SUBJ: Siting Criteria for Ground Based Augmentation System (GBAS)

1. This order establishes procedures for determining, evaluating and approving the siting required to install a Ground Based Augmentation System (GBAS) Ground Facility.

FEDERAL AVIATION ADMINISTRATION ORDER

2. Title Terminology - The Federal Aviation Administration' (FAA's) Local Area Augmentation System (LAAS), is also referred to as Ground Based Augmentation System (GBAS) in the international standards documents. GBAS will be used in this document. For the purpose of this document, the terms LAAS and GBAS can be considered interchangeable.

3. GBAS Siting Flexibility - The GBAS transmits a signal that carries a series of approach paths, and correction messages to the aircraft. The GBAS uses an omni directional antenna to transmit the message. GBAS is not fixed by function (e.g., proximity to runway centerline). This increases the siting location options and potentially reduces the need for an extensive site preparation effort typically associated with ground-based precision approach and landing systems. Other constraints are applicable to the installation and this order provides the information necessary to properly site the GBAS antennas.

Teri L. Bristol Vice President, Technical Operations Services

Distribution: Selected Air Traffic Organization Offices; A-W(AS/FS)-2; AST-1 (2 Copies); A-X(AS/FS)-2; A-FAF-0 (STD)

Initiated By: AJW-91

12/15/10 6884.1

Table of Contents

Chapter 1 General Information 1

1. Purpose of This Order 1

2. Audience 1

3. Where Can I Find This Order 1

4. Distribution 1

5. Perquisites for Users of this Order 1-2

5. Perquisites for Users of this Order 1-2

6. Applicable Documents 1-2

7. Application 1-3

8. Directive Verbs 1-3

9. Safety 1-3

10. Physical Requirement Considerations 1-4

11. GBAS Components as Obstructions 1-5

12. National Airspace Systems Changes 1-5

Chapter 2 GBAS System Description 2-1

1. System Overview 2-1

1. System Overview 2-1

2. GBAS Equipment Subsystems 2-3

Chapter 3 Siting Procedures 3-1

1. GBAS Ground Facility Equipment Siting Overview 3-1

2. Initial Site Inspection 3-3

3. Site Trade-Off Analysis 3-6

4. Formal Site Survey 3-9

5. VDB Interference Data Collection 3-12

6. Equipment Shelter Site Survey 3-12

7. Formal Site Survey Report 3-12

7. Formal Site Survey Report 3-12

Chapter 4 General Considerations for Siting 4-1

1. Analysis of Operational Requirements 4-1

2. Antenna Phase Center Height (PCH) Considerations 4-1

3. Power Considerations 4-1

12/15/10 6884.1

4. Cable Run Considerations 4-2

5. Site Access Considerations 4-2

6. Equipment Siting Considerations 4-3

6. Equipment Siting Considerations 4-3

7. Equipment Environment and Maintenance Considerations 4-3

8. Real Estate Assessment 4-3

Chapter 5 System Sitting Criteria 5-1

1. GBAS Ground Facility Equipment Local Object Consideration Areas (LOCA's) 5-1

2. Reference Receiver Siting 5-5

3. VDB Antenna Siting 5-14

3. VDB Antenna Siting 5-14

4. Obstruction Zones 5-22

5. Communication, NAVAID Protection Areas 5-22

6. Airport Development Plans 5-22

7. Implementation 5-23

Chapter 6 Acronyms 6-1

Appendix A GBAS PARAMETERS CRITICAL TO ATC OPERATIONS A-l

1. GBAS Integration A-l

2. GBAS Integrity Parameters A-2

3. GBAS Continuity A-4

3. GBAS Continuity A-4

4. GBAS Availability A-5

5. GPS Reception Capabilities A-5

6. Nominal Radio Frequency Interference (RFI) Environment A-5

7. Data Broadcast Capabilities A-6

8. Operational Coverage Volumes A-7

Appendix B VDB SUBSYSTEM CONFIGURATION B-l

1. Standard VDB Subsystem Configuration B-l

2. Option 1 - Standard Primary VDB Subsystem with Additional VDB Subsystem B-2

2. Option 1 - Standard Primary VDB Subsystem with Additional VDB Subsystem B-2

3. Option 2 - Non-Standard Primary VDB Subsystem without Additional VDB Subsystem B-3

4. Option 3 -Non-Standard Primary VDB Subsystem with Additional VDB Subsystem(s) B-4

Appendix C DATA ANALYSIS AND MATH MODELING C-l

1. Overview of Data Analysis C-l

1. Overview of Data Analysis C-l

12/15/10 6884.1

2. Math Modeling C-l

Appendix D HONEYWELL SLS-4000 SPECIFIC PARAMETERS D-l

1. RRA to Centroid DH Distance D-l

2. RRA Placement Parameters D-l

3. VDB Antenna Safety Area D-l

in

12/15/10 6884.1

Table of Figures

Figure 2-1 Ground Based Area Augmentation System GBAS 2-2

3. VDB Antenna Safety Area D-l

Figure 5-1 RRALOCA 5-2

Figure 5-2 VDB Safety Area and LCOA 5-3

Figure 5-3 GBAS Constrained Siting Example 5-7

Figure 5-4 Guidance for Determining the RRA Selective Masking or Critical Areas at

The Intersection of the LOCA and Movement Area 5-11

Figure 5-5 Ground and Non-Ground Multipath 5-13

Figure 5-6 VDB Coverage Volume 5-17

Figure 5-7 VDB Non-Ground Reflection and Shadowing 5-21

Figure A-1 Ground Accuracy Designator (GAD) B and C Curves A-3

Figure A-2 CAT I Approach Coverage Volume A-8

Figure A-3 CAT I Missed Approach Coverage Volume A-9

Figure B-l Standard PVS Equipment Configuration B-l

Figure B-2 Option 1: PVS Configuration with 2 AVS's B-2

Figure B-3 Option 2: Non-Standard Primary Subsystem Without AVS B-3

Figure B-4 Option 2: Non-Standard Primary Subsystem With AVS B-4

IV

12/15/10 6884.1

Chapter 1 General Information

Chapter 1 General Information

1. Purpose of This Order.

This Order provides guidance to engineering personnel engaged in the siting of the Federal Aviation Administration (FAA) Ground Based Augmentation System (GBAS) Ground Facility. The criteria contained in this document, along with requisite information collected during site visits and review of relevant equipment documentation, will enable the engineer to select the optimum siting of the GBAS Ground Facility to support precision approach procedures. The GBAS siting shall be in accordance with requirements specified in this order In addition, the document provides:

• Installation requirements.

• Facility requirements for the installation.

• Requirements for maintaining the areas around the antennas associated with the GBAS Ground Facility.

2. Audience.

Federal Aviation Administration (FAA) personnel responsible for the installation or approval of GBAS. This document provides information on GBAS components and expected configurations, can also be used as a template for the development of the Siting Plan.

3. Where Can I Find This Order.

You can find this order on the Directives Management System (DMS) website: https://employees.faa.gov/tools_resources/orders_notices/.

4. Distribution.

This order is distributed in headquarters to director level in all Air Traffic Organization service units under the Senior Vice President for Operations; to group level in the Technical Operations Safety and Operations Support, Aviation System Standards, and Navigation Services directorates; to the Associate Administrator for Commercial Space Transportation; to division level in the Office of Airport Safety and Standards and the Flight Standards Service; to group level in the Technical Operations Service Areas and the Service Centers; to division level in the regional Airports and Flight Standards divisions; and to all Technical Operations field offices with a standard distribution.

1-1

12/15/10 6884.1

5. Perquisites for Users of this Order.

The Order assumes that the reader has an engineering background and knowledge of the operating principles of GBAS and the GBAS Ground Facility. Additionally, this Order does not attempt to duplicate all information found in other applicable FAA documents. The user is expected to have access to and a working knowledge of those documents found in Chapter 1, Paragraph 6, Applicable Documents. The information and procedures described in this Order present methods for siting a GBAS Ground Facility.

6. Applicable Documents.

The following documents form a part of this specification to the extent specified herein. In the event of conflict between the documents referenced herein and the contents of this specification, this document shall be considered a superseding requirement.

Document Number [1] FAA-E-3017

[2] FAA Order 8260.3

[3] Title 14CFRPart77

Title Non-Federal Specification Category I Local Area Augmentation System Ground Facility

United States Standard for Terminal Instrument Procedures (TERPS)

Title 14, Aeronautics and Space, Code of Federal Regulations (CFR), Part 77, Objects Affecting Navigable Airspace

[4]

[5]

[6]

Series 150 Advisory Circulars Advisory Circular, Airport Design (AC) 150/5300-13

FAA Form 7460-1

DO-245A

Airway Notice of Proposed Construction or Alteration

Minimum Aviation System Performance Standards for Local Area Augmentation System (LAAS) [MASPS]

[7] Advisory Circular 150/5340-1 Standards for Airport Marking, Marking of Paved Areas on Airports, for marking information

[8] FAA Order 6950.2 Electrical Power Policy Implementation At National Airspace System Facilities

1-2

12/15/10 6884.1

Document Number Title

[9] FAA Order 5050.4

[10] DO-246D

National Environmental Policy Act [NEPA] Implementing Instructions for Airport Projects

GNSS-Based Precision Approach Local Area Augmentation System (LAAS) Signal-in-

Space Interface Control Document [ICD]

7. Application.

The criteria set forth in this Order apply only to new establishments or relocated facilities. Changes to existing facilities for the sole purpose of obtaining compliance with these criteria are not required.

8. Directive Verbs.

The material in this Order contains FAA criteria, policy, recommended practices, and other guidance material that require the use of certain directive verbs such as must, shall, should, will, and may. In this Order, the explicit meaning of the verbs is as follows:

• Must - The action is mandatory. For example: "Obstacle clearance requirements must be met in accordance with the United States Standard for Terminal Area Procedures (TERPS)." • Shall - The action is mandatory. It is used for mandatory requirements with measurable results. • Should - The action is desirable. For example: "Proximity of site access roads should be considered. • Will - The action is to be taken in the future. For example: "The site survey will be conducted to provide quantitative data on the candidate sites chosen during the initial site selection process." • May - The action is permissible. For example: "The site survey flight check may be necessary in difficult siting environments to assess the coverage volume impact of obstructions and terrain."

9. Safety.

Personnel should use caution in working on GBAS Ground Facility equipment, particularly radio transmitters, since the voltages presented are dangerous to life. Observance of precautions necessary to avoid electrical shock is the direct responsibility of the individual. No one should perform work on

12/15/10 6884.1

the equipment without full knowledge of the dangers involved. An individual should not attempt work on high-voltage circuits without the services of an assistant. The standards and tolerances for the GBAS Ground Facility are contained in the Commercial Instruction Book (CIB) generated by the equipment manufacturer.

10. Physical Requirement Considerations.

The location of the electronic systems should be considered when making the GBAS siting selection. The size of the airport needs to be considered so that coverage is provided to the entire airport. Siting within restricted areas should only be considered when standard installations are not practical.

a. Equipment Type and Configuration Considerations. Equipment type and configuration used in GBAS establishments should be carefully chosen for the environment in which it is installed. Consideration should be given not only to siting the GBAS Ground Facility equipment to account for current terrain, obstructions, etc., but also for airport expansion and other developments around the airport environment. See Chapter 3, Paragraph 2.a Initial Data Acquisition.

b. Key Factor 1. The GBAS system components need to be installed in a secure area. In general terms, this is usually the Airport Operations Area (AOA) of a given airport. For additional information, see Chapter 4, Paragraph 6, Equipment Siting Considerations.

c. Key Factor 2. The transmitting antenna, part of the Very High Frequency (VHF) Data Broadcast (VDB)

Subsystem, should be within 3 nautical miles (NM) (3 kilometers) of the runway thresholds for which the system is providing service. For additional information, see Chapter 5, Paragraph 3.f (2), Location with Respect to Runway Threshold.

d. Key Factor 3. The 4 GBAS receive antennas as a group, arranged on a given area of land, will have a mathematical virtual center point that is referred to as the centroid. This centroid should be within 3.2 Nautical Miles (NM) (6 Kilometers) of any desired Decision Height (DH) points (measured at ground

level). For additional information, see Chapter 3, Paragraph 3.c, RRA Centroid to DH Distance.

e. Key Factor 4. The VDB Antenna (VDBA) max field strength exclusion region must not exceed 656 feet (200 meters) in radius. For conservative siting, measures should be taken to site the VDBA 656 feet (200 meters) from any operational aircraft venues. These areas generally include runways, taxiways, and ramps. This Radio Technical Commission for Aeronautics (RTCA)/FAA requirement exists to preclude overdriving GBAS avionics. For additional information see Chapter 5, Paragraph 3 f (2) Maximum Field Strength.

f. Key Factor 5. The GBAS Reference Receiver antenna siting is flexible. See Chapter 5, Paragraph 2, Reference Receiver Siting for guidance.

g. Siting Criteria Deviations. If in the process of planning or locating a GBAS Ground Facility, it is determined that the siting criteria set forth in this Order cannot be followed, the deviation shall be documented in the facility approval documentation.

12/15/10 6884.1

11. GBAS Components as Obstructions.

The siting engineer considers the effects of the GBAS Ground Facility components themselves as obstructions. These considerations should include guidance given in: Order 8260.3, United States Standard for Terminal Instrument Procedures (TERPS), Title 14 CFR Part 77, Advisory Circulars AC

150/5300-13 and Airway Notice of Proposed Construction or Alteration FAA Form 7460-1. Both the Airport Division Office and Flight Procedures Office should be consulted and provide approval and/or waiver for any penetrations as part of the required airspace review. Failure to obtain approval or a waiver will preclude installation of that component.

12. National Airspace Systems Changes.

Siting a GBAS Ground Facility component shall not result in an adverse affect on existing or planned instrument procedures at the level of minima desired for the procedure(s). See Order 8260.3, United States Standard for Terminal Instrument Procedures and/or associated directives. AC 150/5300-13 provides a description of the obstruction clearance and protection surfaces (i.e. Obstacle Free Zone (OFZ), Runway Safely Area (RSA), Object Free Area (OFA)) on the airport. If it is not feasible to design and install a GBAS Ground Facility without penetrating these surfaces, a configuration control decision will be required, resulting in a NAS Change Proposal (NCP).

12/15/10 6884.1

Chapter 2 GBAS System Description

Chapter 2 GBAS System Description

1. System Overview.

a. The GBAS provides guidance to pilots of properly equipped aircraft to assist them in landing safely under Category (CAT) I weather conditions. The use of a GBAS materially aids the service to airports under all weather conditions.The GBAS is categorized according to the minimum visibility conditions under which aircraft landings are permissible. The criteria specified in this Order only apply to GBAS CAT I systems. The requirements for the CAT II / HI systems are being validated. Once the validation is complete, this document will be revised as required.

b. GBAS is based on the concept known as Differential Global Positioning System (DGPS). In addition to application of basic DGPS concepts, the GBAS utilizes hardware and software to ensure accuracy, integrity, continuity, and availability to support precision approach, area navigation (RNAV), and surface operations.

c. GBAS consists of three primary subsystems:

• Space Segment • Ground Subsystem • Airborne Subsystem

An overview of the subcomponents of GBAS and their interaction is provided in Figure A-l Ground Based Area Augmentation System (GBAS).

12/15/10 6884.1

Reference Receivers

Omnidirectional VHF Data Broadcast (VDB) Signal

Figure A-l Ground Based Area Augmentation System (GBAS)

d. The space segment consists of the GPS satellites, which transmit ranging signals and navigation messages to airborne receivers. The GPS signals are received by the ground station via a set of Reference Receiver (RR) Antennas (RRA's). The reference receivers decode the GPS signal to obtain the ranging source and navigation data for each of the satellites tracked. The Differential Corrections Processor (DCP) computes a pseudorange to the satellite, generates differential corrections for pseudoranges computed for GPS, performs integrity checks, and transmits corrections, integrity parameters, and path point data to the user via a Very High Frequency (VHF) Data Broadcast (VDB) transmitter/antenna. The GBAS Ground Facility employs multiple reference receivers to increase accuracy and provide integrity. The GBAS Ground Facility computes an average of the corrections from the multiple RR's and broadcasts this average correction to the user. This improves the accuracy of the correction over that of a single RR.

The use of multiple reference receivers is also used to provide fault isolation by performing measurement consistency checks. These checks are performed through the computation of an integrity parameter termed a B-value. B-values are described in Appendix A, Paragraph 2..b, B-Values. .Differential GPS (DGPS) uses the commonality of measurement errors between the Ground Subsystem in a local area DGPS system such as GBAS; many errors are highly correlated between the Ground Subsystem and the Airborne Subsystem. The broadcast DGPS correction will not correct for errors which are uncorrelated between the Ground Subsystem and the Airborne Subsystem. These errors can be mitigated through other techniques including proper siting of the GBAS Ground Facility RRA's. These uncorrelated errors, if not mitigated through other techniques, introduce errors in the user position solution. These uncorrected errors are known as

12/15/10 6884.1

pseudorange correction errors. Following is a list of some of these uncorrected errors, which are uncorrelated between the air and ground and are not compensated by the uplinked correction factors alone.

• Multipath error observed at the GBAS Ground facility RRA's. • Radio Frequency Interference (RFI) induced errors. • Spatial decorrelation due to Ionosphere and Troposphere. • Multipath error observed at the airborne GPS antenna. • Surveying errors of the RRA's. • Rare satellite signal anomalies (that cause dissimilar errors at the Ground Subsystem and the Airborne Subsystem when there are differences in receiver signal processing techniques).

e. The GBAS is designed to minimize the effect due to most of the aforementioned error sources. However, some of these error sources, such as multipath observed at the GBAS Ground Facility RRA, are site specific and their effect can be minimized using proper siting procedures The Airborne Subsystem also decodes the satellite navigation messages, applies the differential corrections transmitted from the GBAS Ground Facility to the satellite messages, computes a position solution and generates deviations based on the broadcast path point data. The Airborne Subsystem also computes an estimate of vertical and lateral position error based on the integrity parameters broadcast from the GBAS Ground Facility and the current satellite geometry.

2. GBAS Equipment Subsystems

2. GBAS Equipment Subsystems

The GBAS is composed of the following equipment:

• Reference Receiver Subsystem • Processor Subsystem • VHF Data Broadcast Subsystem • Operations and Maintenance Subsystem • Infrastructure / Ancillary Equipment

a. Reference Receiver Subsystem. The Reference Receiver Subsystem consists of a minimum of four Reference Receiver Stations (RRS) each containing a Reference Receiver (RR) and Reference Receiver Antenna (RRA). The RRS provides a weatherproof enclosure to protect the References Receiver (RR) and is mounted in close proximity to the Reference Receiver Antenna (RRA). In addition, the enclosure contains the power supply, and lightning protection circuits. The Reference Receiver Subsystem is responsible for providing 4 pseudorange measurements (typically) for each visible GPS satellite. It also provides basic health status of each satellite.

12/15/10 6884.1

(1) Reference Receiver (RR). The Reference Receiver processes the Global Positioning

System (GPS) signal from the RR and sends it to the processor Subsystem.

(2) Reference Receiver Antenna (RRA). The RRA is a Multipath Limiting Antenna (MLA).

The MLA design minimizes GPS signal reflections that cause measurement errors.

b. Processor Subsystem. The Processor Subsystem consists of the GBAS Ground Facility processors that perform the correction computations, integrity processes, and message generation functions. The Processor Subsystem is housed in the Primary Equipment Shelter. The processors are mounted in a 19 inch wide rack. The Processor Subsystem is also responsible for critical safety and integrity monitoring of both incoming pseudorange and satellite status and outgoing correction data.

c. VDB Subsystem. The VDB Subsystem consists of the Primary VDB Subsystem (PVS) and any optional / required (also referred to as Additional) VDB Subsystem (AVS). The utilization of the two subsystem types is to allow for configurations that mitigate coverage-related siting issues. The GBAS Ground Facility design allows for multiple VDB configurations. The VDB configuration options are described in Appendix B, Subsystem Configurations.

(1) VDB Antenna. The VDB antenna is a VHF antenna (single or multi-bay) designed to

reduce the gain pattern in the direction of the ground plane in order to minimize multipath. The antenna is located with line-of-sight to all approaches.

(2) VDB Electronic EquipmentA fully redundant set of VDB Electronic Equipment consists

of two VHF transmitters, and two VDB monitor receivers. The equipment is housed in a single standard 19 inch wide rack.

d. Operations and Maintenance Subsystems. The Operations and Maintenance Subsystem includes the following equipment:

• Local Status Panel (LSP) • Maintenance Data Terminal (MDT) • Air Traffic Status Unit (ATSU)

(1) Local Status Panel (LSP). The LSP is physically located in the equipment cabinet. The

LSP is mounted in a standard size 19 inch wide rack. The Local Status Panel provides visual and audible indicators of the system status. System mode and fault conditions are

12/15/10 6884.1

indicated via colored Light Emitting Diodes (LED's), with fault conditions also have audible indication.

(2) Maintenance Data Panel (MDT). The MDT is a typical laptop computer, and may be

physically located with the GBAS equipment rack. The Operations and Maintenance Subsystem is responsible for providing an interface to operator and maintainers of the GBAS Ground Facility.

(3) Air Traffic Status Unit (ATSU). The ATSU provides an interface between the system and

Air Traffic Controllers (ATC) with only the status of the system (there are no provisions for ATC to control the GBAS). '

12/15/10 6884.1

Chapter 3 Siting Procedures

Chapter 3 Siting Procedures

1. GBAS Ground Facility Equipment Siting Overview.

Siting a GBAS Ground Facility involves finding suitable locations for the following major components:

• Reference Receiver Stations (RRS) - The RRS is comprised of a Reference Receiver (RR), Reference Receiver Antenna (RRA), and control and interface equipment. The RR and RRA are collocated. • VDB transmitting equipment, processing equipment - The VDB transmitting equipment consists of a transmitter, antenna, and control and interface equipment. The VDB antenna may be located adjacent to the shelter housing the VDB transmitter. In complex locations the transmitter and VDB antenna may be located remotely from the shelter. The siting of multiple

VDB transmitters and/or antennas may be required at difficult or complex sites. The GBAS processing equipment consists of the GBAS computers and interface equipment. The GBAS processing equipment will typically be sited in the GBAS equipment shelter although existing shelters or facilities may be used to house the processing equipment in some cases. • Remote control and status units.

a. Reference Receiver Station Siting. The siting of the RRS involves finding suitable locations for the multiple RRA's. A minimum of four RRA's will be required to be installed at each GBAS installation. It may be determined during the site survey that an additional RRA is required to meet system performance requirements. In addition to installation of the designated equipment, the potential for upgrade of the GBAS in the foreseeable future, which may require the installation of additional RRA's, should be determined. There are two fundamental criteria for selecting a RRA location. The first criterion ensures sufficient real estate is available for installation of the RRA. The required real estate should take into account the minimum required separation distance between the RRA's. The second is the actual location. It should be free of sources of multipath and shadowing which may cause unacceptable degradation of the RRS performance. Having met these fundamental criteria, the next steps involve assessing the potential for designated critical areas to impact surface operations and evaluating the potential for Radio Frequency (RF) interference at the candidate RRA location. These topics are addressed in the following subsections. Selecting candidate RRA locations should take into consideration the feasibility and cost of routing electric, communication, and RF cables between the RR, RRA, and shelter. Further, the location of existing underground facilities (electric, communication, RF, gas, sewer, water lines, etc) should be determined and assessed to ensure that these will not be problematic.

12/15/10 6884.1

(1) Separation Distance Criteria. Determining the minimum separation between the RRA's

requires consideration of the following factors:

• RRA near-field boundary and / or the intermediate Local Object Consideration Area (LOCA) boundary. • Mitigation of common multipath error sources.

b. Separation Distance - Depending on the equipment configuration to be deployed, the separation distance required to satisfy each of these factors may differ. Proper integrity monitoring requires that there are no common-mode (correlated) multipath error sources among the RRS or that the magnitude of such errors is controlled so that the system error budget is not violated. This statement does not mean that any single object cannot cause multipath at multiple RRA locations. It means that the characteristics of significant multipath error caused at multiple RRA locations at the same instance in time must be dissimilar. Ground reflections are always a potential source of correlated multipath errors. Similarly, a large building in close proximity to the RRA's has the potential to generate correlated multipath errors in certain instances.

Since real-time detection of correlated multipath errors may be difficult to achieve during normal GBAS operations, application of the GBAS multipath model or data collection and analysis shall be performed to ensure suitability of the candidate RRA locations. Mitigation of the common-mode multipath problem in this case is achieved by both using a sufficient separation between RRA and selecting an appropriate RRA phase center height (PCH) or installing RRA's that provide significant rejection of ground reflections. Determining the RRA PCH to be used is addressed in Chapter 4, Paragraph 2, Antenna Phase Center Height (PCH) Considerations. For antennas that do not provide significant rejection of ground reflections, irregularities that may be present in the ground plane will result in decorrelation of the multipath error. In addition, separation should be provided between the RRA's to ensure that multipath from service vehicles and aircraft, for example, are not correlated at multiple RRA locations.

In some instances, the use of a separation distance that is larger than the minimum distance determined by consideration of the above three factors may be required. For example, a larger separation may be required to satisfy critical area requirements such as, when two RRA's straddle a service road.

c. Remote Units -Air Traffic Status Unit (ATSU). The GBAS provides a status output intended for use by Air Traffic Control. A given airport may install an Air Traffic Status Unit (ATSU) to display this information, as required. This status output is available for connection to additional display interfaces as those systems develop.

d. VDB Transmitter Siting - There are two possible locations for the VDB transmitter. The transmitter could be located near the antenna and be connected to the GBAS processor via a data line or the transmitter could be located with the GBAS processor and coaxial cable used to supply RF to the antenna. The size of the enclosure will be dictated by the amount of equipment at the location and the required area around the equipment for service personnel. An existing equipment shelter may be used if available. If a new shelter must be installed, there are no specific requirements for its location. It should be located outside the GBAS Ground Facility Local Object Consideration Area (LOCA) where possible and as close to the transmit antenna as practical. Refer to Chapter 5, Paragraph 1 GBAS Ground Facility Local Object Consideration Areas (LOCA's) and c VDB Antenna Installation Consideration Area, for further information regarding LOCA. Transmission line losses will dictate the maximum distance from the antenna. Although the presence of fixed structures within the GBAS Ground Facility LOCA should be avoided, the impact of

12/15/10 6884.1

fixed structures should be analyzed through data analysis and/or math modeling. The GBAS Ground Facility configurations are described in Appendix B VDB SUBSYSTEM CONFIGURATION OPTIONS

e. Criteria for siting any one of these configurations is provided in this chapter. In addition, various GBAS components may need to be installed in a building or shelter. Criteria for determining if an existing building or shelter may be used, as well as criteria for installing a new equipment shelter, are provided.

f. Processor Siting. A location for housing the processing equipment will need to be identified. This equipment may be housed in an existing building, an existing equipment shelter, or a shelter may need to be installed. When considering the use of an existing building or shelter, the criteria contained in Chapter 5, Paragrph 2.c, VDB Antennna Installation Considerationscmust be applied to determine the minimum separation required between the building or shelter and each RRA. The required minimum separation of RRA's shall be assessed against the maximum length permitted for the communication cables running between the RR and the processing equipment. If the separation results in unacceptable cable lengths, an equipment shelter may be installed in a manner compliant with Appendix B VDB SUBSYSTEM CONFIGURATION OPTIONS

g. An alternative location for the processing equipment may be identified, or the location of the RRA may be adjusted when possible. Similarly, when the VDB transmitter is collocated with the VDB antenna, the required minimum separation of the VDB transmitter and the VDB antenna shall be assessed against the maximum length permitted for the communication cables running between the transmitter and processing equipment. The existing building or shelter shall have sufficient space available for housing the processing equipment. The availability of electrical power, cable access and routing, environmental control, and security shall be assessed when determining the suitability of the building or shelter.

2. Initial Site Inspection.

The purpose of the initial site visit is to better define the siting environment in order to perform comparative trade-off studies between potential sites. The data collected will include required service, terrain features, and potential sources of multipath and shadowing, land availability, proximity of power, environmental impact, and site access. This initial data collection should include an initial horizon profile (using a portable or handheld instrument such as clinometers) and a panoramic photograph at the proposed antenna sites. The initial phase of the project engineering is to gather information necessary to make informed decisions regarding initial site selection. The siting engineer should consult the cognizant authorities to obtain the required information. These authorities should include airport officials, Flight Standards, Air Traffic, Airports, and Technical Operations. The information gathered should include: The airport authority and terminal services should provide operational requirements (e.g. runways to be served, threshold/decision height locations), priorities, and specific equipment requirements related to status and control of the GBAS (e.g., number and location of status units) for the airport. This information will be used by the siting engineer to identify initial GBAS installation sites that lead to formal site surveys. The inputs to the initial site inspection are listed in Chapter 3, Paragraph 2.a Initial Data Acquisition. The output of the initial site inspection is an Initial Site Assessment Report. As a minimum, the Initial Site Assessment Report includes:

12/15/10 6884.1

• Results of the initial site inspection. • Evaluation of the map and paper study. • Evaluation of the following:

o Availability of power. o Availability of communications lines. o Trenching considerations. o Site access.

a. Initial Data Acquisition. During the initial data gathering activities, the siting engineer meets with the airport authorities and other project stakeholders on the GBAS siting and installation plans. Prior to the site visit the documentation needed to assist in the initial site assessment needs to be obtained and reviewed. Prior to the site visit the siting engineer will request that the following information be made available

(1) Airport Layout Plan (ALP), including:

(a) Airport Property Lines (b) Obstacle Free Zones (OFZ) (c) Runway Safety Areas (RSA) (d) Object Free Areas (OFA) (e) Location of Navigational Aids (f) Run-up and Jet blast areas (g) All Building locations. (h) Location of National Geodetic Survey (NGS) survey monuments, i.e. Primary Airport

Control Stations (PACS) and Secondary Airport Control Stations (SACS).

12/15/10 6884.1

(2) Airport Master Plan (5-10 year planning document).

(3) Airport Clearance Charts (Department of Commerce publication).

(4) Topographic Charts (U.S. Geological Survey publication) and aerial photographs of the

airport and GBAS terminal service area.

(5) Locations of environmentally-sensitive areas within the Airport Operations Area (AOA).

(6) Description of existing Air Traffic Control (ATC) facilities, Navigation Aid (NAVAID)

lighting and power sources.

(7) Airport conduit and cable information.

(8) Ground traffic patterns.

(9) Determination of the Landing Threshold Point (LTP) and minimum glide path (Flight

Procedures Office (FPO).

(10) Visual Flight Rules (VFR) Terminal Area Chart.

(11) GBAS equipment configuration options and configuration-unique characteristics

pertinent to siting.

(12) United States (U.S.) Instrument Approach Procedures (IAP's) defining existing and

proposed approach procedures to the airport and identifying obstacles in the terminal area. (Flight Procedures Office).

(13) Noise abatement regions, procedures, and plans.

(14) Restricted airspace.

(15) Existing and future traffic procedures.

(16) Any required alteration to proposed flight paths. (Flight Procedures Office).

12/15/10 6884.1

b. Initial Site Analysis The initial site analysis will involve the review of data collected during the real estate assessment (refer to Chapter 4, Paragrph 8, Real Estate Assesment and the initial site inspection. This analysis will be comparative in nature since the data gathered to this point is primarily qualitative. The quantitative analysis will be availability and coverage comparisons based on the initial horizon profiles at the RRA and VDB antenna sites respectively. The RRA centroid to DH distance Chapter 3 Paragra 3.c RRA Centroid to DH Distance for each supported runway end will also be considered in the initial availability assessment. The results of the initial site analysis will determine which sites deserve further survey and investigation. The Initial Site Analysis will identify the sites that will be considered in the final site selection process. The analysis will refine the analysis work performed during the initial site assessment and site inspection efforts.

The analysis should be provided to the airport authority in a report that documents potential sites identified in earlier investigative efforts. The reason for eliminating sites from consideration should be included in the report. If any proposed locations critically impact airport operations, or where buildings (objects) fall within the GBAS Ground Facility LOCA boundaries and are a potential multi-path source, these items will be highlighted in the report for further discussion with the airport authority, and as areas for analysis during the Formal Site Survey. The report should identify a minimum of three prospective sites to address as many of the Formal Site Survey Requirements as possible realizing that each site contains its own set of trade-offs. Off-airport locations will be considered if on-airport locations are infeasible or fail to meet significant operational requirements.

c. Initial Site Review After the potential sites for system installation have been identified. The siting engineer will meet with the airport authority to review the sites identified in the initial report. This will be an opportunity for airport authorities to eliminate sites which they feel will not work. It is possible they may suggest other locations, which must be evaluated to determine if they satisfy the siting requirements.

3. Site Trade-Off Analysis

3. Site Trade-Off Analysis

The Site Trade-off Analysis reviews the data collected during the Initial Site Inspection in order to provide the following site specific information:

a. Global Positioning System (GPS) Reception Mask / Ranging Source Broadcast Mask Determination. The GBAS Ground Facility GPS Reception Mask is used as an input to the Availability Model. The GBAS Ground Facility GPS reception mask is based on the precise horizon profile described in Chapter 3, Paragrph 4.a (6) Precise Horizon Profile. The horizon profile should be inflated, where applicable, to account for a five-year nominal tree growth of six inches per year. The distance from the RAA to the trees that was recorded during the Site Survey will be used to determine the inflated elevation angles. The Ranging Source Broadcast Mask is computed from the GBAS GPS Reception Mask by taking into account the time required for the RR data to be able to be used for the computation of measurement blocks after a satellite is acquired.

12/15/10 6884.1

b. RRA Performance Curve Determination. The RRA performance curve is an input to the Availability Model. The RRA performance curve is based on the estimation of CTpr-gnd, using the GBAS RRS model results and ranging source data collected during the Site Survey. The ranging source data analysis techniques are based on Government-approved CTpr-gnd data analysis and processing techniques. The data analysis techniques will be the same as the Government-approved techniques to minimize the risk of meeting the requirements during Site Survey and not at Final Installation and Checkout

c. RRA Centroid to DH Distance. The distance between the RRA centroid and the DH shall be computed for each supported runway end during the Real Estate Assessment described in Chapter 4, Paragraph 8 Real Estate Assessment. If the distance is greater than the nominal separation distance determined through analysis, the availability impact shall be computed using the equipment manufacturer's Availability Model. Based on the understood behaviors of the Ionosphere on GPS/Differential GPS (DGPS) there is a restriction on the radius from the RRA centroid (the RRA centroid is the geometric center of the RRA's) to any desired Decision Height point (measured at ground level). For the Honeywell SLS-4000 system refer to Appendix D Appendix D HONEYWELL SLS-4000 SPECIFIC PARAMETERS

d. Contunuity Analysis. The siting engineer performs a continuity analysis for each of the potential sites identified. For further information, see Appendix A, Paragraph 3, GBAS Continuity.

e. Availability Analysis. The siting engineer performs an availability analysis for each of the potential sites identified. For further see Appendix A, Paragraph 4, GBAS Availability.

f. RRS Tracking Perfromance Evaluation. The RRS tracking performance should be evaluated and the impact to continuity assessed. The RRS continuity fault occurs when the number of valid B-values is reduced below three (3) for any valid ranging source. Since the optimum number of RRS's is four, this allows for a loss of data from a single RRS at each epoch for any or all ranging sources.

g. VDB Coverage Analysis. The assessment of VDB continuity during siting is primarily based on the VDB coverage analysis. It is assumed that a VDB site that provides the minimum field strength within the required coverage volume (s) is an acceptable site with respect to continuity. The VDB coverage analysis is based on the VDB model results and precise horizon profile. The actual coverage volume is verified as part of the flight inspection for the site. An initial assessment of the quality of each proposed VDB site shall be made based on the line-of-sight (LOS) to the primary runways' approach coverage volume and other required coverage areas. The proper antenna height shall be chosen to meet field strength requirements throughout the required coverage volumes. Although this initial analysis is based on LOS, it is recognized that there may be constructive and destructive interference which may impact the VDB coverage volume.

12/15/10 6884.1

h. Ranging Source Pseudorange Error Analysis. An analysis of the pseudorange errors at each antenna site is performed using the guidelines in Chapter 3, Paragraph 3.b RRA Perfromance Curve Determination. The analysis includes the generation of error statistics that will be compared to the requirements curves. Analysis is also conducted to identify sources of excessive multipath, to evaluate error correlation between RR's, and to estimate the distribution of the errors. In addition, if the proposed equipment shelter location is within the RRA LOCA, its effect on system performance should be evaluated using the equipment manufacturer's RRS Model.

i. Interference Analysis.

(1) RRA Interference Analysis. An analysis of the interference environment is performed

using the data collected. This data should be compared to the interference mask in Appendix A GBAS PARAMETERS CRITICAL TO ATC OPERATIONS If the interference environment does not meet the interference mask, the interference source must be identified and mitigation strategies developed. If the interference signal is in conformance with its licensed operating signal parameters, and mitigation of the interference is not feasible, the RRA will need to be relocated or additional filtering added.

(2) VDB Interference Analysis. An analysis of potential interference to other airport systems

must be performed using the data collected in VDB Interference Data Collection. If is determined that the VDB is interfering with other airport system, corrective action must be identified to mitigate the interference to levels acceptable to airport and FAA authorities.

j . Site Environmental Analysis. The Site Environmental Analysis involves identification of locations of

environmentally sensitive areas such as wetlands, floodplains, historical or archeological sites, and endangered species habitats. Whenever possible, siting engineers should select alternative sites to avoid these environmentally sensitive areas. During the initial airport survey, and before selecting a site for the GBAS Ground Facility, the locations of environmentally sensitive areas such as wetlands, floodplains, historical or archeological sites, and endangered species habitats within the AOA should be noted. Whenever possible, siting engineers should select alternative sites to avoid these environmentally sensitive areas. FAA Order 5050.4B, National Environmental Policy Act [NEPA] Implementing Instructions for Airport Projects has detailed information on these and other environmental requirements that the sponsor must meet to assess the proposed project's environmental effects. Engineers and other reviewers should follow the instructions it contains. To expedite this process, the airport sponsor should be able to provide to the engineers and other interested parties the locations of these or other areas of environmental concern.

k. Cost Analysis. All data necessary to estimate the cost of establishing a GBAS Ground Facility at each proposed location is collected during the Formal Site Survey. Some of the items that require special attention due to their potential impact upon the cost of site development include: GBAS configuration, soil

12/15/10 6884.1

analysis and bearing capability, trenching, drainage, grading, access roads, utility service, and earth resistivity.

I. Trade-Off Analysis Reporting. The siting engineer will create a trade-off analysis report of each candidate site analyzed during the site survey. This process takes into account all the topics presented in Chapter 3. Paragraph 3 Site Trade-Off Analysis. The siting engineer presents the comparison analysis between a minimum of three prospective GBAS sites / layouts. The siting engineer will provide the results of the siting trade-off analysis in a Final Site Survey Report. The siting engineer shall use all pertinent data and analysis for each prospective site to generate a trade-off analysis between the sites. The siting engineer identifies any requirements that are at a high risk of not being met at the prospective sites. The siting engineer proposes siting mitigation strategies that may improve the performance at any of the prospective sites. The customer will select the site for GBAS Ground Facility installation. Weighting for this process is somewhat subjective and will be mostly based on the predicted system performance/availability and the objectives of the customer. It is recommended that the siting engineer generate a scale based on predicted overall system performance/availability criteria and the customer's desired outcomes for each prospective site. Major factors in order of importance are:

• Security / Airport Operations Area (AOA) locations

• System Availability.

• RRA Multipath Performance.

• VDB coverage / procedures gained.

• Infrastructure Concerns.

• Signal in Space Lead Time.

• Access.

• Cost.

4. Formal Site Survey

After the Initial Site Survey Report is accepted by the customer, the siting engineer will proceed with a Formal Site Survey of the prospective sites. The purpose of the Formal Site Survey is to gather technical data at each prospective site to aid in the trade-off analysis. The Formal Site Survey will consist of VDB and RR antenna location surveys including recording 360 degree horizontal profiles, VDB and RRS data collection, and survey of shelter layout. The Formal Site Survey provides the following data:

4. Formal Site Survey

• Measured Multipath Error Data (for each prospective site)

• LOS Measurements/Estimates (for each prospective site)

• Formal Site Survey Report

12/15/10 6884.1

a. RRA Candidate Site Survey Procedure. The siting engineer will locate and position a RRA at each candidate site identified from the initial site assessment results. Antenna stands are set on these points and setup with GBAS GPS antennas mounted on the stands. The output of each RR is fed to a dedicated data recorder and the recorder is set to record data for a period of at least 24 hours. The data is then analyzed.

(1) Ranging Source Data Collection. The ranging source data collection will include

temporary setup of the GBAS RR/RRA for any RRS site, which has been identified with concerns from the previous steps (for any of the proposed sites). The ranging source data collection will be used to evaluate the pseudorange errors at the prospective sites. It is anticipated that this additional data collection will be required for early GBAS Ground Facility installations. For later installations, the mature RRS math model will be used predominantly while the ranging source data collection will be used to assess pseudorange errors due to scatterers and terrain in difficult siting environments. Twenty-four (24) contiguous hours of ranging source data will be collected for each site to be analyzed. The data will be analyzed for the presence of multipath at the site using a code-minus-carrier technique. The horizon profile will be established based upon the elevation that ranging sources were acquired and lost during the data collection period. The statistical confidence of the data collected during this step will be quantified based on the number of measurements taken in each elevation bin.

(2) Recommended Equipment. The following equipment is typically required to perform

Ranging Source Data Collection. The specific equipment will be identified by the siting engineer.

(a) Reference Receiver Data Collection

1 DGPS receiver, same design as the GBAS RRS

2 GPS antenna, same design as GBAS GPS antennas

3 Dedicated data recorder

3 Dedicated data recorder

4 Power supply for the DGPS receivers and data recorder

5 Antenna stand

6 Dual-frequency GPS receiver and antenna (used for Iono data collection, removal) i.e. total station with ranging

(b) Additional Survey Equipment

I Portable generator if local power is not available. If a portable generator is used, the fuel tank should be sufficiently large to run the generator 30 hours without stopping.

5 Antenna stand

12/15/10 6884.1

2 Hand and power tool (i.e. Cordless Drill/Screwdriver) as required.

b. RRA Precise Horizon Profile. The RRA site survey consists of the precise horizon profile described in d(l)Precise Horizon Profile The precise horizon profile will be used as an input to the availability and RRS math models. Further details regarding the availability analysis and RRS math models are contained in Appendix C Data ANALYSIS and MATH MODELING.

c. RRA Interference Data Collection. The RRA interference data analysis will be done on the same data collected for the ranging source performance above. The signal-to-noise of the measurements will be reviewed to ensure signal blockages or attenuations are minimized, and reviewed for the presence or absence of interference. It should be determined that the selected RRA site is free from interference to the GPS signal. A spectrum analyzer with either automated data collection or an operator will be required. To characterize the RF environment, an RRA should be located at the proposed site on a temporary support and data collected. The test RF components should consist of the antenna, bandpass filter, and preamp that will be used at the selected site. It is important to use the same components that will be installed at the site for this test. The antenna pattern and/or pre-amp design may contribute to interference susceptibility at a particular location. The output from the preamp should be input to a spectrum analyzer with suitable attenuation. Set up the spectrum analyzer to look at the GPS center frequency (15 75.42 Megahertz (MHz)) and + / -10 MHz. The frequency should be monitored for at least 24 hours to ensure that there are no intermittent interference sources.

d. RRA Location Survey Precision. The antenna position is to be determined for each prospective antenna site considered for the site survey. The survey accuracy is defined in the Commercial Instruction Book. The survey coordinates will be used to identify prospective antenna sites, as an input to the GBAS models, and by the installation team to identify selected site locations.

Note: The antenna location survey refers to both the horizontal and vertical survey required for antenna locations during formal site survey. Precise survey positions for the GBAS antennas are determined after installation.

(1) Precise Horizon Profile. A precise horizon profile is generated for each prospective

antenna site using precise survey equipment. The precise horizon profile includes distance measuring to objects that are within visual range of the candidate antenna sites. The recording instrument should be set up at the candidate antenna phase center location. Readings should be recorded for any object that is greater than 2 ° (objects below 2 ° are assumed to be insignificant unless present in the LOCA) in elevation relative to the recording instrument. In addition, these objects should be identified by name and salient characteristics (e.g., materials, roof pitch). The recording of the azimuth and vertical angles should be taken to the nearest minute. The horizon profile will be used as an input to the

12/15/10 6884.1

GBAS math models (refer to Appendix C Data ANALYSIS and MATH MODELING for further details on math modeling).

5. VDB Interference Data Collection.

The VDB equipment can be a source of RF interference to other systems. The siting engineer must consider the electromagnetic impact of the siting of the VDB antenna on other systems when considering a potential site. Controlled tests are conducted to determine if there is any interference from the VDB to other airport systems, especially those systems that are close to or within the equipment manufacturer's -developed separation distance criteria for that system. The tests include interference testing with ATC communications, and airport NAVAIDs. The tests are conducted with the VDB antenna installed temporarily at the proposed location and height. The VDB test setup includes the same type equipment (i.e., same part number) that will be installed at the site. In addition, the power budget variables (e.g., RF cable loss, transmitter output power) should be the same as the proposed installation. The siting engineer should provide the VDB Interference Test methodology. The test description includes the test setup, data collection, and test duration. For the installation of a non-Federal system the frequency assignment must be obtained from the Federal Communications Commission (FCC) prior to testing. For the installation of a Federal system the frequency assignment must be obtained from the local FAA Spectrum Engineering Office.

6. Equipment Shelter Site Survey

6. Equipment Shelter Site Survey

The location of the equipment shelter will be surveyed. If the location of the shelter violates the GBAS equipment siting criteria (i.e., LOCA), an analysis will be performed to ensure the site meets GBAS performance requirements.

7. Formal Site Survey Report

7. Formal Site Survey Report

The formal site survey report provides an evaluation of each of the candidate sites recommended GBAS site. The site survey report, as a minimum, should include the review of the following items:

(a) VHF Data Broadcast (VDB) Antenna

• VDB coverage (far field): Within 3 nautical miles of decision height for each approach Runway end.

12/15/10/10

• Coverage (near field):

• Line of Sight along approach path, Final Approach Fix (FAF) or 6 nautical miles.

• Phase center Height Range: 5 to 45 feet (above Ground Plane).

• Signal quality - VDB height in the optimal range.

• Signal quality Object Free Area.

• System separation - VDB is located a minimum of 656 feet (200 meters) from any existing systems).

(b) Reference Receiver (RR) Antenna

• Antenna separation.

• Antenna geometry (Common reflector mitigation).

• RF Interference (Are the GPS Antennas close to other transmitting antennas at or near the airport, take into account the frequency and power along with distance.

• Height at optimal range to (to reduce ground common multipath)

• Local Object Consideration Area (LOCA), Area extends 508 feet (155 meter) radius at the 3° slope

(c) Primary Equipment Shelter

• Proximity of VDB antenna and Reference Receiver antennas to the primary shelter.

• Security.

• Environmental impacts, results of the environmental survey.

• Siting outside of safety/obstruction surface region (Part 77 surfaces).

• Access to the site from existing infrastructure.

• Access to primary power.

• Access to communication lines.

• Access to the VDB antenna.

• Access to the reference receiver antennas.

3-13

12/15/10 6884.1

Chapter 4 General Considerations for Siting

Chapter 4 General Considerations for Siting

1. Analysis of Operational Requirements.

The Analysis of Operational Requirements must be performed to ensure that the operational needs of the airport are considered in the siting evaluation. These requirements include the runways in which Category I (CAT I) coverage is required.

2. Antenna Phase Center Height (PCH) Considerations.

The antenna should be installed at the manufacturer's specified height above local ground, wherever possible, to provide the required coverage volume. Trade-offs between coverage and multipath that can cause nulls in the pattern should be considered when using antenna heights outside of the manufacturer's suggested height range. Several RRA types may be available for installation. All of these antennas have vertical pattern shaping that favor reception above the horizon while suppressing ground reflections from flat terrain. The amount of the vertical pattern shaping varies with antenna type. The antenna performance characteristics relevant to determining antenna PCH requirements are:

• The slope of the vertical pattern about the horizon

• The vertical pattern side lobe levels below the horizon.

In general, determining a suitable PCH height involves making a careful trade-off between the following opposing requirements. The phase center must be high enough to prevent unacceptable RF coupling to the ground, which may inadvertently degrade antenna performance. The range (minimum to maximum height) of the PCH is specified in the Commercial Instruction Book (CIB).In addition, the height should allow for snow accumulation where applicable, as well as reasonable margin for vegetation grown in between scheduled mowing. Increased PCH generally provides better protection against multipath from transient vehicles. For antennas that provide both significant vertical pattern shaping at the horizon and substantial sidelobe suppression, limiting the PCH to control the error due to multipath from ground reflections is not a consideration. Such antennas provide the greatest flexibility in siting and are generally the best option for building top installations. However, additional structural precautions may be required to ensure the physical stability of the installation as the PCH is increased. The installation manual for the particular antennas to be installed should be consulted to determine PCH limitations. In extreme cases, installation-specific analysis may be required.

3. Power Considerations.

Proximity of power should be considered when making the GBAS Ground Facility siting decision. The impact of proximity to power on the siting decision is primarily a cost impact. The cost of

12/15/10 6884.1

obtaining power at a prospective location from a prospective power source must be weighed against other siting considerations when conducting the trade-off analysis between prospective GBAS Ground Facility sites. The power at the site shall be in accordance with the GBAS power requirements as specified by the equipment manufacturer, FAA Order 6950.2 Electrical Power Policy Implementation at National Airspace System Facilities, local and state requirements.

4. Cable Run Considerations

4. Cable Run Considerations

Trenching and maximum cable length requirements should be considered when making the GBAS Ground Facility siting decision

a. Trenching Considerations. The impact of trenching on the siting decision is primarily a cost impact. The cost of cable trenching should be weighed against other siting considerations when conducting the trade-off analysis between prospective GBAS Ground Facility sites.

b. Maximum Cable Length Considerations. Maximum cable lengths will be determined as part of the system design process for all GBAS Ground Facility configuration options. The maximum cable length will be dictated by the maximum acceptable signal loss and is dependent on the type of cable and the nature of the transmitted information (i.e., digital or RF). The details are included in the Commercial Instruction Book (CIB) for the GBAS Ground Facility. Consideration is given to both radio frequency (RF) and data cables. Data cables are typically copper cable and will be used to connect RR's to the GBAS Ground Facility equipment. The maximum cable lengths may impose restrictions on the prospective locations for any equipment connected to the cables. This may include the RR's, RRA's, VDB antennas and the ATSU.

5. Site Access Considerations.

Proximity of site access roads should be considered when making the GBAS Ground Facility siting decision. The impact of proximity to site access roads on the siting decision is primarily a cost impact. The cost of building new access roads at a prospective location must be weighed against other siting considerations when conducting the trade-off analysis between prospective GBAS Ground Facility GBAS Ground Facility sites. Access to the GBAS Ground Facility equipment may require site access roads. The access to roads, driveways and parking area will be designed in accordance with FAA standards.

12/15/10 6884.

6. Equipment Siting Considerations

6. Equipment Siting Considerations

The GBAS equipment is not fixed by function; this provides flexibility in locating the GBAS components. A list of equipment siting considerations has been established to guide the siting engineer in choosing potential sites. GBAS equipment should be sited such that:

• The equipment is located on airport property, preferably within the Airport Operations Area (AOA). Equipment locations that are not under airport control will require a deviation or waiver to the GBAS siting requirement. • Adequate VDB coverage is provided so that no restrictions are required for the primary CAT I approach. • Adequate reception of GPS / SB AS ranging sources is provided for sufficient availability. • There are no objects in the GBAS Local Object Consideration Areas and no potential for transient scatterers in the GBAS Critical Areas. • There are no penetrations of airport obstruction surfaces. Any penetrations of the airport obstruction surfaces will require a deviation or waiver (for example OFZ, OFA and RSA) • Installation issues are considered (e.g., proximity of power, site accessibility). • Environmental Issues are considered.

7. Equipment Environment and Maintenance Considerations

7. Equipment Environment and Maintenance Considerations

Equipment environmental considerations (Heating Ventilation, Air Conditioning (HVAC), etc.) should be reviewed when the proposed equipment site is other than the standard GBAS Ground Facility equipment shelter. The impact of equipment environmental considerations on the siting decision is primarily a cost impact. Prospective non-standard GBAS Ground Facility equipment sites may be unsuitable or may require modifications to meet the equipment environmental and maintenance requirements. The GBAS Ground Facility will be housed in an environmentally controlled building/structure that is compliant with current OSHA requirements. The building/structure must have as a minimum, sufficient room for routine maintenance and repair to be performed within the required time period.

8. Real Estate Assessment

8. Real Estate Assessment

The site selection process will involve the study of maps, charts and other data delineated in Chapter 3, Paragraph 2, Site Inspection. These studies will start with the identification of areas that can support the physical footprint, including consideration of the LOCA and critical area criteria, of the GBAS equipment. The RRA centroid for each candidate RRA configuration to DH distance for all of the primary runway ends will also be estimated. Information on the object consideration areas is given in Chapter 5, Paragraph 1 GBAS Ground Facility Equipment Local Object Consideration Areas

12/15/10 6884.1

(LOCA's). Other information such as the required coverage volume and location of significant obstructions (e.g., hangars, terminals, access roads) will also assist in defining eligible siting locations for the GBAS Ground Facility. This process will assist in defining potential siting areas in preparation for an initial site inspection.

12/15/10 JO 6884.1

Chapter 5 System Sitting Criteria

Chapter 5 System Sitting Criteria

1. GBAS Ground Facility Equipment Local Object Consideration Areas (LOCA's).

a. Description. The GBAS Ground Facility Equipment Local Object Consideration Area (LOCA) is a clearance volume near the GBAS Ground Facility Reference Receiver Antennas (RRA's) Figure 5-1, RRA LOCA and Figure 5-2, VDB Safety and LOCA, shows the safety area and LOCA for the GBAS VDB antenna. Antenna(s) should be free from stationary objects (e.g., trees, equipment shelters) to ensure GBAS accuracy, integrity, and continuity. There are two separate LOCA's; one for the RRA's and one for the VDB antenna(s). Although the presence of fixed structures within the GBAS Ground Facility LOCA should be avoided where possible, the impact of fixed structures on GBAS Ground Facility accuracy, integrity, and continuity should be analyzed through data analysis, or math modeling, or both.

b. LOCA Penetration. Although it is desirable to completely restrict the surface traffic from all critical areas, this is generally not feasible since access to and from the runway, terminal areas, ramp, and hangar areas may necessitate traffic movement through these regions. The restrictions must therefore be sufficiently permissive, as delineated in the following subparagraphs, to permit this traffic flow under controlled conditions.

>

Objects beyond 155m, @ greater than 3 degrees elevation (on the LOCA Horizon) should also be masked

o

Masked Objects Area

Interior RRA LOCA

RRA Distortion Protection Area - No

Objects, Vegetation

and Transients

Restricted

Masked Objects Area

' Selective masking of

objects Coordinated

transients

Infrequent transients - .below antenna base

permissible-...

Selective Masking of

objects Infrequent

transients OK

Transients below antenna

base permissible Infrequent persistent

transients OR""--.

4 meters

Drawing Not

To Scale 155 meters

OS 0 0 0 0

12/15/10 6884.1

Figure 5-2 VDB Safety Area and LOCA

(1) On Airport Surface Traffic. All on airport surface traffic shall remain clear of RRA interior

LOCA (Figure 5-1, RRA LOCA). On airport surface traffic may pass through the RRA intermediate LOCA and the VDB LOCA (Figure 5-2, VDB Safety Area and LOCA) whenever the equipment is in operation. Parking of unattended vehicles or aircraft within these areas shall be prohibited at all times, except for maintenance technician vehicles, which may be parked adjacent to the equipment shelter.

(2) Off Airport Non-Aviation Traffic. Off airport Non-aviation traffic shall not pass through

the RRA interior intermediate and outer LOCA (Figure 5-1, RRA LOCA)) and VDB LOCA Figure 5-2, VDB Safety Area and LOCA) as unacceptable degradation is expected from traffic movement along these routes (e.g., on roads, highways, railroad tracks, etc.). In the event where LOCA intersection with non-aviation traffic routes is unavoidable, effective measures shall be taken to overcome the condition. Such measures may include masking (refer to Chapter 5, Paragrph l.c (1) Selective Masking). If selective masking cannot be fully implemented then, alternate measures should be considered, such as math

12/15/10 6884.1

modeling and / or field testing (to determine the magnitude of the degradation), controlling traffic along the route, elevation or relocation of the antenna array.

(3) Aircraft Over Flight and Over Head Movement. Areas where aircraft will be frequently

flying overhead, especially nearby overhead, should be avoided. While occasional overflights can be tolerated by the system, frequent traffic, such as high volume rush hours, may result in reduced availability of the GBAS system due to disruption of satellite signal reception at the reference receivers. Attempt should be made to avoid siting an RRA so the LOCA intersects the region anywhere between a touchdown, threshold, or decision height point or other frequent overhead movement areas/objects (i.e. cranes, monorails, gondolas, helicopters).

(4) Maintenance Vehicles. Maintenance vehicles may pass through the RRA intermediate and

outer LOCA and VDB LOCA, along access roads when traveling to and from the equipment shelter, provided they do not stop and the route does not pass in the RRA interior LOCA. Refer to Figure 5-1 RRA LOCA. The airport authority should provide proper signage along access roads to indicate that maintenance vehicles should not stop. There are no access roads in the RRA interior LOCA and the area is fenced / marked.

(5) Critical Jet Blast Areas. In addition to safeguarding the GBAS Ground Facility information

from surface traffic interference, the system must be protected from long term deterioration resulting from accumulation of jet engine exhaust residue. Therefore, jet aircraft must not be permitted to operate with its jet exhaust directed toward the facility, within 600 feet (183 meters) of the GBAS Ground Facility equipment shelter and antennas.

c. Evaluation of Permanent Objects. The detrimental effects of permanent objects planned for placement in the RRA intermediate and outer LOCA and VDB LOCA should be analyzed and/or mathematically modeled prior to construction. If this is not possible prior to construction, a confirming flight inspection must be conducted to determine the effects, if any, on the GBAS subsystems. Note that placing an object outside the LOCA does not guarantee non-interference with the GBAS signal in space. Significant objects beyond the LOCA that penetrate 3 degrees elevation (i.e. Air Traffic Control (ATC) tower, Airport Surveillance Radars (ASR's), etc.) shall also be masked. These objects and obstructions will be first recorded during the precise horizon profile. Momentary blockages of a Space Vehicle (SV) behind permanent un-masked structures can be misevaluated as a failing SV, and the GBAS system may eliminate that SV for suspect behavior.

(1) Selective Masking. The GBAS has the capability to mask off the areas the reference

receiver includes in the calculations for differential correction. Refer to the equipment manufacturer's instructions on the proper procedure for excluding an object in the

12/15/10 6884.1

reference receiver's antenna reception area. This will allow the placement of an antenna in an area that is in the vicinity of an obstruction. The need for the masking must be weighed against the reduced availability of the receiver by masking too large an area.

2. Reference Receiver Siting

2. Reference Receiver Siting

a. RRA Siting Environment Evaluation (Multipath/Shadowing).Objects in the airport environment can produce multipath and shadowing, and these objects are commonly referred to as scatterers. For the purpose of this discussion, there are two main classes of scatterers: permanent and transient. A permanent scatterer refers to fixed objects whose signal reflections and/or blockage can cause multipath and/or shadowing at the RRA locations. Examples of permanent scatterers are aircraft hangars, equipment shelters, and sloping terrain. LOCA criteria are used to establish an area about the RRA, which forms the basis for the evaluation of multipath from permanent scatterers. A transient scatterer refers to an object, which is in the LOCA for a short period of time but whose signal reflections and/or blockage can cause multipath and/or shadowing at the RRA locations. Examples of transient scatterers are an airborne aircraft, moving service vehicles, taxiing aircraft, parked/holding aircraft, and parked vehicles. Critical areas are established to limit the movement of transient scatterers during CAT I operations. These critical areas are developed based on the LOCA.

b. RRA LOCA. The LOCA's are defined volumes about the RRA's within which stationary objects have a high potential to cause unacceptable degradation of system performance. Objects located within the RRA LOCA can cause either blockage of the GPS satellite signals resulting in the potential for the RR to lose lock, or reflection/diffraction of the GPS satellite signals resulting in an inability to generate sufficiently accurate range corrections. All areas of the RRA LOCA are important and should be carefully evaluated when choosing a prospective RRA site. Ideally, a clear area of 508 feet (155 meters) is desired around each RRA site. At those airports where this is not possible, some areas within the LOCA offer limited flexibility given the understood behaviors of DGPS grade antennas. The following text describes these areas; see Figure 5-1. RRA LOCA for a pictorial of the RRA LOCA.

(1) Interior RRA LOCA. The Interior RRA LOCA is a cylinder about the antenna (from the

ground up), with a radius equivalent to the maximum RRA Phase Center height 13 feet (4 meters). The area immediately around the RRA is the RRA's near-field and must be protected from distortion. No stationary objects or transients (i.e. objects moving through) are allowed. Movement and unmitigated vegetation is restricted in the Interior LOCA, and it is desirable to utilize a non-metallic perimeter barrier or markings to protect the interior LOCA. Any perimeter protection method shall be lower than the antenna's base.

(2) Intermediate RRA LOCA. The Intermediate RRA LOCA is also a cylinder with a cone at

the top centered about the antenna base with an angle of 3 degrees. The base of the cylinder (at ground level) has a radius of 164 feet (50 meters). The Intermediate RRA LOCA From 13 feet to 164 feet (4 meters to 50 meters) out laterally. Ideally, the Intermediate LOCA should be object free. Coordinated transient objects only may

12/15/10 6884.1

penetrate the Intermediate RRA LOCA above the base antenna height. Siting minimizes inclusion of roads, taxiways and other transient venues. Nothing may be allowed to persist in this area. Selective RRA reception masking can be utilized if an object must exist or is expected to wander into predicted sections of this area. Transients below the base of the antenna can be tolerated for short durations.

(3) Outer RRA LOCA. The Outer RRA LOCA is also a cylinder with a cone at the top

centered about the antenna base with an angle of 3 degrees. The base of the cylinder (at ground level) has a radius of 508 feet (155 meters). From 164 feet to 508 feet (50 meters to

155 meters) out laterally is the Outer RRA LOCA. Infrequent parked transients below the antenna base height are permissible. Any permanent objects and areas where transient object movement would be known to occur must be selectively masked.

(4) RRA LOCA Horizon. The RRA LOCA Horizon refers to the region beyond 508 feet (155

meters) above 3 degrees. Significant objects that penetrate 3 degrees elevation should be selectively masked.

(5) RRA Placement Considerations. A standard GBAS Ground Facility configuration includes

4 RRA's. The relative placement / separation criteria of the RRA's must be considered in the siting. These criteria are derived from commonly understood GPS / DGPS existing equipment and system behaviors. Each antenna shall be separated from any adjacent antenna by a minimum of 328 feet (100 meters), 508 feet (155 meters) is desirable for installations that must be collocated. Much longer baselines are permissible, provided other system requirements are not violated (i.e. RRA Centroid to DH Distance). The RRA's shall be placed to exclude collinear placement of the RRA's (applies to 3 or more). For flat installation areas (rooftops, tarmac areas within the LOCA(s), etc.) that vary less than % wavelength (k) of LI 1.87 inches (4.75 centimeters (cm)), the Phase Center (PC) heights shall not be placed so any are equal in height, or vary by 7.48 inches (19 cm) increments (IX) in height. Ellipsoid heights shall be used for confirmation. Flat installation area PC heights ideally should be staggered in !4 X increments (without violating previous text).

Phase center heights above immediate local terrain shall be limited to a height specified by the equipment manufacturer. For the Honeywell SLS-4000 system see Appendix D, Appendix D HONEYWELL SLS-4000 SPECIFIC PARAMETERS. In order to mitigate the chance of 2 RRA's experiencing common multipath errors, no 2 RRA's shall be sited parallel to or equidistant from, common large multipath sources or transient venues. Common sources include: runways, building edges, metallic fences, roads, taxiways, concrete barriers, jet blast diverters, equipment and shelters, water canals, highways and railings. A constrained GBAS siting example, with above criteria included, is shown figure 5-3, GBNAS Contrained Siting Examples.

< l

3 era' s n <M i

«

n o

n a. in s ore

V^

to

o

O N OO OO

O N OO OO

12/15/10 6884.1

c. RRA Physical Antenna Installation Considerations (Interior RRA LOCA). The candidate sites for installing the RRA antennas should be chosen with the following considerations for the interior LOCA region:

(1) Provide an area around the RRA with minimum radius of 13 feet (4 meters)

(2) A fence or non-metallic barrier/ marking may be placed around the antenna to mark the

area.

(3) The ground in the enclosed area should be prepared to eliminate the growth of vegetation.

(4) Ground reflections are dictated by the material at the base of the interior LOCA. If the

material below the antenna is highly reflective properly graded gravel may be used to disperse the reflected undesired signals. Other appropriate materials may be substituted for gravel.

(5) The ground in the enclosed area should be prepared to eliminate standing water and

provide the proper drainage away from the foundation of the antenna pedestal. Properly graded gravel can be used to satisfy this requirement.

(6) Any lease or installation agreements should contain provisions to control vegetation

growth.

(7) Growth of crops of any type must not be permitted.

(8) Piling snow in the Interior area LOCA should not be allowed.

12/15/10 6884.1

d. Maintenance of the LOCA (Intermediate and Outer LOCA). Monitors within the system will detect outof tolerance RRA Multi-path performance in all cases and will protect the user if maintenance activates degrade the system performance. The RAA LOCA diagram Figure 5-1 RRA LOCA provides guidance on allowable transgressions of the LOCA. If the planned maintenance activities are expected to degrade system performance to unacceptable levels, the system should be NOTAM'ed out of service. The candidate sites for installing the RRA antennas should be chosen with the following considerations for the intermediate and outer LOCA regions:

(1) Vegetation should not be permitted to exceed 3.3 feet (1 meter) in height in an area with a

radius of 20 feet (6.1 meters) around the RRA's.

(2) Snow depth below the RRA is not an issue for single reflection Multi-Path. The RRA

should be installed so that naturally-accumulated snow does not cover any part of the RRA (the maximum RRA height restrictions should not be violated, the RRA mast is excluded). If snow accumulation overcomes the RRA, then it must be removed. Vegetation has a different impact (diffuse Multi-Path) and is therefore limited to 1 meter.

(3) Action must be initiated when observed vegetation growth exceeds 3.3 feet (1 meter).

(4) A fence using non-metallic material may be placed around the antenna to mark this area.

(5) Mowing operations should be coordinated for a time to coincide with scheduled facility

maintenance.

(6) Should plowing operations be required, this should be coordinated for a time to coincide

with scheduled facility maintenance.

(7) Piling snow in the Intermediate area LOCA should not be allowed.

(8) Piling snow in the Outer area LOCA is acceptable with the conditions: Refer to Figure 5-1

RRA LOCA.

(9) The movement of the equipment is limited to infrequent persistent transients (parking

equipment or allowing the equipment to remain stationary for long periods is not permitted)

(10) Total height of the of the naturally accumulated snow and piled snow is not higher than

the antenna base

12/15/10 6884.1

e. RRA LOCA's, Selective Masking vs. Critical Areas. Critical areas, as defined in ILS terms (for example - hold short lines), are not normally required for GBAS installations. However, there may be situations due to constrained siting where "critical areas" may be necessary. RRA LOCA's are defined as volumes about the RRA's within which transient objects have a high potential to cause unacceptable degradation of system performance. The criteria for defining the Critical areas is to provide zoning requirements intended to protect the RRA from multipath and shadowing caused by transient scatterers. Protection from transient scatterers requires that the appropriate critical area be defined for each RRA location. These critical areas will be based on the RRA LOCA criteria and will differ from airport to airport. The LOCA criteria are determined by those airport surface movement areas where an object of specified size penetrates a surface of the LOCA. These areas will either need to be selectively masked (preferred method), or be designated as a critical area (not preferred).

The LOCA area criteria consider a stationary worst-case user with respect to size in the airport surface movement areas. The airport surface movement areas include runways, taxiways, and roadways. In addition to surface movement areas, areas where hovering rotorcraft are present should be considered. It will be conservatively assumed that any aircraft or vehicle passing near the LOCA is causing the worst-case response at the reference antenna. This implies that there would be no filtering of multipath variation due to vehicle motion and that the penetrated area would effectively be the intersection of the RRA LOCA with all surface movement areas. Extensive modeling, of known aircraft speeds and geometries may help reduce this requirement in the future. Selective masking is also a well understood method that could preclude measurements ever being taken from a LOCA penetration or multipath object (transient or stationary).

The physical dimensions of vehicles on the airport surface must be taken into account when determining critical areas, see Figure A-l Guidance for Determining RRA Selective Masking or Critical Areas at the Intersection of the LOCA and Movement Area

12/15/10 6884.1

LOCA penetrated by tailfin RRA LOCA

Selective RRA AZ/EL

Masking (preferred),

or Critical Area creation (Not

Preferred) required

Hold lines not necessary in these cases

Figure 5-4 Guidance for Determining RRA Selective Masking or Critical Areas at the Intersection of the LOCA and Movement Area

Parked vehicles or aircraft are prohibited from being in the critical area. At a minimum, the movement of surface traffic through the critical area is controlled, and it may be prohibited entirely, depending on the location of the road/taxiway relative to the RRA locations. Accordingly, the selection of RRA locations should take into consideration the impact of critical area requirements on surface operations. The objective is to find RRA locations that provide an acceptable multipath/shadowing environment and critical areas that do not impact surface operations. Selective masking can be applied to objects that will pass through the critical area. See Chapter 5, Paragraph l.c (1) RRA LOCA's, Selective Maksing vs Critical Areas for additional information. The GBAS performance can be adversely affected by the presence of strong multipath / shadowing at one or more RRA locations. The presence of strong multipath at any given RRA location can cause the RR to lose track of a satellite or degrade the ranging accuracy of the RR. The presence of shadowing sources at any given RRA location can cause the RR to lose track of the satellite. The selection of the appropriate

12/15/10 6884.1

RRA siting is essential to avoid unacceptable multipath signal levels and shadowing at the RRA location, as well as errors due to correlated multipath at two or more RRA locations. In general, the satellite-RRA-scatterer geometry, as well as the scatterer size, orientation, and composition are all factors that influence the magnitude, duration, and scalloping characteristics of the multipath error. However, certain satellite-RRA-scatterer geometries are not capable of generating detectable multipath error levels regardless of scatterer size, orientation, and composition. These geometries form the basis for the RRA LOCA criteria used for evaluation the of multipath environment around the RRA location. The siting engineer provides the methodology for defining the RRA selective masking or Critical Areas. The siting engineer provides simulation results, analysis, and test data to demonstrate that the siting engineer defined Critical Areas that are consistent with and traceable to the equipment manufacturer's continuity and integrity allocations and inflation factors

f. RRA Multipath

Multipath is the phenomena whereby signals arrive at the receiver via different paths due to reflections and diffraction. It is the characteristics of these reflected / diffracted signals, relative to the direct signal, that determines the characteristics of the multipath incident at the receiver. A DGPS system, such as the GBAS, corrects for pseudorange errors that are common between the reference station and the user platform. Any residual errors that are not common between the reference station and user platform that are not eliminated by the GBAS Ground Facility using other techniques will result in errors in the aircraft position solution. Multipath is not common between the two stations and therefore cannot be corrected for using differential techniques. The GBAS Ground Facility relies on the design of the RR's, RRA's, and siting to mitigate unacceptable multipath effects. Multipath is generally accepted to be the largest pseudorange correction error source. The minimization of RRA multipath is a primary goal of RRA siting. RRA multipath can be classified as either ground multipath or non-ground multipath.

(1) RRA Ground Multipath. RRA Ground multipath is defined as multipath that is incident at

negative elevation angles relative to the RRA phase center. Ground multipath is typically caused by the local terrain (e.g., ground, surface water, or rooftop). The impact of the ground multipath on the pseudorange measurement will depend on the reflective medium's dielectric properties and the RRA pattern. Figure 5-5 Ground and Non-Ground Multipath, shows an example of a simplified ground reflection multipath. Ground multipath can cause significant low frequency pseudorange errors that are difficult to mitigate through siting and / or signal processing. The most effective mitigation technique is to employ an RRA design that attenuates the ground multipath signal relative to the direct signal. The siting engineer will make decisions for mitigating ground multipath based on the type of RRA. The engineer can mitigate ground multipath by choosing the optimum phase center height for the particular antenna and by avoiding sites in proximity to mediums with high reflection coefficients (e.g., bodies of water) where possible.

(2) RRA Non-Ground Multipath. RRA Non-ground multipath is defined as multipath that is

incident at positive elevation angles relative to the RRA phase center. Non-ground

12/15/10 6884.1

multipath is typically caused by objects (e.g., equipment shelters, antenna towers) that are within the RRA LOCA, but can also be caused by up-sloping terrain. The impact of these objects on the multipath error seen at the RRA will depend on the objects' reflection coefficients and their relative position to the antenna/satellite line-of-site. Figure 5-5 Ground and Non-Ground Multipath shows an example of a simplified non-ground reflection multipath.

NOTE - All of the signals are from the same Space Vehicle (SV)

Signal path

1 2 3 4

5 6

Description Direct signal from SV to antenna Ground reflection Object Reflection + Ground Reflection Object Edge Reflection / Diffraction + Ground Reflection Object Reflection Object Edge Reflection / Diffraction

6

5 4

Figure 5-5 Ground and Non-Ground Multipath

12/15/10 6884.1

Since non-ground multipath enters the antenna at positive elevation angles, there is usually no inherent attenuation of the reflected signal due to the antenna gain pattern. This makes the elimination of sources of non-ground multipath a primary goal in the siting of RRA's.

The siting engineer will make decisions for mitigating non-ground multipath based on the LOCA for the RRA. The engineer should also study the local topography to evaluate the potential for nonground multipath caused by up-sloping terrain.

g. RRA Shadowing. Shadowing is defined as the blockage of either the reception or transmission of signals. Terrain and objects in the local environment may cause signal shadowing. The shadowing of the GPS SPS signal-in-space within the GBAS reception mask may cause a degradation of system availability. Permanent scatterers such as terrain, trees, and man-made structures and transient scatterers such as aircraft and vehicles typically cause RRA shadowing. An availability analysis should be performed to determine the extent of the availability degradation caused by permanent scatterers. Controlling surface movement in the critical areas during CAT I operations can be used to preserve the GBAS availability in the presence of transient scatterers. The siting engineer will use the GBAS RRS model and/or horizon profiles to determine the presence and sources of shadowing of the GPS constellation. Mitigation techniques include increasing antenna height or removal of the shadowing source. The incorporation of additional RRA's may also reduce the impact of shadowing on system availability.

3. VDB Antenna Siting

3. VDB Antenna Siting

a. VDB Antenna Siting Environment Evaluation. The VDB Antenna siting environment evaluation is similar to the RRA siting environment evaluation described in Chapter 5, Paragraph2.a RRA Siting Environment Evaluation. The VDB site should also be evaluated with respect to permanent and transient scatterers. There are corresponding VDB Antenna LOCA criteria and VDB Antenna critical areas, which must be defined analogous to the RRA case. The primary difference is the impact that objects within these areas have on the GBAS performance. In the VDB Antenna siting evaluation, the impact is primarily on the VDB coverage volume.

b. Safety Area. Safety area is defined as the area around the VDB antenna that indicates an area that personnel should not enter. This area is to protect personnel from the VDB antenna emissions. See Figure 5-2 VDB Safety Area and LOCA.

c. VDB Antenna Installation Considerations. During GBAS precision approach operations, parked vehicles or aircraft are prohibited from being in the critical area. At a minimum, the movement of surface traffic through the critical area is controlled, and it may be prohibited entirely depending on the location of the road/taxiway relative to the VDB antenna locations. Accordingly, the selection of VDB antenna locations takes into consideration the impact of critical area requirements on surface operations. The objective is to find VDB antenna locations that provide an acceptable multipath/shadowing environment and critical areas that do not impact surface operations. The GBAS performance can be adversely affected by the presence of strong multipath and/or shadowing at the VDB antenna location. The presence of strong multipath and/or shadowing sources at the VDB antenna location can cause nulls in the VDB coverage volume. The selection of the appropriate equipment configuration and proper equipment siting are essential in avoiding

12/15/10 6884.1

unacceptable multipath signal levels and shadowing at the VDB antenna location. In general, the VDB antenna-scatterer geometry, as well as the scatterer size, orientation, and composition are all factors that influence the magnitude, duration, and scalloping characteristics of the multipath. These geometries form the basis for the VDB LOCA criteria used for evaluation the multipath environment about the VDB antenna location.

(1) VDB Antenna LOCA. The VDB LOCA's are defined volumes about the VDB antenna(s)

within which stationary objects have a high potential to cause unacceptable degradation of

system performance. Objects located within the VDB Antenna LOCA may either block the VDB signal or generate reflections that cause nulls in the VDB signal in operationally significant regions of its coverage volume. The siting engineer provides the dimensions of the VDB Antenna LOCA. The siting engineer shall provide simulation results, analysis, and test data to demonstrate that the defined LOCA's are consistent with, and traceable to the equipment manufacturer's continuity allocations.

(2) VDB Antenna Phase Height Considerations. The VDB Antenna Phase Center Height

(PCH) shall be chosen to ensure at least the minimum field strength is met in the operational coverage volumes. The selection of the antenna phase center height may involve trade-offs between coverage to the approach and coverage on the surface. The siting engineer shall provide an optimum VDB antenna PCH range. The siting engineer performs a sensitivity analysis to determine the effect of PCH height on approach coverage and surface coverage. The siting engineer shall provide simulation results, analysis, and test data to validate the height range and the trade-off analysis. Figure 5-2, VDB Safely Area and LOCA shows the safety area and LOCA for the GBAS VDB antenna.

(3) VDB Critical Area Dimensions. VDB Antenna Critical Areas are defined volumes about

the VDB antenna(s) within which transient objects have a high potential to cause unacceptable degradation of system performance. These areas should be protected from the unlimited movement of surface and air traffic to ensure GBAS Ground Facility continuity. The critical area criteria are determined by those airport surface movement areas where an object of specified size penetrates a surface of the LOCA. The critical area criteria shall consider a stationary worst-case user with respect to size, in the airport surface movement areas. The airport surface movement areas include runways, taxiways, and any roadways. In addition to surface movement areas, areas where hovering rotorcraft are present shall be considered. The siting engineer uses the system manufacturer's information (as defined in the Commercial Instruction Book (CIB)) in establishing the methodology for defining the VDB Antenna Safety and Critical Areas. The siting engineer provides simulation results, analysis, and test data to demonstrate that the critical areas are consistent with, and traceable to the equipment manufacturer's continuity allocations.

12/15/10 6884.1

(4) VDB Physical Antenna Installation Consideration Considerations. The candidate sites for

installing the VDB antennas should be chosen with the following considerations:

Provide a safety area around the VDB antenna as specified by the equipment manufacturer. For the Honeywell SLS-4000 system refer to Appendix D Appendix D HONEYWELL SLS- 4000 SPECIFIC PARAMETERS A fence or non-reflective barrier/ marking may be placed around the antenna to mark the area. The ground in the enclosed area should be prepared to eliminate the growth of vegetation. The ground in the enclosed area should be prepared to eliminate standing water and provide the proper drainage away from the foundation of the antenna pedestal. Properly graded gravel can be used to satisfy this requirement. Any lease or installation agreements should contain provisions to control vegetation growth. Growth of crops of any type must not be permitted. Airport management shall provide proper signage indicating that personnel should not enter the area when the GBAS is in operation.

(5) Maintenance of the VDB LOCA. The following maintenance actions should be performed

for the VDB antenna (s) installed as part of the LGF facility: Monitors within the system will detect out-of tolerance GBAS operation. If the planned maintenance activities are expected to degrade system performance to unacceptable levels, the system should be NOTAM'ed out of service. Vegetation should not be permitted to exceed 3.3 feet (1 meter)

in height in an area with a radius of 6 meters around the VDB antenna. Action must be initiated when observed vegetation growth exceeds 3.3 feet (1 meter). A fence using nonreflective material may be placed around the antenna to mark this area. Mowing operations should be coordinated for a time to coincide with scheduled facility maintenance.

d. VDB Antenna Site Survey. The VDB antenna site survey shall consist of the precise horizon profile described in Chapter 3, Paragraph 4.a (6), Precise Horizon Profile. The precise horizon profile will be used as an input to the VDB math model, which is a major part of the final VDB antenna site selection process. The site survey flight test will verify the coverage attained at the selected site. It is anticipated that this additional data collection will be required for early GBAS installations. For later installations, the mature VDB math model will be used predominantly while the site survey flight test will be used to assess the coverage volume impact of obstructions and terrain in difficult siting environments.

e. Requirement for an Additional VDB Antenna. There will be one VDB antenna required for typical GBAS installations. It may be determined during the site survey that an additional VDB may need to be installed to meet the coverage requirements at the site. The criteria for selecting the location for the additional VDB antenna shall be the same as that of the primary VDB antenna.

12/15/10 6884.1

f. VDB Field Strength Considerations

(1) Minimum Field Strength. The VDB shall be sited to meet, at a minimum, the minimum

field strength requirements throughout the CAT I Approach Coverage Volume described in Appendix A GBAS PARAMETERS CRITICAL TO ATC OPERATIONS, for each runway end designated for a CAT I approach. If required, the VDB will also be sited to meet the minimum field strength requirements in the CAT I Missed Approach Coverage Volume and the Appendix A GBAS PARAMETERS CRITICAL TO ATC OPERATIONS. The GBAS Ground Facility is designed with an allowance of not meeting the field strength directly above the antenna. This region is defined as a 5° cone, which is an upper bound of the coverage volume. The actual upper bound must be verified during the flight inspection. This cone must be considered when siting the VDB antenna to ensure that it does not impact the required coverage volume. The minimum VDB RF field strength is defined in 3.2.4 VDB RF Field Strength of DO-245A, the Minimum Aviation System Performance Standards for Local Area Augmentation System (LAAS) [MASPS]

Max field strength coverage exclusion area NTE 200 meter radius about VDB antenna by design Actual maximum field strength coverage exclusion area may be less than 200 meters

/NTE 5

^

Mm field strength coverage exclusion area NTE 5 degree cone above VDB antenna by design Actual minimum field strength coverage exclusion area may be less than 5 degrees

10,000 ft

Earth