ORDER 6750.36
SITE SURVEY, SELECTION, AND ENGINEERING DOCUMENTATION FOR INSTRUMENT LANDING SYSTEMS AND ANCILLARY AIDS
11/25/77
DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION
Distribution: W - SELECT; RAF/AT/FS/AS/PL-3; RLG/BU-2; Initiated By: AOP-400 (FORMERLY AAF-560) CAE/AY/DE-3; FAF-2/3 (Minimum); FAS-1 (Minimum)
RECORD OF CHANGES
RECORD OF CHANGES
DIRECTIVE NO. 6750.36
OPTIONAL
CHANGE SUPPLEMENTS TO BASIC
CHANGE TO BASIC
SUPPLEMENTS OPTIONAL
11/25/77 6750.36
FOREWORD
1. PURPOSE. This document is provided as a guide to engineering personnel engaged in the site survey, selection, and engineering documentation of instrument landing systems (ILS) and ancillary aids. Sufficient information supplemented with typical drawings is provided to enable the engineer to perform the site survey and prepare reports and drawings necessary. for selecting and establishing Category I and Category II ILS.
SUPPLEMENTS OPTIONAL
2. DISTRIBUTION. This order is distributed to selected offices in the Airway Facilities, Air Traffic, Flight Standards, Logistics, and Systems Research and. Development Services and the Offices of Airports Programs, Budget, and Environmental Quality in Washington headquarters; to branch level in the regional Airway Facilities, Air Traffic, Flight Standards, and Airports divisions and Planning staffs; to division level in the regional Budget and Logistics divisions; to branch level in the Airway Engineering Support Division, FAA Academy, and FAA Depot at the Aeronautical Center; and to all Airway Facilities sectors and Airports district offices.
3. BACKGROUND. Recent agency experience with ILS site surveys has highlighted the need for comprehensive guidance for the site survey, selection, and engineering documentation for ILS and ancillary aids. The agency expertise has been unavailable to newer FAA employees as well as to site survey contractors. Technical continuity, a greater degree of uniformity among the various regions, and significant cost economies in all facets of ILS establishment are needed. With the considerable input and invaluable assistance of many individuals oth in the Washington headquarters and the regions, such a document has been prepared." It is designed to focus diverse elements into a common purpose and standardize them to levels that will enhance technical performance.
4. APPLICATION. This document is to be used as a companion document with Order 6750.16A, Siting Criteria for Instrument Landing Systems, to assist the plant engineering organization involved with the site survey, selection, and documentation of ILS systems.
5. IMPLEMENTATION. The basic requirements for the site survey, selection, and engineering documentation for ILS and ancillary aids, as presented herein, are applicable FAA-wide. However, there are many approaches, methods, and techniques that are and can be employed successfully to achieve the same goals - the effective, efficient, timely, economical, and safe establishment of ILS and ancillary aids. There are significant differences in regional organizations and the distribution of responsibilities, which impact significantly on how such projects are accomplished. Thus, to derive maximum benefit from using this document in dayto-day activities, it is imperative that each region develop
Par 1 Page i
6750.36 11/25/77
implementation instructions to reflect its own policies, practices, and procedures - either as a formal supplement to this directive or as a companion document. Such implementation guidance should be published within i20 days of the issuance of this order and should include, but not be limited to, delineation of the following:
a. Organizational responsibilities within the regional Airway Facilities division for the planning, programming, siting, engineering, establishment, and coordination activities described herein. This includes those involving the project engineer and site survey engineer as defined in paragraph 8.
b. Interface responsibilities of the regional Airway Facilities division, and the regional Airports, Air Traffic, Budget, Flight Standards, and Logistics divisions and Planning staff.
c. Coordination responsibilities between the regional Airway Facilities diyision and Airway Facilities sectors, Airports District offices, airport traffic control towers, and Flight Standards field offices, and the airport sponsor.
d. Feasibility study concept, including the nature, timing, regional/ local participation, documentation of findings, and management concurrences.
e. Site survey accomplishment via FAA personnel and/or via contracting for limited scope engineering services or for the complete survey and documentation. This includes the preparation of the proper written guidance defining the work requirements.
f. Site survey report, including format, content, coordination, and management concurrences.
g. Authorization for and/or restriction on site survey engineers to conduct discussions with airport sponsors, utility companies, and property owners.
h. Airport obstruction survey responsibilities, including its accomplishment, verification, and validation plus the resultant removal of penetrations to the applicable obstruction surfaces.
i. Maximum practicable use of national standard drawings and specifications issued by the Airway Facilities Service to enable FAA-wide uniformity compatible with site technical requirements and local cost economies.
Page ii Par 5
11/25/77 6750.36
6. DIRECTIVE VERBS. The material in this order contains FAA criteria, policy statements, recommended practices, and other guidance material that require the use of certain directive verbs such as SHALL, SHOULD, WILL, and MAY. In this order,'the explicit meaning of these verbs is as follows:
a. SHALL - The action is mandatory. For example: "The glide slope antenna SHALL be sited in accordance with Order 6750.16A."
b. SHOULD - The action is desirable or recommended. For example: "When a runway has been designated and authorized for the establishment of an ILS, the project engineering SHOULD commence promptly."
c. WILL - The action is to be taken in the future. For example: "A DME WILL usually be planned where an outer marker facility is not practical."
d. MAY - The action is permissible. For example: "In some areas, particularly where property is very valuable or property lines are ill defined, it MAY be desirable to use a registered land surveyor to perform plot surveys for markers."
Nanen C. Director, Airway Facilities Service WARREN C. SHARP Shap
Par 6 Page iii (and iv)
11/25/77
TABLE OF CONTENTS
TABLE OF CONTENTS
CHAPTER 1. GENERAL INFORMATION.
1. Introduction. 2. General. 3. Emphasis.
Page No.
1
1 1 1
Figure 1-1. Typical ILS Facilities Placement.
4.
2 3
Abbreviations, Acronyms, and Publication References.
5.
3
Relationship with Other ILS Siting Documents.
6. Responsibilities. 7. Technical References.
3 6 6
8. Project Engineer Versus Site Survey Engineer.
9.-20. RESERVED.
CHAPTER 2. ILS PROGRAMMING AND PLANNING.
21. General. 22. Feasibility Study. 23. Feasibility Report. 24. Budget Estimate. 25. Initial Concurrence. 26. Project Authorization (PA). 27. Sponsor Notification. 28. A-95 Review Process. 29.-40. RESERVED.
CHAPTER 3. PROJECT ENGINEERING.
41. General. 42. Scheduling. 43. Project File Data. 44. Accomplishment of Site Survey.
6
21
21 21 25 25 26 26 26 26 27
41
41 41 41 42
Figure 3-1. Methods Used for Performing ILS
Site Survey.
44
45. Technical and Administrative Requirements for
45. Technical and Administrative Requirements for
Site Surveys.
45
46. Contracted ILS Site Survey Services (Specialized).
47.-60. RESERVED.
CHAPTER 4. OFFICE PLANNING.
61. General. 62. Obtaining Maps and Drawings. 63. Plotting Potential Sites. 64. Field Liaison. Figure 4-1. Vertical Sketch of Localizer Antenna Height Requirements.
52 56
71
71 71 74 75
76
Page v
65. Airport Development Aid Program (ADAP). 66.Environmental. 67.-80. RESERVED.
CHAPTER 5. FIELD SURVEY.
SECTION 1. INTRODUCTION. 81. Factors to Consider. 82. Personnel Liaison. 83. Local Maps and Drawings. 84. Cursory Inspection of Potential ILS Sites. 85.-90. RESERVED.
SECTION 2. GENERAL ILS SITE SURVEY REQUIREMENTS.
11/25/77
Page No.
77 77 77
91
91 91 91 92 92 93
101
91. Determination of Coordinates, Distances, and
91. Determination of Coordinates, Distances, and
Elevations.
101
Table 5-1. Length of a Second of Longitude.
103 105
Figure 5-l. Correction for Earth Curvature.
92. Real Estate Considerations.
106
Figure 5-2. Sample of Earth Curvature Correction
at Outer Marker. 93. Electrical Power and Cables. 94.
107 108 112
Access Roads, Turnarounds, and Parking Areas.
95. Monitor and Control Cables. 96. Fencing and Security. 97. Investigation of Soil Conditions. 98. Environmental Information. 99. General Construction Considerations. 100. Frequency Interference Survey. 101. Obstructions. 102. Determination of Runway Threshold. 103. Multiple Ownership and Joint-Use Runways. Figure 5-3. Precision Instrument Runway Obstruction Surfaces. 104. Year-Round Site Conditions. 105. Use of Photographs. 106.-120. RESERVED.
SECTION 3. DETAILED ILS SITE SURVEY REQUIREMENTS.
SUBSECTION 1. LOCALIZER. 121. Factors to be Considered. 122. Types of Localizer Antennas. 123. Localizer Antenna Location. 124. Elevation of Localizer Antenna. 125. DME Collocated with Localizer. 126. Location of Equipment Shelter(s). 127. Obstruction Criteria.
Page vi
114 114 115 116 118 119 120 120 120
121 122 122 122
131
131 131 132 133 134 135 135 135
11/25/77
128. Typical Localizer Plot Sizes and Layouts. 129. Electrical Power and Cable. 130. Access Roads, Turnarounds, and Parking Areas. 131. Monitoring. 132. Remote Control. 133. Far Field Monitor (FFM). 134. Ground Checkpoints 135.-150. RESERVED.
SUBSECTION 2. GLIDE SLOPE. 151. Factors to be Considered. 152. Types of Glide Slopes. Figure 5-4. Typical Glide Slope Siting Conditions. 153. Determination of Site Location. 154. Field Survey. Figure 5-5. Glide Slope Survey Area. 155. Special Survey Work for Computer Modeling. 156. Monitor Detector. 157. Ground Matting. 158. Typical Glide Slope Plot Sizes and Layouts. 159. Electrical Power and Cable. 160. Access Roads, Turnarounds, and Parking Areas. 161. Monitoring. 162. Remote Control. 163.-180.RESERVED.
SUBSECTION 3. MARKER BEACONS. 181. General. Figure 5-6. Optimum Middle Marker Location. Figure 5-7. Optimum Inner Marker Location 182. Factors to be Considered. 183. Examination of Search Area. Figure 5-8. Outer Marker Search Area and Location Tolerance of Desired Point. Figure 5-9. Middle Marker Location Tolerance of Desired Point. 184. Location Survey of Markers. Figure 5-10. Inner Marker Location Tolerance of Desired Point. 185. Elevation of Markers. 186. Real Estate Considerations. 187. Typical Plot Size and Layout. 188. Electrical Power and Cables. 189. Access Roads, Turnarounds, and Parking Areas. 190. Monitoring.
Page No.
136 136 136 136 136 136 137 137
151 151 152
153 154 155 156 157 157 158 158 158 158 158 159 159
171 171 172 172 173 173
175
175 176
177 177 177 177 178 178 178
Page vii
191. Remote Control. 192. Fencing and Security. 193.-210. RESERVED.
SUBSECTION 4. ANCILLARY AIDS.
11/25/77
Page No.
178 178 178
191
211. Compass Locators (COMLO) and Nondirectional
Beacons (NDB).
191
Figure 5-ll. Typical Layout for DME at Mark
Id Localizer. 212. Distance Measuring Equipment (DME). 213.-220. RESERVED.
SECTION 4. REVIEW OF FIELD DATA. 221. Data Evaluation. 222. Field Drawings. 223. Examination of Problem Areas. 224. Field Data Checklist. 225. Field Notes. 226.1 Program Changes.
192 193 193
201 201 201 202 203 203 204 204
227. Contracted Survey and Consulting Services.
228.-240. RESERVED.
CHAPTER 6. SITE FINALIZATION.
SECTION 1. PRELIMINARY FINDINGS. 241. Analysis of Data. 242. Discussions Within the Regional Office. 243. Discussions with Non-FAA Officials. 244.
204
211
211 211 211 211
Discussions with FAA Personnel Associated with
Airport. 245.-250. RESERVED.
SECTION 2. SITE SURVEY REPORT. 251. General. 252. Site Survey Report Content. 253.-260. RESERVED.
SECTION 3. REVIEW OF SITE SURVEY REPORT. 261. Regional Coordination. 262. Review Cycle. 263. Feedback for Required Changes. 264.
212 212
221 221 221 226
231 231 231 231
Reporting of ILS Data to the National Flight
Data Center (NFDC). 265.-270. RESERVED.
Page viii
231 231
11/25/77
CHAPTER 7. SITE CONSTRUCTION DRAWINGS.
SECTION 1. DRAWING STANDARDS AND SELECTION. 271. FAA-STD-002. 272. Selection of Drawings for Construction. 273.-280. RESERVED.
SECTION 2. SITE DRAWINGS. 281. Genera1. 282. General Drawing Practices. 283. General Plan Drawing. 284. Localizer Site Drawings. 285. Glide Slope Site Drawings. 286. Marker Beacon Site Drawings. 287. Electrical Power Drawings. 288. Property Description Drawings. 289. Obstruction Drawing. 290. COMLO/NDB Site Drawings. 291. DME Site Drawings. 292.-300. RESERVED.
SECTION 3. NATIONAL STANDARD DRAWINGS/SPECIFICATIONS. 301. General. 302. National Standard Drawings. 303. National Standard Specifications. 304.-310. RESERVED.
SECTION 4. REGIONAL SITE ADAPTATION. 311. Site Construction Drawings and Specifications. 312. New Construction Drawings. 313.-320. RESERVED.
CHAPTER 8. ENVIRONMENTAL CONSIDERATIONS WHEN PLANNING ILS FACILITIES.
SECTION 1. THE SITE SURVEY ENGINEER'S ROLE IN THE ENVIRONMENTAL ASSESSMENT PROCESS. 321. General. 322. Collecting Environmental Data. 323. Excepted Projects. 324.-330. RESERVED.
Page No.
241
241 241 241 241
251 251 251 252 253 254 256 258 258 259 259 259 259
271 271 271 272 272
281 281 281 282
291
291 291 291 292 293
SECTION 2. PREPARATION OF THE ENVIRONMENTAL ASSESSMENT.
331. General. 332. Initiation of Environmental Assessment. 333.
301 301 301
Preparation of an Environmental Impact Assess-
ment Report by a Non-Federal Entity. 334.1 Proposed Outline for Environmental Assessment.
301 301
Page ix
11/25/77
Page/Drawing No.
APPENDIX 1. GLOSSARY OF ABBREVIATIONS AND ACRONYMS (5 Pages) APPENDIX 2. APPLICABLE FAA DOCUMENTS (3 Pages) APPENDIX 3. TECHNICAL REFERENCES (1 Page) APPENDIX 4. ILS PROJECT DATA CHECKLIST (52 Pages) APPENDIX 5. SAMPLE FIELD WORK ORDER (4 Pages) APPENDIX 6. SITE CONSTRUCTION DRAWINGS (7 Drawings) CN-D-0001 General Plan CN-D-0002 Localizer Vicinity Sketch CN-D-0003 Localizer Plot Plan CN-D-0004 Glide Slope Vicinity Sketch CN-D-0005 Glide Slope Plot Plan CN-D-0006 Middle Marker Vicinity Sketch and Plot Plan CN-D-0007 COMLO/Outer Marker Vicinity Sketch and Plot Plan APPENDIX 7. SAMPLE SITE SURVEY REPORT (17 Pages) APPENDIX 8. ILS EQUIPMENT REQUIREMENTS (3 Pages; 2 Drawings) Figure 1. Category I and II ILS Equipment Requirements Figure 2. ILS Equipment Construction Requirements APPENDIX 9. PREPARATION OF PLOT DESCRIPTIONS (2 Pages) APPENDIX 10. INSTALLATION OF UTILITIES IN A HIGHWAY RIGHT-OF-WAY (2 Pages) APPENDIX 11. ILS SURVEYING DATA (2 Drawings) APPENDIX 12. GLIDE SLOPE SITING CALCULATIONS (7 Pages) Figure 1. Example for Glide Slope Lateral Distance Figure 2. Determination of Glide Angle Correction for Sloping Terrain Figure 3. TCH Computed from Crown of Runway Elevation Figure 4. TCH Computed from Ground Elevation at Antenna Figure 5. Typical Near Field Monitor Layout Table 1. Antenna Heights for Null Reference System APPENDIX 13. INDEX OF NATIONAL STANDARD CONSTRUCTION DRAWINGS (1 Drawing) APPENDIX 14. SAMPLE FIELD NOTEBOOK (3 Pages) Figure 1. OM Field Survey APPENDIX 15. SAMPLE PROCUREMENT REQUEST (POWER SERVICE) (2 Pages) APPENDIX 16. REPORTING OF ILS DATA TO THE NATIONAL FLIGHT DATA CENTER (NFDC) (5 Pages) Figure 1. Instrument Landing System Data
Page x
1 1 1 1 1 1 1 2 3 4 5
6
7 1 1
1
1 1
1 1 1
2
2
5
5 7
3
1 1 1
1
1 5
11/25/77
Page/Drawing No.
APPENDIX 17. TYPICAL A-95 NOTIFICATION DATA SHEET APPENDIX 18. INSTRUMENT LANDING SYSTEM DESCRIPTION
APPENDIX 17. TYPICAL A-95 NOTIFICATION DATA SHEET APPENDIX 18. INSTRUMENT LANDING SYSTEM DESCRIPTION
(1 Page)
(3 Pages)
1
1
Page xi
11/25/77 6750.36
CHAPTER 1. GENERAL INFORMATION
1. INTRODUCTION.
a. The instrument landing system (ILS) provides guidance to pilots of properly equipped aircraft, which assists them in landing safely under conditions of reduced ceilings and lowered visibility. The ILS consists of a localizer (LOC), providing lateral guidance along the approach runway centerline extended; a glide slope (GS), providing vertical guidance along the approach path; and marker beacons (MKR), indicating approximate distances of the approaching aircraft from the runway threshold. Figure 1-1 indicates a typical layout of an ILS.
CHAPTER 1. GENERAL INFORMATION
b. Instrument landing systems are categorized according to the minimum visibility and ceiling conditions in which aircraft landings are permissible. Category I ILS provides guidance for minimums of approximately one-half mile visibility (or 2,400 feet runway visual range (RVR) and 200-foot ceiling; in conjunction with other navigational aids, the minimums may be further reduced to 1,800 feet RVR. Category II ILS provides guidance for minimums of approximately onequarter mile visibility (or 1,200 feet RVR) and 100-foot ceiling. Category III ILS systems are designed for minimums approaching zero visibility and ceiling. There are intermediate steps for various combinations of navigational aids and airport configurations.
c. Additional navigational aids, which are sometimes used with the ILS, are nondirectional beacons (NDB) (such as the compass locator (COMLO), distance measuring equipment (DME) (usually located at ·the localizer site), and the various approach lighting systems (ALS).
2. GENERAL. This order sets forth validated techniques, methods, and procedures for use by FAA personnel and/or FAA contractors engaged in the site survey, selection, and construction of an ILS and its ancillary aids. Particular attention is devoted to conducting efficient, effective, and economical in-office and onsite survey activities. National standardization in this area will better enable site survey engineers to present data collected in the office and in the field in a fashion suitable for FAA management to make appropriate decisions, and to develop a completely detailed site drawing and specification package that can be used for competitive bidding and construction purposes.
3. EMPHASIS. This publication contains information that:
a. Is primarily directed to civil, architectural, structural, mechanical, electrical, electronics, environmental, and land acquisition aspects of an ILS establishment.
Chap 1 Par 1 Page 1
6750.36 11/25/77
FIGURE 1-1. TYPICAL ILS FACILITIES PLACEMENT
FIGURE 1-1. TYPICAL ILS FACILITIES PLACEMENT
FRONT COURSE
APPROACH
OUTER MARKER (OM)-
RUNWAY CENTERLINE EXTENDED 4 TO 7 MIDDLE MARKER (MM)- NAUT.MILES
2000 TO 6000 FEET INNER MARKER (IM) (REQUIRED FOR CATEGORY I SYSTEM ONLY) 800 TO I0ÓO FÉET THRESHOLD OF ILS RUNWAY
700 TO 1250 FEET
GLIDE SLOPE (GS) ANTENNA EQUIPMENT SHELTER
GLIDE SLOPE (GS) ANTENNA EQUIPMENT SHELTER
250 TO 650 FEET ILS RUNWAY
STOP END OF ILS RUNWAY
2000 FEET 300TO 250 FEET MINIMUM
LOCALIZER (LOC) -EQUIPMENT SHELTER -ANTENNAS
BACK COURSE
Chap 1 Page 2 Par 3
11/25/77 6750.36
b. Responds to the needs of the Airway Facilities, Air Traffic, Airports, Environmental Quality, Flight Standards, and Logistics elements of the FAA.
BACK COURSE
Covers the siting aspects of Category I and II localizers, glide slopes, markers, and ancillary aids.
d. Indicates the use of national, regional, and industry standards, and identifies those standards and parameters for which compliance is mandatory.
e. Stipulates the specific engineering and nontechnical data that shall be obtained as part of an ILS site survey. A sample checklist is provided herein.
f. Establishes a standard format and content for a site selection report.
g. Identifies the coordination and interface requirements within the FAA as well as with other Federal, state, local, airport, private property owners, and utility company representatives.
h. Delineates criteria, procedures, techniques, cost vs. benefit tradeoffs, and validation required to survey, select, and construct an ILS.
4. ABBREVIATIONS, ACRONYMS, AND PUBLICATION REFERENCES. Abbreviations and acronyms relating to FAA organizations, equipments, and terminology as well as references to FAA directives, advisory circulars, and regulations are used extensively throughout this document. All abbreviations and acronyms are fully explained in Appendix 1, Glossary of Abbreviations and Acronyms, and the complete titles of all cited publication numbers are provided in Appendix 2, Applicable FAA Documents.
5. RELATIONSHIP WITH OTHER ILS SITING DOCUMENTS. This order largely consolidates the methods and techniques for ILS site survey, selection, and engineering documentation that are delineated in other ILS siting documents. Basic siting criteria for ILS equipment and ancillary aids has been extracted from Order 6750.16A. Placement limitations of ILS components and descriptions of their operational characteristics are contained in Orders 6750.4, 6750.7, 6750.13, and 6750.20, and Handbook 8260.3. These publications contain the primary siting guidelines available to the site survey engineer. A list of other applicable material with which the site survey engineer should be familiar is contained in appendix 2. This order will be updated as required to reflect accurately data revised in other existing documents as well as additional information in new documents.
6. RESPONSIBILITIES. A great degree of coordination and interface is required during the site selection and establishment process. It is the intent here to list most of the FAA and out-of-agency elements with whom interaction may be required. The site survey engineer should be
Chap 1 Par 3 Page 3
6750.36 11/25/77
thoroughly familiar with the FAA organizational structure at the national and regional levels. By knowing who is responsible for the various aspects of an ILS establishment, the site survey engineer will be better equipped to seek assistance when required. It is recognized that some functions of the regional elements may vary and, thus, the identity and titles of Airway Facilities division branches will differ from region to region.
a. FAA Elements.
(1) Washington Office.
(a) Airway Facilities Service.
1 Establishment Programs Division. Budget estimates, project authorizations, funds adjustments, etc.
2 Navaids/Communications Engineering Division. Program management, siting criteria development, waivers to siting criteria, electronic engineering, etc.
Environmental Systems Division. Plant engineering support.
(b) Flight Standards Service. Compatibility of siting criteria with aircraft operations; reviews waivers to siting criteria, etc.
(c) Air Traffic Service. Impact on air traffic procedures.
(d) Office of Airports Programs. Interface with Airport Development Aid Program (ADAP) policy.
(e) Logistics Service. Real estate and utility service acquisition policy.
(f) Office of Environmental Quality. Environmental quality policy.
(2) Regional Office.
(a) Airway Facilities Division.
1 Planning and Programming Branch. Budget estimates, project assignment, funds adjustments, environmental assessment (Environmental Impact Statements, Negative Declarations), A-95 Notification. See paragraph 6a(2)(a)2below.
Chap 1 Page 4 Par 6
11/25/77 6750.36
2 Establishment/Engineering Branch. Program implementation including feasibility study, concurrences, site survey, project transmittal, liaison with Airports district offices, and ADAP program, etc. (also, may be responsible for environmental assessment in lieu of Planning and Programming Branch).
3 Maintenance Operations Branch. Liaison with Airway Facilities sectors concerning day-to-day maintenance problems, safety, etc.
4 Frequency Management and Leased Communications Staff. ILS frequency assignments, processes lease requests for telephone lines, etc.
(b) Air Traffic Division. Airspace approval and concurrence.
(c) Airports Division. Liaison with Airports district offices (ADo), airport sponsors, ADAP program, etc. (e.g:, airport obstruction clearances).
(d) Flight Standards Division. Consultants in determination of marker beacon search area, glide slope angle calculations, and obstruction studies; establishes liaison with Flight Standards National Field Office (FSNFO); establishes ILS procedures, glide slope intercept altitude, etc.
(e) Logistics Division. Processes procurement requests for real property, commercial electrical service, construction invitation for bids; provides custodial management of real property records; secures option for acquisition of real property.
(3) Field Offices.
(a) Airway Facilities Sector. Responsible for maintenance of existing local FAA navaid facilities.
(b) Airport District Office. Status of ADAP projects dealing with the proposed ILS.
(c) Airport Traffic Control Tower. Responsible for air traffic activity on and in the vicinity of the airport.
b. Non-FAA Elements.
(1) Airport Sponsor. Al1 airport related activities.
(2) Airport Engineer or Consultant. Airport construction drawings and special airport construction requirements. Contact with these elements should be made through the airport sponsor.
Chap 1 Par 6 Page 5
6750.36 11/25/77
(3) Utility Companies. Technical discussions regarding power service, telephone line services, intervening utilities, etc.
(4) Contracted Professional Services. Professional engineers, surveyors, aerial photographers, geotechnical engineering firms.
(5) Property Owners. Ascertain attitudes of property owners regarding property lease or purchase by FAA (when so authorized by regional Logistics division).
7. TECHNICAL REFERENCES. Appendix 3, Technical References, contains a list of suggested reference material for surveying, cost estimating, and electrical design. These documents provide additional guidance in specialty areas,which are discussed herein as they apply to ILS estab- 1ishments.
8. PROJECT ENGINEER VERSUS SITE SURVEY ENGINEER. The terms "project engineer" and "site survey engineer" are used extensively throughout this document and are defined as follows.
a. Project Engineer. The project engineer is the regional Airway Facilities division engineer assigned the responsibility of scheduling the site survey, compiling the necessary preliminary site survey data, and overseeing the project to completion.
b. Site Survey Engineer. The site survey engineer is the FAA regional Airway Facilities division engineer or private site survey contractor engineer assigned the responsibility of performing the field survey work as detailed in paragraph 81, chapter 5, and documenting the results of the field survey effort in the form of site drawings and a site survey report.
9.-20. RESERVED.
Chap 1 Page 6 (thru 20) Par 6
11/25/77 6750.36
CHAPTER 2. ILS PROGRAMMING AND PLANNING
CHAPTER 2. ILS PROGRAMMING AND PLANNING
21. GENERAL. It is recognized that the availability of time, manpower, and/ or funding may be the overriding factors in determining the method employed to establish an ILS. It is the intent here to identify and define all of the tasks required during the conceptual planning stage of an ILS establishment. The concept of a feasibility study prior to the budget submission is the most logical approach, although it may not always be the most workable, since in some cases the ILS runway has not been designated. A designated instrument runway is one that has, or is anticipated to have at some future time, a precision type landing aid. An ILS instrument runway (including approach direction) should be designated on the sponsor's airport layout plan at the earliest practicable date on which the location meets the required level of activity in annual instrument approaches (AIA) per Order 7031.2, or where it is forecasted that the activity level will be reached in the near future. The designation of the instrument runway is a coordinated determination based on a preliminary study by the Airway Facilities, Air Traffic, Flight Standards, and Airports divisions.
22. FEASIBILITY STUDY. In order to properly respond to the call for F&E budget estimates, it is recommended that an onsite technical feasibility study be conducted. The feasibility study should be primarily an Airway Facilities function. If circumstances (e.g., lack of project funding) do not permit the feasibility study to be conducted prior to the budget submission, it should be performed as soon as practicable after project authorization (see paragraph 26). Optimally, the feasibility study should consist of a study of existing documentation conducted in the regional office and an actual onsite visit. The onsite study will serve both to confirm data indicated in the documentation (topographic data, as-built construction drawings, etc.) and to identify any potential problem sites. The assigned Airway Facilities personnel should coordinate all site meetings and gather all documentation relative to the site in question.
a. Office Planning. Before conducting the onsite study, the project engineer should obtain the following data, preferably in writing, from the indicated regional organizations:
(1) ILS data.
(a) Runway designation - Air Traffic, Flight Standards, Airports divisions, or project authorization (PA) sheet.
(b) Tentative glide angle, threshold crossing height (TCH), decision height (DH), and intercept altitude - Flight Standards division.
(c) Category of performance required, and expected landing minimums - Flight Standards division.
Chap 2 Par 21 Page 21
6750.36 11/25/77
(d) Acceptable marker search area - Flight Standards division.
(e) Pertinent information already contained in the project file - Airway Facilities division.
(f) Construction history at the airport from personnel previously involved in work at the site location - Airway Facilities division.
(g) Ongoing or planned ADAP and non-ADAP projects at the airport - Airports district office, or Airway Facilities division liaison group.
(h) Ascertain availability of frequency channels for proposed ILS installation - regional frequency management officer, Airway Facilities division.
(2) Maps and Drawings. (The following are described in greater detail in chapter 4, paragraph 62.)
(a) USGS topographic maps.
(b) Airport obstruction charts.
(c) Instrument approach procedure charts.
(d) FAA drawings and/or maps.
1 Airport layout plans.
2 Air navigational facilities drawing.
3 Plans and detail drawings of previous FAA construction.
(e) Airport civil works drawings.
(f) Other published maps and drawings.
1 Aerial photographs.
2 Photogrammetrics.
3 Sectional aeronautical charts.
b. Participants. The project engineer should contact and arrange to meet with the following personnel, as required, at the site. It is essential that Airway Facilities division civil and/or electronic engineering personnel be in attendance during the field trip since this is a technical feasibility study. However, if the runway assignment and desired minimums have not yet been established, personnel
Chap 2 Page 22 Par 22
11/25/77 6750.36
from Air Traffic, Flight Standards, and Airports divisions will also be required. A checklist of participants should include personnel from the following organizations:
(1) Airway Facilities division.
(2) Flight Standards division.
(3) Air Traffic division.
(4) Airports division.
(5) Logistics division.
(6) Airway Facilities sector office.
(7) Airport management or authority (non-FAA).
(8) Airport engineering or consultant (non-FAA). (Request airport consultants participation only at the invitation of the sponsor since there is usually a contractual agreement between the sponsor and the consultant.)
c. Onsite Feasibility Study. The onsite study should be planned as a one- or possibly a two-day trip. The type of information that should be obtained and the determinations that should be made should include but should not be limited to:
(1) General.
(a) Ascertain airport sponsor's attitude towards acquiring land located off airport property. (See Order 4660.1)
(b) Determine names and addresses of utility companies.
(c) Determine any airport work that may affect the proposed ILS.
(d) Identify any ILS siting or construction waivers that may be required.
(e) Obtain photographs of candidate sites (refer to chapter 5, paragraph 105 for a discussion on photographs).
(f) Record any existing or proposed structures or obstacles that may cause electronic or other interference to the proposed ILS.
Chap 2 Par 22 Page 23
6750.36 11/25/77
(2) Localizer and Glide Slope.
(a) Determine tentative locations.
(b) Investigate potential access road, utility routings, and alternates. (Actual contact with utility representatives will not usually be possible because of time limitations.)
(c) Record general terrain and soil conditions.
(d) Determine land ownership and acquisition feasibility (not intended to imply actual title search).
(e) Generally estimate grading and clearing requirements. Extensive site preparation, usually accomplished by the airport sponsor with ADAP funds, may warrant a cost analysis of the possible installation of an upgraded glide slope (including its maintenance costs) as an alternative resulting in the least cost to the Government.
(f) Determine airport expansion and construction plans.
(g) Consider potential sources of signal interference (e.g., hangars, water towers).
(h) Identify fm radio stations broadcasting in the airport vicinity within interference range of the localizer and glide slope signals. See paragraph 100.
(i) Identify security requirements for locations off airport property (possible at some localizer locations).
(3) Markers On Airport Property.
(a) Determine tentative location.
(b) Investigate access road, utility routing, and alternates.
(c) Record general terrain and soil conditions.
(d) Generally estimate grading and clearing requirements.
(e) Consider possible signal obstructions.
(4) Markers Off Airport Property.
(a) Locate potential marker sites in search area. Actual entry onto private property may require written permission in certain areas.
Chap 2 Page 24 Par 22
11/25/77 6750.36
(b) Estimate distance from public access and utilities.
(c) Make effort to determine land ownership (sponsor may have this information).
(d) Record terrain and soil conditions.
(e) Make note of any obvious environmental considerations, e.g., television interference (tvi).
(f) Identify security requirements.
23. FEASIBILITY REPORT. The data package developed during the feasibility trip should be condensed into a report form (such as a trip report). This data should also be recorded on an ILS proiect data checklist similar to that contained in appendix 4. This will enable reviewing organizations to make appropriate decisions relative to the ILS establishment. It is not intended that the feasibility report be as extensive or conclusive as the site survey report described in chapter 6, section 3; however, the report should include as much pertinent information as possible to help management make a go-no-go decision or possibly even recommend a partial ILS. It should also serve as a basis for site engineering and establishment cost estimates. The feasibility report should be made a permanent part of the project file since it will be useful in the future, particularly should the project be postponed. The type of information that should be detailed in the feasibility report should include:
a. Date and purpose of trip.
b. Participants.
c. Recommendations for equipment locations (including alternatives).
d. Recommendations for access, power, and control (including alternatives).
e. General description of site preparation.
f. Recommended equipment types compatible with sites.
24. BUDGET ESTIMATE. The data compiled during the feasibility study will enable the engineer to prepare the budgetary estimate on a more knowledgable basis. Order 601l.3 should be consulted to cover those line items whose costs cannot be determined based upon data derived from the feasibility study. By using cost estimates based upon the best available data, a greater correlation will be achieved between the appropriated funds and the actual construction costs. Land acquisition costs, coordinated with the Logistics division, shall be included in the badget submission as a. line item. This action will help to ensure that sufficient funds will be provided, thus avoiding delay to the project.
Chap 2 Par 22 Page 25
6750.36 11/25/77
25. INITIAL CONCURRENCE. Upon completion of the feasibility study and preparation of the budgetary estimate, a review by the Airway Facilities, Flight Standards, Air Traffic, and Airports divisions shall be made to receive the necessary concurrence. A concurrence of this nature will help to obtain uniform agreement and understanding of the decisions reached by all organizations involved in F&E projects. Once all concurrence has been met, the budget (or, if the project has already been approved, necessary requests for funding adjustments) is submitted to the Washington office.
26. PROJECT AUTHORIZATION (PA). The project authorization is an enabling document defining project scope and funding limitations. The PA, FAA Form 2510-1l, is issued by the Office of Budget, Facilities and Equipment Division, in Washington. The PA is sent to the regional Budget division, which furnishes a copy to the Planning and Programming branch in the Airway Facilities division. Internal regional project assignments are developed therefrom, to establish scope and funds allocations to cognizant branches within the Airway Facilities division.
27. SPONSCR NOTIFICATION. The sponsor generally is not aware of the .pending approval of a proposed ILS project for his airport; consequently, he should be officially notified. Depending on the prevailing regional practice, this notification action should be accomplished by the Airports division, or by the Airway Facilities division in coordination with the Airports division. This notification should be given prior to any site survey work being conducted at the airport and should include information that indicatus:
a. That an ILS has been programmed to be installed at his airport, including the category of ILS and ancillary aids, if any.
b. The runway designation.
c. The ILS siting requirements and the possible eligibility of required land acquisition and/or construction under ADAP as outlined in AC 150/5300-2. This should include the site grading, clearing, land acquisition, and building restriction requirements.
d. The estimated project start and completion date.
e. That a commitment to support the project is required of the sponsor.
28 A-95 REVIEW PROCESS.
a. General.: The A-95 review is a parallel but separate process from the environmental impact statement/negative declaration process. The Office of Management and Budget has provided guidance to Federal agencies dealing with state and local governments concerning the evaluation, review, and coordination of Federal assistance programs in fts OMB Circular A-95, Federal and Federally-Assisted Programs and
Chap 2 Page 26 Par 25
11/25/77 6750.36
Projects Evaluation, Review and Coordination. The A-95 notification shall take place prior to contract bid advertisement. If the A-95 notification is completed as early as possible in the ILS establishment process, it can be a useful instrument to alert planners to potential problems. Order 1200.21 transmits for appropriate office and service action Order DOT 4600.4. These orders should be referenced for guidance when implementing the regulations in OMB Circular A-95.
b. Data to be Provided in A-95. Since the ILS comes under the category of being a federally funded program, notification must be made to'the state and area-wide planning and development clearinghouses having jurisdiction in the area where the project is to be located. A typical A-95 notification data sheet is contained in appendix 17. The project notification should contain the following information:
(1) Location of the project, including the name of airport, city, and county. The actual physical location of all of the components of the ILS system is probably unknown early in the ILS planning stages; however, since the siting criteria for ILS is restrictive, the optimum locations for a typical system may be specified in the A-95 notification. The optimum locations for ILS facilities is detailed in Order 6750.16A.
(2) Description of the project in relation to area wide and community development. This brief description will enable clearinghouses to make appropriate distribution of the notifications.
(3) Program under which project is planned.
(4) Date on which project is scheduled to begin (actual development, construction, or other activities involved in its physical implementation).
c. Submission of A-95 Notification. The A-95 process may take up to 60 days, 30 days in which the clearinghouse informs state agencies and local or regional governments of the proposed project, and 30 days to review the recommendations and comments produced by the review process.
29.-40. RESERVED.
Chap 2 Par 28 Page 27 (thru 40)
11/25/77 6750.36
CHAPTER 3. PROJECT ENGINEERING
CHAPTER 3. PROJECT ENGINEERING
41. GENERAL. When a runway has been designated and authorized for the establishment of an ILS, the project engineering should commence promptly. The general guidelines for the project engineering are defined in chapter 7, Order 6750.16A. In order to comply with the requirements of the various project engineering phases, close coordination between planning/ programming, engineering, and establishment is essential. The preliminary survey and report suggested in chapter 7, Order 6750.l6A is related to the feasibility study discussed in this document.
42. SCHEDULING. The engineer assigned to the project has the function of coordinating his efforts with planning/programming, plant, and electronic engineering with regard to:
a. Reviewing money allocated in the project authorization for adequacy.
b. Determining the type and availability of equipment scheduled for installation.
c. Scheduling the site survey and engineering.
d. Scheduling construction, installation, and commissioning.
e. Coordinating with Air Traffic, Flight Standards, and Airports divisions, the Maintenance Operations branch in the Airway Facilities division, as well as the local Airway Facilities sectors.
f. Developing the project file folder, where not previously established.
43. PROJECT FILE DATA. Assuming that an ILS feasibility study as outlined in chapter 2 has been accomplished, most of the following data should be available. In any event, the project file should be established as soon as the PA is obtained.
ILS Data.
(1) Airport.
(2) Category of ILS.
(3) Runway designation.
(4) System geometry including glide angle, threshold crossing height, decision height, etc.
Chap 3 Par 41 Page 41
6750.36 11/25/77
b. Equipment Types (not always known at time of onsite survey).
(1) Equipment programmed.
(2) Equipment availability date.
(3) Power requirements.
(4) Control/monitoring requirements.
c. Interface Requirements with Existing Facilities.
(1) Interlock requirements (i.e., facing or multiple ILS).
(2) Compatibility with the location of visual approach Slope indicator (VASI) units (see Order 6850.2).
(3) Taxiways, restricted areas, etc.
(4) Frequency assignments.
(5) Construction in approach light systems.
d. Constraints to Construction.
(1) Unsuitable terrain conditions and the status of any ongoing or programmed ADAP construction or land acquisition projects.
(2) Inadequate space because of limited terrain or property boundaries.
(3) Requirements for installation of elevated platform for localizer antenna array(s).
(4) Inaccessibility to proposed facility locations.
44. ACCOMPLISHMENT OF SITE SURVEY.
a. Responsibility of Project Engineer. The project engineer, as defined in paragraph 8a, is responsible for arranging, monitoring, and sometimes supervising the actual onsite survey work that will be required for the establishment of an ILS.
b. Personnel Performing the Field Work. Within the Airway Facilities division, the engineering organization(s) responsible for performing the field survey shall be determined by the region. The designated project engineer may choose to perform most of the field survey work himself, possibly with engineering assistance from other FAA personnel or specialized commercial engineering services. More often, the field work may be performed by a site survey engineer(s) under the technical direction of the project engineer. Where personnel Chap 3 Page 42 Par 43
11/25/77 6750.36
availability, time, or efficiency dictates, the region may decide to contract for engineering services. These services may be of limited scope as required, or by means of a formal contract for the entire site survey effort. Figure 3-1 depicts in graphic form the various means by which the field site survey effort may be performed.
c. Site Survey Engineer. The site survey engineer, as defined in paragraph 8b, performs the actual field survey work and supplies ILS engineering data, sketches, and/or drawings to the project engineer. If the project engineer and the site survey engineer are within the same organizational element, the initiation and technical direction of the field survey work performed by a site survey engineer(s) may be verbal but should preferably be written (e.g., internal letter). If the project engineer and the site survey engineer are in two separate organizational elements, the task may be defined by a more formal work order, detailing the site survey work to be performed and the engineering data required. The technical direction by the project engineer, whether verbal or written, shall specify the detailed requirements of the field work to be performed. Paragraph 45 outlines the technical survey work to be performed and the ILS engineering data required.
d. Contracted Engineering Support.
(1) Support Requirements (Limited Scope). In some regions, the project engineer may use particular types of engineering support services, such as a local land surveyor for a marker property survey or an engineering service for a topographical survey in front of a glide slope. If the work to be performed by the service is of limited scope and dollar value, the project engineer may be able to engage the service by arrangement at the field site, outlining the work and technical data required by verbal agreement or a letter.
(2) Support Requirements (Extensive Scope). Where the engineering support work to be performed is extensive, the work should be performed under a formal contract arranged through the Logistics division. In such cases, a formal statement of work or specifications outlining the work and technical data required will have to be prepared.
(3) Photogrammetrics. In some instances, the region may desire a complete aerial survey, requiring that photogrammetrics be supplied to the project engineer prior to performing an onsite field survey effort. Such arrangements are usually made by formal contract through the Logistics division and will require a thorough statement of work or specification of the service to be provided. Paragraph 46 outlines the typical work to be performed under a photogrammetrics contract.
Chap 3 Par 44 Page 43
Page 44
PROJECT AUTHORIZATION
PROJECT AUTHORIZATION
PROJECT ENGINEER
Par Chap
44 3
FIGURE 3-1. METHODS USED FOR. PERFORMING
ILS SITE SURVEY
OFFICE PLANNING AND FIELD SITE SURVEY
PROJECT ENGINEER PERFORMS FIELD SURVEY
DIRECTION ORAL OR WRITTEN SITE SURVEY ENGINEER LIMITED SUPPORT SERVICES
PROPERTY SURVEY (CADASTRAL) /ENGINEERING SUPPORT AS REQUIRED TOPOGRAPHY & ENGINEERING
GEOTECHNICAL (SOIL) WORK ORDER IDEFINES DATA REQUIRED) SURVEY SITE ENGINEER
GEOTECHNICAL (SOIL) WORK ORDER IDEFINES DATA REQUIRED) SURVEY SITE ENGINEER
PHOTOGRAMMETRICS OR AERIAL SURVEY (CONTRACTED)
CONTRACTED SERVICES
FORMAL REGISTERED LAND CONTRACT SURVEYOR (CADASTRAL) (PERFORMED TOPOGRAPHIC AND TO SPEC'S) ENGINEERING GEOTECHNICAL(SOIL)
COMPLETE SITE SURVEY AND DOCUMENTATION (CONTRACTED)
COMPLETE SITE SURVEY AND DOCUMENTATION (CONTRACTED)
6750.36
(SUPPLIED
TO PROJECT ENGINEER) DRAFT SITE SURVEY REPORT ILS ENGINEERING DATA PACKAGE AND REVIEW AND CONCURRENCES FINAL REPORT AND DRAWINGS
11/25/77
11/25/77 6750.36
(4) Complete Site Survey Service. In some instances, a region may find it desirable to have the entire site survey effort (including the complete site survey report and construction drawings) performed by an engineering firm through a formal contract arranged by the Logistics division. Where work is to be performed in this manner, the project engineer shall prepare a thorough statement of work ortechnical specification, fully describing the survey to be performed and the ILS engineering data to be supplied in the report and drawings.
45. TECHNICAL AND ADMINISTRATIVE REQUIREMENTS FOR SITE SURVEYS. RegardleSS of the methods used to accomplish the ILS site survey, the technical requirements of the site survey as well as the technical documentation to be produced are essentially the same, whether accomplished by FAA engineers or by a contract service. The major variations are the coordination procedures before, during, and after the onsite activities as well as the extensiveness of the required documentation. The type of information that should be included in work orders, statements of work, technical specifications, or other written descriptions of work requirements is discussed below. The intent is to delineate for the site survey engineer what is expected and to provide information and standards as applicable to the work effort. Not all items. will be appropriate for every site survey. A sample field work order, which may be prepared on FAA Form 1196 or on‘a specially designed regional form, is contained in appendix 5. These guidelines should also be followed in contracting for a complete ILS site survey (in which the contractor is responsible for the site survey, selection, and engineering documentation), recognizing that some of the information may be part of the contract provisions visa-vis the technical specifications.
a. Administrative Data.
(1) Work order, statement of work, or specification number.
(2) Project code.
(3) Type of project; e.g., final site survey.
(4) Organization initiating work to be done.
(5) Organization accomplishing work to be done.
(6) Project commencement and expected completion dates.
(7) Project engineer who will provide technical direction and/or consultation.
(8) Estimate of employee-hours and costs (on work order only).
Chap 3 Par 44 Page 45
6750.36 11/25/77
b. Background Information. The site survey engineer should be provided with the following background information, along with a copy of the feasibility report (if a feasibility study has been conducted as detailed in chapter 2 of this order).
(1) Geographic location of site.
(2) Runway identifier.
(3) Desired category of ILS operation.
(4) Fu11 (LOC/GS/MM/OM) or partia1 (LOC/OM or GS/MM) ILS. (5) Requirements for COMLO, NDB, DME, and/or far field monitor (FFM).
(6) Model of ILS equipment programmed for installation, including:
(a) Antenna and shelter size.
(b) Power requirements.
(c) Power panel and demarcation box locations.
(d) Monitoring and/or control requirements.
(7) Desired glide angle, TCH, and DH.
(8) Search areas for markers as approved by the regional Flight Standards division.
(9) Air navigational facilities plan and/or other relevant drawings.
(10) Contact points at regional office, Airway Facilities sector, airport, and utility companies. (11) Status of ongoing construction that may affect the project.
c. General Site Survey Requirements.
(1) Facility Site Survey.
(a) If exact equipment locations are already known, provide corresponding station numbers for these locations and include a drawing detailing the proposed locations. If exact equipment locations are to be determined as a part of the site survey, indicate that the site survey engineer shall determine the exact location of the ILS system components - localizer, glide slope, marker(s), monitoring equipment, distance measuring equipment (where required), and compass locators (where required).
Chap 3 Page 46 Par 45
11/25/77 6750.36
(b) ILS siting shall be in accordance with Order 6750.16A. If the selected locations exceed any of the governing criteria of Order 6750.16A, the site survey engineer shall be required to contact the project engineer before proceeding with the site survey.
(c) The site survey engineer shall stake the center of the antenna points for the localizer, glide slope, and all associated markers.
(d) The site survey engineer shall use bench marks for vertical control.
(2) Access and Utilities Survey.
(a) The site survey shall determine the routing of primary power, telephone lines (if required for control or remote monitoring), and access roads to the various sites, including trenching and ducting requirements.
(b) If traverses are to taken along access road centerlines and along cable routes, they shall be specified.
(3) Clearing, Grubbing and Grading. The site survey engineer shall determine the approximate acreage of clearing, grubbing, and grading that will be required to ensure satisfactory ILS performance, accommodate ILS shelters, and provide proper drainage of the sites.
(4) Land Availability and Acquisition.
(a) In association with airport authorities and the Airports division or ADO representatives, the site survey engineer shall obtain land acquisition and availability data. For details concerning determination of property ownership and land availability, the site survey engineer shall refer to the regional Logistics division personnel through the project engineer.
(b) The scope of lease data that should be obtained on tne work order by the pite survey enginneer shall be indicated.
(5) Accuracy Requirements. Specify the minimum degree of accuracy to be attained in each of the onsite measurements. Refer to paragraph 91 for the accuracy requirements of an ILS site survey.
(6) Environmental Assessment. Indicate what type (if any) of environmental data is to be obtained by the site survey engineer. If an environmental assessment is conducted by
Chap 3 Par 45 Page 47
6750.36 11/25/77
non-FAA personnel (e.g., a contractor), a formal environmental assessment report must be prepared per Order 1050.1.
(7) Photographs. Indicate to the site survey engineer the types and quantities of photographs to be taken at the proposed sites.
d. Localizer Site Requirements.
(1) Localizer Topography. The site survey engineer should be directed to:
(a) Obtain contour data for the antenna and equipment shelter plot. A cross section should be obtained at the antenna location for at least the full length and width of the antenna foundation. If staking is required, specify it.
(b) Obtain contour data for the ful1 right-of-way width of the access road, including drainage data.
(c) Indicate on a topography drawing the location and height of any obstructions in the localizer restrictive zone (e.g., structures, poles, trees, fences, etc.).
(d) Obtain an extended runway centerline profile from the adjacent runway threshold to the centerline of the 1ocalizer.
(2) Localizer Property Survey. The site survey engineer should be directed to obtain a property survey for a typical localizer plot including the access road right-of-way. The site survey engineer should check with the project engineer for legally acceptable tie-in points.
(3) Localizer Access and Utilities Survey. The site survey engineer should be directed to:
(a) Locate all drainage structures with recommended size based on 10-year flood intensity. The 20- and 50-year flood elevations should be noted.
(b) Coordinate acceptable power routing with the power company. The site survey engineer should obtain power company specifications for electrical installations and details for transformer pads, if required.
(c) Perform subsurface investigation by probing or boring for all construction functions (i.e., trenches, equipment installation locations, etc.). The site survey engineer should note if bedrock or rock outcrop is encountered and indicate the extent of surface and subsurface drainage problems affecting foundation and earthwork.
Chap 3 Page 48 Par 45
11/25/77 6750.36
e. Glide Slope Site Requirements.
(1) Glide Slope Topography. The site survey engineer should be directed to:
(a) Obtain contour data for the glide slope site survey areas defined in figure 5-5 of this order and figure 3-1la of Order 6750.16A. Area "A" should always be included, but areas "B" and "C" should be included only where the terrain roughness dictates the need for this information.
(b) Obtain contour data for the full right-of-way width of the access road including drainage data.
(c) Obtain an accurate runway centerline elevation at the point opposite the antenna mast.
(d) Determine the highest point in the runway touchdown zone (TDZ) to the nearest 0.1 foot.
(e) Indicate on the topography drawing the location and height of all obstructions in areas "A", "B", and "C" of the glide slope survey areas (see paragraph 45e(1)(a) above).
(2) Glide Slope Property Survey. The site survey engineer should be directed to obtain a property survey for a typical glide slope plot (see sample in appendix 6), including the access road right-of-way and the monitor antenna. The site survey engineer should check with project engineer for legally acceptable tiein points for locations on airport property.
(3) Glide Slope Access and Utilities Survey. Same as for localizer; see paragraph 45d(3).
f. Marker Beacon Site Requirements.
(1) Marker Beacon Topography. The site survey engineer should be directed to:
(a) Obtain contour data for all marker facilities. Limits of data will be dependent on relevant antenna plot sizes.
(b) Obtain contour data for full right-of-way of access roads, including drainage data.
(c) Check marker beacon restrictive area in accordance with figure 4-3, Order 6750.16A. The site survey engineer shal1 indicate the height and location of possible interference sources on site drawings.
Chap 3 Par 45 Page 49
6750.36 11/25/77
(d) Locate and indicate a clearly defined bench mark if construction is to be done to an exact grade.
(2) Marker Beacon Property Survey. The site survey engineer should be directed to obtain property descriptions by metes and bounds for markers and needed access roads located off airport property and make property ties to recognized property corners. If the marker is to be located on airport property, the site survey engineer should contact the project engineer for legally acceptable tie-in points. He should also determine the ownerofrecord for off-airport properties. The responsibilities, authority, and restrictions of site survey engineers in conducting discussions with property owners should be clearly specified.
(3) Marker Beacon Access and Utilities Survey. In addition to the access and utilities survey requirements listed in paragraph 45d(3), the site survey engineer should be directed to:
(a) Locate and identify any roads, railroads, overhead or underground utilities, fences, etc., in the area to be contoured.
(b) Locate and indicate the height of isolated trees or groups of trees in the area with enough information pertaining to tree size and density to permit a clearing contract to be issued.
g. Obstruction Survey. If an obstruction survey to the ILS final approach surface is required, specify it. Define its scope and accuracy requirements.
h. Project Engineer/Site Survey Engineer Coordination. The site survey engineer should be made fully aware of the coordination procedures to be fo11owed:
(1) Pre-Site Survey. A pre-site survey meeting should be held between the project engineer and the site survey engineer to ensure complete mutual understanding of the requirements.
(2) During Site Survey. The site survey engineer is expected to maintain close liaison with local airport authorities and FAA representatives. The FAA project engineer at regional headquarters shall be contacted if there are any unusual or unforeseen conditions that may influence the work., Before leaving the field, the site survey engineer shall contact the project engineer to ensure that all necessary data has been obtained, thus possibly avoiding the need for an additional trip.
Chap 3 Page 50 Par 45
11/25/77 6750.36
(3) Post-Site Survey. Before the site survey data is developed into final form, the field sketches and data should be reviewed by the project engineer. This coordination effort will serve to point out any relevant information that may be lacking and to highlight any additional details that the project engineer will want to see discussed in the report.
i. Airport Coordination and Safety. The site survey engineer should be directed to coordinate his schedule of work on airport property with the airport manager and the local Airway Facilities sector (and/or sector field office (SFO), airport traffic control tower (ATCT) personnel), and ensure that ali airport safety regulations are strictly complied with regarding work areas, parking, and movement.Radio controlled vehicles are usually required when operating on airport property.
j. Preparation of the Site Survey Report. The work requirements should indicate that a formal report is to be prepared to document the site survey findings and recommendations. The report shall include al1 essential information for site construction and installation, as applicable, within the criteria set forth in applicable FAA documents relating to ILS siting criteria (see chapter 1, paragraph 5). The report shall encompass location details of equipment to be installed, site preparation, electrical power service, construction of access roads, communication lines, foundation details, ground planes, grading, trenching, ducting, and cables requirements, .and routing for power and monitoring lines. The report should include a recommendation fora computer study or site testing where, because of poor siting conditions (terrain irregularity close to the glide slope or the presence of large metal structures along the runway), it is not possible to predict the quality of facility performance. Depending on regional practices and the complexity of the field work effort involved, reports prepared by FAA site survey engineers may range from relatively concise trip reports with illustrative attachments to more comprehensive documents intended for management review, approval, and/or action. Reports prepared by a site survey contractor, which shall provide detailed justifications of site recommendations, shall be similar in format and content to the sample report presented in appendix 7.
k. Preparation of Site Construction Drawings. The work requirements should discuss the preparation of site construction drawings.
(1) FAA Site Survey Engineer. Depending on regional practices and the complexity of the field work effort, the FAA site survey engineer should provide usable sketches or full-size engineering drawings (suitable for tracing by drafting personnel) for ultimate use as facility construction drawings. The required type and degree of completeness of these drawings should be conveyed to the site survey engineer either in the work requirements or during the pre-site survey coordination meeting.
Chap 3 Par 45 Page 51
6750.36 11/25/77
(2) Site Survey Contractor. Site surveys conducted by a contractor shall culminate in complete site construction drawings. The drawings to be submitted with the site survey report shall outline all siting geometry, construction details, instructions, specifications, and materials necessary to accomplish the installation. These drawings are to be ultimately used in the Invitation for Bidders (IFB) package, and thus shall be usable for competitive bidding. Sample site drawings are included in appendix 6 of this document. The drawings shall include as a minimum:
(a) The location of all transmitting antennas together with the associated equipment shelter, buried cable routing, and monitoring devices for all components of the instrument 1anding system.
(b) Site preparation requirements including clearing, grubbing, and grading.
(c) Information required for the construction of access roads and the installation of protective fencing.
(d) Primary power installation details including terminal poles, transformer mountings, substation layouts, and wiring.
(e) Monitor/control circuit routing and details of installations where required in ATCT cabs.
(f) Schedule of national and/or regional standard drawings to be used in conjunction with site drawings for the various portions of an ILS (e.g., localizer, glide slope, etc.)
1. Submittal of Report and Drawings. Indicate in the work requirements when and to whom the site survey report and drawings are to be submitted. In the case of a contracted site survey, the engineering report and associated drawings should be submitted in at least four copies (one of which is reproducible) to the Government Contracting Officer for review and approval. One copy of the report should be returned to the contractor, either with a statement that the report is acceptable and approved by the Government or with a statement of disapproval pointing out deficiencies and recommendations for correction. In the event of the latter, the contractor shall resubmit the revised report for approval.
46. CONTRACTED ILS SITE SURVEY SERVICES (SPECIALIZED). When specialized engineering services (e.g., land surveys, geotechnical analyses and/or unique foundation designs, and photogrammetrics) are required prior to or as a part of an ILS site survey, the procurement methods employed (e.g., IFB, Request for Proposal (RFP), Request for Quotation (RFQ), Standard Form 44, etc.) will vary according to regional procedures,
Chap 3 Page 52 Par 45
11/25/77 6750.36
complexity of work, and the anticipated cost. The technical requirements should thoroughly outline the work to be done and they may be conveyed verbally if limited in scope. Procedures for obtaining such specialized services are discussed below.
a. Land Surveys. The services of a land surveyor may be required to obtain property data for a particular ILS site(s), and may be engaged by verbal contract in the field when the site survey engineer is authorized to do so. Information necessary to prepare a plot description is discussed in appendix 9.
b. Geotechnical Engineering Services. Where, because of questionable local soil conditions, geotechnical engineering services are to be obtained, the technical description for the service should include the following, as appropriate.
(1) Administrative Data.
(a) Type of project; e.g., ILS site survey.
(b) Organization initiating work to be done.
(c) Project commencement and expected completion date.
(d) Project engineer assigned to provide technical direction and/or consultation.
(e) Scope of contract, defining requirements ,and limitations of work.
(2) Technical Data. The geotechnical engineering firm should be provided with the location(s) of the proposed site(s), foundation, and/or access road alignment (as appropriate) clearly shown on an engineering drawing. In addition, the size, weight, and wind-loading requirement of the ILS equipment scheduled for installation should be provided.
(3) Contractor Work Requirements. The work requirements should contain provisions that the geotechnical engineering firm provide the following as appropriate:
(a) Test borings at the loçations indicated on the accompanying drawing. (Proposed construction over suspected unstable boggy soil, fresh land fill, or at a near-surface water table may require more frequent soil samplings.)
(b) Technical inspection of the boring work so that depth and sampling methods can be varied to meet subsurface conditions encountered.
Chap 3 Par 46 Page 53
6750.36 11/25/77
(c) Performance of laboratory tests and analysis on soil samples recovered from subsurface explorations as required to aid in soil classification.
(d) Analysis related to geotechnical engineering aspects of foundation design and construction, and an engineering report, which will include the following items applicable to the project and site:
1 Boring logs and records of other field explorations indicating soil and rock conditions and water table.
2 Location plan of subsurface explorations.
3 Results of laboratory soil tests.
4 Recommended foundation type with foundation design criteria including allowable bearing capacity, pile loading, foundation depth, and other information required for final design and preparation of plans and specifications.
5 Evaluation of construction problems related to soils and foundations including excavation and filling.
6 Recommended pavement cross section for access roadways.
7 Estimate of cost of excavation and granular fill replacement, if applicable.
(4) Airport Coordination and Safety. The geotechnical engineering firm should be instructed to coordinate its schedule of work on airport property with the airport manager and local Airway Facilities sector/SFO and ATCT personnel, and that all airport safety regulations shal1 be strictly complied with regarding work areas, parking, and movement.
c. Photogrammetric Drawings. Photogrammetric drawings, using aerial photography techniques, prepared at sites with severe terrain conditions may enable the site survey engineer to locate prospective equipment locations, consider drainage characteristics, determine site preparation requirements, locate promising marker locations, prepare site construction drawings, and identify objects penetrating Federal Aviation Regulation (FAR) Part 77 surfaces. The technical specification for this service should include the following types of information.
(1) Administrative Data.
(a) Type of project, e.g., preliminary ILS site survey.
Chap 3 Page 54 Par 46
11/25/77 6750.36
(b) Organization initiating work to be done.
(c) Project commencement and expected completion date.
(d) Project engineer assigned to provide technical direction and/or consultation.
(e) Scope of contract, i.e., definition of requirements and limitations of work.
(2) Drawings to be Provided. The work requirements should describe the photogrammetric drawings desired. Specify the precise requirements as noted along with the quantity and scale of the drawings desired.
(a) An airport general plan should indicate:
1 Runway numbers .and dimensions.
2 Runway true azimuth.
3 Airport reference point and magnetic variation.
4 Existing airport features and property lines.
(b) Approach coverage drawings should indicate:
1 Specified length and width of coverage.
2 Runway centerline extended marked at specified nautical mile points.
(c) Plan and profile drawings (1f an ALS is planned) should indicate:
1 Elevation contours at specified intervals.
Specified coverage area.
Vertical scale specified for profile drawings.
(3) Conventions to be Followed and Definitions to be Reflected. Specify the following conventions and definitions to be followed or reflected on the drawings.
(a) All elevations should be above mean sea level (amsl).
(b) Directions to the left and right-of-runway centerline should be those of an observer facing in the direction of an aircraft on straight-in final approach (i.e., as the pilot sees it).
Chap 3 Par 46 Page 55
6750.36 11/25/77
(c) Penetrations to the final approach and transitional surfaces shall be those defined in FAR Part 77.
(d) The threshold of the runway should be considered a line perpendicular to the runway centerline marking the beginning of the runway surface available for landing.
(e) The TDZ elevation is defined as the highest point in the runway within the first 3,000 feet of runway beyond the threshold.
(4) Photographic Quality and Layout.
(a) Drawing Types. Specify in the work requirements the type of reproducible sheets to be used. Nonphotographic features should be drafted on the sheets in ink.
(b) Drawing and Drafting Practices. Specify such information as required to ensure conformance with FAA drawing practices; e.g.,
1 FAA format and title block.
2 Orient layout to depict true north toward the top of the drawing.
3 All sheets should bear the runway true azimuth, the Government agency that determined the azimuth, and the date of survey from which the azimuth was determined, e.g., 249° 36' 08" (NOS 8/74).
4 Al1 planimetric features (such as rivers, lakes, roads, schools, churches, etc.) should be identified.
5 All airport property lines, runways, taxiways, etc. should be identified.
(5) Contract Coordination. Indicate in the work requirements that:
(a) The contractor should contact the FAA technical representative for clarification of the technical requirements and to report any unusual or unforeseen conditions.
(b) The contractor should make necessary arrangements with the airport sponsor to the extent authorized by the contract requirements.
47.-60. RESERVED.
Chap 3 Page 56 (thru 70) Par 46
11/25/77 6750.36
CHAPTER 4. OFFICE PLANNING
CHAPTER 4. OFFICE PLANNING
61. GENERAL. Systematic office planning should be accomplished prior to the actual field investigation and survey work. Thorough office study and planning will provide a. good understanding of the site survey effort that will be required and allow for the best use of field personnel.
62. OBTAINING MAPS AND DRAWINGS. Obtain the existing maps and drawings, not previously obtained, which are necessary and useful to the preliminary design, sketch preparation, and field planning. In the event adequate drawings and/or maps are not available for plotting the location of the facilities or the search areas, a decision should be made regarding the possibility of obtaining documentation through the sponsoring airport or by means of contracted engineering services. Where photogrammetrics are used as a matter of regional practice, the preparation of specifications for contracted services is discussed in the foregoing chapter 3. The drawings and maps that generally will be available are outlined in the following subparagraphs.
a. U.S. Geological Survey Topographic Maps.
(1) The U.S. Geological Survey (USGS) publishes standard topographic maps to cover the United States, Puerto Rico, Guam, American Samoa, and the Virgin Islands. The most useful quadrangles are those covering 7-1/2 minutes of latitude and longitude with a scale of 1:24,000 (1 inch = 2,000 feet). In some areas of the United States, quadrangle sheets are only available in the smaller scale 15 minute series (1:62,500, 1 inch = approximately 1 mile). Each of the quadrangle sheets bears a geographical name and should be obtained by that name. Maps of abutting quadrangles join without a break in continuity of map detail. These maps are available from:
(a) Branch of Distribution U.S. Geological Survey 1200 South Eads Street Arlington, Virginia 22202, or
(b) Branch of Distribution U.S. Geological Survey Federal Center Denver, Colorado 80225
(2) Additionally, the U.S. Geological Survey publishes an index map showing the location and name of the quadrangle sheets in each state; these index maps further give the names of local dealers stocking the maps in principal cities. Topographic sheets should be obtained that embrace the area approximately 1 mile on either side of the proposed ILS runway centerline extended, and
Chap 4 Par 61 Page 71
6750.36 11/25/77
between points approximately 8 miles from either end of the proposed ILS runway. This area will cover the approach end of the runway and provide information over the missed-approach area beyond the opposite end of the runway.
b. Other Topographic Maps. In some instances, public lands under the control of U.S. Forest Service, national parks, military facilities, and other agencies are not covered by the USGS quadrangle sheets. Topographical maps covering these areas are generally available from the governmental agency in control of the land. Maps along the coastline and navigable streams are also published by the applicable Government agency and may readily be obtained from the appropriate agency when required.
c. Airport Obstruction Charts. The Airport Obstruction Chart (OC) shows selected planimetry, a plan of the airport including obstacles in the aircraft circling areas, and a plan and profile of the runways, their approaches, and obstacles therein. An aerial photographic portrayal of the entire chart area, or of only the airport and its immediate surroundings, may appear as background. The chart is used for determining the status of obstructions. OC charts are prepared for the FAA and are published by the National Ocean Survey (NOS) of the U.S. Department of Commerce, National Oceanic and Atmospheric Administration. Each chart bears the name and location of the airport, an OC chart number, and the date of the field survey. These charts, and an index of the OC charts, are available from:
National Oceanic and Atmospheric Administration Distribution Division 6501 Lafayette Avenue Riverdale, Maryland 20840
d. Instrument Approach Procedure Charts. Charts indicating certain instrument approach procedures that should be used at the airport are useful in determining navaid facilities available and the current applicable minimums for the airport. Instrument Approach Procedures (charts) are prepared under FAA direction and are published by the Defense Mapping Agency Aerospace Center (DMAAC), NOS, and by various non-governmental publishing concerns. FAA regional office personnel in the Flight Standards and Air Traffic organizations generally have these charts on file and may be consulted when required. One source for the procedure charts is:
National Ocean Survey Distribution Division, C44 Riverdale, Maryland 20840
FAA Drawings and/or Maps. The following FAA drawings and/or maps may have been previously prepared and should be obtained if they are available.
Chap 4 Page 72 Par 62
11/25/77 6750.36
(1) Airport layout plans may have been prepared by the sponsoring airport and reviewed and approved by the Airports division. A similar drawing may be titled as an Airport General Plan or as an Airport Master Plan. Copies of these plans are usually available through the Airports division. In addition to providing a master layout of the airport, they may include facilities planned for the future and indicate the sponsor's past planning with respect to preparation for the proposed ILS system. Such drawings may also indicate the airport property boundaries, provide runway azimuth data, and other information that will be useful.
(2) Air navigational facility (ANF) drawings of the existing FAA navigational facilities (i.e., existing ILS, VOR, ALS, or VASI facilities, etc.) should be in the regional office files. These drawings provide important data regarding potential power sources, extent of control cables instalied, and the possible interface with other systems with respect to physical conflicts and shared services. ANF drawings are a variation of the airport general plan and/or layout drawings.
(3) Plans and detail drawings for FAA construction of existing or proposed FAA facilities should be available in the regional office files. Typical of these will be ALS construction drawings, which would be helpful in determining the preliminary siting of localizer antennas and markers. These should include drawings covering work performed at both ends of the runway. In some instances an airport power and buried cable plan is maintained. This information will enable more thorough planning for both the preliminary engineering design and for the following site survey.
f. Airport Civil Works Drawings. These are prepared by airport public works authorities or by sponsor-contracted architecturai and engineering organizations are available in the regional office. Drawings prepared for runway extensions, drainage construction, sewage, buried utilities, and earthwork provide an excellent source of contour information. Every effort should be made to determine that these drawings represent the true "as-built" conditions.
g. County Soil and Geological Maps. These are available in most locations and will yield valuable information on subsurface conditions.
h. Other Published Maps and Information. Some that may be readily available (sometimes at the regional office), are:
Chap 4 Par 62 Page 73
6750.36 11/25/77
(1) Aerial photographs over many areas have been made by various governmental agencies and may be available either in the appropriate agency field office or the office of the mapping and consulting engineering firms who contracted the work. Aerial photographs over rural and farming areas are generally on file in the agricultural extension department of the counties or parishes concerned. These are especially useful in siting of marker facilities and determining the ownership of property.
(2) Photogrammetrics have been made for many purposes by mapping and consulting firms and are often available from their offices in principal cities. Photogrammetrics are particularly helpful inasmuch as they generally give contours at two-(2) foot intervals over areas ·that would otherwise require costly ground survey effort. Paragraph 46 further discusses the use of photogrammetrics for ILS engineering and siting.
(3) Sectional aeronautical c.harts are published by NOS and developed by the FAA. These charts are used primarily for navigational purposes but are readily available and useful in selecting the proper USGS topographic quadrangle sheets (see paragraph 62a) where exact airport locations are difficult to identify on the USGS state index sheets. Sectional aeronautical c'harts are titled with the name of one of the principal cities within the area covered by the chart.
63. PLOTTING POTENTIAL SITES. Following the accumulation of the maps and drawings available in the regional office, the proposed facility locations and marker search areas should be plotted on that map or drawing that will provide the most useful data for determining and planning the field survey requirements. Appendix 8, ILS Equipment Requirements,wil1 aid the engineer in determining the typical plot sizes and layouts desired for the system.
a. Facilities to be Located on the Airport.
(1) General. In the case of ILS equipment to be located on the airport, the airport general plan drawings, prepared for existing or proposed ALS facilities, or detailed drawings used for runway construction, with elevation information, may be most useful. Since some of the drawings may contain so much information as to be congested or confusing, it may be advantageous to prepare a new sketch at the appropriate scale containing only that information required for the proposed ILS work. Photogrammetrics may be very useful at this stage of the planning.
(2) Inner Marker. In most cases, the Category II ILS system inner marker location will be on the airport property and the marker location may be plotted on the airport or general layout plan. The location tolerances for the inner marker
Chap 4 Page 74 Par 62
11/25/77 6750.36
(within a radius of 25 feet from the desired DH point) is given by 0rder 6750.4.
(3) Localizer Elevated Antenna. Where there are requirements for a localizer elevated platform, or problems associated with antennas penetrating approach surfaces or approach light systems, it will be useful to make a simple vertical plot or calculation of the facility and surfaces involved. Figure 4-l suggests a non-scaled presentation of the vertical situation. This type of plotting minimizes the study time required in the field and gives the engineer a quick reference, which helps to ensure that all of the information required by the field investigation is, in fact, obtained.
b. Facilities to be Located Off Airport Property. The USGS topographic maps will be most useful for plotting the proposed location or search area for the outer marker, COMLO, NDB, and possibly the middle marker.If photogrammetrics with the extended runway centerline are available, the plotting may be accomplished directly on the photogrammetric or photograph. Figures 5-8 and 5-9 suggest the manner in which the search areas should be plotted. Where the Flight Standards division and others have identified a specific marker location that is required by specific approach procedures, the tolerance of the search areas should extend from the specific point rather than the entire 4-to 7-nautical miles from runway threshold.
64. FIELD LIAISON. Prior to actually going to the field to perform the site survey, contact should be made with field personnel who are responsible for, and cognizant of, the facilities and operations at the airport. In general, the following personnel or organizations should be contacted.
a. The Airway Facilities sector and/or sector field office, and the Airports district office should be contacted and advised of the proposed site survey and the approximate time frame over which the field work is proposed.
b. The Airport Manager and/or the Airport Authority responsible for the airport operation should be contacted. The airport manager is aware of personnel or departments knowledgeable with airport civil works such as power, ducting, and drainage. He can also provide information on consulting engineering firms that will have drawings and documentation related to planning, construction, finished elevations, and previous survey work. Advance scheduling and arrangements should be determined as much as possible with respect to general airport security and access. Details regarding access arrangements and work requirements may be arranged after arriving at the airport.
Chap 4 Par 63 Page 75
FIGURE 4-1. VERTICAL SKETCH OF LOCALIZER Page 76 ANTENNA HEIGHT REQUIREMENTS
FIGURE 4-1. VERTICAL SKETCH OF LOCALIZER Page 76 ANTENNA HEIGHT REQUIREMENTS
TCH EL 995
EL 952.8 EL 962. Line of sight (LOC to TCH)
10.8 ft. 1000 ft. RWY Profile EL 942 1100 ft. 7500 ft.
8500 ft.
6750.36
GS Path
55 ft.
EL 940
Threshold
Localizer Stop End
Par 64
11/25/77
11/25/77 6750.36
c. USGS and National Geodetic Survey (NGS) Datum (bench marks) available in the area may be determined by a telephone call to the nearest appropriate government office or from the consulting engineering firm retained by the airport. Paragraph 91b describes the source of monumented locating points.
65. AIRPORT DEVELOPMENT AID PROGRAM (ADAP). Although it is not the function of the site survey personnel to participate in any discussions or arrangements regarding the role of ADAP in the ILS site preparation, the site survey engineer should acquaint himself with the status and extent of proposed site preparation. This information may be obtained from the Airports division in the regional office or the local ADO. Copies of the drawings indicating the proposed finished grades may be available. This information, whether obtained during the office planning work or during the site survey, is necessary in the preparation of the final design locations and elevations. The Airport division or ADO is especially cognizant of ADAP construction plans and scheduling.
66. ENVIRONMENTAL. The Airway Facilities personnel in the regional office are responsible for coordinating the environmental impact considerations relating to the establishment of ILS systems. In some instances, they may also prepare the environmental assessment and subsequently an environmental impact statement (EIS) or negative declaration (ND). The environmental considerations and statements shall be in accordance with Order 1050.1. The engineers performing the site survey work should familiarize themselves with those items that. will have an impact on the proposed installation. For on-airport facilities, the airport sponsor or the Airports division of the regional office may have already developed an environmental assessment encompassing ILS elements.
67.-80. RESERVED.
Chap 4 Par 64 Page 77 (thru 90)
11/25/77 6750.36
CHAPTER 5. FIELD SURVEY
CHAPTER 5. FIELD SURVEY
SECTION 1. INTRODUCTION
81. FACTORS TO CONSIDER. The field survey work should proceed in a planned and orderly manner to best use the available time, interface with the normal airport operations, and ensure that the required data for the ILS design and documentation is complete. It is suggested that the field work proceed along the following lines:
SECTION 1. INTRODUCTION
a. Contact Local Personnel. Contact and discuss the task with the local FAA and airport personnel.
b. Access Arrangements. Make the necessary airport access arrangements.
c. Obtain Maps and Drawings. Obtain those maps and/or drawings not previously available.
d. Ascertain Special Requirements. Ascertain special construction standards required by the airport, as well as insurance and security requirements.
e. Cursory Visual Inspection. Make an initial visual inspection of the areas where the proposed facilities are to be located.
f. Examine Sites Requiring Real Estate Action. Accomplish investigation for outer marker and/or COML0 facilities sites. Logistics division real estate personnel should be advised of the site requirements prior to beginning the field survey work. Investigation for the other markers or facilities, which may be off the airport property, should also begin early in order to provide as much time as practical for the real estate considerations. Bear in mind that the LG division would prefer to have a minimum of four months to lease and six months to purchase real property wherever possible.
g. Detailed Survey of Sites. Accomplish detailed survey of the proposed facilities.
h. Prepare Preliminary Report and Review. Prepare field sketches or drawings and evaluate data.
82. PERSONNEL LIAISON. Upon arrival at the airport, the site survey engineer should make arrangements for access to the areas to be surveyed and determine the sources of information available for the survey.
a. FAA. The ADO office should have the information on the status of the sponsor's site preparation as well as other information that will be needed. The local Airway Facilities organization will be cognizant of all existing facilities and may be able to provide on-airport transportation and assistance with the investigation and survey work.
Chap 5 Par 81 Page 91
6750.36 11/25/77
The local air traffic control personnel are familiar with the operations and can assist in scheduling work. All work performed on the airport should be coordinated with local air traffic personnel.
b. Airport Manager. The airport manager can provide existing sources of documentation that have been used for construction and planning. He can further advise of consulting engineering sources that have been responsible for airport planning and engineering and that often have complete sets of drawings. The equipment facilities of many of the larger airports are under the control of an airport authority or county or municipal public works department. These organizations usually have one or two engineers whose particular responsibility is the airport engineering. The use of airport power sources, duct bank availability, access roads, and other matters should be discussed with the airport manager or those responsible for the airport engineering. In discussions of the ILS project with the airport manager or other local authority, care must be taken regarding the facility site preparation plan since the airport manager may not be aware of the distinction between the Airway Facilities and the Airports organizations. Unless specifically authorized to do so, the site survey engineer should not conduct discussions regarding plans for site preparation work with the sponsor. He may discuss the extent and progress of work regarding ILS site preparation with the Airports divisions or local ADO.
c. Civil and Consulting Engineers. Airport civil and consulting engineering organizations should be contacted, through the airport sponsor whenever necessary in order to determine what additional drawings, proposed or finished elevations, construction conditions, and previous survey work have been accomplished and may be useful in the ILS survey work. In most cases drawings and information will be supplied without cost.
83. LOCAL MAPS AND DRAWINGS. Those maps and drawings providing information for the survey and not previously available in the regional office should be obtained through the sources discussed in paragraph 82. Paragraph 62 describes these maps and drawings.
84. CURSORY INSPECTION OF POTENTIAL ILS SITES. Before beginning the survey work for each of the components of the ILS system, it is suggested that a cursory general inspection be made of the areas involved. The purpose of such a visual inspection is to learn if there may be unusual requirements and/or problems that may be encountered in the survey. Examples of the insights to be gained by a visual inspection are listed.
a. A shelter or antenna located in dense undergrowth may require the need for additional help for surveying.
b. Areas temporarily flooded or under standing water may necessitate the rescheduling of work.
Chap 5 Page 92 Par82
11/25/77 6750.36
c. Obvious construction difficulties or unusual terrain may require reconsultation with the project engineer or other regional engineers.
d. Marker search areas in densely populated communities may suggest consultation regarding other means for establishing approach fixes.
e. Obvious requirements for waivers because of physical restrictions, etc.
f. The site survey engineers can better plan their work if they are familiar with the area over which they will be working.
85.-90. RESERVED.
Chap 5 Par 84 Page 93 (thru 100)
11/25/77 6750.36
SECTION 2. GENERAL ILS SITE SURVEY REQUIREMENTS
SECTION 2. GENERAL ILS SITE SURVEY REQUIREMENTS
91. DETERMINATION OF COORDINATES, DISTANCES, AND ELEVATIONS.
a. Tolerances. The required survey accuracy of the locations of ILS facility elements is determined by the headquarters Flight Standards Service. The location accuracy of ILS equipment antennas situated on the airport (including the middle marker) shall be determined to within ±1 foot in the horizontal plane and elevations of the antennas shall be determined within +0.1 foot. The accuracy location of the outer marker and/or COMLO or NDB shall be within ±40 feet in the horizontal plane and ±100 feet in elevation. An accuracy in location of 1 foot in distance is approximately equivalent to 0.01 second of latitude and approximately 0.01 second of longitude at the equator to approximately 0.02 second of longitude at sites located in northern Alaska.
b. Published Information.
(1) The geographical coordinates of the airport reference point (ARP) and certain runway ends for many airports have been determined by NOS, Department of Commerce, National Oceanic and Atmospheric Administration. These surveys by NOS are "third order" surveys and the coordinates and runway centerline azimuths are shown on many published OC charts. The coordinates of the runway ends are shown to the nearest hundreths of a second. The geodetic azimuth of the runway centerlines are shown to the nearest second. The coordinates of the ARP are shown to the nearest tenth of a second. The information determined by the NOS surveys has been supplied to the FAA and is available from the FAA National Flight Data Center (AAT-430). Many monuments or horizontal and vertical control positions have been estab- 1ished over the United States and at most airports by USGS, and by NOAA, National Geodetic Survey (formerly the U.S. Coast and Geodetic Survey). Where these monuments can be located and identified, information regarding their position and elevation is available from the appropriate agency. Information regarding USGS monuments may be obtained from:
U.S. Geological Survey National Center Reston, Virginia 22092 Attention: Geodetic Control Section Phone:(703) 860-6045
(2) The USGS also publishes a list of the horizontal and vertical control positions,which is available from the National Center. Information regarding monuments established by the National Geodetic Survey is available from:
Chap 5 Par 91 Page 101
6750.36 11/25/77
National Oceanic & Atmospheric Administration Director, National Geodetic Survey Rockville, Maryland 20852
(3) In addition to the monuments established by the above mentioned Federal agencies, many states have established a plane coordinate system, which may be used for accurately determining the position of approach navaid facilities.
c. Determination of Locations.
(1) Scaling of coordinates and distances from an OC chart will normally yield accuracies of approximately ±0.2 second for geographical coordinates and +10 feet in distance; consequently, to meet the accuracies required in paragraph 91a, the coordinates and distances of ILS facilities located on the airport will have to be determined by actual measurement from existing data Careful scaling from the 7-1/2 minute series (scale approximately 1 inch = 2,000 feet) of USGS topographic charts can yield an accuracy of approximately ±40 feet; consequently, this method may be used for determining the location of a distance to the outer marker and/or COMLO or NDB where no other datum is available. The site survey engineer should make an effort to locate and use either USGS, National Geodetic Survey, or state plane coordinate system monuments if practical. The distance and geodetic azimuth between sets of geographic coordinates may readily be calculated with hand-held calculators using the following equations:
D = K cos -1 [sin(L) sin(L2) + cos(L1) cos(L2) cos( λ1- λ2)]
B = cos -1 [sin(L2) - sin(L1) cos(D/K)] sin(D/K) cos(L1)
where: L1, ^1 latitude and longitude of first point
L2, ^2 latitude and longitude of second point
D distance between the points (see K)
B bearing from first point to second point
K 60 for D in nautical miles
K 364, 566.90 for D in feet
K 111.120 for D in kilometers
Chap 5 Page 102 Par 91
11/25/77
The coordinates of locations on and in the vicinity of the air-
(2)
port may more conveniently be determined by using the distances per second of latitude and longitude. One (1) second of latitude is equal to a north-south distance of 101.3 feet. The east-west distance represented by one (1) second of longitude varies due to the convergence of meridians and is given in table 5-1 for latitudes between the equator and 70 degrees.
TABLE 5-1. LENGTH OF A SECOND OF LONGITUDE
TABLE 5-1. LENGTH OF A SECOND OF LONGITUDE
LATITUDE (DEGREES)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Chap 5 Par 91
FT./SEC. OF LONGITUDE
101.45 101.44 101.39 101.31 101.21 101.07 100.90 100.70 100.47 100.21 99.92 99.60 99.25 98.87 98.46 98.02 97.55 97.05 96.52 95.96 95.37 94.76 94.11 93.44 92.73 92.00 91.24 90.46 89.65 88.80 87.94 87.04 86.12 85.17 84.20 83.20
LATITUDE (DEGREES)
LATITUDE (DEGREES)
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70
FT./SEC. OF LONGITUDE
82.17 81.12 80.05 78.95 77.83 76.68 75.51 74.31 73.10 71.86 70.60 69.32 68.01 66.69 65.34 63.98 62.59 61.19 59.77 58.32 56.86 55.39 53.89 52.38 50.86 49.32 47.75 46.18 44.60 43.00 41.38 39.76 38.12 36.46 34.80
FT./SEC. OF LONGITUDE
6750.36 11/25/77
d. Determination of Elevations. The elevations for the approach navaid facilities located on the airport (including the middle marker) shall be determined by ground level surveying to the nearest 0.1 foot, using datum at the airport such as the elevation of the runway threshold or suitable bench marks. The elevation of the ground at the outer marker and/or COMLO or NDB may be carefully interpolated from the contours on the 7-1/2-minute series of USGS topographic charts if no reliable datum is available in the vicinity.
e. Recording of Distances, Elevations, and Coordinates.
(1) Horizontal Distances. Horizontal longitudinal and lateral distances on the airport (including the location of the middle marker) shall be recorded to the nearest foot. The corresponding distances to the outer marker and/or COMLO or NDB shali be recorded to the nearest 10 feet. The distance to the outer marker should also be recorded in nautical miles (1 nautical mile = 6,076 feet) to the nearest one-hundreths of a mile as calculated from the distance used in feet. The international unit now officially used in the United States is equal to 6076.115 feet. The old United States unit equal to 6080.20 feet has not been used officially since July 1, 1959.
(2) Elevations. Elevations of the ground and/or structures associated with the approach navaids facilities on the airport shall be recorded to the nearest tenth of a foot. Elevations of the ground at the outer marker and/or COMLO or NDB shall be recorded to the nearest 100 feet. However, since the contour intervals shown on the USGS topographic maps are 20 feet, the site survey engineer may record the elevation that can readily be interpolated from the map.
(3) Geographical Coordinates. The geographical coordinates of the approach navaid locations on the airport shall be recorded to the nearest 0.01 second. The coordinates of the outer marker and/or COMLO or NDB shal1 be noted to the nearest one-half second.
(4) Threshold Crossing Height. The calculated threshold crossing height shal1 be recorded to the nearest tenth of a foot. The calculated specific intercept points along the glide path above the markers shall be recorded to the nearest foot.
f. Intercept Altitude. The intercept altitude of the glide path with respect to the outer marker should be calculated. At distances beyond 2 miles from the runway threshold, corrections that are due to the curvature of the earth become significant and should be added to the elevation computed from the glide slope path extended from the airport. The earth curvature may be calculated or may be conveniently taken from Figure 5-1, Correction for Earth Curvature. The calculated elevation of the intercept of the glide slope approach plane
Chap 5 Page 104 Par 91
11/25/77
FIGURE 5-1. CORRECTION FOR EARTH CURVATURE
FIGURE 5-1. CORRECTION FOR EARTH CURVATURE
COR UDE
4
NAUT. MILES ANTENNA TO OM
6 8 10 CORRECTION FOR EARTH CURVATURE
1 Nautica1 M1le = 6076'
Chap 5 Par 91
6750.36 11/25/77
with a point directly above the outer marker shall be noted in feet above mean sea level. Figure 5-2 is a sample application of the earth curvature correction.
1 Nautica1 M1le = 6076'
92. REAL ESTATE CONSIDERATIONS.
a. Availability of Land. Land used for the outer marker, COMLO, and NDB (and sometimes the middle marker) sites are located away from the airport. The location for the facility plot will depend upon the availability of land in the desired area.
b. Lease or Purchase of Land. The decision as to whether land for a facility plot should be leased or purchased will be made by the Logistics division and depends upon the value of the land, the recurring costs for leasing, and the period of time the facility may be required. Orders 4423.2 and 4660.1 prescribe the policy that will be used.
c. Contacting Property Owners. The site survey engineer should not conduct negotiations with a property owner either for purposes of leasing or purchasing a site. He may, with the permission of or at the direction of the Logistics division (real estate), participate in discussions relating to the conduct of surveys and general information necessary to determine the suitability of the site and the construction requirements. In this connection, the site survey engineer should become familiar with the general provisions and implications of the Uniform Relocation Assistance and Real Property Act of 1970 (Public Law 91-646). The Logistics division real estate personnel will provide guidance on FAA precautions and responsibilities under this Act. The Logistics division will need to know of the requirements for a plot as soon as a suitable location or locations can be determined. It is desirable that real estate personnel from the regional Logistics division accompany the survey engineer in the field. Where Logistics personnel are unavailable at the time of the survey, the required information may have to be exchanged with real estate personnel by mail or telephone. In some instances, the site survey engineer may have to return to the site for detailed survey work after negotiations are completed.