a. The master planning process will vary with the size, complexity, and role of the study
airport and may include a variety of supporting studies. However, all master planning studies will fall within one of two basic types: Airport Master Plans or Airport Layout Plan (ALP) Updates.
b. Airport Master Plans – An airport master plan is a comprehensive study of the airport
and typically describes short-, medium-, and long-term plans for airport development. Master planning studies that address major revisions are commonly referred to as “Master Plans,” while those that change only parts of the existing document and require a relatively low level of effort tend to be known as “Master Plan Updates.” In common usage, however, the distinction refers to the relative levels of effort and detail of master planning studies. In most cases, the master plan will include the following elements:
1) Pre-planning – The pre-planning process includes an Initial Needs Determination, Request for Proposal and Consultant Selection, Development of Study Design, Negotiation of Consultant Contract, and Application for Study Funding.
2) Public Involvement – Once the consultant team is under contract and has been issued a notice-to-proceed, establish a public involvement program and identify and document the key issues of various stakeholders.
3) Environmental Considerations – A clear understanding of the environmental requirements needed to move forward with each project in the recommended development program.
4) Existing Conditions – An inventory of pertinent data for use in subsequent plan elements.
5) Aviation Forecasts – Forecasts of aeronautical demand for short-, medium-, and long-term time frames.
6) Facility Requirements – Assess the ability of the existing airport, both airside and landside, to support the forecast demand. Identify the demand levels that will trigger the need for facility additions or improvements and estimate the extent of new facilities that may be required to meet that demand.
7) Alternatives Development and Evaluation – Identify options to meet projected facility requirements and alternative configurations for each major component. Assess the expected performance of each alternative against a wide range of evaluation criteria, including its operational, environmental, and financial impacts. A recommended development alternative will emerge from this process and will be further refined in subsequent tasks. This element should aid in developing the purpose and need for subsequent environmental documents.
8) Airport Layout Plans – One of the key products of a master plan is a set of drawings that provides a graphic representation of the long-term development plan for an airport. The primary drawing in this set is the Airport Layout Plan. Other drawings may also be included, depending on the size and complexity of the individual airport.
9) Facilities Implementation Plan – Provides a summary description of the recommended improvements and associated costs. The schedule of improvements depends, in large part, on the levels of demand that trigger the need for expansion of existing facilities.
10) Financial Feasibility Analysis – Identify the financial plan for the airport, describe how the sponsor will finance the projects recommended in the master plan, and demonstrate the financial feasibility of the program.
c. Airport Layout Plan Updates – An update of the airport layout plan (ALP) drawing set
should be an element of any master plan study. In fact, keeping the ALP current is a legal requirement for airports that receive Federal assistance. An update of the ALP drawing set will reflect actual or planned modifications to the airport and significant offairport development. An accompanying ALP Narrative Report should explain and document those changes and contain at least the following elements:
1) Basic aeronautical forecasts.
2) Basis for the proposed items of development.
3) Rationale for unusual design features and/or modifications to FAA Airport Design Standards.
4) Summary of the various stages of airport development and layout sketches of the major items of development in each stage.
Chapter 2 Content of Master Planning Studies › 204. Products of the Master Planning Process
1/27/2015 AC 150/5070-6B Change 2
An ALP drawing set update is an appropriate alternative to a full master plan whenever the fundamental assumptions of the previous master plan have not changed. If there have not been any major changes in airport activity or improvements that have had unanticipated consequences, a master plan update is not necessary. Another situation where only an ALP update would be appropriate is the examination of a single development item, such as runway safety area improvements. As indicated above, an ALP update will typically involve fewer elements than a full master plan study, including only the aviation demand forecasts, an assessment of facility requirements, a facility implementation and financing plan, and an airport layout plan drawing set. If additional steps are required to complete the ALP update, a full master plan study is probably a better choice.
203. LEVEL OF STUDY DETAIL
Although almost every master plan includes the full list of elements discussed above, the complexity of the individual elements will vary, depending on an airport’s size, function, and particular issues and problems. Each element should be analyzed only to the extent required to produce a meaningful product for that particular airport. The planning process should consider the facility planning needed to enable a seamless transition to subsequent projects.
The scoping process used by the airport sponsor, the sponsor’s consultant, and the FAA to develop a work program for the planning study should determine the appropriate level of detail for each study element. The availability of planning information from Federal, state and local organizations may eliminate the need to develop similar information in a study effort. Chapter 3 contains additional information on the scoping process, while Part II provides greater detail on the various elements of an airport master plan.
204. PRODUCTS OF THE MASTER PLANNING PROCESS
a. The products of the master planning process will vary with the complexity of the effort.
Master plans can include the following deliverables:
1) A Technical Report contains the results of the analyses conducted during the development of the master plan. For complex studies, interim reports may be produced to facilitate coordination with various government agencies, tenants, users, the general public, and other interested parties. At the conclusion of the study, the interim reports are assembled into the final technical report.
2) A Summary Report is useful in bringing together pertinent facts, conclusions and recommendations for public review.
3) An Airport Layout Plan Drawing Set contains a graphical representation of the proposed development in the master plan and is typically produced as a separate set of full-sized drawings. In addition, the ALP drawing set is typically included in the Technical Report in reduced form.
4) A Web Page – Many airport sponsors maintain a public access web page with general information about the governmental unit involved and specific information regarding
AC 150/5070-6B Change 2 1/27/2015
the airport or airports operated by the sponsor. The Internet provides an excellent forum for the distribution of information on the progress of the study and its final findings and recommendations.
Chapter 2 Content of Master Planning Studies › 205. Master Plan Reviews by the FAA
5) Public Information Kit – Throughout the master plan study, airport sponsor representatives may be asked to speak to community associations, civic clubs, and other organizations with an active interest in the airport. Visual aids such as models, summary brochures, or computer presentations are excellent tools to use at these events to maintain support for the airport development program.
b. The master plan technical report, summary report, and airport layout plan may be
produced as paper versions and/or in an electronic format, as determined by the airport sponsor and the FAA. The electronic format will ease distribution of the final reports after the initial printing is exhausted.
c. It is again emphasized here that the level of complexity of each of these products should
be determined during the development of the study design. The airport sponsor and the FAA have the flexibility to assess the level of detail that is appropriate for the individual airport and may identify other deliverables that should be produced to support the study effort.
205. MASTER PLAN REVIEWS BY THE FAA
a. The recommendations contained in an airport master plan represent the views, policies
and development plans of the airport sponsor and do not necessarily represent the views of the FAA. Acceptance of the master plan by the FAA does not constitute a commitment on the part of the United States to participate in any development depicted in the plan, nor does it indicate that the proposed development is environmentally acceptable in accordance with appropriate public law. The FAA reviews all elements of the master plan to ensure that sound planning techniques have been applied. However, the FAA only approves the following elements of airport master plans:
1) Forecasts of Demand – The master plan forecast should be reviewed to ensure that the underlying assumptions and forecast methodologies are appropriate. Paragraph 704.h of this guidance should be used to determine consistency of the master plan forecast levels and the Terminal Area Forecast (TAF). Inconsistencies between the master plan forecast and TAF must be resolved, and the forecast approved, before proceeding with subsequent planning work.
2) Airport Layout Plan – All airport development at Federally-obligated airports must be done in accordance with an FAA- and sponsor-approved ALP. Furthermore, proposed development must be shown on an approved ALP to be eligible for Airport Improvement Program (AIP) funding. FAA approval of the ALP indicates that the existing facilities and proposed development depicted on the ALP conforms to the FAA airport design standards in effect at the time of the approval or that an approved modification to standard has been issued. Such approval also indicates that the FAA finds the proposed development to be safe and efficient.
Chapter 3 Pre-planning › 302. Request for Qualifications and Consultant Selection
Chapter 3 Pre-planning
Planners, along with airport sponsors, must make two major decisions in tailoring a study to the needs of an individual airport: what type of study to conduct and what level of detail to use for the individual elements of the study. This chapter outlines these and other steps of the preplanning process.
301. INITIAL NEEDS DETERMINATION
a. Identifying General Need for Study – The airport sponsor usually identifies the need
for a planning study, based on existing or potential shortcomings in the existing plan or airport. These deficiencies may be the result of demand exceeding capacity, the introduction of new aircraft types, or the emergence of a critical environmental problem. The airport sponsor’s strategic vision or business plan for the airport may drive the need for a planning study. In addition, national, state, or regional planners may have identified issues requiring the airport sponsor’s attention. Alternatively, airport users, such as the scheduled airlines and general aviation pilots, may have identified needs that prompted the airport sponsor to undertake a study. The airport sponsor should formulate priorities to establish which issues are most important. Periodic meetings between the airport sponsor and FAA representatives offer an excellent opportunity to review these issues.
b. Determining Type of Study – Deciding whether the study in question will lead to a
master plan or to an ALP update largely determines the elements to be included and the required level of effort. Even at this early stage of the process, the airport sponsor and the FAA should be able jointly to determine what type of study is appropriate. The sponsor usually will not make decisions regarding specific variations on the basic study type until the consultant has come on board. Although a master plan study will always include a technical report and an airport layout plan drawing set, supplemental products, which may often be related to public outreach efforts, will usually be determined during the scoping process.
302. REQUEST FOR QUALIFICATIONS AND CONSULTANT SELECTION
a. The current version of AC 150/5100-14 Architectural, Engineering and Planning
Consultant Services for Airport Grant Projects provides important guidance for consultant selection, and its use is recommended. Another useful reference is “Guidelines to Selecting Airport Consultants” published by the Airport Consultants Council, an aviation industry trade association.
b. As a general rule, airport sponsors hire a consultant to prepare planning studies. Before
soliciting statements of qualifications (SOQs) from consultants, the airport sponsor should have a clear understanding of the issues that have defined the need for the study. This information should be provided in the Request for Qualifications (RFQ) that the airport sponsor will issue.
c. The sponsor should assemble an unbiased and technically qualified selection panel to
conduct the consultant selection. The qualifications of a firm should be judged on its
Chapter 3 Pre-planning › 303. Development of Study Design
experience in similar work and its staff’s professional credentials. The planning team that is proposed by the consultant should include firms with relevant experience that can commit to complete the study in the amount of time specified. It is not uncommon for several firms to join together in a master planning effort for the purpose of providing specialized skills or local knowledge and expertise.
d. The sponsor should avoid the use of elaborate submittal requirements or interviews,
which add substantially to the cost of the selection process for both the sponsor and the prospective consultants. If the sponsor determines that interviews or requests for additional information are necessary, the sponsor should limit this activity to a short list of three to five firms selected by the evaluation panel.
e. If sponsors anticipate an Environmental Assessment (EA) or Environmental Impact
Statement (EIS), they should consult with the local FAA Airports office to determine the appropriate time to begin the consultant selection process. If a sponsor or the local FAA Airports office anticipates the need for an Environmental Assessment, the sponsor should select a qualified environmental contractor to prepare the EA. Sometimes, it may be appropriate for the sponsor to expand the scope of the master plan consultant’s responsibilities to include the EA. When the sponsor or the FAA have substantial concerns that the EA may suggest that an action may cause significant impacts, the appropriate FAA Airports office should select the contractor to prepare the EA. This is because if the EA shows that significant impacts would occur, the FAA must select the contractor to prepare its EIS. FAA’s selection of the EA contractor in this case saves time by eliminating the need for later contractor selection to prepare the EIS.
303. DEVELOPMENT OF STUDY DESIGN
a. The second decision in designing an effective planning study is to determine the level of
detail or depth of analysis for each element. The airport sponsor and the selected consultant should negotiate these basic decisions as the work program is established.
b. The airport sponsor, the consultant, the FAA, and others (as appropriate) begin this
process by (1) identifying the airport development issues to be addressed in the master plan and (2) determining the types of analyses and level of effort needed to address each issue individually. Known as “scoping,” this is an important step in designing any planning study.
c. The sponsor and the selected consultant should address a broad range of topics during the
scoping process. As the scoping process proceeds, the planners must remember that each master plan study is unique and the appropriate scope of work will vary from airport to airport. The airport sponsor is encouraged to develop a scope of work that is appropriate to the circumstances of the individual airport. Some of the specific topics that should be addressed at this time include:
1) Goals and Objectives – Discuss key airport development issues that the master plan will attempt to resolve. This discussion should answer questions such as: “Why is this master plan study being conducted?,” “What are the key issues that need to be addressed in the future development of the airport?,” and so forth.
2) Data Availability – Review the availability of activity forecasts and capacity assessments produced by state and regional system plans and FAA Terminal Area Forecasts and decide how to use them. If these data are not used, the reasons should be discussed with and accepted by all parties, including the FAA. This is especially true for low activity airports where demand/capacity relationships are usually not a critical consideration. Current inventory data may also be available to the consultant as a result of continuous planning efforts by the airport sponsor. Use of these data may reduce the need for new data collection efforts or surveys by the consultant.
3) Forecast Horizons – Although 5-, 10-, and 20-year time frames are typical for short-, medium-, and long-term forecasts, some studies may want to use different time frames. For any forecast horizon, the short-term forecast should support a capital improvement program, the intermediate-term a realistic assessment of needs, and the long-term a concept-oriented statement of needs. Schedules for airport development that are directly related to demand levels should be tied to those demand levels, rather than dates, since the actual demand will often vary from that forecast, particularly as the time frame increases. At some airports, it may be necessary to look beyond the 20-year time frame to protect the airport from incompatible land use development. The need to do longer range planning must clearly be justified during the scoping process.
4) Environmental Considerations – Identify the level of environmental documentation that is likely to move forward with the recommendations of the completed master plan study. Sponsors, in consultation with the appropriate FAA Airport’s environmental specialist, should identify whether an Environmental Assessment (EA) or Environmental Impact Statement (EIS) may be required or whether categorical exclusions may apply. As noted previously, if sponsors anticipate an EA or EIS, they should consult with the local FAA Airports office to determine the appropriate time to begin the consultant selection process. Consideration should also be given to the appropriate state environmental regulations and the need to develop applicable documentation.
5) Schedules – Agree upon schedules showing milestones for the completion of technical products and for coordination and review. The schedule should clearly indicate decision points beyond which work should not proceed without FAA or airport sponsor approval, such as FAA review and approval of the master plan forecast.
Realistic schedule development is important. From a practical standpoint, adhering to the schedule for a complex study, such as a long-range plan for a high activity airport, is very difficult. Less complex studies should not have such a problem. In any case, the schedule for a master plan study should be firm so that all reviewers are aware of their responsibilities with respect to it. The airport sponsor should emphasize the importance of meeting planning process deadlines.
6) Deliverables – The specific draft and final products of the planning process, and the general level of detail, should be listed in the scope of work and include the number, type, and format of paper reports, drawings, and electronic files.
Chapter 3 Pre-planning › 304. Negotiating Consultant Contracts
7) Coordination and Public Involvement Program – For less complex studies, the FAA, the airport sponsor and the consultant may be the only participants as long as they coordinate with appropriate local officials, stakeholders, and ensure citizen participation through public information sessions. These sessions may be conducted separately or in conjunction with other public meetings. Often written updates for regional or state aviation, transportation and comprehensive planning agencies will be sufficient.
For complex studies, it may be necessary to organize formal policy, technical, and review committees that meet regularly and use structured communications systems, including public hearings, public information workshops, and web-based information sharing tools. The committee membership may consist of representatives of local, state, and Federal government agencies as well as airport tenants, user groups, community associations, and business organizations. In addition, the active participation of the FAA concerning airspace management, navigational aid and approach aid installation, designation of instrument runways, potential financing of planning and development, and safety and security matters is essential.
The local FAA Airports office can coordinate the involvement of the FAA organizations that are interested in the development of the airport. Advice from the airlines concerning aircraft types they plan to use and other operational and financial matters will also be essential to the development of an effective plan.
The airport sponsors staff probably will participate in the day-to-day activities of the planning study. A large airport sponsor will likely have a more extensive management and staff structure than the sponsors of smaller airports.
8) Budget – Development of the work scope and the associated fees is usually an iterative process. The work scope contemplated in early draft narratives may require fees that exceed a sponsor’s budget. Planners must adjust the scope of work, the proposed fees, or the available budget until all three components have been balanced to the satisfaction of the sponsor, the consultant, and the FAA.
d. Careful attention to the development of the scope of work for the master plan study sets
the stage for a successful study. Establishing a sound scope of work will also allow the sponsor, consultant, and the FAA to develop a budget that meets the goals and objectives of the study. Failure to do so may result in a study that is lacking vital details that affect the decision making process. It is important to note that Federal planning grants cannot be amended to cover increased costs. If additional work is needed beyond the original scope of work, an additional grant would probably be required. Many of the decisions made at this point will have an impact on the degree of difficulty that is encountered as the development program moves from planning to implementation.
304. NEGOTIATING CONSULTANT CONTRACTS
After scoping the study and negotiating a price for the consulting services, a contractual arrangement must be negotiated.
Chapter 3 Pre-planning › 305. Application for Federal Funding
1/27/2015 AC 150/5070-6B Change 2
a. The recommended type of agreement between the airport sponsor and the consultant is a
firm, fixed price contract. This is advisable whenever the level of effort can be fairly well predicted and where reasonable fees can be established at the outset. This type of contract imposes a minimum administrative burden and provides incentives for effective cost control and contract performance.
b. Where the level of effort or duration of the study is uncertain, a cost plus fixed-fee
contract or a time and materials contract may be required. Also, some airport sponsors, recognizing that master planning often uncovers unanticipated issues that need study, add an on-call component to their consultant contract, which allows the scope and fees to be developed as new tasks are identified. These contract provisions typically provide for payment on a time and materials basis, but not to exceed a specified amount. The use of such contracts must be well justified if Federal financial assistance will be provided. The FAA does not recommend contracts based on a cost-plus percentage of cost and they are not permitted if Federal financial assistance will be provided for the study.
c. Advisory Circular 150/5100-14, Architectural, Engineering and Planning Consultant
Services for Airport Grant Projects, is also a good reference for guidance on the options for a contract format. The procedures in this AC must be followed if Federal funds are involved.
305. APPLICATION FOR FEDERAL FUNDING
The point at which a sponsor submits a grant application to the FAA varies with the individual study. For large and complex master plans, the sponsor should divide the total grant funding into two phases. The initial phase can fund early tasks such as the definition of issues, inventory of existing conditions, preparation of forecasts, and determination of facility requirements. The second phase grant application could be prepared after the study team has gained a better grasp of the key issues and a more precise cost estimate of the effort needed to complete the master plan. The FAA should be involved in the overall process as early as possible. The FAA can advise the sponsor on the best strategy for obtaining funding and on questions of the eligibility of the elements of the proposed scope of work.
This page intentionally left blank.
PART II: ELEMENTS OF MASTER PLAN STUDIES
PART II: ELEMENTS OF MASTER PLAN STUDIES
Part II of this Advisory Circular provides detailed discussions of the elements of a typical master plan study. As noted in Chapter 1, the elements to be included in a particular study will vary depending on the size, function, and challenges facing the study airport. The following key elements of master plan studies are discussed in Part II of this Advisory Circular:
Chapter 4: Public Involvement Program Chapter 5: Environmental Considerations in Airport Master Planning Chapter 6: Existing Conditions Chapter 7: Aviation Forecasts Chapter 8: Facility Requirements Chapter 9: Alternatives Development and Evaluation Chapter 10: Airport Layout Plans Chapter 11: Facilities Implementation Plan Chapter 12: Financial Feasibility Analysis Each chapter in Part II ends with a section titled “Documentation Guidelines.” These guidelines are not mandatory, and planners should use their discretion in adopting only the guidelines that are consistent with their negotiated scope of work. Planners also have the flexibility to adopt other documentation guidelines that they feel are better suited to the particular circumstances of a study. Appendix B contains a comprehensive listing of other planning documents and guidelines that may be helpful.
This page intentionally left blank.
Chapter 4 Public Involvement Program › 401. Timing
Chapter 4 Public Involvement Program
The first task in a master plan study, after the consultant receives a notice-to-proceed, is the creation of a public involvement program. The level of public involvement in airport planning should be proportional to the complexity of the planning study and to the degree of public interest. Most planning studies will fall between the minimal requirements of a small airport study and extensive public involvement required of a large and complex study. Particularly complex studies may merit the use of a consultant experienced in the public involvement process.
Figure 4-1: Public Meeting
Source: Portland Airport Project Advisory Committee
Over the course of the study, the public involvement program will encourage informationsharing and collaboration among the airport sponsor, users and tenants, resource agencies, elected and appointed public officials, residents, travelers, and the general public. Collectively, these various groups form the stakeholders who have an interest in the outcome of the study. An effective public involvement program should provide these stakeholders with an early opportunity to comment, before major decisions are made; provide adequate notice of opportunities for their involvement; and should provide for regular forums throughout the study.
401. TIMING
Public involvement has its greatest impact during the early stages of the planning process, before irreversible decisions have been made and while many alternatives can be considered. When the stakeholders become involved before major decisions or commitments are made, the planners can better deal with issues of community concern and improve the chances of reaching a consensus on controversial matters. If stakeholders become aware that the important decisions were made before they were invited to participate, they may distrust the planners. In addition, when public involvement opportunities are not provided until late in the planning process, there may not be enough time to make significant changes. The tendency, instead, will be for planners to merely defend previously determined courses of action, rather than exploring any new alternatives. An effective public involvement program will usually avoid such an undesirable outcome.
Chapter 4 Public Involvement Program › 402. Tools and Techniques
402. TOOLS AND TECHNIQUES
The study team may use a variety of forums, such as committees, public information meetings, small group meetings, and public awareness campaigns in a public involvement program. The selection of a specific platform depends on the particular complexities associated with the airport, the expected public interest in the master plan, the practices and policies of the airport sponsor, and budget considerations. In addition, it may be necessary to consider the special needs and sensitivities of low income and minority populations, consistent with the provisions in Executive Order 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations. Although the public involvement program is important to the master plan effort, planners must balance the need for stakeholder involvement with the costs of such a process. Complex, large, or unfocused stakeholder groups can impede meaningful input, unnecessarily raise study costs, and frustrate participants as they struggle to communicate with the study group.
a. Committees – Committees that facilitate the public involvement program often include a
Technical Advisory Committee (TAC) and a Citizen’s Advisory Committee (CAC). The TAC is responsible for providing input and insight on technical issues. Committee members typically have a high level of technical competency associated with some aspect of aviation or airport operations and are major stakeholders in the airport’s operation. The CAC serves as a sounding board and information exchange group for stakeholders, reviews the planning team’s plans and proposals, interacts with the planning team members during the review, makes consensus recommendations to the planning team, and finally gives its recommendations on the finished plan to the airport sponsor. The membership of the CAC should be representative of all stakeholders.
In reviewing the master plan, the TAC will evaluate its technical merit, while the CAC will weigh the recommendations against community goals, values, and needs. The committees are advisory, however, and have no decision making power of their own. In establishing these committees, the airport sponsor does not delegate its authority and responsibilities to them. The specific roles of such committees should be clearly defined at the outset and carefully explained at the initial meeting to prevent later misunderstandings. The size of both the TAC and CAC should be kept manageable. In some cases, it may be appropriate to combine the committees into a single group.
The public involvement program should also include a management/policy/oversight committee to advise the planning team on policy decisions that will likely need to be made throughout the study. Committee members would typically include senior airport or airport sponsor staff that have the responsibility for decision making for the airport.
b. Public Information Meetings – Traditional public hearings, where stakeholders are
given the opportunity to make public statements about the study, are not a good forum in which to conduct a continuing discussion of issues and alternatives because of the formal and inflexible nature of such hearings. An “open house” format with interactive information stations staffed by knowledgeable staff or consultants is more informal, yet a very effective method by which to engage the public and stakeholders in soliciting their opinions on development options. A public information meeting using the open house format will permit stakeholders to visit a meeting site at their convenience and visit with
planners on an informal one-on-one basis. A short slideshow or videotape, which all attendees can view upon arrival at the open-house site, may be a useful introduction to the study process. If a more formal meeting is desired, starting with an open house and moving into a more formal forum can be effective.
The number of public information meetings to be held over the course of the study can vary depending on the complexity of the study. It may also be necessary to hold meetings in more than one location to provide adequate geographic coverage for communities affected by the planning proposals. Public information meetings are typically held in the evening to provide most people the opportunity to attend. In some unique conditions, such as with a large elderly population, a day meeting may be needed. Complex projects may require that these meetings be scheduled throughout the day.
c. Small Group Meetings and Briefings – Small group meetings may be held throughout
the study to provide opportunities for detailed discussions of plan alternatives. These informal sessions allow study team members to learn about local concerns. Such meetings may be scheduled with community boards, elected officials, civic organizations, and other interested organizations.
d. Public Awareness Campaign – An effective public awareness campaign is an essential
part of the public involvement program. It is instrumental in generating initial stakeholder involvement, in maintaining stakeholder interest throughout the program, and in keeping the general public informed of the progress of the study.
1) Informational and Educational Materials – Informational materials designed to educate a broad audience about all aspects of the study may be distributed to stakeholders. These materials might include fact sheets, flyers, press releases, newspaper ads, and general information packets. Planners should provide translations of this material if the airport is located in an area where English is not the first language for a large percentage of the residents. A mechanism should be provided for individuals or organizations to add their names to a mailing list to receive these materials.
2) Web Pages – Web pages, with interactive or self-guided presentations, as well as electronic copies of study documents, are increasingly used as part of a public awareness campaign. Planners often link the master plan web page to the airport’s web site.
e. Public involvement programs can place special requirements on an airport planning team.
The team must be sensitive to the interests of stakeholders and have a positive attitude toward their participation in the planning process. The members of the team must also be aware of the extra time and personal effort that will be required, since they will have to meet regularly with the stakeholders at committee and public information meetings.
The same planners who work with the stakeholders at the various stakeholder forums should do the actual planning. Experience shows that planners must gain the confidence of the stakeholders and overcome their initial concerns before any real progress can be
Chapter 4 Public Involvement Program › 405. Documentation Guidelines
achieved. Extensive public involvement from start to finish in the planning process enhances all plans and proposals and satisfies the goals of long-range planning.
403. IDENTIFY THE STAKEHOLDERS
The types of stakeholders will vary at each airport, depending on the size of the airport and the complexity of the planning issues. The following is a list of the general categories of potential stakeholders, from which a list of appropriate participants can be developed:
Users and tenants Groups and individuals from within the sponsor’s organization FAA personnel from the appropriate Regional and Field offices Resource agencies and other governmental units with regulatory or review authority Other interested groups
The individuals from a particular stakeholder group must be able to effectively represent their interests in discussions with the master plan preparation team. Furthermore, they should present the consensus view of the stakeholder group and not a special interest minority opinion. Although planners should make every effort to identify and communicate with all appropriate stakeholders early in the master plan process, it may also be necessary to add stakeholders as the study progresses. They must also be able to take study information back to their group to keep them informed throughout the planning process. Appendix C contains a more detailed list of potential stakeholders.
404. IDENTIFY KEY ISSUES
a. The identification of key issues is an early product of a well-designed public involvement
program. Recall that the pre-planning activities identified in Chapter 3 included establishing which issues are of greatest concern to the airport. The results of that effort are essential in determining the type of study to be completed and in developing the scope of work. These will probably not include all issues that are of concern to each of the stakeholders. Discussions with the stakeholders (through use of the tools and techniques described earlier in this chapter) will help identify a broader set of problems, challenges, and opportunities that should be examined. These key issues will shape policy decisions, influence technical criteria and standards, and help identify development alternatives.
b. Once the key issues are identified, the sponsor may want to modify the study approach to
address any important issues that had not been previously included in the proposed study. Some issues may be raised during this process that are not appropriate to include in the master plan study; these should be addressed outside of the master plan effort. The airport sponsor may establish a separate forum to handle such issues.
405. DOCUMENTATION GUIDELINES
a. Document Key Issues – Accurate documentation of the key issues is essential, because
stakeholders will track how the planning team addresses them throughout the study. Grouping the critical issues into major functional categories, such as facilities, business,
operational, properties, and environmental issues, will help planners understand the stakeholders’ concerns. The documentation should divide issues into those that will be addressed by the master plan study and those that will be addressed in a different forum.
b. Document Public Involvement Program – Documentation of the public involvement
program should appear in an appendix to the Master Plan. Copies of committee rosters, meeting minutes, advertisements, newsletters, and other elements of the Public Awareness Campaign can be placed in an appendix as the official record of the public involvement program. This documentation should be revised regularly over the course of the study rather than being prepared at the end of the process.
This page intentionally left blank.
Chapter 5 Environmental Considerations › 501. General
Chapter 5 Environmental Considerations
501. GENERAL
a. The purpose of considering environmental factors in airport master planning is to help the
sponsor thoroughly evaluate airport development alternatives and to provide information that will help expedite subsequent environmental processing. By using existing maps of the airport area, prior environmental documents, and the Internet, planners and environmental specialists can get an excellent overview of sensitive environmental resources in and around the airport. The planner should understand that the consideration of environmental factors in the evaluation of alternatives should be tailored to each airport’s size, unique setting, and operating environment, and will typically not be as detailed as that in subsequent environmental reviews. The consideration of environmental factors in the planning process will typically result in an inventory (overview) of the airport’s environmental setting, the identification of potential environmental impacts of airport development alternatives, and the identification of environmentally related permits that may be required for recommended development projects.
b. The FAA recommends that the planning process consider the needs of subsequent
environmental review processes. The master plan should include thoroughly supported project justifications and thorough documentation of alternatives that meet the planning need and are reasonable and feasible (environmentally as well as technically); and should note any effects of the airport development alternatives on sensitive environmental resources. Considering environmental factors in master planning provides useful information and planning principles that will help expedite the environmental review of projects.
c. Planners should develop each chapter of the master plan with environmental
considerations in mind. Normally the environmental considerations should not be in a stand-alone chapter, but should be incorporated into the appropriate chapters, such as existing conditions and alternatives development and evaluation.
d. When considering environmental factors in master planning, the planner and
environmental specialist do not need to follow the specific impact categories outlined in FAA Order 5050.4, NEPA Implementing Instructions for Airport Projects. Rather, FAA Order 5050.4 should be consulted as a guide to help planners identify potential environmental impacts specific to the study airport that should be considered as planning continues.
e. During the master plan scoping process, planners and environmental specialists should
attempt to identify key environmental issues that will be involved in analyzing airport development alternatives to ensure that the master plan budget provides enough resources to analyze them. If such early identification is not possible, planners should propose an initial budget for the issues that may be identified during the master planning inventory and data collection process. If additional environmental issues are uncovered later in the planning process, the planner can prepare a separate scope and budget for a more detailed
Chapter 5 Environmental Considerations › 502.
analysis. However, sponsors and planners should be aware that Federal planning grants cannot be amended and the more detailed analysis would need to be accomplished in a separate study.
f. Planners, in consultation with environmental specialists, should consider appropriate
Federal environmental laws and regulations when analyzing proposed airport development alternatives. There are approximately 40 Federal laws, executive orders, and regulations protecting particular parts of the environment, such as the Clean Air, Clean Water, and Endangered Species Acts, and an Executive Order on Protection of Wetlands. There are also many state and local environmental laws and regulations that should be considered in the master planning process.
g. During the master plan scoping process, planners should try to identify any potential
short-term capital development projects that might be recommended in the master plan that are known to trigger additional environmental processing, such as safety related projects. For such projects, the airport sponsor should consider beginning the environmental processing before the master planning process is completed. Otherwise, the various agencies and public involved may perceive that the NEPA analysis is biased because a recommended alternative was selected in the master plan before the NEPA process began. This guidance can be extended to longer-term projects in the case of new airports or major reconfigurations of existing airports.
h. Planners should recognize the need to achieve a balance between the manmade and the
natural environment. Although every proposed development project will have some impact on the natural environment, the use of prudent planning criteria, along with sound environmental data and analysis, will help minimize unavoidable environmental impacts and the delay of project design and construction.
502. ENVIRONMENTAL CONSIDERATIONS IN MASTER PLANNING ALTERNATIVES ANALYSIS
a. In the airport master planning process, the planner, along with an environmental
specialist, should identify potential key environmental impacts of the various airport development alternatives so that those alternatives that avoid or minimize impacts on sensitive resources are considered. The planner should understand that the consideration of environmental factors in the evaluation of alternatives should be tailored to each airport’s size, unique setting, and operating environment, and will typically not be as detailed as that in subsequent environmental reviews. The evaluation of potential environmental impacts should only be done to the level necessary to evaluate and compare how each alternative would involve sensitive environmental resources.
b. Project justifications and the analysis and selection of alternatives, including an
explanation of why certain alternatives were not carried forward, should be completed and documented in the master plan before the NEPA process is started. Only those alternatives that could solve the identified problems and have aeronautical utility should be forwarded for NEPA analysis. (See Appendix E, “Consideration of Environmental Factors in Airport Master Planning,” for additional discussion of this topic.)
c. Environmental factors should be considered during the development and analysis of
airport project alternatives. This evaluation can help an airport sponsor identify a recommended alternative that the FAA may eventually select as its preferred alternative during the NEPA review process. It also facilitates the decision making process the FAA must complete as part of its project approval process.
1) The facility requirements and alternatives analysis chapters of the master plan should provide sufficient documentation regarding the justification for each project so that these chapters may serve as the basis for the purpose and need section of any environmental document.
2) Planners and environmental specialists should identify the potential key environmental impacts of each development project as part of the master plan alternatives analysis. Categories of potential impacts are defined in FAA Order 1050.1, Environmental Impacts: Policies and Procedures and FAA Order 5050.4, FAA Airports guidance for complying with NEPA. A matrix showing each alternative and its potential environmental impacts may be useful for subsequent environmental processing.
3) For some airports, only a few of the environmental impact categories will need to be discussed in the alternatives analysis (such as noise, wetlands, and social impacts), based on location-specific environmental issues identified in the environmental overview. Planners do not need to list each specific impact category mentioned in FAA Order 5050.4, but only those resources the alternatives would likely affect. In many cases, a simple environmental screening will be sufficient to identify those impacts. Detailed impact analyses will be conducted in any Environmental Assessment or Environmental Impact Statement that follow the master plan.
d. Permits that may be needed for each proposed project should be identified in the
alternatives analysis. Although such requirements can vary greatly from state to state and within each locality, some of the permits that are usually necessary include:
Clean Water Act, Section 404 Dredge and Fill Permit Air Quality Permit for on-site batch plants or other construction-related activities Local government construction permits Growth Management Permits United States Fish and Wildlife Service, National Marine Fisheries Service opinions,
or State Wildlife and Game Commission Permits, if protected and endangered species could be impacted Clean Water Act, National Pollution Discharge Elimination System Permits
Chapter 5 Environmental Considerations › 504. Documentation Guidelines
503. FURTHER GUIDANCE ON CONSIDERATION OF ENVIRONMENTAL FACTORS IN AIRPORT MASTER PLANNING
Appendix D, “Consideration of Environmental Factors in Airport Master Planning,” contains recommendations on how to evaluate environmental factors for large or complex projects in airport master planning. It contains a discussion of the interaction of the airport planning and environmental processes and recommendations on how to effectively integrate these processes. The appropriate treatment of environmental factors in airport master planning can make subsequent detailed environmental processing more efficient and speed the completion of airport development. Although Appendix D is primarily intended for large and complex projects, many of the techniques in the guide can be applied to all levels of master planning.
504. DOCUMENTATION GUIDELINES
a. The existing conditions chapter should document the airport’s environmental setting.
The alternatives analysis chapter should document the potential environmental impacts associated with each development project alternative. In addition, the master plan should identify potential Federal, State, and local permits that may be required for each project alternative. Planners, with the help of environmental specialists, should include a matrix in the alternatives analysis chapter of the master plan that lists each development project alternative and its associated potential environmental impacts and required permits. This will be beneficial in subsequent environmental processing.
b. Planners should use appendices for the majority of the technical documentation, such as
noise analysis, wetland mapping, and threatened and endangered species reports to improve the readability and organizational flow of the alternatives analysis chapter.
c. The potential environmental impacts of the proposed airport development alternatives
should be addressed in a candid manner and written so that the public easily understands them.
Chapter 6 Existing Conditions › 603. Inventory and Description of Existing Facilities
1/27/2015 AC 150/5070-6B Change 2
Chapter 6 Existing Conditions
601. GENERAL
a. Most data gathering for a master plan study takes place when planners evaluate existing
conditions. Typical broad categories of information to be collected include: the history of the airport; description and condition of physical facilities on the airport including buildings and airfield pavement; the regional setting of the airport and surrounding land uses; the environmental setting of the airport; socioeconomic and demographic data for the airport service area; historical aviation activity; and airport business affairs.
b. To initiate data collection, planners should carefully review the scope of work and verify
the type and quantity of data needed for subsequent analyses. It is easy to collect information that is not really necessary or to fail to gather critical information needed for later analyses. Planners can avoid these mistakes by carefully reviewing the scope of the study.
c. To avoid unnecessary data gathering, planners should use existing data as much as
possible. Previous master plans, other recent planning studies, and regional planning agencies can provide useful information that should be reviewed before any data gathering begins. However, planners should ensure the validity of the existing data before using them for the master plan study.
602. BACKGROUND SECTION
a. The background section should provide a brief overview of the history of the airport,
describe its aeronautical role in the national aviation system, and identify its role in the community’s infrastructure. Many sponsors periodically assemble information about the economic benefits of their airport, such as employment, direct salaries, and air service, which can be summarized in the background section.
b. Major milestone events in the history of the airport, such as ownership changes,
construction of significant facilities, and the introduction of air service can be identified. A timeline, like that shown in Figure 6-1, may be used to present this information.
603. INVENTORY AND DESCRIPTION OF EXISTING FACILITIES
a. A significant portion of the inventory will be devoted to identifying the existing physical
facilities at the airport. Drawings and other documents in FAA databases and on file with airport management are a good source of data and should be reviewed early in the inventory effort. These data may need to be supplemented with field observations, personal interviews with tenants and users, Internet searches, and surveys of passengers and employees.
Figure 6-1: Timeline of Events
1934 – Airport officially opened
1928 – Original land donation
1937 – First commercial airline flight
1960 – VORTAC installed
1970 – Passenger terminal expanded
1941 – Additional 40 acres donated
1953 – Dedication of new terminal building and ATCT
1975 – New ATCT constructed
1987 – Airport Authority established
1990 – Airport master plan updated
1998 – Terminal expansion began
1998
1975
1934
1934 – Airport officially opened
1928 – Original land donation
1937 – First commercial airline flight
1960 – VORTAC installed
1970 – Passenger terminal expanded
1941 – Additional 40 acres donated
1953 – Dedication of new terminal building and ATCT
1975 – New ATCT constructed
1987 – Airport Authority established
1990 – Airport master plan updated
1998 – Terminal expansion began
1998
1975
1934
b. Classifications that are commonly used to organize this information include the
following:
1) Airfield/Airspace – The functional use and geometry of runways, taxiways, and holding aprons; lighting, marking, and signing of runways and taxiways; navigational aids; visual approach aids, and instrument approach procedures. Information on the use of the airspace and how air traffic is managed should also be collected, including operational limitations resulting from traffic interaction with other airports or reserved airspace, obstructions to air navigation, noise abatement procedures, and airfield or navigational aid shortcomings. Planners should also compile historical data on weather conditions, such as prevailing wind direction and speed, as well as the occurrence of critical combinations of ceiling and visibility. The existence of, and the need for, Remain-Overnight-Parking (RON) should also be determined.
2) Commercial Passenger Terminal Facilities – Inventory of terminal building space by functional use and size: check-in hall/ticket lobby, number of gates, lineal feet of gate frontage, aircraft parking apron area, restaurants and other concession space, and passenger security screening procedures. Surveys conducted in hold rooms are often used to gather information about passenger characteristics that can be useful in determining future facility requirements.
3) General Aviation Facilities – The quantity and type of hangars; transient aircraft parking apron areas, tie-down positions; general aviation terminal facilities; aircraft parking aprons; fixed base operators; flight schools; pilot shops; and the number and mix of based aircraft.
4) Cargo Facilities – The quantity and area of air cargo buildings and aircraft parking aprons. At airports with significant air cargo activity, freight forwarders and other support functions are often located in areas adjacent to the airport. These should be identified on the airport layout plan.
5) Support Facilities – The quantity and type of support facilities at an airport that encompass a broad set of functions that ensure smooth and efficient airport operation, include Aircraft Rescue and Fire Fighting stations, airport administrative areas, airport maintenance facilities, airline maintenance hangars, flight kitchens, aircraft fuel storage, heating and cooling systems, FAA facilities. For airport towers, determine their hours of operation.
6) Access, Circulation and Parking – The quantity and type of ground access systems and commercial areas that serve the airport, or are served by it, such as on-airport access roads, circulation and service roads, parking and curb space, including information on their alignment, condition and capacity. Also include information on public transportation services, such as bus, rail, taxi and limousine, and the split between personal and public transportation. Consultation with state and local transportation agencies responsible for planning and operating surface transportation systems should produce data on proposed highway and transit plans, as well as traffic density statistics relative to surface systems leading to and from the airport. Furthermore, include information on rental car facilities and activity. It may difficult
Chapter 6 Existing Conditions › 604. Describe Regional Setting and Land Use
to obtain information from rental car companies, but rental car facility planning is typically a critical element of planning for the terminal area and parking facilities, even at smaller airports.
7) Utilities – Description of major elements of the infrastructure that service the airport’s utility demands for water, sanitary sewer, communications, heating and cooling, and power. Historical consumption data may be necessary to quantify future utility loads. Storm-water drainage, deicing and industrial waste disposal systems should also be included.
8) Other – Non-aeronautical uses such as recreational facilities and parks, industrial parks, agricultural or grazing leases, and retail businesses.
c. The inventory of existing facilities need not include all the classifications described
above. That list is a general outline that should be modified to conform to the specific circumstances of an individual airport. For example, a general aviation master plan does not need a section on commercial passenger terminal facilities. Similarly, a plan for a large commercial service airport with little general aviation or air cargo activity could include the inventory of those facilities in a subsection describing support facilities.
d. Whatever format is used to describe existing conditions should be followed in subsequent
chapters, using a parallel structure, to describe demand/capacity and determination of facility requirements, identification and evaluation of alternatives, presentations of estimated capital costs, and the airport plans chapter.
e. The inventory of existing conditions at an airport is a critical task in a master plan study
and must be closely managed. Data should be collected only when there is a clear understanding of the need for the information to support the demand/capacity analyses and determination of facility requirements.
604. DESCRIBE REGIONAL SETTING AND LAND USE
a. A master plan study should examine the regional setting of an airport and the land use
patterns around it. This is a critical task, because the impact of airport planning decisions can extend well beyond the airport property line.
b. Collect information on the political boundaries of the airport and the political entities
with jurisdiction over the operation of the airport and adjacent land uses. Identify the airport service area and the presence and role of airports that might compete with the study airport.
c. Collect all applicable documents, such as official maps, the latest area-wide
comprehensive land use and transportation plan, applicable municipal zoning ordinances and other land use controls and unusual building code provisions, including height zoning ordinances, noise overlay zones, and airport overlay districts. The development of practical land use strategies requires an understanding of the political context and local preferences regarding land use.
Chapter 6 Existing Conditions › 605. Environmental Overview
d. Identify the land uses in areas that will be exposed to airport operations. Land use is a
continuously changing process, particularly in urban environments, so the land use inventory should collect information on planned and proposed land uses, as well as on existing uses. Note if there are any governmental programs designed to direct land use patterns in the area under review. For example, if the airport sponsor has completed a noise compatibility-planning program, it should contain valuable information on land use.
e. Identify land uses that may affect the safe operation of the airport or influence its
expansion. Structures that could obstruct air navigation, or the presence of other airports that may interfere with the study airport, are the principal safety concern. Also identify areas located near the airport that may represent a potential hazard to aircraft, such as flood control areas, stockyards, and sanitary landfills.
f. Use geographic information systems (GIS), aerial photographs, topographical maps,
obstruction charts, aeronautical charts, approach plates and other mapping tools to examine and display land use details. Many local governments have comprehensive GIS systems that contain electronic files for land use analysis and zoning.
g. Consider off-airport drainage and flood control issues, which may be affected by airport
development.
605. ENVIRONMENTAL OVERVIEW
a. The principal objective of an environmental overview is to document environmental
conditions that should be considered in the identification and analysis of airport development alternatives. In the past, master plan studies often focused only on the environmental consequences of the recommended development plan. In those cases, much of the environmental overview would be conducted while other technical analyses were already underway and the environmental data would not be considered in the formulation of alternative development concepts. Current practice is to develop the alternatives with the subsequent environmental processes in mind and to consider environmental data in the evaluation of the alternatives. As a result, the master plan may aid in the formation of the purpose and need statements in subsequent environmental documents.
b. Noise levels and air and water quality are the most common environmental concerns.
However, other environmental conditions in and around the airport should also be examined, including: solid waste generation and disposal; toxic material disposal; floodplains and wetlands; endangered and threatened species of flora and fauna; biotic communities; parklands and recreational areas; historic, architectural, archaeological and cultural resources; and prime and unique farmland. Planners should refer to the current version of FAA Order 1050.1, Environmental Impacts: Policies and Procedures, for a complete list of environmental impact categories that may need to be examined. In addition to NEPA requirements, planners should consider appropriate state environmental regulations. Past and current uses of airport property should be examined to identify areas that may be contaminated, including fuel farms, chemical or agricultural aerial application refilling stations, and hangar areas used for various industrial processes such as aircraft maintenance and plating.
Chapter 6 Existing Conditions › 607. Assemble Historical Aviation Activity
AC 150/5070-6B Change 2 1/27/2015
c. Planners should ask local resource agencies to provide any information they think should
be considered in the process of identifying and evaluating alternative development options.
d. Any existing airport noise or environmental programs should be discussed in the
environmental overview.
e. When cost effective, data collected in the environmental inventory can be placed in a GIS
database for better data visualization, communication, and analysis.
606. DEVELOP SOCIOECONOMIC DATA
a. Socioeconomic data serve two purposes in a master plan study: to ascertain the nature of
the community and market the airport serves and/or impacts and to provide specific inputs for the preparation of aviation demand forecasts, particularly econometric demand models.
b. An effective understanding of the community is helpful in ensuring that the planning is
responsive to its long-term needs. Planners should focus on those socioeconomic factors that affect the community’s need for air transportation. For example, an economy based on tourism would have air transportation needs that would be quite different from those of an agricultural region.
c. A vast array of socioeconomic data are available from many different sources, including
a number of commercial vendors; the U.S. Bureau of the Census; metropolitan planning commissions; and state, county, or local agencies. Planners should be careful when using different sources of socioeconomic data to ensure compatibility.
607. ASSEMBLE HISTORICAL AVIATION ACTIVITY
a. The historical data necessary for forecasting aviation demand are generally available in
the records maintained by the airport. At airports with FAA airport traffic control towers, FAA records of operations by commercial service, air taxi, military, and general aviation aircraft and revenue passenger enplanements are available in the Air Traffic Activity Data System (ATADS) on the FAA Policy Office’s data system website at http://www.apo.data.faa.gov/. At airports without control towers, airport records, FAA Form 5010, Airport Master Record, and airport system plan studies are good sources of information.
For commercial service activity, planners should collect data that identify the air carriers; the proportion of operations and enplanements by each; markets served; the number of originating, terminating, and connecting passengers; the proportions of domestic and international passengers; and air cargo activity. It will also be useful to have a breakdown of the fleet mix of aircraft using the airport.
For general aviation activity, planners should collect data that identify the category and class of aircraft, types of fuels those aircraft use, the type of airport services used, and the availability of hangars for tenant and transient aircraft.
1/27/2015 AC 150/5070-6B Change 2
Chapter 6 Existing Conditions › 608. Financial Data
b. Master plans for large airports often involve the use of computer simulation models. For
an airfield simulation, planners will need a detailed schedule of arrival and departure times for all commercial operations. Records for average or peak days can often be obtained from airport tower records, radar tapes, or noise monitoring systems. Commercial vendors such as the Official Airline Guide can also be helpful. For terminal and landside simulations, planners will need the passenger flow volumes in each terminal associated with the aircraft schedules.
608. FINANCIAL DATA
Airport master planners must examine an airport’s financial resources, including its basic business model, operating revenues and expenses, and sources and uses of capital funds.
a. Airport Business Model – Summarize the airport’s basic business model to help
planners organize the vast amount of financial data available at most airports. The business model summary should describe the financial operations of the airport, including how its costs and revenues are charged or credited to airport users and how any operational surplus or deficit is handled. In addition, the business model summary should outline how the airport typically funds capital projects (i.e., with AIP and other grants, Passenger Facility Charges, airport revenue bonds, and so forth). If the airport sponsor owns and operates a multi-airport system, the business model summary should discuss how the financials for the study airport are addressed in relation to the whole airport system.
b. Operating Revenues and Expenses – Summarize broad categories of operating
revenues and expenses. The FAA requires all commercial service airports to submit financial information to the FAA annually on FAA Form 127 and these reports may provide a good starting point. Airport managers often divide operating revenues into airline revenues and non-airline revenues. Non-airline revenues are often subdivided into categories such as terminal concessions; rental car; parking; hangar, land, and other rentals; other; and tax revenues. Operating expenses are often divided into broad categories such as personnel, maintenance, utilities and supplies, other, and debt service.
c. Capital Funding – Summarize the airport’s ongoing capital improvement program and
how it funds its capital development program. The capital improvement program can be funded from many sources, including revenues from the airlines, concessionaires, other airport tenants, tax levies (if applicable), passenger facility charges, AIP grants, other federal and state grants-in-aid, and airport revenue bond proceeds.
The financial feasibility of the capital improvement program will be determined largely by the magnitude and reasonableness of the charges, rents, and taxes paid by airport users, tenants, and others. The information collected in this inventory will be used to prepare a financial plan for the recommended development program.
Much of the information discussed in the preceding paragraphs relates primarily to the financial data for commercial service airports and larger general aviation airports. Many
Chapter 6 Existing Conditions › 609. Documentation Guidelines
smaller general aviation airports will not have such data readily available; however, such information may be part of the financial records of the sponsor.
609. DOCUMENTATION GUIDELINES
a. The documentation of existing airport conditions should make liberal use of drawings,
tables, aerial photographs, and exhibits produced from geographic information system databases. Presented in this manner, such information is easy to understand, interpret, and locate for later reference.
b. Planners do not need to include all collected information in the report. Some should
simply remain in work files until needed to support the technical analyses.
Chapter 7 Aviation Forecasts › 701. General
Chapter 7 Aviation Forecasts
701. GENERAL
a. Purpose of Aviation Forecasts – Forecasts of future levels of aviation activity are the
basis for effective decisions in airport planning. These projections are used to determine the need for new or expanded facilities. In general, forecasts should be realistic, based upon the latest available data, be supported by information in the study, and provide an adequate justification for airport planning and development. Any activity that could potentially create a facility need should be included in the forecast.
Planners should prepare a reliable activity baseline, select an appropriate forecast methodology, develop a forecast, compare it to other forecasts for reasonableness, and submit the forecasts to the FAA for approval. The planning agency should use appropriate statistical techniques to estimate activity where actual operations counts are not available.
Figure 7-1: Sample of FAA Forecast Graphs
Source: FAA Aerospace Forecasts, Fiscal Years 2005-2016, U.S. Department of Transportation, Federal Aviation Administration, Office of Aviation Policy & Plans, March 2005
U.S. REGIONAL/COMMUTER INTERNATIONAL ENPLANEMENTS
0
1 2
3 4
5 6
7 8
9
96 98 00 02 04 06 08 10 12 14 16
Fiscal Year
Passengers (Mil)
U.S. REGIONAL/COMMUTER SYSTEM ENPLANEMENTS 2004-2016
3.9
9.9
15.4
18.7
3.9
9.3
13.7
18.9
0
5
10
15
20
2004 2005 2006 2007-16 Year
ANNUAL PERCENT
GROWTH
FY CY
U.S. REGIONAL/COMMUTER INTERNATIONAL ENPLANEMENTS
0
1 2
3 4
5 6
7 8
9
96 98 00 02 04 06 08 10 12 14 16
Fiscal Year
Passengers (Mil)
U.S. REGIONAL/COMMUTER SYSTEM ENPLANEMENTS 2004-2016
3.9
9.9
15.4
18.7
3.9
9.3
13.7
18.9
0
5
10
15
20
2004 2005 2006 2007-16 Year
ANNUAL PERCENT
GROWTH
FY CY
Chapter 7 Aviation Forecasts › 702. Forecast Elements
b. Level of Forecast Effort – The level of effort required to produce a planning forecast
will vary significantly from airport to airport. Considerable effort, including the use of elaborate forecasting tools and techniques, may be warranted in the case of more complex projects. An existing forecast, on the other hand, may be all that is required for simpler projects. Planners should determine the appropriate level of forecasting effort in the course of pre-planning and scoping the study.
A number of forecasts are readily available for use in developing and evaluating the master plan forecast. These include the Terminal Area Forecast (TAF), state aviation system plans, and other planning efforts.
c. Use of the Forecasts – Prior to use in the master plan, the proposed forecasts must be
submitted to the FAA for review and approval. Once approved, the forecasts may be used to provide an initial timetable for facility improvements, as a basis for the development of alternatives to meet the projected demand, and as a basis for environmental analyses and economic and financial plans
702. FORECAST ELEMENTS
a. Types of Aviation Activity – To establish the demands likely to be placed on airport
facilities, forecasts should include all relevant aviation demand elements, including both the type and level of aviation activity expected at the airport over the planning horizon. The specific activity elements to be forecast will vary depending on the size and category of an airport and the objectives of the master plan study. Planners should note if the forecast projects the introduction of jet aircraft at the study airport, since this will be important to the future environmental review process.
Aviation demand forecasts typically include aircraft operations and identify the critical aircraft. Forecasts for commercial service airports will also include, at a minimum, passenger enplanements, while forecasts for general aviation airports will include the number and type of based aircraft. The aviation demand elements to be forecast are shown below in Figure 7-2.
Chapter 7 Aviation Forecasts › 703. Factors Affecting Aviation Activity
Figure 7-2: Aviation Demand Elements
Required Included Where Appropriate Operations (annual) Itinerant Air Carrier Air Taxi and Commuter (Regional) General Aviation Military Local General Aviation Military
Domestic vs. International Annual Instrument Approaches IFR vs. VFR Operations Air Cargo Aircraft Operations Touch and Go Operations (Training) Helicopter Operations Average Load Factor Fuel Use
Passengers (annual) Enplanements Air Carrier Commuter Enplanements Originating Connecting
Passenger and Cargo Data Domestic vs. International General Aviation Passengers Helicopter Air Taxi Other Number of Student Pilots Number of Hours Flown Aircraft Based Aircraft Aircraft Mix Critical Aircraft
Average Seats/Aircraft
b. Term of Aviation Forecasts – Prepare forecasts for short-, medium- and long-term
periods and specify the existing and future critical aircraft. Short-term forecasts, for up to five years, are used to justify near-term development and support operational planning and environmental improvement programs. Medium-term forecasts (a 6- to 10-year time frame) are typically used in planning capital improvements and long-term forecasts (beyond 10 years) are helpful in general planning.
c. Peak Period Forecasts – Forecasts of annual aircraft operations or passenger activity
may not adequately describe the needs of individual airport facilities. Because they average demand levels over the course of an entire year, annual metrics are only useful when activity tends to be evenly distributed over the hours, days, and months of a particular airport facility’s operation. However, most airports have peak periods where demand far surpasses those averages. Stresses arising from activity peaks are critical at commercial service airports serving as hubs or that have substantial international traffic. Master plan forecasts must include appropriately defined peak period activity levels for facilities planning, such as terminal buildings and ground access systems.
703. FACTORS AFFECTING AVIATION ACTIVITY
Planners preparing forecasts of demand or updating existing forecasts should consider socioeconomic data, demographics, disposable income, geographic attributes, and external factors such as fuel costs and local attitudes towards aviation.
a. Economic Characteristics – The economic characteristics of a community will affect
the demand for air traffic. In addition to national and regional economic activity, these include specific, identifiable, local activities that distinguish the geographic area served by the airport. The type of industry in an airport’s service area also will affect aviation demand, with manufacturing and service industries tending to generate more aviation activity than resource industries such as mining.
b. Demographic Characteristics – The demographic characteristics of an area’s population
also affect the demand for aviation services. Demographic characteristics influence the level, composition, and growth of both local traffic and traffic from other areas. Factors such as leisure time and recreational activity are important in estimating activity, but can be difficult to measure. Another important demographic characteristic is the level of disposable income, usually measured on a per capita basis, which is a good indicator of the propensity to travel and general aviation aircraft purchases and use.
c. Geographic Attributes – The geographic distances between populations and centers of
commerce within the airport’s service area may have a direct bearing on the type and level of transportation demand. The existence of populations and centers of commerce beyond an airport’s service area may indicate the need for additional airports that serve transportation demand. The physical characteristics of the area and the local climate may also be important, since they may stimulate holiday traffic and tourism. The role of the airport within the airport system and its relationship to other airports may also have an effect on the services that are demanded at the airport.
d. Aviation-related Factors – Business activity, changes in the aviation industry, and local
aviation actions can markedly affect the demand for airport services. Business developments in the airline industry, such as consolidations, mergers, and new marketing agreements, can affect airline operations at a particular airport, while fractional ownership can affect others. Wider industry trends, such as the introduction of new lowfare service, the introduction of new classes of aircraft, and the growth or curtailment of airline hubbing, may also alter the level and pattern of demand. To the extent that such actions affect all aviation activity in a region or the country, their effects will be captured in the FAA’s forecasts. If, however, only the demand at a particular airport is affected, appropriate adjustments should be made in that airport’s forecast. Actions taken by local airport authorities, such as changes in user charges, ground access policies or their support services can also stimulate or hinder the demand for airport services. Investment decisions made as a result of the planning process itself can also produce change by removing physical constraints to airport growth, which should be reflected in the forecasts.
e. Other Factors – External factors may also influence the demand for airport services.
These include economic actions such as fuel price changes, availability of aviation fuels, currency restrictions, and changes in the level and type of aviation taxes. Political developments, including rising international tensions, changes in the regulatory environment, and shifting attitudes toward the environmental impacts of aviation, may also impact future demand and should be considered in developing or updating airport forecasts.
Chapter 7 Aviation Forecasts › 704. Steps in the Forecast Process
704. STEPS IN THE FORECAST PROCESS
The forecast process for airport master plan studies consists of a series of basic steps that may vary from airport to airport, depending on the issues to be addressed and the level of effort required to develop the forecast. Steps in this process include the identification of parameters and measures to forecast, review of previous forecasts, determination of data needs, identification of data sources, collection of the data, selection of the forecast methods, preparation of the forecasts, and evaluation and documentation of the results.
Planners should refer to a report prepared by the FAA’s Office of Aviation Policy and Plans (APO-110), Forecasting Aviation Activity by Airport, dated July 2001, to help them determine what approach to use. That report can be accessed at http://www.faa.gov/data_research/aviation_data_statistics/. The APO data systems web site, at http://www.apo.data.faa.gov, provides historical traffic counts, forecasts of aviation activity, and delay statistics. The forecast process can be summarized as follows:
a. Identify Aviation Activity Measures – The aviation activity measures that planners
need to forecast are the level and type of activities that are likely to affect facility needs. For airfield planning, the most important activities are aircraft operations and the fleet mix, since these define the runway and taxiway requirements. As a general rule, plans for general aviation airports require forecasts of aircraft operations and based aircraft. Airports with commercial service require forecasts of aircraft operations, fleet mix, and passenger enplanements. Passenger levels are particularly important, since they determine the size of the terminal building and other important elements of airport infrastructure such as parking facilities and access roads. Planners should forecast instrument operations and instrument approaches, since these data will be needed if they expect to add or upgrade navigational aids and instrument landing systems. For some airports, additional forecast elements may be required, including peak hour operations and peak hour passenger flows.
b. Review Previous Airport Forecasts – Planners should review the latest published FAA
Terminal Area Forecast for the study airport and any forecasts from an earlier master plan. Contact regional planning bodies and state aviation agencies to determine whether they have conducted airport system planning studies that included forecasts of demand for the study airport.
c. Gather Data – Determine what data are required to prepare the forecasts, identify the
data sources, and collect historical and forecast data. What data to gather, and for what time period, will depend not only on the parameters to be forecast but also on what data are available from previous airport forecasts. In some cases, it may be necessary to conduct additional activity counts.
d. Select Forecast Methods – There are several appropriate methodologies and techniques
for forecasting aviation activity at a specific airport. The selection and application of appropriate methodologies and techniques requires professional judgment. A forecast effort may involve a number of different techniques. The FAA report referenced above provides a detailed discussion of several forecasting techniques. The most common techniques include the following:
1) Regression Analysis – A statistical technique that ties aviation demand (dependent variables), such as enplanements, to economic measures (independent variables), such as population and income. Regression analysis should be restricted to relatively simple models with independent variables for which reliable forecasts are available.
2) Trend Analysis and Extrapolation – Typically uses the historical pattern of an activity and projects this trend into the future. This approach is useful where unusual local conditions differentiate the study airport from other airports in the region.
3) Market Share Analysis or Ratio Analysis – This technique assumes a top-down relationship between national, regional, and local forecasts. Local forecasts are a market share (percentage) of regional forecasts, which are a market share (percentage) of national forecasts. Historical market shares are calculated and used as a basis for projecting future market shares. This type of forecast is useful when the activity to be forecast has a constant share of a larger aggregate forecast.
4) Smoothing – A statistical technique applied to historical data, giving greater weight to the latest trend and conditions at the airport; it can be effective in generating shortterm forecasts.
e. Apply Forecast Methods and Evaluate Results – After the list of activities to forecast
has been identified, the appropriate forecast methods have been selected, and necessary data have been assembled, the actual forecasts can be prepared. If several methods are used to project specific aviation activities, they will probably produce different estimates. Therefore, an evaluation of the reasonableness of the results and their consistency with other forecasts should be conducted.
A useful procedure in such an evaluation is to prepare a time line showing both forecast results and historical trends. Similarly, one might compare the history and forecast for the airport with the FAA national history and forecast for the same activity parameter. If the comparison of the growth rates shows a significant difference, the planners must be able to explain it. Forecast results may also be evaluated by comparing them with other forecasts prepared for the airport, such as those contained in state or regional aviation system plans. One might also review the operational factors and events implicit in the forecast to determine if differing assumptions regarding those factors have affected the forecast results. For example, a constraint on operations associated with runway and apron limitations at the airport could affect the results. Therefore, it is useful to evaluate forecasts both with these constraints and with the constraints removed, i.e., a constrained and an unconstrained forecast.
If demand levels are likely to be particularly sensitive to one or more factors, the planner should estimate the impact of reasonable changes in the underlying assumptions about those factors. For example, if expected growth in aircraft operations is highly dependent on the continued operation of a fixed base operator (FBO) and there is a reasonable possibility that the FBO will close, the planner should estimate how much that closing would change the predicted demand. The planner should also examine general aviation hangar activity, including the airport hangar waiting list, and estimate how much increased hangar space would change predicted demand.
If the timing of important demand-generating factors (specific local or national events or activities resulting in an increased demand for aviation services) is uncertain, the forecaster can construct a time line showing the period of uncertainty, during which demand constraints or the diversion of traffic to another airport may be needed. In this respect, the actual number of operations or enplanements in any specific future year is less important than the certainty that a particular threshold will be reached during the planning period. This approach acknowledges that demand is expected to exceed the airport’s capacity, but that there is a range of time (with a range of forecast error costs, i.e., costs in terms of delays and reduced service levels as a result of airport capacity not keeping up with aviation demand because of forecast inaccuracy) during which this problem needs to be considered.