AC 150/5000-9B Guidelines for Sound Insulation of Structures Exposed to Aircraft Noise

This AC provides guidelines to develop and implement a sound insulation program (SIP).

Official source ↗ Open PDF

Text read by OCR from a scanned file (11 of 167 pages). Check the original, as some words may be misread.

U.S. Department of Transportation Federal Aviation Administration

Advisory Circular

Subject: Guidelines for Sound Insulation of Structures Exposed to Aircraft Noise

Date: 6/8/2022 Initiated By: APP-400

AC No: 150/5000-9B Change:

1. Purpose.

This advisory circular (AC) provides guidelines to develop and implement a sound insulation program (SIP).

2. Cancellation.

This AC cancels AC 150/5000-9A, Announcement of Availability--Report No. DOT/FAA/PP/92-5, “Guidelines for the Sound Insulation of Residences Exposed to Aircraft Operations” dated July 2, 1993, and changes the title of the AC to “Guidelines for Sound Insulation of Structures Exposed to Aircraft Noise”.

3. Application.

This AC is intended for use by the Federal Aviation Administration (FAA), airport operators,1 airport sponsors,2 and airport consultants or contractors to develop and manage sound insulation programs (SIPs) established to mitigate noise impacts to structures3 exposed to aircraft noise around airports. The FAA considers the standards and processes described in this AC essential for the fidelity of SIPs. However, this AC does not constitute a regulation and is not legally binding in its own right and it will not be relied upon as a separate basis by the FAA for affirmative enforcement action or other administrative penalties. Conformity with this AC is voluntary and 1 Airport operator means the operator of an airport as defined in 49 U.S.C. § 47501 (2)(A) and (B) which states “for an airport serving air carriers that have certificates from the Secretary of Transportation, any person holding an airport operating certificate issued under 49 U.S.C. § 44706 and for any other airport, the person operating the airport”.

2Airport Sponsor means a federal financial assistance recipient as defined in 49 U.S.C. § 47102(26)(A) and (B) which states “a public agency that submits to the Secretary […]an application for financial assistance” and “a private owner of a public-use airport that submits to the Secretary […] an application for financial assistance for the airport” and in FAA Order 5100.38D- Change 1 (Airport Improvement Handbook), Chapter 2, Section 2-2, page 2-1 through 2-2. For the purposes of this AC, not all airport sponsors are airport operators, and several programs at airports are managed by program sponsors, not airport operators. Therefore, airport operator or sponsor is used throughout unless otherwise specified. 3 Residences, public buildings (e.g., educational and medical facilities, places of worship), and historic properties that are eligible for sound insulation are referred to as “structures” in this AC.

ii

nonconformity will not affect rights and obligations under existing statutes and regulations, except for circumstances involving federal financial assistance.4 This AC is effective on the date of publication. Airports with established SIPs should consult with FAA regarding changes to airport operations that may require re-evaluation and following the standards and processes in this AC.

4. Principal Changes.

The previous AC focused on technical aspects of developing SIPs, such as sound exposure and insulation metrics. However, information regarding other aspects of SIP implementation was limited or outdated. This AC provides standards, processes and procedures, and guidelines for all phases of developing and implementing a SIP as well as technical updates5 associated with SIP development, including property surveys, acoustic engineering principles and testing methods, establishing boundaries, and determining noise level reductions. Therefore, principal changes included, but were not limited to, details on roles and responsibilities and procedures for SIP initiation through completion; standards for acoustic testing, funding opportunities, and project costs; and considerations for community outreach, project phasing, and sound insulation treatments.

Robert Craven Director, Office of Airport Planning and Programming

4 Use of standards and guidelines in this AC is mandatory for relevant sound insulation projects funded though Federal grant assistance programs, including the Airport Improvement Program (see Grant Assurance #34) and projects funded through the Passenger Facility Charge Program (see PFC Assurance #9). 5 Technical updates to this AC included incorporating sources such as the Transportation Research Board’s Airport Cooperative Research Program Reports, specifically the “Guidelines for Airport Sound Insulation Programs” (Report 89) and “Evaluating Methods for Determining Interior Noise Levels Used in Airport Sound Insulation Programs” (Report 152). Additionally, this AC includes methods for measuring the aircraft noise level reduction of building façades as described in Aerospace Recommended Practice: Airport Noise Level Reduction Measurement of Building Facades report (ARP6973)

CONTENTS Paragraph Page

iii

Chapter 1. Introduction … 1-1

1.1 Introduction … 1-1

1.2 Purpose … 1-2

1.3 Background … 1-3

1.4 Relevant Laws, Regulations, and Policies … 1-3

Chapter 2. Roles and Responsibilities … 2-1

2.1 Overview … 2-1

2.2 FAA Personnel … 2-1

2.3 Airport Operator or Sponsor and Consultant Team … 2-2

2.4 Property (Structure) Owner Responsibilities … 2-11

Chapter 3. Sound Insulation Program Process … 3-1

3.1 Overview … 3-1

3.2 Initiate Sound Insulation Program Efforts (Phase 1) … 3-2

3.3 Implementation Phase (Phase 2) … 3-11

3.4 Close Out Phase (Phase 3) … 3-13

Chapter 4. Estimating Project Costs and Funding … 4-1

4.1 Funding … 4-1

4.2 Cost Development … 4-2

4.3 Contracting and Procurement … 4-4

Chapter 5. Community Outreach … 5-1

5.1 Community Involvement … 5-1

5.2 Plan … 5-1

5.3 Design and Implement … 5-2

5.4 Assess, Reevaluate, and Update as Necessary … 5-2

Chapter 6. Developing a Sound Insulation Program … 6-1

6.1 Introduction … 6-1

6.2 Funding, Scheduling, and Strategic Phasing … 6-1

6.3 Determination of Phase Boundaries … 6-3

6.4 Identification of Non-compatible (Impacted) Structures … 6-4

CONTENTS Paragraph Page

iv

6.5 Treatment Options and Procurement … 6-5

Chapter 7. Sound Insulation Treatment Strategies … 7-1

7.1 Background … 7-1

7.2 Windows and Doors … 7-1

7.3 Ventilation … 7-3

7.4 Insulating Public Buildings … 7-4

7.5 Hazardous Materials … 7-4

Chapter 8. Acoustical Engineering and Testing … 8-1

8.1 Background … 8-1

8.2 Habitable Spaces Overview … 8-1

8.3 Acoustical Testing … 8-6

8.4 Flyover Measurement Method … 8-7

8.5 Loudspeaker Measurement Method … 8-11

8.6 Determination of Interior Noise Levels for SIP Eligibility … 8-37

8.7 Application of Modeled Results … 8-51

8.8 Acoustical Retesting … 8-52

8.9 Recommendations for Retesting … 8-53

Chapter 9. Reporting and Closeout … 9-1

9.1 Background … 9-1

9.2 Quarterly and Annual Reporting … 9-1

9.3 Closeout Reporting … 9-3

9.4 Links to Tools, Forms, and Templates … 9-5

v

FIGURES

Number Page Figure 3-1. Overview of the Sound Insulation Program Process … 3-2 Figure 5-1. Community Outreach Process … 5-3 Figure 6-1. Sample SIP Phasing Under AIP Grants … 6-2 Figure 8-1. Acoustical Testing Process … 8-1 Figure 8-2. Design Chart for Determining Loudspeaker Distance and Angle of Incidence to

Figure 5-1: picture of page 5Figure 5-1 · page 5
Picture of the page from the copy saved here

Achieve a Maximum Variation of 3 dB over a Façade Surface … 8-15 Figure 8-3. Process for Selecting the Testing Sample for Apartment Buildings … 8-42 Figure 8-4. Process for Selecting the Testing Sample for Condominium Buildings … 8-44

TABLES

Number Page Table 2-1. Airport Operator or Sponsor’s SIP Development and Implementation Team Roles and

Figure 8-3: picture of page 5Figure 8-3 · page 5
Picture of the page from the copy saved here

Responsibilities … 2-4 Table 4-1. Program Elements to Consider in Determining Program Cost … 4-3 Table 6-1. Examples of Common Types of Residential Structures and Typical Treatments … 6-7 Table 7-1. Hazardous Materials Typically Found During Structure Inspections … 7-5 Table 8-1. Property Survey Data Collection for Multi-Family Residences … 8-3 Table 8-2. Property Survey Data Collection for Educational and Other Facilities … 8-4 Table 8-3. Documentation Checklist Onsite Setup and Conditions … 8-10 Table 8-4. Data to be Recorded in Field Testing for Flyover Measurement Method … 8-10 Table 8-5. Corrections for Roof Transmission Exterior Façade … 8-31 Table 8-6. Example of Octave Band Calculation of NLR … 8-35 Table 8-7. Data to be Recorded in Field Testing for the Loudspeaker Measurement Method .. 8-37 Table 8-8. Appropriate Interior Noise Level Metrics by Structure Type … 8-38 Table 8-9. Specific Noise Level Assumptions for Single Family Residences … 8-39 Table 8-10. Specific Noise Level Assumptions for Multi-Family Residences … 8-43 Table 8-11. Process for Determining Average Interior DNL for Apartment and Condominium

Buildings … 8-46 Table 8-12. Specific Noise Level Assumptions for Educational Facilities … 8-48 Table 9-1. Examples of Types of SIP Documents … 9-6

vi

Page Intentionally Left Blank

CHAPTER 1. INTRODUCTION

1.1 Introduction

1.1.1 The goal of a Sound Insulation Program (SIP) is to develop a plan and approach to implementing sound insulation treatment to mitigate or minimize the effects of noise from aircraft and other airport operations in communities near airports. Specifically, when sound insulation treatment for structures6 determined to be non-compatible with aviation noise is recommended as a result of the analysis completed as part of a Noise Compatibility Program (NCP) or analysis prepared in compliance environmental protection laws, such as the National Environmental Policy Act of 1969 (NEPA). Not all airports have SIPs; however, airports that have or plan to develop SIPs, tailor these to address the local community and rely on the SIP development process to determine items such as who is eligible for sound insulation treatment and the timeline for SIP implementation.

1.1 Introduction › 1.1.2 This chapter presents the purpose, background, and an overview of…

1.1.2 This chapter presents the purpose, background, and an overview of information relevant to the purpose and content of this advisory circular (AC). The remaining chapters and appendices address the following topics or information:

 Chapter 2 - Roles and Responsibilities. Describes responsibilities of the Federal

Aviation Administration (FAA), airport operators or sponsors, and airport contractors or consultants.

 Chapter 3 - Development of a Sound Insulation Program. Outlines process and

procedures for SIP development, including preparation of a Program Policy and Procedure Manual (PPM).

 Chapter 4 - Project Cost Development and Funding. Describes SIP funding

opportunities, cost development, and contracting and procurement.

 Chapter 5 - Community Outreach. Outlines the strategies for conducting

community outreach during development and implementation of SIPs.

 Chapter 6 - Defining and Implementing Individual Phase Components. Explains

recommended strategies for phasing SIPs in relation to funding, identification of non-compatible buildings, determination of phase boundaries, and acoustical testing and construction.

 Chapter 7 - Sound Insulation Treatment Strategies. Identifies sound insulation

treatments considerations based on architectural design, interior features, and exterior influences. This chapter also addresses other design and construction considerations.

 Chapter 8 - Acoustical Engineering and Testing. Defines the acoustical testing

process to measure and calculate interior noise level reductions, the application of modeled results, field measurement adjustment, and acoustical retesting.

6 Residences, public buildings (e.g., educational and medical facilities, places of worship), and historic properties that are eligible for sound insulation are referred to as “structures” in this AC.

1.2 Purpose › 1.2.2 As indicated in the preface to this AC, the FAA considers the…

 Chapter 9 - Reporting and Closeout. Describes best practices for reporting and

closeout requirements.

 Appendices with additional information:

o Appendix A Roles and Responsibilities Matrix

o Appendix B Definitions and Acronyms

o Appendix C Sample Checklists and Other Forms

1.2 Purpose

1.2.1 The purpose of this AC is to provide standards, processes and procedures, and guidelines for the development and implementation of SIPs to mitigate aircraft noise impacts around airports. This AC is intended for use by Federal Aviation Administration (FAA) personnel, airport operators,7 airport sponsors,8 and airport consultants or contractors to ensure a SIP is prepared and implemented with applicable requirements and in concert with laws, regulations, and policies that have a bearing on SIPs (see section 1.4), and are accurately presented to the public. This AC includes uniform procedures to define and implement a SIP for structures determined to be noncompatible with aviation noise, standardized acoustic testing methodology to identify non-compatible structures, and best practices for use in public outreach efforts to ensure informed expectations of SIPs.

1.2.2 As indicated in the preface to this AC, the FAA considers the standards and procedures in this AC essential for the fidelity of SIPs, however, this AC does not constitute a regulation, is not legally binding in its own right, and it will not be relied upon as a separate basis by the FAA for affirmative enforcement action or other administrative penalties. Conformity with this AC is voluntary and nonconformity will not affect rights and obligations under existing laws and regulations, except for circumstances involving federal financial assistance as follows:

 Use of standards and guidelines in this AC is mandatory for projects funded

through Federal grant assistance programs, including the Airport Improvement Program (see Grant Assurance #34); and

 Use of standards and guidelines in this AC is mandatory for projects funded

through the Passenger Facility Charge (PFC) Program (see PFC Assurance #9).

7 Airport operator means the operator of an airport as defined in 49 U.S.C. § 47501 (2)(A) and (B) which states “for an airport serving air carriers that have certificates from the Secretary of Transportation, any person holding an airport operating certificate issued under 49 U.S.C. § 44706 and for any other airport, the person operating the airport”. 8 Airport Sponsor means a federal financial assistance recipient as defined in 49 U.S.C. §47102(26)(A) and (B) which states “a public agency that submits to the Secretary […]an application for financial assistance” and “a private owner of a public-use airport that submits to the Secretary […] an application for financial assistance for the airport” and in FAA Order 5100.38D- Change 1 (Airport Improvement Handbook), Chapter 2, Section 2-2, page 2-1 through 2-2. For the purposes of this AC, not all airport sponsors are airport operators, and several programs at airports are managed by program sponsors, not airport operators. Therefore, airport operator or sponsor is used throughout unless otherwise specified.

1.4 Relevant Laws, Regulations, and Policies › 1.4.2 14 CFR Part 150 Airport Noise Compatibility Program

1.3 Background

Since the enactment of the Aviation Safety and Noise Abatement Act (ASNA) and promulgation of regulations governing Noise Compatibility Programs, (14 Code of Federal Regulations (CFR) Part 150), the FAA has played a key role in encouraging airport noise compatibility planning and strives to reduce noise impacts in ways within its purview, including supporting airports with the implementation of SIPs by providing financial assistance for sound insulation treatment for residences and public buildings, land use measures such as the acquisition of surrounding properties, and funding research initiatives for noise mitigation. Airport operators or sponsors may receive financial assistance from the FAA to implement measures to achieve noise compatibility pursuant to 14 CFR Part 150 (commonly referred to as the “Part 150 Process” or “Part 150 study”) or as part of a federal action9 per applicable environmental protection laws and regulations (see section 1.4). However, airport operators or sponsors do not have to use the Part 150 process to achieve noise compatibility. Some airports can establish a successful program to achieve noise compatibility outside of the Part 150 process, by working proactively with neighboring communities and user groups to address similar objectives.

1.4 Relevant Laws, Regulations, and Policies

This section provides an overview of laws, regulations, and policies that have a bearing on the development and implementation of SIPs, including determining funding eligibility (e.g., residents eligible for sound insulation treatment or land acquisition opportunities). Details about how these apply are also discussed throughout, in other chapters, when relevant.

1.4.1 Aviation Safety and Noise Abatement Act The ASNA of 197910 was enacted in February 1980 to provide assistance to encourage airport operators to prepare and carry out noise compatibility programs, among other purposes. ASNA required the promulgation of regulations to meet three key requirements: (1) Establish a single system for considering aviation noise around airport communities that has a highly reliable relationship between projected noise exposure and surveyed reactions of individuals to noise; and is applied uniformly in measuring noise at airports and the surrounding area; (2) Establish a single system for determining noise exposure from airport operations, which takes into account noise intensity, duration of exposure, frequency of operations, and time of occurrence; and (3) Identify land uses which are normally compatible with various exposures of individuals to noise.

1.4.2 14 CFR Part 150 Airport Noise Compatibility Program To implement the requirements established under the ASNA, the FAA published 14 CFR Part 150. This regulation describes standards, procedures, and methodologies governing the development, submission, and review of noise compatibility programs (NCPs), including the associated noise exposure maps (NEMs). It also established a

9 A federal action may involve federal funding and/or a project subject to federal control and responsibility. 10 Aviation Safety and Noise Abatement Act of 1979, Pub. L. No. 96-193 (Feb. 27, 1979).

1.4 Relevant Laws, Regulations, and Policies › 1.4.4 National Environmental Policy Act of 1969

single system for measuring noise exposure and outlines compatible land uses for varying noise exposure levels from airport operations. The Part 150 process provides a structured approach for collaboration between the airport, airlines, other airport users, neighboring communities, and the FAA. It results in the airport’s submission of NEMs and NCPs to the FAA,11 which describes the proposed methods to achieve land use compatibility. A variety of different strategies to reduce the impacts of noise and achieve compatibly can be considered during the Part 150 process, such as changes in operational procedures (e.g., take-offs or landings or routing flight paths over less noise sensitive areas), purchasing land near airports to maintain compatible land use or installing sound insulation for homes, schools, and other buildings near the airport that meet the required standards. Therefore, the development of a SIP is a common component of the Part 150 process and the resulting NCP. A SIP is useful in identifying and prioritizing the installation of sound insulation treatment for properties exposed to aircraft noise around airports. This prioritization is largely based on boundaries defined in a SIP which are determined during Part 150 process using NEMs. NEMs must be current to determine impacted structures, therefore, initial boundaries in a SIP will be updated if updated NEMs reflect shifts in noise exposure.

1.4.3 FAA Final Policy on Part 150 Approval of Noise Mitigation Measures Effect on the Use of Federal Grants for Noise Mitigation Projects (63 Federal Register 16409, April 3, 1998), establishes that residential property constructed after October 1, 1998 and within the DNL 65 dB, or above, contour of an NEM published prior to the property’s construction, is not approved for remedial noise mitigation. This also applies to partial renovations and additions.

1.4.4 National Environmental Policy Act of 1969 NEPA requires federal agencies to examine the environmental impacts of their proposed actions within the United States and its territories. A NEPA document12 provides an assessment of the potential effects a major federal action may have on the human environment. Major federal actions include activities that federal agencies fully or partially fund, regulate, conduct, or approve. Therefore, FAA analyzes the environmental effects associated with a proposed action and prepares the appropriate NEPA documentation. During the NEPA process, noise impacts and mitigation measures for significant noise impacts13 may be identified and analyzed and noise mitigation commitments are documented in a decision document (e.g., a Record of Decision (ROD) associated with an Environmental Impact Statement (EIS) or Finding

11 The FAA approves or disapproves NCP conformance with 14 CFR Part 150, however, this approval does not imply funding eligibility. 12 For the purposes of this explanation, a NEPA document is an environmental assessment or environmental impact statement. An environmental assessment is more concise and less detailed than an environmental impact statement. 13 In FAA Order 1050.1F, “Environmental Impacts: Policies and Procedures,” FAA identifies its significance threshold as an “increase [in] noise by DNL 1.5 dB or more for a noise sensitive area that is exposed to noise at or above the DNL 65 dB noise exposure level, or that will be [newly] exposed at or above the DNL 65 dB level due to a DNL 1.5 dB or greater increase, when compared to the no action alternative for the same timeframe.”. FAA adoption of DNL 65 dBA in the NEPA significance threshold was based on the "significance" of aviation noise exposure at or above that level, as described in "general guidelines for noise compatibility" and reflected in the Part 150 land use compatibility guidelines.

1.4 Relevant Laws, Regulations, and Policies › 1.4.7 FAA Order 5100.38, Airport Improvement Program Handbook.

of No Significant Impact (FONSI)/ROD associated with an Environmental Assessment (EA)). If a decision document under NEPA includes sound insulation treatment for structures as a mitigation measure, this information will be used to support the definition of the boundaries outlined in a SIP. In addition, noise mitigation commitments defined in a ROD or FONSI/ROD will not change unless project modifications result in new or altered significant noise impacts.14 For information about compliance with NEPA, refer to FAA policies and procedures for implementing NEPA, FAA Order 1050.1, Environmental Impacts: Policies and Procedures.

1.4.5 National Historic Preservation Act of 1966 Section 106 of the National Historic Preservation Act (NHPA), 54 United States Code (U.S.C.) § 306108 and its implementing regulations, 36 CFR Part 800 require federal agencies to consider the effects of federally funded projects on historic properties (i.e., listed or eligible for listing, in the National Register of Historic Places), and when applicable, consult with the State Historic Preservation Officer (SHPO) and provide other consulting parties and the public an opportunity to comment on these projects prior to the expenditure of any federal funds. Therefore, any sound insulation treatment project to be funded through AIP grants or PFC revenue is subject to review under Section 106 and airport operators or sponsors must coordinate with the FAA prior to starting initial phases (e.g., design/pre-construction testing) for installing sound insulation treatment so that compliance with Section 106 is adequately addressed.

1.4.6 Section 4(f) of the Department of Transportation Act of 1966 Section 4(f) of the Department of Transportation Act of 1966 (now codified in 49 U.S.C. § 303 and 23 U.S.C. §138) is triggered by funding or approval from a DOT agency for a project that proposes use of resources protected under Section 4(f) including historic property or land from a publicly owned park, recreation area, or wildlife. Consideration should be given to better integrate and streamline Section 4(f) and Section 106 of the NHPA with the NEPA process. Consideration of these requirements should also be given during the Part 150 process.

1.4.7 FAA Order 5100.38, Airport Improvement Program Handbook. The AIP Handbook provides guidance on eligibility and justification for noise abatement and mitigation measures under the AIP. The AIP Handbook is regularly updated in response to changes to AIP-related legislation in U.S. Code (U.S.C.). This AC refers to the AIP Handbook for determinations of AIP eligibility. As defined by the AIP Handbook, eligibility for noise projects—or qualified for funding through AIP grants—is determined by modeled noise impact and noise level reduction (NLR) values determined through testing. If an NCP or decision document under NEPA (e.g., FONSI/ROD associated with an EA or ROD associated with an EIS) includes a noise abatement or mitigation measure not explicitly identified as eligible for funding in the AIP Handbook, the ADO must coordinate with FAA’s Airport Planning and Environmental (APP-400) and Airports Financial Assistance Divisions (APP-500) for

14 If this is the case, a new or supplemental analysis under NEPA may be required. Consult with designated Regional or Airport District Office Environmental Protection Specialists to determine the appropriate NEPA approach.

an eligibility determination. Additional information on AIP grants and the AIP Handbook is available on the Internet at: https://www.faa.gov/airports/aip/.

1.4 Relevant Laws, Regulations, and Policies › 1.4.8 FAA Order 5500.1, Passenger Facility Charge.

1.4.8 FAA Order 5500.1, Passenger Facility Charge. Passenger Facility Charges (PFCs) are authorized by 49 U.S.C. § 40117. Included in the Aviation Safety and Capacity Expansion Act of 1990 (Pub. L. No. 101-508), this provision authorizes the Secretary of Transportation to allow an airport operator or sponsor to impose a fee for each paying passenger of an air carrier enplaned at (or departing from) the airport. These fees can be used to finance eligible airport projects at the airport, including sound insulation programs. Under 49 U.S.C. § 40117, the airport operator or sponsor must receive approval from FAA before implementing a PFC program. Additional information on PFC-eligible projects is included in FAA Order 5500.1, Passenger Facility Charge.

2.2 FAA Personnel › 2.2.2 FAA Noise Subject Matter Expert (SME).

CHAPTER 2. ROLES AND RESPONSIBILITIES

2.1 Overview This chapter describes the roles and responsibilities of the various entities within the FAA, airport operators or sponsors, airport consultants and contractors, and property owners that are involved in SIPs. The Responsibility Matrix in Appendix A presents the roles and responsibilities for each entity described in this section in terms of whether they are responsible, assist, are consulted, or are informed.

2.2 FAA Personnel

2.2.1 FAA personnel may include contacts from the district, region, and headquarter offices. In this AC, Airports District Office (ADO) refers to the FAA Office of Airports personnel that work directly with the airport operator or sponsor. In the Office of Airports regions with no ADOs, “ADO” refers to the Regional Office (RO) that works directly with the airport operator or sponsor. In addition, the structure of FAA offices are not all the same, therefore, multiple individuals may perform some or all of the specified roles explained in this Chapter based on how district and regional offices are structured. NOTE: The FAA approves and accepts the following documents before the airport operator or sponsor begins the SIP process:

 NEM – ADO Manager or Office of Airports Regional Director accepts NEMs.

 NCP – Regional Director approves NCPs and prepares Records of Approval except

in certain instances.15

 NEPA documents (e.g., the Environmental Assessments (EA) and associated

Findings of No Significant Impact (FONSI)/Record of Decision (ROD) or Environmental Impact Statements (EIS) and associated ROD.16

2.2.2 FAA Noise Subject Matter Expert (SME). The FAA Noise SME is the designated noise program specialist in each ADO or RO. The Noise SME has the following responsibilities:

 Conducts technical reviews of all aspects of noise programs and noise projects that

may be considered for AIP grants or PFC revenue.

 Reviews scopes of work and coordinates comments and changes with the FAA

Program Manager and airport operator or sponsor.

15 In accordance with DOT/FAA Delegation Authority Order 1100-154A, for those Noise Compatibility Programs which contain proposed mandatory use restrictions, coordination with the Office of Airport Planning and Programming (APP-400) is required before the FAA region makes a determination of the sufficiency of the documentation for the 180-day review period. Mandatory use restrictions include, but are not limited to, time-of-day restrictions or curfews; denial of the use of the airport or specified runways on an airport for noise reasons; cumulative or single-event noise limitations for an airport or for a specified runway on the airport; airport or runway capacity limitations for noise reasons; and other types of differential treatment of users based on noise, including operating fees.[Appendix 4, Section 3.C.(2)(b)] 16 In certain situations Airport Planning and Environmental (APP-400) approves RODs unless approval authority has been delegated to the region or ADO on a case-by-case basis (refer to FAA Order 1100.154 Delegations of Authority).

2.3 Airport Operator or Sponsor and Consultant Team › 2.3.2 Airport operators or sponsors should consider creating a formal…

 Reviews and accepts airport operators or sponsors SIP Policies and Procedures

Manual (PPM), particularly the Acoustical Test Plan (see PPM requirements in Chapter 3 and Acoustical Testing Plan in Chapter 8). Provides comments to the airport operator or sponsor about any elements of the PPM not in accordance with FAA policy or that would make the program ineligible for FAA funding.

2.2.3 FAA Program Manager The FAA Program Manager works directly with the airport operator or sponsor and has the following responsibilities:

 Assists in the development of SIP funding strategies with the airport operator or

sponsor (in consultation with the FAA planner and others as appropriate).

 Reviews and approves the PPM and scope of work for sound insulation projects (in

consultation with the FAA Noise SME).

 Makes decisions regarding AIP grant or PFC eligibility per the AIP Handbook or

PFC Order. For items not specifically addressed or clearly defined in the AIP Handbook, works with the FAA Region to determine eligibility and coordinates as appropriate with APP-400 and APP-500 for a written determination.

 Attends project meetings (including public meeting as appropriate) and leads pre-

design discussions.

 Provides feedback throughout the SIP process.

 Coordinates with APP-400/500 to approve additional testing (if necessary).

 Ensures compliance with NEPA and other applicable environmental protection or

special purpose laws such as Section 106 of the NHPA.

 Receives and reviews quarterly reports for grants through grant closeout.

2.2.4 FAA Headquarters, Airport Planning and Environmental (APP-400) and Airports Financial Assistance (APP-500) Divisions APP-400 outlines and addresses national policy and guidance on Part 150 programs, SIPs, and NEPA implementation. APP-500 provides national policy and guidance on financial assistance through AIP grants and PFC programs. These divisions coordinate with the ROs and ADOs for SIP establishment and implementation on an as-needed basis.

2.3 Airport Operator or Sponsor and Consultant Team

2.3.1 In general, the airport operator or sponsor is responsible for defining the project team composition (comprising airport personnel and consultants; see Chapter 3), preparing the PPM, developing a financial plan for implementation, developing the program phasing (see Chapter 6), and implementing the SIP.

2.3.2 Airport operators or sponsors should consider creating a formal roles and responsibilities matrix that identifies each position title and member role for the SIP team. The Responsibility Matrix in 9.4.3Appendix A can be used as a template to help

2.3.5 Airport Program Manager › 2.3.5.2 The specific responsibilities of the Program Manager include:

the airport operator or sponsor assign the position titles needed and identify the tasks for which each will be responsible.

2.3.3 The roles and responsibilities of professional disciplines and technical experts that will make up the airport operator or sponsor and consultant team are described further in this section. The composition of the team could be a combination of the airport’s in-house personnel and consulting support personnel and could include the following positions:

2.3.4 Airport Authority, Board, or Approving Officials All SIPs must meet the program requirements for noise level reduction (NLR), accuracy of noise contours, reporting, and other factors defined by the 14 CFR Part 150 Record of Approval or mitigation commitments defined in a ROD. The Airport Authority, Board, or approving official(s) are ultimately responsible for providing milestone documentation, application for funding, quarterly reporting, and closeout information to the FAA.

2.3.5 Airport Program Manager

2.3.5.1 A Program Manager ensures all project work from SIP development, implementation, and close out is completed in accordance with the AIP Handbook and PFC Order in a timely manner. The Program Manager is also responsible for the airport operator or sponsor’s quarterly reporting and project closeout (see Chapter 9). The airport operator’s Program Manager can be a member of the airport personnel or a consultant team.

2.3.5.2 The specific responsibilities of the Program Manager include:

 Supervise and oversee SIP development and implementation.  Assist with defining SIP objectives and priorities.  Prepare bid packages, oversee the bid process, and review legal

documents.  Ensure efficient and timely completion of a SIP, which includes:

o Development of SIP schedules, tasks, and budgets; o Contract compliance; o Managing consultant team and conducting routine team meetings; o Submitting weekly/monthly/quarterly status reports on schedule, tasks, and budget for the SIP; and o Providing progress reports to the Airport Authority, Board or approving officials, and the FAA.  Supervise the development of design documents for construction

material options.  Select display materials and develop presentations of sound insulation

products and construction processes for presenting to property owners.17

17 In the category of property owner, this AC includes structure owners and other public entities.

2.3.6 Airport Operator or Sponsor’s Sound Insulation Program Team › 2.3.6.2 The program development and implementation team can be…

 Manage the program website and advertisements.  Actively participate in the public outreach process (review public

outreach activity plans, conduct and attend public meetings).  Coordinate and assist in SIP closeout activities to the FAA.

2.3.6 Airport Operator or Sponsor’s Sound Insulation Program Team

2.3.6.1 Depending on the size of the program, the development and implementation team could include a variety of personnel responsibilities. It is up to the airport operator or sponsor’s Program Manager to determine the appropriate team composition, including the use of consultants. The team is responsible for identifying program objectives, designing the program, construction and testing, and overall implementation of the SIP.

2.3.6.2 The program development and implementation team can be comprised of, but not limited to, the team members listed in Table 2-1. Team composition will vary depending on the complexity of the SIP and local issues. The roles identified in Table 2-1 can be filled by airport personnel or consultants as needed. Airport operator or sponsors should customize their program structure to meet their unique situation.

Table 2-1. Airport Operator or Sponsor’s SIP Development and Implementation Team

Roles and Responsibilities

Position Responsibility

Property Owner Liaison  Assist in the coordination of program

activities with the team and impacted property owners; notify and communicate with the participants.

 Document interactions with property

owners.

 Attend regular development and

implementation team meetings and all public meetings.

 Assist in property owner orientation

session, distribute property owner handbooks, and project documentation.

 Provide legal documents to property

owners, answer questions and concerns, and coordinate property owner schedules with the program team as needed.

 Attend the design review meeting and pre-

bid open house.

Position Responsibility

 Update, maintain, and document file and

database information and assist in invoicing and payments.

 Assist the Program Manager in preparing

closeout documents for submittal to the FAA. Legal Consultant  Prepare all legal documents, including

title certifications, participation agreements, avigation easements, lender consent documents, subordination agreements, etc.

 Provide recommendations for changes in

legal documents.

 Record and document all avigation

easements.

 Review and discuss legal issues as needed

with airport operator or sponsor’s Program Manager. Design Consultant/Project Architect  Identify potential code issues for pre-

existing deficiencies that may be related to the scope of the sound insulation program work; prepare pre-existing deficiency report for submittal to the airport operator or sponsor, including the legal release and corrections needed in properties with deficiencies.

 Coordinate with acoustical engineer.

 Conduct a design (property) survey at

each impacted property, prepare designs and design packages, review designs with property owners, review design revisions, and provide solutions to property owners on functionality and aesthetics.

 Attend pre-design meeting and develop

final scope of work that incorporates corrections and changes.

 Determine construction cost estimates.

 Prepare bid documents, attend pre-bid,

respond to contractor questions, prepare

Position Responsibility

addenda, and participate in bid opening meetings.

 Review contractors’ bids and prepare a

recommendation to award documents for the airport operator or sponsor to submit to the ADO.

 Develop and initiate contractor training.

 Document with photographs all impacted

properties before, during, and after construction.

 Review contractor’s requests for

information, change orders, Buy American waiver requests,18 and submit to Program Manager.

 Attend regular construction meetings and

review contractor pay requests.

 Develop technical construction plans and

specifications and submit them to the ADO at 90 percent completion (for each phase of the SIP as the program progresses). The ADO will review within a reasonable timeframe.

Depending on local building code requirements and the airport’s sustainability goals, a Design Consultant/Project Architect may incorporate sustainable design measures. In this case, the Design Consultant/Project Architect would preferably be a LEED® Accredited Professional (LEED AP) to design and administer certification of any buildings if necessary. The Design Consultant/Project Architect could also provide these services:

 Coordinate with the local utility and

government to determine what rebate or incentive programs might be available, as well as ensure compliance of the SIP with

18 Appendix Y of FAA Order 5100.38, AIP Handbook provides Buy American guidance, including market or product conditions that may exist requiring a waiver request allowable under 49 U.S.C. Section 50101(b).

Position Responsibility

any energy codes and ratings enforced by local, national, or international entities.

 Identify and determine any other

sustainability opportunities throughout the program. Mechanical or Ventilation Engineer  Conduct a design (property) survey to

determine mechanical and ventilation requirements, inspect properties for observable deficiencies or nonconforming existing conditions that would impact changes necessary to support the SIP scope of work (such changes may be considered to be homeowner pre-work), and provide recommendations to correct deficiencies to the existing ventilation, insulation, and mechanical designs.

 Design necessary heating, cooling, and

ductwork, as well as modify ventilation design if the property survey determines it is necessary.

 Provide schedules, details, and drawings

to include in the plans’ specifications.

 Coordinate with the Design

Consultant/Project Architect(s) throughout the process.

 Inspect all completed mechanical,

ventilation, and insulation work, and conduct pre- and post-construction ventilation tests.

 Depending on the sustainability goals of

the airport and SIP, conduct energy audits as necessary, and create policies and procedures to meet Environmental Protection Agency (EPA) EnergyStar performance criteria. Hazardous Materials Consultant  Create a testing and sampling protocol

based on the project scope.

 Conduct tests in impacted structures

where hazardous materials may be located and record all materials found.

Position Responsibility

 Attend pre-design meetings and additional

design meetings if hazardous materials are found in impacted structures.

 Provide cost estimate for abatement work,

develop abatement specifications and documentation, and perform periodic inspections to ensure the work is being performed in compliance with the contract documents.

 Provide air quality monitoring, clearance

testing, and hazardous materials assessment of the project based on the results of the hazardous materials testing of the impacted structures. Electrical Engineer  Determine if any observable deficiencies

or non-conforming conditions exist that would impact changes necessary to support the SIP scope of work. Such changes may be considered homeowner pre-work.

 Design electrical wiring and provide

schedules, details, and drawings for inclusion in the plans and specifications.

 Coordinate with the Design

Consultants/Project Architects throughout the process.

 Inspect all completed electrical work post-

construction. Structural Engineer The structural engineer responsibilities may be performed by the Design Consultant/Project Architect because it is not always a necessity or requirement to have both an architect and an engineer.19 When a structural engineer is part of the design and implementation team, their responsibilities are to:

19 Some states allow engineering firms to do all the work described in this section, however, most states will not allow an architectural firm to do engineering work unless there are professional engineers on personnel to sign and affix a seal to the design map. The airport operator or sponsor’s program manager should determine the applicable laws in the state that the SIP is being conducted.

Position Responsibility

 Determine the general condition of each

structure.

 Assess existing structural deficiencies

observed by the Design Consultant/Project Architect that may impact SIP installations.

 Assess whether SIP improvements would

create issues within an existing structure.

 Inspect all deficiency corrections, if

necessary. Construction Manager/Resident Engineer The Construction Manager/Resident Engineer is familiar with the design of the project and coordinates closely with the Design Consultant/Project Architect before and during construction. Specific responsibilities of the Construction Manager/Resident Engineer include:

 Help communicate pertinent information

to construction personnel.

 Develop the construction safety and

phasing plan with the construction contractors and submit it to the Program Manager. The construction safety and phasing plan will ultimately be submitted to the ADO by the Program Manager at 60 percent completion of the technical construction plans and specifications.

 Conduct daily site visits to all properties

under construction.

 Review change orders and pay requests

from the contractor (the Design Consultant/Project Architect is responsible for developing and ultimately submitting change orders to the Program Manager).

 Review compliance documentation

prepared by Design Consultant/Project Architect of contractor disadvantaged business enterprise (DBE) requirements.

Position Responsibility

 Perform inspections before final

inspection.

 Attend regular construction meetings.

 Perform final inspection and prepare

necessary reporting and closeout paperwork. Acoustical Engineer  Develop the Acoustical Test Plans (ATP)

with input from the Design Consultant/Project Architect. Provide the ATP to the Program Manager for review and submittal to the ADO.

 Conduct testing of sound levels for a final

determination of noise impact (see Chapter 8 for details on activities).

 Determine design goals in consultation

with the Design Consultants/Project Architects.

 Consult and coordinate with Design

Consultants/Project Architects throughout the design process.

 Coordinate with the Design

Consultants/Project Architects to determine the required level of pre- and post-testing.

 Conduct acoustical testing. Ensure

acoustical compliance when conducting those tests.

 Review design documents.

 Assist with inspection of materials, new

product review, and review of requests for information and change orders in coordination with the Design Consultants/Project Architects and the Construction Manager/Resident Engineer.

 Coordinate noise monitoring data for the

airport based on the needs identified in the SIP.

Chapter 2. Roles and Responsibilities › 2.4 Property (Structure) Owner Responsibilities

Position Responsibility

 Prepare final report for acoustical

performance to be submitted to the FAA. Historic Preservation Professional  Assist in identifying historic properties.

 Work with State Historic Preservation

Office to avoid, minimize, or mitigate adverse effects of sound insulation on historic properties. Finance Manager  Grant management.

 Process pay requests.

 Track project expenditures.

 Prepare financial reports.

2.4 Property (Structure) Owner Responsibilities

SIPs are voluntary and property owners are not required to participate. For property owners who volunteer to participate, interior acoustical testing occurs to determine if their structures are impacted. Owners of impacted structures are responsible for understanding the SIP through coordination with the property owner liaison. Owners should sign an application if interested in the SIP, then sign an agreement for the airport to acknowledge that they understand the program and treatment strategy. If required by the airport operator or sponsor, property owners may be required to provide an avigation easement on their property in exchange for sound insulation. Owners are also informed that residences currently included in the DNL/CNEL 65 dB or greater contour may not be eligible for federal funding for sound insulation if interior acoustical testing doesn’t demonstrate an impact or if contours change in future NEM updates.

Chapter 3. Sound Insulation Program Process › 3.1 Overview

CHAPTER 3. SOUND INSULATION PROGRAM PROCESS

3.1 Overview The development of a SIP generally begins when sound insulation is recommended to reduce impacts of aircraft noise to structures near airports. Noise mitigation measures are typically identified in a decision document associated with a NCP, decision documents associated with an analysis under NEPA,20 or a request to impose and use Passenger Facility Charges (PFC) to implement noise mitigation measures. Airport operators or sponsors will follow a series of phases and steps to develop, implement, and close out a SIP, which includes FAA review and approval at key points in the SIP process. The SIP process overview illustrated in Figure 3-1 depicts the phases and steps described in this Chapter.

20 A Record of Decision (ROD) or a Finding of No Significant Impact (FONSI/ROD)

Figure 3-1: picture of page 25Figure 3-1 · page 25
Picture of the page from the copy saved here

3.2 Initiate Sound Insulation Program Efforts (Phase 1) › 3.2.1 Step One Establish a Team and Management Structure and Hire…

Figure 3-1. Overview of the Sound Insulation Program Process

3.2 Initiate Sound Insulation Program Efforts (Phase 1) The initial phase of the SIP process involves efforts to establish a team and management structure, defining the SIP objectives and priorities, preparing or verifying information pertinent to defining boundaries for eligible structures, identifying structures eligible for sound insulation treatment and federal financial assistance, and preparing a policy and procedure manual (PPM) to guide SIP implementation. The following subsections identify important considerations for each step of the initial phase.

3.2.1 Step One Establish a Team and Management Structure and Hire Consultants

As explained in Chapter 2, a SIP Team is responsible for all aspects of the development and implementation of an airport’s SIP, including objectives, designing the program, construction, and testing. The SIP Team composition will vary depending on the complexity of the SIP and local community issues so the airport operators or sponsors

3.2.3 Additional factors that should be considered when outlining… › 3.2.3.3 Federal Financial Assistance.

should customize their structure to meet their unique situation. Refer to Table 2-1 in Chapter 2 for the basic SIP team structure.

3.2.2 Step Two Define SIP Objectives, Priorities, and Boundaries

Since the purpose of sound insulation is to reduce the effects of aircraft noise inside impacted structures, in particular, habitable areas,21 it is imperative to outline the objectives and priorities of the SIP based on a Noise Exposure Map (NEM) with respect to compatible and non-compatible land uses so there is a direct relationship between objectives, priorities, boundaries and sound insulation treatment options defined for a SIP.

3.2.3 Additional factors that should be considered when outlining objectives and priorities and defining boundaries for compatible/non-compatible land uses of the SIP in a PPM include:

3.2.3.1 Controlling Documents. For the purposes of this AC, the Record of Approval (ROA) associated with current NCPs/NEMs, the Record of Decision (ROD), Finding of No Significant Impact (FONSI)/ ROD,22 and PFC project approval are “controlling documents”. This is important because the controlling document is needed when defining the boundaries for a SIP. For example, compatible land uses identified in NEMs/NCPs are based on the definition provided in 14 CFR Part 150, Table 1. However, if a state or local governmental entity with jurisdiction and land use enforcement authority define land use compatibility differently, the state or local government entity’s definition takes precedent.

3.2.3.2 Relationship of Acoustic Modifications to Design Objectives. This is important because acoustic modifications, as defined in the AIP Handbook for doors, windows, etc., are used to achieve the design objectives of a SIP. Other measures not defined in the AIP Handbook are not allowed unless the ADO and RO, in coordination with APP-400 and APP-500 approve them in advance. In this case, the ADO must keep a copy of the airport operator or sponsor’s request to use other measures and the FAA approval of the request in the project files.

3.2.3.3 Federal Financial Assistance. When an airport operator or sponsor will be relying on federal financial assistance from the FAA (e.g., via AIP grants or PFC revenue) to accomplish noise mitigation, the sound insulation

21 Areas considered to be habitable generally include areas for educational instruction, living, sleeping, eating, or cooking. Facilities located in leased storefront property are not included. 22 If the controlling document for the SIP is a mitigation commitment identified in a FONSI/ROD or ROD associated with an analysis under NEPA, that commitment remains binding until it is completed or until it is no longer warranted (e.g. the project does not move forward into construction/operation).

3.2.4 Step Three Data Collection and Validation › 3.2.4.1 A SIP developed for noise mitigation recommendations outlined…

treatment should be designed to meet the minimal 5 dB NRL requirement.23 If the airport operator or sponsor will not be relying on federal financial assistance (e.g., not seeking AIP grants or PFC revenue) to accomplish noise mitigation, this requirement does not apply. In addition, a phased approach to implementing a SIP may be necessary to account for adequate funding (locally and federally) to implement the SIP. For example, for longer-term and/or more complex SIPs, implementation efforts will occur over time based on several factors, including funding availability.

3.2.3.4 Block Rounding. When applying block rounding, the program boundaries may be adjusted to account for block rounding in residential areas. Block rounding expands the SIP boundaries to include parcels that are contiguous to the DNL 65 dB noise contour area.24 This prevents SIP boundaries from splitting a block. FAA Order 5100.38, AIP Handbook outlines options for block rounding. Before owners can be offered sound insulation for additional structures or areas outside the boundary, the ADO reviews and agrees with the extended boundaries.

3.2.3.5 Neighborhood Equity. Neighborhood equity is distinct from block rounding. The program boundaries may be adjusted to account for neighborhood equity in residential areas. Neighborhood equity allows an airport operator or sponsor to provide a separate treatment package for a percentage of residences that do not meet the interior noise level requirements, but are scattered among residences that do meet the criteria. The AIP Handbook describes options for neighborhood equity for boundaries. Before additional structures or areas outside the boundary can be included in the SIP, the ADO reviews and agrees with the properties to be included.

3.2.4 Step Three Data Collection and Validation

Review the controlling documents and associated analyses and verify or re-evaluate when defining the boundaries for the SIP program. This is especially important for longer-term (e.g., SIPs that may take five or more years to complete) and/or more complex (e.g., multiple locations and structures) SIP implementation.

3.2.4.1 A SIP developed for noise mitigation recommendations outlined in a NCP will be completed as stipulated unless there are changes in the operation of the airport that would create any substantial, new non-compatible use in any area depicted on the NEM beyond what is forecast for a period of at least five years after the date of the NEM submission. Typical changes in airport operations that may change noise exposure, and subsequently, may 23 If the sound insulation treatment design accommodates more than the 5 dB NLR reduction, and the airport operator or sponsor is seeking federal funding, advance coordination with the FAA ADO and/or RO is required to determine next steps. 24 In locations where structures are proximal to or will expand beyond the contiguous DNL 65 dB noise contour area, advance coordination with the FAA ADO and/or RO is required to determine next steps for applying the block rounding approach.

3.2 Initiate Sound Insulation Program Efforts (Phase 1) › 3.2.5 Step Four Determining Funding Eligibility and Impacted Structures…

change the land use designation include, but are not limited to: aircraft operation frequency, a reapportionment between day/night flight schedules, and changes in aircraft fleet mix.

3.2.4.2 Before developing a formal NEM update, the airport operator or sponsor may conduct an analysis without public involvement to validate the current NEM or determine if a formal update is needed. When considering whether a formal update is needed, refer to 14 CFR 150.21(d)(1), which indicates a change that creates a substantial new noncompatible use is one that results in an increase in the yearly day-night average sound level of 1.5 dB or greater in either a land area previously determined to be compatible but is made non-compatible or in a land area previously determined to be non-compatible and whose non-compatibility is now significantly increased. This also applies if there is a decrease in the yearly day-night average sound level of 1.5 dB or greater. If a formal update is needed, the airport operator or sponsor shall, in accordance with 14 CFR 150.21(d)(1), prepare and submit a revised NEM to the FAA.

Note: Validating and updating NEMs to account for potential changes in noise contours is needed when first establishing a SIP and when it is relative to SIP implementation timeframes for existing SIPs (see Chapter 6 for phasing a SIP). This will result in greater clarity to property owners on SIP parameters. In scenarios where a SIP was established prior to the publication of this AC and the airport sponsor or operator is implementing a phased approach, consult with the FAA ADO or RO regarding changes to the existing and ongoing SIP. The FAA ADO and RO should also consult with APP-400 for next steps.

3.2.5 Step Four Determining Funding Eligibility and Impacted Structures for Sound Insulation

There are several methods by which structures may be considered impacted and eligible for FAA funding. The most common methods are through an FAA-approved 14 CFR Part 150 program or a decision document (e.g., FONSI/ROD or ROD) associated with a NEPA evaluation. FAA Order 5100.38, AIP Handbook, Table R-1 also notes that noise mitigation that is included in a land use compatibility plan prepared by a local jurisdiction surrounding a medium or large hub airport that either (1) has not prepared a 14 CFR Part 150 program or (2) has not updated a 14 CFR Part 150 program in the preceding 10 years may not be eligible for financial assistance from the FAA. Per 49 USC § 47141(f), grants for projects approved under an FAA accepted compatible land use plan are only allowable until September 30, 2023. After this date, the ADO must check the current legislation to see if the sunset date was extended. A facility used primarily for medical or educational purposes (typically, hospitals, and schools) may be considered for FAA funding if it is adversely impacted per 49 U.S.C. § 47504(c)(2)(D), regardless if the airport has a 14 CFR Part 150 program. Finally, PFC noise eligible projects may qualify for FAA funding per FAA Order 5500.1 paragraph 4-6.c, which states in part that “…PFC eligible noise projects which are not AIP eligible include any

3.2.5 Step Four Determining Funding Eligibility and Impacted Structures… › 3.2.5.2 Building Construction Date Requirement.

project that would qualify for inclusion in a Part 150 NCP, even though the public agency has not undertaken and/or completed a Part 150 NCP or the project is not included in an implemented NCP. However, the eligibility of any proposed PFC noise project not in an approved Part 150 NCP must be supported by noise contours, which could be prepared in conjunction with a Part 150 study, airport master plan, environmental assessment or other suitable planning analysis. Additional considerations for determining funding eligibility and impacts include:

3.2.5.1 Addressing Impact Requirements under 14 CFR Part 150 process. Several impact requirements should be met before land uses identified as “normally non-compatible” can be tested to determine if they are actually non-compatible:

 An airport operator or sponsor must have completed an NCP in

accordance with the requirements of the statute.  The airport operator or sponsor must have recommended a SIP as an

NCP measure to reduce non-compatible land uses around the airport.  The FAA must have approved the SIP as an NCP measure in its ROA

for the subject NCP.  With each AIP grant application associated with a SIP, the airport

operator or sponsor must submit the most recent supporting NEM that has been reviewed and approved by the FAA.

3.2.5.2 Building Construction Date Requirement. A building’s construction date is important in determining the mitigation considerations encompassing the structure. The building permit of a structure must have been issued prior to October 1, 199825 unless the airport operator or sponsor has demonstrated to the FAA that no published noise contours existed at that time. If a noise contour is published after October 1, 1998, the building permit of a structure must have been issued prior to the date the contour was published. Structures are not eligible to be included in a SIP if they were permitted after NEMs (14 CFR Part 150) or noise contours (for NEPA studies) that have been made available to the public indicate that the underlying property is normally non-compatible for the type of structure. New non-compatible land uses created by subsequent airport expansion or development may also be considered impacted by aviation noise.

25 October 1, 1998 is the date included in the FAA Final Policy on Part 150 Approval of Noise Mitigation Measures: Effect on the Use of Federal Grants for Noise Mitigation Projects, Federal Register: April 3, 1998 (Volume 63, Number 64), Rules and Regulations, Page 16409-16414. The policy states, “As of October 1, 1998, the FAA will approve under 14 CFR Part 150 (Part 150) only remedial noise mitigation measures for existing non-compatible development and only preventative noise mitigation in areas of new non-compatible development.” Remedial measures include sound insulation. Preventive measures include zoning and other land use regulations. Exceptions to this policy are outlined in the Federal Register notice. Exceptions are supported by justification and submitted to FAA for consideration on a case-by-case basis.

3.2.5 Step Four Determining Funding Eligibility and Impacted Structures… › 3.2.5.6 If there are a relatively small number of residential…

3.2.5.3 If the project meets the criteria explained above, the following, criteria apply:

 All structures proposed for consideration in the program are located on

parcels that have property lines within or intersecting the boundaries of a non-compatible noise contour. In addition, the parcel in question also needs to be within the noise contour at the time it was published for this to apply.  In accordance with the AIP Handbook, the airport operator or sponsor

submits a proposal to apply block rounding to a phase boundary, applicable only to residential structures, for FAA approval.26

3.2.5.4 The airport operator or sponsor should contact all owners of structures located within the SIP boundary that meet the criteria outlined herein to identify those wishing to have their structure tested to determine if their structure is impacted.

3.2.5.5 Pre-construction acoustical testing to determine which structures are impacted and can participate in the SIP is arranged according to public outreach protocols defined by the airport operator or sponsor, and completed to determine potential impacts in accordance with Chapter 8 and the AIP Handbook. Structures are considered to be impacted if the test results for the structure’s interior finds the interior noise level is at or above DNL/CNEL 45 dB for residences or Sound Equivalent Level (Leq) at or above 45 dB for educational facilities.

3.2.5.6 If there are a relatively small number of residential structures in the program boundary area that do not meet the interior noise level requirements that are dispersed among residences that do, an airport operator or sponsor may submit a neighborhood equity proposal to the FAA per the requirements outlined in the AIP Handbook. Per FAA policy, the ADO must not approve neighborhood equity for more than 10% of the residences in the neighborhood (as logically bounded by either streets or other geographic delineation) or 20 residences in a phase of the noise insulation program, whichever is less.27 If approved, the extent of improvements offered under a neighborhood equity proposal is limited (such as caulking, weather stripping, and installation of storm doors or ventilation packages) when compared to full SIP phase improvements.

26 An airport operator or sponsor can propose to expand the noise mitigation boundary just beyond the DNL/CNEL 65 dB contour to include parcels proximal to the contour area. Advance coordination with FAA ADO and/or RO is recommended to determine appropriateness of applying the block rounding considerations for FAA acceptance are included in FAA Order 5100.38, AIP Handbook. 27 In rare cases, ADO may determine that the program will benefit by providing noise equity packages to more than the 10%/20% residence limit. In this instance, the ADO must have written approval from APP-1 to exceed this limit.

3.2.5 Step Four Determining Funding Eligibility and Impacted Structures… › 3.2.5.9 The below additional steps apply to facilities used primarily…

3.2.5.7 Requirements for Facilities Used Primarily for Medical or Educational Purposes.28 Under the authority of 49 U.S.C. § 47504(c)(2)(D), a facility used primarily for medical or educational purposes that is impacted by noise can be considered for sound insulation, even if it has not been evaluated under 14 CFR Part 150 or NEPA. For the structure to be considered, the airport operator or sponsor prepares and submits to the FAA:

 A NEM using the current version of the FAA’s accepted noise

modeling software that demonstrates the structure is located within a noise exposure contour that is normally non-compatible for such land use.  The corresponding aircraft operational and fleet assumptions that were

used to develop the submitted NEM.

3.2.5.8 Once this information is received, the FAA reviews and determines that the submitted NEM meets the acceptability criteria that would apply had it been submitted under 14 CFR Part 150. The FAA also reviews and validates that the structure(s) is located within a noise exposure contour that is normally non-compatible for such land use.

3.2.5.9 The below additional steps apply to facilities used primarily for medical or educational purposes regardless of how they were identified as potentially requiring sound insulation (i.e. through the completion of an NCP, analysis supporting a NEPA decision document, or neither of these):

 Interior testing of the structure(s) in accordance with the testing

protocol (see Chapter 8) and Appendix R of the AIP Handbook must be completed by the applicant. Structures are considered for sound insulation if the test results indicate an interior noise level at or above DNL/CNEL 45 dB.  Interior testing for educational facilities will consider the following

parameters:

o The noise level is represented effectively by the Leq for the

hours of operation (typically daytime) rather than the 24-hour period measured by DNL. Leq quantifies noise that varies over a continuous period of time—in this case over the school day—into a single value in decibels. o The single-event Sound Exposure Level (SEL) can be used

with Leq long-term averaging as a more practical measure of determining existing and improved interior NLRs. SEL measures discrete, short-duration transient noise instances such as an aircraft flyover. Single loud events can be disruptive to teaching and learning, so these are important to consider for schools. 28 The ADO/RO should contact APP-400 in situations where the use and type of medical facility, educational facility, or place of worship is unclear. For example, differing understandings how these facilities are being defined or considered qualified or questions about transient lodging eligibility.

3.2 Initiate Sound Insulation Program Efforts (Phase 1) › 3.2.7 Step Six Policy and Procedure Manual

3.2.5.10 Testing Requirements when National Environmental Policy Act Decision Document is the Controlling Document. If the controlling document is a NEPA decision document (i.e., FONSI/ROD or ROD) and the project is eligible for AIP grants or PFC revenue, the project-related mitigation commitments remain until the commitment is completed or it is no longer warranted (e.g., the project does not move forward into construction). However, interior testing is still required for individual structures to be designated as impacted. In order to be considered for AIP grants or PFC revenue, the airport operator or sponsor must complete interior testing for the structure(s) in accordance with the testing protocol (see Chapter 8) and the AIP Handbook for final consideration for a sound insulation project. Structures are considered impacted and candidates for sound insulation if the interior test results for the structure indicate a noise level at or above DNL/CNEL 45 dB as stipulated in the FAA Order 5100.38, AIP Handbook. For NEPA related controlling documents published before August 17, 2012 (PGL12-09), mitigation requirements will be reviewed by the FAA on a case-by-case basis.

3.2.5.11 If structures are similar in construction type, then operators may choose to conduct pre-construction sampling, testing a smaller number of structures in the phase boundary. The SIP testing plan and analysis are discussed in detail in Chapter 8.

3.2.6 Step Five Develop Acoustical Testing Protocol Preparing the acoustical testing protocol to outline and explain the acoustical testing process is integral to ensuring the acoustical testing is conducted accurately and efficiently. Determining and documenting the interior noise levels of structures potentially impacted by aircraft noise, as identified in NCPs and depicted in NEMs, is also necessary if the airport operator or sponsor will be seeking federal financial assistance. The acoustical testing process outlined in the acoustical testing protocol should adhere to the testing protocol discussed in Chapter 8 and the AIP Handbook.

3.2.7 Step Six Policy and Procedure Manual

A Policy and Procedure Manual (PPM) should be prepared to establish why a SIP for the airport is being undertaken and how it will be implemented. In general, developing and following a PPM is imperative to ensure compliance with applicable FAA and state or local requirements, that the process is as transparent as possible, and aligns with community expectations. For example, if a SIP is being developed pursuant to 14 CFR Part 150, the PPM must explain how the initial boundaries defined in the NEM are not static, could shift given operational changes at the airport, and indicate any limitations associated with the boundaries. The PPM can be refined, as needed, as the SIP progresses, based on lessons learned or changing priorities and schedules. Since the PPM also outlines the funding strategy that guides the phasing of funding requests

submitted to the FAA and the installation of sound insulation treatments, this may also be revised as the program progresses. The minimum required content of PPMs is listed below.

I. Overview of the SIP process

II. Administration

a. Roles and responsibilities of the SIP team

b. Coordination and communication protocols within the airport operator or

sponsor’s personnel, between the SIP team and airport operator or sponsor, and with FAA

III. Stakeholder Involvement and Public Outreach

a. Coordination and communication protocols with the public and other

stakeholders

b. Criteria for prioritizing participation

c. Consideration of residences other than single-family permanent structures29 and

other special situations associated with public buildings (criteria and approval responsibility)

d. New owner participation in the program (in cases where a previous owner opted

out)

e. Applicability of block rounding and neighborhood equity (see Section 6.3)

f. Handling complaints on design or construction

g. Common templates for standard documents and forms that will be used

throughout the program. Chapter 9 describes sample documents in more detail and includes some of the following examples:

o Letters to residents describing the program phase and soliciting interest in

acoustic testing to determine noise impact

o Disclosure of property owner’s responsibilities

o Discussion of program limitations

o Easement language (if the airport wishes to require it as a condition of

participation)

o Testing and inspection forms

IV. Contractor Outreach

a. Prime contractor prequalification policy

b. Review process for prime contractor statements of qualification

29 Modular structures (permanent structures on a foundation) can be considered for sound insulation, but require an assessment by acoustical engineers and a Design Consultant/Project Architect. They must be approved by FAA if an airport operator or sponsor is requesting AIP/PFC funding. Manufactured structures (mobile or nonpermanent) are not practical for sound insulation treatments.

Chapter 3. Sound Insulation Program Process › 3.3 Implementation Phase (Phase 2)

c. Contractor training and certification procedures

V. Design Policy, Process and Procedures

a. Acoustical testing protocol to determine program participation (see Chapter 8)

b. Addressing nonconforming building codes and pre-existing deficiencies

c. Consideration of mixed-use residential properties (most sensitive land use

according to 14 CFR Part 150)30

d. Handling of requests for exceptions (requires early coordination with the ADO

to determine eligibility of exceptions)

e. Consideration and inclusion of sustainability-related items to address local

building codes or the airport’s sustainability goals (e.g. enhanced indoor environmental quality)

f. Addressing special design considerations for historic properties to avoid,

minimize, or mitigate adverse effects

g. Addressing other design requirements and considerations imposed by

authorities having jurisdiction

VI. Construction

a. Pre-construction submittals, procurement materials, and meetings

b. Construction administration and inspection process

3.2.8 The Program Manager reviews and approves PPMs with assistance from the FAA Noise SME.31 As explained in Chapter 2, the FAA Noise SME will review the PPM in consultation with the FAA ADO Program Manager. The SME will provide comments to the airport operator on elements of the manual that are not in accordance with FAA policy or would not be considered for FAA funding. If the FAA finds the PPM is not acceptable, the ADO should notify the Region, which should, in turn, notify APP-400 and APP-500. If the airport operator or sponsor does not make the required revisions, the FAA notifies the airport operator or sponsor that the particular element of the program will not be considered for federal participation and will be limited to local funds.

3.3 Implementation Phase (Phase 2) SIP implementation involves efforts such as community outreach, preconstruction testing and treatment plan designs, and sound insulation treatment installations. The following subsections identify important considerations for each step of the implementation phase.

30 Only the non-compatible portions of mixed use would be eligible. 31 If the SIP is being implemented with AIP or PFC funding, FAA must review and approve the PPM before completion and public release.

3.3.1 Step One Property Owner Outreach

The outreach process starts after the program boundary is defined and policies and protocols are reviewed and approved by FAA to engage property owners identified within the program boundary. Airport operator or sponsors should contact potentially impacted property owners, provide a description of the SIP, and require property owners to sign a participation agreement if they volunteer to be included in the program. The airport operator or sponsor should express to structure owners that noise contours and impact determinations for sound insulation treatment can change before the treatments are installed. The FAA recommends that airport operator or sponsors require property owners to sign an avigation easement agreement.32 Examples of these documents are provided in Appendix B of ACRP Report 89, Guidelines for Airport Sound Insulation Programs.33 More detail on community outreach is discussed in Chapter 5 of this AC.

3.3 Implementation Phase (Phase 2) › 3.3.3 Step Three Treatment Plan Design

3.3.2 Step Two Pre-Construction Acoustical Testing

Airport operator or sponsors prepare acoustical testing protocols and conduct preconstruction acoustical testing to determine impacts and assist in the finalization of product and treatment recommendations. The pre-construction testing establishes a baseline for the structures within the phase boundary and provides each structure with accurate treatment suggestions to decrease interior noise levels. Depending on the type of structures in the program boundary, not all structures must be tested.

3.3.3 Step Three Treatment Plan Design

The design process begins after the airport operator or sponsor has identified, and FAA has confirmed, potentially impacted structures for sound insulation. This process may involve the following steps when appropriate:

 Developing a detailed Scope of Work by the airport operator or sponsor and design

team to comply with design policies, approved products, and recommended treatments.

 Completing property owner outreach, pre-construction acoustical testing, and

documentation of the existing conditions of each structure through assessment surveys, and indoor air quality and hazardous materials testing.

 Completing a treatment plan design prior to advertising bids. Otherwise, the grant

could remain open for an excessive period of time (which is inconsistent with the AIP Handbook).

32 An avigation easement grants rights of overflight in the airspace above or near a property. It also grants the right to create noise or other effects that may result from the lawful operation of aircraft, and the right to remove any obstructions to overflight, in the nearby airspace. 33 ACRP Report 89, Guidelines for Airport Sound Insulation Programs (2013).

3.4 Close Out Phase (Phase 3) › 3.4.2 Step Two Secondary Package

 Releasing the project for bidding. The project should be awarded to the lowest

qualified bidder following the 2 CFR Part 200 rules of procurement and the AIP Handbook.

3.3.4 Additional SIP implementation considerations:

 Airports that will be implementing long term and/or more complex SIPs may need

to revisit steps that normally occur during the initial development of a SIP, such as validating and updating NEMs, updating PPMs and implementation schedules. Airport operators or sponsors should coordinate and consult with the FAA early to address any changes to airport operations that will require updates to existing documentation that supports SIP implementation.

3.4 Close Out Phase (Phase 3) Once the installation of sound insulation treatment is completed, the airport can initiate efforts to close out the SIP. The following subsections identify important considerations for each step of the close out phase.

3.4.1 Step One Post-Construction Acoustical Testing

For projects involving federal funding, airport operators must conduct post-construction acoustical testing to ensure they have met the goals of the insulation program. Not all structures must be tested, depending on the type of structures in the program boundary. If structures are similar in construction type, operators may choose to conduct postconstruction sampling, testing a smaller number of structures in the phase boundary. Details on the SIP testing plan are described in Chapter 6.

3.4.2 Step Two Secondary Package

Offer secondary package if necessary to achieve noise compatibility if post construction testing of structures results in objectives not being met.

4.1 Funding. › 4.1.4 The FAA does not reimburse the airport for the full cost of the…

CHAPTER 4. ESTIMATING PROJECT COSTS AND FUNDING

4.1 Funding.

4.1.1 Airport operator or sponsors should determine project funding sources during the administration phase of a SIP. Airports have multiple funding options for SIPs, which includes:

 AIP grants, as described in the 2019 FAA Order 5100.38D - Change 1, Chapter 2

(i.e., the AIP Handbook),

 PFC revenue, as described in the 2001 FAA Order 5500.1 Passenger Facility

Charge, Chapter 1, Section 2

 Airport revenue, including, but not limited to revenue collected from an airport’s

disposal of noise land.34

 State or local agency grants are also available sources of funding in addition to the

three options above that have a federal approval requirement associated with them.

4.1.2 In addition to funding sound insulation projects, airport operators or sponsors can also consider if there are other programs that provide options for assisting homeowners and improve land use compatibility. For example, some counties offer a Voluntary Sales Assistance (VSA) Program.35 VSA programs can support eligible homeowners who want to sell their home on the open market and relocate outside the DNL/CNEL 65 dB noise contour area. The owner receives compensation from the county and in exchange the county receives a Conveyance and Release Agreement. Some counties also offer Voluntary Conveyance and Release programs. These programs are for eligible homeowners who wish to stay in their homes. They receive a benefit payment in exchange for a recorded Conveyance and Release Agreement on their property.

4.1.3 When airport operators or sponsors, planning agencies, and other organizations accept funds from FAA-administered airport financial assistance programs, such as AIP grants, they must agree to certain obligations (or assurances). The assurances may be attached to the grant for federal assistance and become part of the final grant offer or in restrictive covenants to property deeds. The duration of these obligations depends on several factors, including recipient and project types. There are two types of assurances that may be relevant to developing SIPs: (1) Airport Sponsor Assurances and (2) Noise Compatibility Assurances for Non-Airport Sponsors. Additional information about grant assurances is available on the Internet at https://www.faa.gov/airports/aip/grant_assurances

4.1.4 The FAA does not reimburse the airport for the full cost of the project. Reimbursement can vary depending on the project size and type of airport (primary versus non-

34 Land an airport operator or sponsor purchased using AIP funds for noise mitigation 35 Broward County Florida provides a Voluntary Sales Assistance program and a Voluntary Conveyance and Release Program.

primary). FAA Order 5100.38, AIP Handbook discusses additional reimbursement for pre- and post-construction testing, and procurement processes.

4.2 Cost Development. › 4.2.4 Multiple areas of a SIP should be included in determining the…

4.2 Cost Development.

4.2.1 To maximize the use of available funding sources, airport operators or sponsors should establish goals and priorities to ensure timely implementation. Early establishment of goals and priorities for cost development can allow for evaluation and tracking of costs throughout the SIP process. Issues can be more easily resolved with early clarification on program costs.

4.2.2 Airport operator or sponsors should work closely with all departments and consultants involved in the SIP process to determine cost estimates for each of its activities. Airport operators or sponsors may also consider hiring a professional to assist in the cost development. It may be helpful to compare previous SIP costs. While not all Part 150 studies determine cost development for SIPs, if a Part 150 study was previously conducted, costs may have been evaluated within that study.

4.2.3 Prioritization of the program stages are imperative to allocate funding to each area. Airport operators or sponsors should create a list of all items and potential issues within the program, and prioritize the list based on importance and necessary cost. Airport operators or sponsors can create multiple lists for each area and the related stakeholders. The lists can be provided to stakeholders for review and comment. Prioritization may be needed throughout multiple phases or areas of the program.

4.2.4 Multiple areas of a SIP should be included in determining the cost of the program. Table 4-1 describes examples of program elements to consider in determining program cost:

Table 4-1. Program Elements to Consider in Determining Program Cost

Program Element Consideration

Administration Administrative duties can be assigned to internal personnel or external personnel hired by the airport operator or sponsor. Evaluation should be completed to determine the need for an internal Administrator rather than hiring an external one, as this can be an important factor in the cost of administration.

The airport operator or sponsor will have the initial and overall task of administering the program. However, other areas of responsibility can be delegated as needed.

Airport operators or sponsors should establish policies for program administration to ensure consistency if changes in management or consultants occur during the program process.

Public Relations (Community Outreach) Airport operators or sponsors should consider all areas of public relations for the program. This includes advertisements, collaterals, meetings, and other areas of public relations. Start-up and continuing costs should be evaluated.

Facilities Separate from the existing facilities used by each department, contractor, or consultant, this consideration includes additional facilities used during the program such as meeting/workshop rooms, store rooms, show rooms, demonstration structures, and more.

Fees Fees associated with the program are primarily fees for professional workers. Fees can vary based on project size and available funding, but generally include all contractors and/or consultants associated with the project.

Consultant fees associated with construction can be extensive due to constant collaboration with the contractor and airport operator or sponsor. AC 150/5100-14, Architectural, Engineering, and Planning Consultant Services for Airport Grant Projects, describes these fees in detail.

4.3 Contracting and Procurement. › 4.3.2 Since projects are typically multi-year projects, outreach to…

Program Element Consideration

Testing and Construction Airport operators or sponsors should consider pre- and post-construction testing for eligible structures. To be funded via AIP grants, refer to Appendix R, Section R-11 “Pre-and Post- Testing Criteria for Noise Insulation Projects”, Table R-4 in FAA Order 5100.38D, Change 1, February 26, 2019.

Construction fees are the largest cost of the program. They require the most detail and time to complete.

4.2.5 Construction costs can be estimated by multiple methods. Benchmarking, unit pricing, pilot programs, and contractor estimates are common methods. Pilot programs offer a unique and more precise approach. Implementing a pilot program can allow for changes in treatment methods, and policies and procedures that affect cost estimates before implementing the full-scale program.

4.2.6 After components have been prioritized, airport operators should create a budget for each program area. This helps the airport operator meet all goals without exceeding budgets and allocated funding. In addition to managing costs, the airport operator should be aware of items throughout the program that can vary in cost. Examples include contract employee wages, testing requirements that may increase over time, deficiencies in structures or buildings, and environmental issues. Treatments offered to the community may also affect the cost of the program. Treatment options can be different depending on the SIP and location of the structures.

4.2.7 Lastly, airport operators should consider the type, brand, and quality of the materials and products that will be purchased for the program. These purchases can vary in price depending on the type of structure or its geographic location. Evaluations should be conducted with the contractor to discuss the products and materials that are the most appropriate for the SIP.

4.3 Contracting and Procurement.

4.3.1 Selection guidance for architectural and engineering consultants is provided in FAA AC 150/5100-14, Architectural, Engineering, and Planning Consultant Services for Airport Grant Projects. Under this guidance, airports select consultants based on qualifications and negotiation of a reasonable price. Airports using AIP funding shall ensure the SIP complies with AIP guidance. This includes conducting an independent cost estimate of the selected architectural and engineering consultants’ fees. Airports not using AIP funding should ensure the SIP complies with all local and state requirements, starting with the team selection.

4.3.2 Since projects are typically multi-year projects, outreach to construction contractors will be ongoing throughout the project. The process begins during outreach to property

4.3 Contracting and Procurement. › 4.3.3 For projects funded through AIP grants, an independent cost…

owners, before the design and construction phase. This process is necessary to identify qualified contractors for bidding on and performing the project. The primary goal is to have a large selection of qualified bidders. Training should be provided to all selected contractors to describe all SIP processes and procedures.

4.3.3 For projects funded through AIP grants, an independent cost estimate of the selected contractor’s fees is required prior to award. Usually the Design Consultant/Project Architect does the independent cost estimate for the construction contracts.

5.2 Plan. › 5.2.2 The airport operator or sponsor should submit the proposed…

CHAPTER 5. COMMUNITY OUTREACH

5.1 Community Involvement.

5.1.1 The FAA’s community involvement policy establishes the agency's commitment to community interests. The goals of the FAA's community involvement policy are to:

 Provide active, early, and continuous public involvement.

 Provide reasonable public access to information.

 Provide the public an opportunity to comment prior to key decisions.

 Solicit and consider public input on plans, proposals, alternatives, impacts,

mitigation, and final decisions.

FAA’s Community Involvement Manual published in 2016 as well as the most recent version of Advisory Circular 150/5050-4, Community Involvement in Airport Planning are useful resources which can be used when developing a community involvement plan for SIPs.

5.1.2 The intent of these goals is to improve the effectiveness of the FAA’s public involvement activities, ensure well-informed decisions, and encourage innovative methods for involving the public. The FAA extends this policy to all planning initiatives and studies receiving federal funding, or which require FAA approvals for implementation, including SIPs. Community outreach within a SIP needs to be a continuation of public involvement efforts conducted during the preceding Part 150 study or NEPA analysis. Within the SIP process, community outreach begins before the design process and continues through the end of the construction phase.

5.1.3 The main steps that should be taken as part of community outreach are summarized below and shown in Figure 5-1.

5.2 Plan.

5.2.1 Successful community outreach should be planned early enough so parties can obtain the necessary resources and data to interact effectively. Defining the goals and objectives of community outreach efforts will guide the process by determining who will be engaged, the level of participation, and the types of public involvement tools and techniques that will be used. As noted earlier, planning for community outreach in the SIP should closely follow the public involvement process used in the preceding Part 150 or NEPA studies.

5.2.2 The airport operator or sponsor should submit the proposed outreach plan and materials to the FAA ADO Program Manager for review and comment. Receiving FAA input will ensure that public information corresponds to the general scale of the SIP.

5.3 Design and Implement. › 5.3.1 The program and implementation team should ensure the following…

5.3 Design and Implement. One of the most important steps is to select the most effective communication techniques and tools. Tools include public meetings, the formation of special committees, data collection techniques, program offices, and the use of internet and mobile technologies (personal cell phones, tablets, instant voting technology, etc.). The communication strategy needs to remain flexible and open to new ideas because these tools are evolving with the advent of new technology and media platforms and not all communications techniques and tools are equally effective for all communities. Special care is required to meet the needs of affected communities such as the visually impaired, hearing disabled, English as a second language communities, low-income communities, and minority communities. Communications methods should be tailored to the needs of the affected community, and with their input.

5.3.1 The program and implementation team should ensure the following information is addressed, understood by the airport, and expressed to the community during the outreach process:

 An explanation of the study and how the sound insulation mitigation project came

about, either through a Part 150 or NEPA Study.

 The Part 150 NEM being used is reflective of current conditions at the airport and

has been accepted by the FAA.

 An explanation of the two requirements for determining qualification for treatment,

namely that:

o The residence is located in a DNL/CNEL 65 dB or greater noise contour.

o The average interior noise levels for habitable rooms must be equal to or greater

than DNL/CNEL 45 dB.

 Provide collateral materials discussing the program and the method of

communication to potentially impacted participants.

5.3 Design and Implement. › 5.3.2 Milestones.

Figure 5-1. Community Outreach Process

5.3.2 Milestones. Within the SIP, important milestones should be communicated and coordinated with the community. This includes:  Identifying potentially impacted structures within the program area.  Creating a phasing plan based on funding availability and project size.  Sending program information and offer letters to residents for pre-construction

testing to determine if the structure is impacted, including required forms and documentation.36  If initial participation agreement (if utilized) and application is confirmed,

conducting pre-construction testing and site assessment on structures identified within the potentially impacted program area.  Identifying impacted structures if a structure meets the testing criteria and including

them in the SIP.  Executing final participation agreements and avigation easements.  Conducting and completing construction of sound insulation based on phasing plan.  Conducting post-construction testing to verify the required NLR or interior noise

level has been accomplished.

36 Letters should only be sent to those within the proposed phase, particularly for multi-year projects.

5.3.3 Coordination.

5.3.3.1 Demographic Analysis. Before contacting potentially impacted residents, airport operators or sponsors should complete an analysis of the program area, including demographics and economic factors. Understanding the individuals living in the program area helps establish appropriate goals and plans that will better serve the community. Demographics include age, income, and primary language. When determining the demographics of the area, airport operators or sponsors should consider the use and function of the facilities (educational, medical, or place of worship), geographic location, and number of people that might work at, reside in, or use facility services (e.g. personnel, students, patients, or members of a congregation). Airport operators or sponsors can identify the area’s demographics by conducting door-to-door questionnaires, distributing surveys (online or mailings), and reviewing census reports, using the American Community Survey, along with other methods.

5.3 Design and Implement. › 5.3.4 Communication.

5.3.3.2 Cultural, Language, and Socioeconomic Considerations. Depending on the demographic findings, the airport operator or sponsor may need to accommodate the culture and language of the surrounding area. Accommodations include providing translations of all documents, and interpreters at local meetings or individual site assessments.

5.3.3.3 Socioeconomic considerations are also important to consider within the program area. This may determine the method in which documentation and collateral materials are developed and delivered to accommodate for the residents’ education, background, and location (e.g., access to Internet). For instance, are email and social media the best communication tools or are direct mailings and announcements in community newsletters more appropriate? Airport operators or sponsors may also consider hiring a local representative to help with outreach efforts. This may add an additional level of trust or comfort for the community when learning about the program.

5.3.4 Communication. Communicating with the public is important for gaining support and trust from the community. To be successful, an airport operator or sponsor should understand its target audience and create a consistent and concise message that is easily understood.

5.3.4.1 Notification Methods. The first step in the communication process is to understand the target audience. Depending on the target audience, various notification methods can be considered. The notification methods also depend on the program size, airport size, funding, demographics, and other relative factors. Consistent, frequent, two-way communication with the community is important to avoid misinformation or misinterpretation of program goals and requirements.

5.3.5 Messaging. › 5.3.5.1 Airport Leadership.

5.3.4.1.1 The most common notification methods include:

 Written correspondence  Airport website  Personal visits to structures  Newspaper advertisements or other publication methods  Videos  Public service announcements  Public or community meetings, open houses, and workshops  Social media posts

5.3.4.1.2 Airport operator or sponsors should ensure consistent, frequent, individualized communication with all property owners who may potentially be impacted.

5.3.4.1.3 Airport operator or sponsors should notify or meet with local elected officials who represent residents involved in noise mitigation.

5.3.4.1.4 Airport operator or sponsors should also notify or meet with planning and zoning, and building permits and inspections personnel who will be involved in the local approval process.

5.3.4.1.5 Holding a property owner’s orientation can be an effective way to inform property owners of the study requirements, impact requirements, program boundaries, and the steps that will be taken if the individual’s property is considered for sound insulation.

5.3.5 Messaging.

5.3.5.1 Airport Leadership. A community’s attitude toward the program may be based on airport leadership’s involvement and attitude toward the program. To that end, airport leadership should be identifiable and active in the SIP process. Communities will gain trust with positive, actively engaged leadership.

5.3.5 Messaging. › 5.3.5.6 Internet and Social Media.

5.3.5.2 Communication to Non-Qualified Residences. To ensure consistent messaging throughout the program, it may be appropriate for airport operators or sponsors to create and develop a policy for communicating to those who do not qualify for sound insulation. A letter with a description of why the resident is not impacted significantly by airport noise to qualify, within the definitions established in the airport industry, may be provided to explain the determination. Also, a letter to the local elected officials who represent the non-qualified residents may be provided in case the resident contacts their elected representative for guidance.

5.3.5.3 Individual Communication. Individual communication to each resident can increase trust and provide a better basis for receiving feedback on the program. It also allows the airport operator or sponsor to understand the type of communication method that suits those individuals. Airport operators or sponsors should provide contact information for the person assigned to represent a specific area of the project. The designated representative should be available to listen to the community’s comments and concerns, and consistently address questions on the program.

5.3.5.4 Transparency. To build trust with the community, the airport operator or sponsor should ensure the SIP process is transparent by remaining truthful and open about the program. To succeed, service-oriented personnel should be part of outreach efforts. Whether personnel are airport employees or are hired for the program, these personnel should have the information necessary to answer questions, comments, and concerns from the public. Personnel should have a positive, helpful attitude when answering the public’s questions. Lack of transparency can create negative perceptions of the SIP and lead to public opposition to the program, and future airport development projects.

5.3.5.5 News Media. Airport operators or sponsors may consider using news media to get information to the public. Many airport operators or sponsors use local events to advertise their programs, and encourage the media to attend and report on the SIP. News articles and press releases can also reach a large population.

5.3.5.6 Internet and Social Media. The internet can be an important resource for the community to learn more about the program and find contact information for communicating their questions and concerns. Airport operators or sponsors who develop a website for their program should ensure information is frequently updated

5.3.5.7 Program Offices. › 5.3.5.7.1 It may also be reasonable for airport operators or sponsors…

and describes the current status of the program. Using the same branding, tone, and message on a project website as other materials is essential to establishing continuity and credibility.

5.3.5.6.1 Social media platforms are a common form of distributing information and seeking input. Airport operators or sponsors should know the types of social media tools used in the community and determine which type of media/technology is best for the project. Existing or project-specific personnel should create and update information on the website and/or social media platforms.37

5.3.5.7 Program Offices. Depending upon the size of the program, it may be reasonable for airport operators or sponsors to consider using a program office for the SIP. A program office provides a community with a single location to contact SIP personnel. It also provides a dedicated work area for the program personnel. If a program office is used, assigning, leasing, or renting space, and the provision of office equipment should be considered during SIP cost development (Chapter 4).

5.3.5.7.1 It may also be reasonable for airport operators or sponsors to consider a product showroom to display the types of equipment, materials, and products that will be used in the SIP process. This may help stakeholders in the community become better informed on the sound insulation process. It is the airport operator’s or sponsor’s responsibility to organize and determine the location of the product showroom to accommodate the contractor’s materials/equipment. Airport operators or sponsors may also consider providing a sample structure so property owners can see an insulated structure. Purchasing a residence to serve as a product showroom is not allowable under AIP. However, there may be instances where this strategy may be used when non-compatible structures are within the 75+ dB contour.38 Despite this, the airport operator or sponsor should consider a fixed or mobile structure that can be easily moved from site to site, or to community meetings. The cost of completing the demonstration structure, with treatments, is coordinated with the FAA. This expense should be considered when developing a program.

37 When selecting social media platforms to use, other factors to consider include prevalence in the community and ability to manage comment moderation. 38 In scenarios where a non-compatible structure is located within the 75+ dB contour, it would not be eligible for sound insulation and the airport operator or sponsor should acquire it. Following acquisition and prior to demolition, it could be repurposed as a model home for sound insulation; however, the cost of insulating that home would not be eligible.

Chapter 5. Community Outreach › 5.4 Assess, Reevaluate, and Update as Necessary.

5.4 Assess, Reevaluate, and Update as Necessary. Assessing community outreach efforts periodically can help the airport operator or sponsor (and FAA) determine if the selected tools are effective, and whether resources have been effectively and efficiently allocated. When effectiveness is evaluated throughout the process, airport operators or sponsors can adjust the outreach program so that it achieves the desired outcome.