This advisory circular (AC) contains methods, techniques, and practices acceptable to the Administrator for the inspection and repair of nonpressurized areas of civil aircraft, only when there are no manufacturer repair or maintenance instructions. This data generally pertains to minor repairs. The repairs identified in this AC may only be used as a basis for FAA approval for major repairs. The repair data may also be used as approved data, and the AC chapter, page, and paragraph listed in block 8 of FAA form 337 when: a. the user has determined that it is appropriate to the product being repaired; b. it is directly applicable to the repair being made; and c. it is not contrary to manufacturer’s data.
AC_43.13-1B_CHG_1_Ed_Upd_Chapter_1
U.S. Department of Transportation Federal Aviation Administration
Advisory Circular
Subject: Acceptable Methods, Techniques,
and Practices—Aircraft Inspection and Repair
Date: 9/8/98 AC No: 43.13-1B Initiated by: AFS-300 Change: 1
1. PURPOSE OF THIS ADVISORY CIRCULAR (AC).
a. This AC contains methods, techniques, and practices acceptable to the Federal Aviation Administration (FAA) for performing inspections and minor repairs of nonpressurized areas of civil aircraft unless the repair at issue is recommended against in the applicable manufacturer’s maintenance or repair instructions. The repair data described in this AC may be used as a basis for FAA-approved data for major repairs. The repair data may be used as FAA-approved data for repairs of nonpressurized areas of civil aircraft provided the AC chapter, page, and paragraph are listed in Block 8 of FAA Form 337, Major Repair and Alteration (Airframe, Powerplant, Propeller, or Appliance) and the data are:
(1) Appropriate to the product being repaired;
(2) Directly applicable to the repair being made; and
(3) Not contrary to manufacturer’s data.
b. The contents of this document do not have the force and effect of law and are not meant to bind the public in any way, and the document is intended only to provide information to the public regarding existing requirements under the law or agency policies.
2. AUDIENCE. This AC is intended for use by persons performing maintenance, alteration, or preventive maintenance on aircraft, engines, propellers, or appliances in accordance with Title 14 of the Code of Federal Regulations (14 CFR) part 43.
3. WHERE YOU CAN FIND THIS AC. You can find this AC on the FAA’s website at https://www.faa.gov/regulations_policies/advisory_circulars and the Dynamic Regulatory System (DRS) at https://drs.faa.gov.
4. WHAT THIS AC CANCELS. AC 43.13-1A, Acceptable Methods, Techniques, and Practices—Aircraft Inspection and Repair, dated December 22, 1976, is canceled.
5. REFERENCE. Title 14 CFR part 43, § 43.13(a) states that each person performing maintenance, alteration, or preventive maintenance on an aircraft, engine, propeller, or appliance shall use the methods, techniques, and practices prescribed in the current manufacturer’s maintenance manual or instructions for continued airworthiness (ICA) prepared by its manufacturer, or other methods, techniques, or practices acceptable to the Administrator, except
Page ii
as noted in § 43.16. FAA inspectors are prepared to answer questions that may arise in this regard. Persons engaged in the inspection and repair of civil aircraft should be familiar with 14 CFR Part 43, Maintenance, Preventive Maintenance, Rebuilding, and Alteration, and Part 65, Certification: Airmen Other Than Flight Crewmembers, subparts A, D, and E, and the applicable airworthiness requirements under which the aircraft was type certificated.
6. ACKNOWLEDGMENTS. The FAA would like to thank the following persons and organization for their assistance in producing AC 43.13-1B: Richard Finch, Richard Fischer, Michael Grimes, Ray Stits, William A. Watkins, and the SAE, Aerospace Electronics and Electrical Systems Division. Acknowledgment is also extended to all in the aviation community who commented on the document.
7. AC FEEDBACK FORM. For your convenience, the AC Feedback Form is the last page of this AC. Note any deficiencies found, clarifications needed, or suggested improvements regarding the contents of this AC on the Feedback Form.
Acting Deputy Director, Flight Standards Service
Page iii
CONTENTS Paragraph Page
CHAPTER 1. WOOD STRUCTURE … 1-1
SECTION 1. MATERIALS AND PRACTICES … 1-1
1-1. GENERAL … 1-1 1-2. WOODS … 1-1 1-3. MODIFIED WOOD PRODUCTS … 1-5 1-4. ADHESIVES … 1-5 1-5. BONDING PRECAUTIONS … 1-7 1-6. PREPARATION OF WOOD SURFACES FOR BONDING … 1-7 1-7. APPLYING THE ADHESIVE … 1-8 1-8. ASSEMBLY TIME IN BONDING … 1-8 1-9. BONDING TEMPERATURE … 1-9 1-10. CLAMPING PRESSURE … 1-9 1-11. METHOD OF APPLYING PRESSURE … 1-9 1-12.–1-17. [RESERVED.] … 1-10
SECTION 2. HEALTH AND SAFETY … 1-11
1-18. GENERAL … 1-11 1-19. SANDING IN AREAS OF EXISTING BOND JOINTS AND FINISHES … 1-11 1-20. HANDLING OF ADHESIVES AND FINISHES … 1-11 1-21.–1-26. [RESERVED.] … 1-11
SECTION 3. INSPECTION … 1-12
1-27. GENERAL … 1-12 1-28. TYPES OF DETERIORATION AND DAMAGE … 1-12 1-29. INSPECTION METHODS … 1-12 1-30.–1-35. [RESERVED.] … 1-15
SECTION 4. REPAIRS … 1-16
1-36. GENERAL … 1-16 1-37. REPLACEMENT OF DRAIN HOLES AND SKIN STIFFENERS … 1-16 1-38. CONTROL SURFACE FLUTTER PRECAUTIONS … 1-16 1-39. SCARF JOINTS … 1-16 1-40. SPLICING OF SPARS … 1-17 1-41. SPAR REPLACEMENT … 1-22 1-42. SPLICING OF BOX SPAR WEBS … 1-23 1-43. REPLACING SOLID-TYPE SPARS WITH LAMINATED-TYPE SPARS … 1-23 1-44. SPAR LONGITUDINAL CRACKS AND LOCAL DAMAGE … 1-23 1-45. ELONGATED HOLES IN SPARS … 1-25 1-46. RIB REPAIRS … 1-25 1-47. PLYWOOD SKIN REPAIR … 1-28
Page iv
1-48. DETERMINATION OF SINGLE OR DOUBLE CURVATURE … 1-29 1-49. REPAIRS TO SINGLE CURVATURE PLYWOOD SKIN … 1-29 1-50. REPAIRS TO DOUBLE CURVATURE PLYWOOD SKIN … 1-30 1-51. TYPES OF PATCHES … 1-30 1-52. FABRIC PATCH … 1-38 1-53.–1-63. [RESERVED.] … 1-38
SECTION 5. FINISHING WOOD STRUCTURES … 1-39
1-64. GENERAL … 1-39 1-65. ACCEPTABLE FINISHES … 1-39 1-66. PRECAUTIONS … 1-39 1-67. FINISHING OF INTERIOR SURFACES … 1-40 1-68. FINISHING OF EXTERIOR SURFACES … 1-40 1-69. FINISHING OF END GRAIN SURFACES … 1-40 1-70. FINISHING WITH FABRIC OR TAPE … 1-41 1-71. SEALING OF BOLT HOLES … 1-41 1-72.–1-79. [RESERVED.] … 1-41
CHAPTER 2. FABRIC COVERING … 2-1
SECTION 1. PRACTICES AND PRECAUTIONS … 2-1
2-1. GENERAL … 2-1 2-2. PROBLEM AREAS … 2-1 2-3. AIRCRAFT FABRIC-SYNTHETIC … 2-1 2-4. AIRCRAFT FABRIC-NATURAL … 2-2 2-5. RECOVERING AIRCRAFT … 2-3 2-6. PREPARATION OF THE STRUCTURE FOR COVERING … 2-4 2-7. FABRIC SEAMS … 2-6 2-8. COVERING METHODS … 2-10 2-9. REINFORCING TAPE … 2-11 2-10. LACING … 2-12 2-11. STITCH SPACING … 2-22 2-12. FASTENERS … 2-23 2-13. FINISHING TAPE … 2-24 2-14. INSPECTION RINGS AND DRAIN GROMMETS … 2-25 2-15.–2-19. [RESERVED.] … 2-26
SECTION 2. APPLICATION OF DOPE … 2-27
2-20. GENERAL … 2-27 2-21. DOPE APPLICATION PROCEDURE (Natural Fabrics) … 2-29 2-22. COVERING OVER PLYWOOD … 2-31 2-23. COATING APPLICATION DEFECTS … 2-32 2-24.–2-29. [RESERVED.] … 2-33
Page v
SECTION 3. INSPECTION AND TESTING … 2-34
2-30. GENERAL … 2-34 2-31. FABRIC IDENTIFICATION … 2-35 2-32. COATING IDENTIFICATION … 2-36 2-33. STRENGTH CRITERIA FOR AIRCRAFT FABRIC … 2-36 2-34. FABRIC TESTING … 2-36 2-35. REJUVENATION OF THE DOPE FILM … 2-37 2-36.–2-41. [RESERVED.] … 2-37
SECTION 4. REPAIRS TO FABRIC COVERING … 2-38
2-42. GENERAL … 2-38 2-43. REPAIR OF TEARS AND ACCESS OPENINGS … 2-38 2-44. SEWN-PATCH REPAIR … 2-40 2-45. DOPED-ON PATCH REPAIR … 2-41 2-46.–2-51. [RESERVED.] … 2-42
CHAPTER 3. FIBERGLASS AND PLASTICS … 3-1
SECTION 1. REPAIR OF LIGHT LOAD LAMINATE STRUCTURES … 3-1
3-1. GENERAL … 3-1 3-2. FIBERGLASS LAMINATE REPAIRS … 3-1 3-3. REPAIRING HOLES … 3-4 3-4. SAMPLE BAGGING AND CURING PROCESS … 3-10 3-5.–3-9. [RESERVED.] … 3-12
SECTION 2. METALLIC SANDWICH SECONDARY STRUCTURE REPAIRS … 3-13
3-10. REPAIRS TO METALLIC SANDWICH SECONDARY STRUCTURE … 3-13 3-11. FINISHING … 3-19 3-12.–3-17. [RESERVED.] … 3-19
SECTION 3. TRANSPARENT PLASTICS … 3-20
3-18. GENERAL … 3-20 3-19. STORAGE AND HANDLING … 3-20 3-20. FORMING PROCEDURES AND TECHNIQUES … 3-20 3-21. HEATING … 3-21 3-22. FORMS … 3-22 3-23. FORMING METHODS … 3-22 3-24. REPAIR OF PLASTICS … 3-26 3-25. CLEANING AND POLISHING TRANSPARENT PLASTIC … 3-29 3-26. REPLACEMENT PANELS … 3-29 3-27. INSTALLATION PROCEDURES … 3-29 3-28.–3-39. [RESERVED.] … 3-30
Page vi
SECTION 4. WINDSHIELDS, ENCLOSURES, AND WINDOWS … 3-31
3-40. GENERAL … 3-31 3-41. PROTECTION … 3-32 3-42. WINDSHIELD INSTALLATION … 3-32 3-43.–3-47. [RESERVED.] … 3-33
CHAPTER 4. METAL STRUCTURE, WELDING, AND BRAZING … 4-1
SECTION 1. IDENTIFICATION OF METALS … 4-1
4-1. GENERAL … 4-1 4-2. IDENTIFICATION OF STEEL STOCK … 4-1 4-3. INTERCHANGEABILITY OF STEEL TUBING … 4-3 4-4. IDENTIFICATION OF ALUMINUM … 4-3 4-5.–4-15. [RESERVED.] … 4-5
SECTION 2. TESTING OF METALS … 4-6
4-16. HARDNESS TESTING … 4-6 4-17. ROCKWELL HARDNESS TEST … 4-6 4-18. BRINELL HARDNESS TEST … 4-7 4-19. VICKERS HARDNESS TEST … 4-8 4-20. MICROHARDNESS TESTING … 4-9 4-21. INDENTATIONS … 4-10 4-22. MAGNETIC TESTING … 4-10 4-23. ALUMINUM TESTING … 4-10 4-24.–4-35. [RESERVED.] … 4-11
SECTION 3. PRECAUTIONARY MEASURES … 4-12
4-36. FLUTTER AND VIBRATION PRECAUTIONS … 4-12 4-37. LOAD FACTORS FOR REPAIRS … 4-13 4-38. TRANSFER OF STRESSES WITHIN A STRUCTURE … 4-13 4-39.–4-49. [RESERVED.] … 4-13
SECTION 4. METAL REPAIR PROCEDURES … 4-14
4-50. GENERAL … 4-14 4-51. RIVETED (OR BOLTED) STEEL TRUSS-TYPE STRUCTURES … 4-14 4-52. ALUMINUM ALLOY STRUCTURES … 4-14 4-53. SELECTION OF ALUMINUM FOR REPLACEMENT PARTS … 4-15 4-54. HEAT TREATMENT OF ALUMINUM ALLOY PARTS … 4-16 4-55. BENDING METAL … 4-16 4-56. SETBACK … 4-16 4-57. RIVETING … 4-19 4-58. REPAIR METHODS AND PRECAUTIONS FOR ALUMINUM STRUCTURE … 4-33
Page vii
4-59. REPAIRING CRACKED MEMBERS … 4-49 4-60. STEEL AND ALUMINUM FITTINGS … 4-55 4-61. CASTINGS … 4-56 4-62. SELECTIVE PLATING IN AIRCRAFT MAINTENANCE … 4-57 4-63.–4-73. [RESERVED.] … 4-62
SECTION 5. WELDING AND BRAZING … 4-63
4-74. GENERAL … 4-63 4-75. EQUIPMENT SELECTION … 4-64 4-76. ACCURATELY IDENTIFY THE TYPE OF MATERIAL TO BE REPAIRED … 4-64 4-77. PREPARATION FOR WELDING … 4-65 4-78. INSPECTION OF A COMPLETED WELD … 4-65 4-79. MICROFISSURES … 4-65 4-80. NONDESTRUCTIVE TESTING … 4-66 4-81. PRACTICES TO GUARD AGAINST … 4-66 4-82. TORCH SIZE (Oxyacetylene welding) … 4-66 4-83. WELDING RODS AND ELECTRODES … 4-66 4-84. ROSETTE WELDS … 4-67 4-85. HEAT-TREATED MEMBERS … 4-67 4-86. TYPES OF WELDING … 4-68 4-87. ELECTRIC-RESISTANCE WELDING … 4-70 4-88. BRAZING … 4-71 4-89. AIRCRAFT PARTS NOT TO BE WELDED … 4-75 4-90. WELDING ROD SELECTION … 4-75 4-91. REPAIR OF TUBULAR MEMBERS … 4-76 4-92. REPAIR BY WELDED SLEEVE … 4-77 4-93. REPAIR BY BOLTED SLEEVE … 4-79 4-94. WELDED-PATCH REPAIR … 4-79 4-95. SPLICING TUBING BY INNER-SLEEVE METHOD … 4-79 4-96. SPLICING TUBING BY OUTER-SLEEVE METHOD … 4-80 4-97. SPLICING USING LARGER DIAMETER REPLACEMENT TUBES … 4-83 4-98. REPAIRS AT BUILT-IN FUSELAGE FITTINGS … 4-84 4-99. ENGINE-MOUNT REPAIRS … 4-86 4-100. BUILT-UP TUBULAR WING OR TAIL-SPARS … 4-86 4-101. WING-BRACE STRUTS AND TAIL-BRACE STRUTS … 4-90 4-102. LANDING GEAR REPAIR … 4-91 4-103. REPAIRS TO WELDED ASSEMBLIES … 4-92 4-104. STAINLESS STEEL STRUCTURE … 4-93 4-105.–4-110. [RESERVED.] … 4-93
SECTION 6. WELDING AND BRAZING SAFETY … 4-94
4-111. GENERAL … 4-94 4-112. FIRE AND EXPLOSION SAFETY … 4-94 4-113. WELDING WORK AREA … 4-94
Page viii
4-114. FIRE PROTECTION … 4-95 4-115. PROTECTIVE APPAREL … 4-95 4-116. FIRST-AID KITS … 4-96 4-117.–4-128. [RESERVED.] … 4-96
CHAPTER 5. NONDESTRUCTIVE INSPECTION (NDI) … 5-1
SECTION 1. GENERAL … 5-1
5-1. GENERAL … 5-1 5-2. APPROVED PROCEDURES … 5-1 5-3. NDT LEVELS … 5-1 5-4. TRAINING, QUALIFICATION, AND CERTIFICATION … 5-2 5-5. FLAWS … 5-2 5-6. SELECTING THE NDI METHOD … 5-6 5-7. TYPES OF INSPECTIONS … 5-8 5-8.–5-14. [RESERVED.] … 5-8
SECTION 2. VISUAL INSPECTION … 5-9
5-15. GENERAL … 5-9 5-16. SIMPLE VISUAL INSPECTION AIDS … 5-9 5-17. BORESCOPES … 5-10 5-18. VISUAL INSPECTION PROCEDURES … 5-11 5-19.–5-24. [RESERVED.] … 5-13
SECTION 3. EDDY CURRENT INSPECTION … 5-14
5-25. EDDY CURRENT INSPECTION … 5-14 5-26. EDDY CURRENT COILS AND PROBES … 5-15 5-27. FIELD APPLICATION OF EDDY CURRENT INSPECTION … 5-16 5-28. SURFACE INSPECTION … 5-16 5-29. SUBSURFACE INSPECTION … 5-17 5-30. CORROSION INSPECTION … 5-18 5-31. ESTABLISHING EDDY CURRENT INSPECTION PROCEDURES … 5-18 5-32.–5-39. [RESERVED.] … 5-19
SECTION 4. MAGNETIC PARTICLE INSPECTION … 5-20
5-40. GENERAL … 5-20 5-41. PRINCIPLES OF OPERATION … 5-20 5-42. APPLICATIONS … 5-21 5-43. ELECTRICAL MAGNETIZING EQUIPMENT … 5-21 5-44. MATERIALS USED IN MAGNETIC PARTICLE INSPECTION … 5-22 5-45. PREPARATION OF SURFACE … 5-24 5-46. METHODS OF EXAMINATION … 5-25 5-47. APPLICATION OF MAGNETIC PARTICLES … 5-25 5-48. MAGNETIZATION … 5-25
Page ix
5-49. DETERMINATION OF FIELD STRENGTH … 5-28 5-50. SPECIAL EXAMINATION TECHNIQUES … 5-28 5-51. DEMAGNETIZATION AND POST-EXAMINATION CLEANING … 5-30 5-52.–5-59. [RESERVED.] … 5-31
SECTION 5. PENETRANT INSPECTION … 5-32
5-60. GENERAL … 5-32 5-61. EQUIPMENT USED IN THE PENETRANT INSPECTION PROCESS … 5-33 5-62. BASIC STEPS TO PERFORM PENETRATION INSPECTION … 5-34 5-63. CLEANERS AND APPLICATIONS … 5-37 5-64. TECHNICAL STANDARDS … 5-38 5-65.–5-72. [RESERVED.] … 5-39
SECTION 6. RADIOGRAPHY (X-RAY) INSPECTION … 5-40
5-73. GENERAL … 5-40 5-74. LIMITATIONS … 5-40 5-75. FILM OR PAPER RADIOGRAPHY … 5-40 5-76. REAL-TIME RADIOGRAPHY … 5-41 5-77. ADVANTAGE OF REAL-TIME RADIOGRAPHY OVER FILM RADIOGRAPHY … 5-41 5-78. COMPUTED TOMOGRAPHY (CT) … 5-41 5-79. USES OF RADIOGRAPHY … 5-41 5-80. COMPARISON WITH OTHER NDI METHODS … 5-41 5-81. FLAWS … 5-42 5-82. FIELD INSPECTION … 5-42 5-83. SAFETY … 5-42 5-84.–5-88. [RESERVED.] … 5-42
SECTION 7. ULTRASONIC INSPECTION … 5-43
5-89. GENERAL … 5-43 5-90. SOUND REFLECTION … 5-43 5-91. ULTRASONIC INSPECTION TECHNIQUES … 5-44 5-92. FLAW DETECTION … 5-44 5-93. BASIC EQUIPMENT … 5-45 5-94. INSPECTION OF BONDED STRUCTURES … 5-47 5-95. BOND TESTING INSTRUMENTS … 5-52 5-96. THICKNESS MEASUREMENTS … 5-53 5-97. LEAK TESTING … 5-54 5-98.–5-104. [RESERVED.] … 5-54
SECTION 8. TAP TESTING … 5-55
5-105. GENERAL … 5-55 5-106.–5-111. [RESERVED.] … 5-55
Page x
SECTION 9. ACOUSTIC-EMISSION … 5-56
5-112. GENERAL … 5-56 5-113. APPLICATIONS … 5-56 5-114.–5-119. [RESERVED.] … 5-56
SECTION 10. THERMOGRAPHY … 5-57
5-120. GENERAL … 5-57 5-121.–5-126. [RESERVED.] … 5-57
SECTION 11. HOLOGRAPHY … 5-58
5-127. GENERAL … 5-58 5-128.–5-133. [RESERVED.] … 5-58
SECTION 12. SHEAROGRAPHY … 5-59
5-134. GENERAL … 5-59 5-135.–5-140. [RESERVED.] … 5-59
CHAPTER 6. CORROSION, INSPECTION, AND PROTECTION … 6-1
SECTION 1. GENERAL … 6-1
6-1. GENERAL … 6-1 6-2. FACTORS INFLUENCING CORROSION … 6-2 6-3. COMMON CORROSIVE AGENTS … 6-3 6-4. MICRO-ORGANISMS … 6-4 6-5.–6-10. [RESERVED.] … 6-4
SECTION 2. TYPES OF CORROSION … 6-5
6-11. GENERAL … 6-5 6-12. GENERAL SURFACE CORROSION … 6-5 6-13. PITTING CORROSION … 6-5 6-14. CONCENTRATION CELL CORROSION … 6-6 6-15. ACTIVE-PASSIVE CELLS … 6-7 6-16. FILIFORM CORROSION … 6-8 6-17. INTERGRANULAR CORROSION … 6-8 6-18. EXFOLIATION CORROSION … 6-9 6-19. GALVANIC CORROSION … 6-10 6-20. STRESS CORROSION CRACKING … 6-10 6-21. FATIGUE CORROSION … 6-12 6-22. FRETTING CORROSION … 6-12 6-23.–6-28. [RESERVED.] … 6-13
Page xi
SECTION 3. CORROSION PROTECTION MEASURES FOR BASIC MATERIALS … 6-14
6-29. GENERAL … 6-14 6-30. ANODIZING AND RELATED PROCESSES … 6-14 6-31. PLATING … 6-14 6-32. PHOSPHATE RUST-PROOFING … 6-14 6-33. CHROME-PICKLE TREATMENT … 6-14 6-34. DICHROMATE TREATMENT … 6-14 6-35. STANNATE IMMERSION TREATMENT … 6-15 6-36. GALVANIC ANODIZING TREATMENT … 6-15 6-37. CLADDING … 6-15 6-38. METAL SPRAYING … 6-15 6-39. SHOT-PEENING … 6-15 6-40. ORGANIC COATINGS … 6-15 6-41. DOPE PROOFING … 6-15 6-42. TUBE INTERIORS … 6-15 6-43.–6-49. [RESERVED.] … 6-15
SECTION 4. CORROSION PREVENTIVE MAINTENANCE … 6-16
6-50. GUIDELINES: ALL AIRCRAFT … 6-16 6-51. GUIDELINES: AIRCRAFT OPERATING OVER SALTWATER … 6-16 6-52.–6-62. [RESERVED.] … 6-17
SECTION 5. VISUAL CORROSION INSPECTION GUIDE FOR AIRCRAFT … 6-18
6-63. GENERAL … 6-18 6-64. EXHAUST TRAIL AREAS … 6-18 6-65. BATTERY COMPARTMENTS AND BATTERY VENT OPENINGS … 6-18 6-66. LAVATORIES AND GALLEYS … 6-18 6-67. BILGE AREAS … 6-18 6-68. WHEEL WELLS AND LANDING GEAR … 6-18 6-69. EXTERNAL SKIN AREAS … 6-18 6-70. WATER ENTRAPMENT AREAS … 6-19 6-71. ENGINE FRONTAL AREAS … 6-19 6-72. ELECTRONIC PACKAGE COMPARTMENTS … 6-19 6-73. FLEXIBLE HOSE ASSEMBLIES … 6-19 6-74. SANDWICH PANELS … 6-19 6-75. CONTROL CABLES … 6-19 6-76. INTEGRAL FUEL CELLS … 6-20 6-77. ELECTRICAL CONNECTORS … 6-20 6-78.–6-88. [RESERVED.] … 6-20
SECTION 6. CORROSION REMOVAL PROCEDURES … 6-21
6-89. GENERAL … 6-21 6-90. SAFETY PRECAUTIONS … 6-21
Page xii
6-91. CORROSION CONTROL WORK PROCEDURES … 6-22 6-92.–6-112. [RESERVED.] … 6-23
SECTION 7. BASIC CORROSION REMOVAL TECHNIQUES … 6-24
6-113. GENERAL … 6-24 6-114. PREPARATIONS FOR REWORK … 6-24 6-115. FAIRING OR BLENDING REWORKED AREAS … 6-24 6-116. CORROSION REMOVAL BY BLASTING … 6-28 6-117. CLEANERS, POLISHES, AND BRIGHTENERS … 6-28 6-118. STANDARD METHODS … 6-29 6-119.–6-131. [RESERVED.] … 6-29
SECTION 8. ALUMINUM AND ALUMINUM ALLOYS … 6-30
6-132. GENERAL … 6-30 6-133. SPECIAL TREATMENT OF ANODIZED SURFACES … 6-30 6-134. REPAIR OF ALUMINUM ALLOY SHEET METAL … 6-30 6-135. CORROSION REMOVAL AROUND COUNTERSUNK FASTENERS IN ALUMINUM ALLOY … 6-31 6-136. EXAMPLES OF REMOVING CORROSION FROM ALUMINUM AND ALUMINUM ALLOYS … 6-31 6-137.–6-147. [RESERVED.] … 6-34
SECTION 9. MAGNESIUM AND MAGNESIUM ALLOYS … 6-35
6-148. GENERAL … 6-35 6-149. TREATMENT OF WROUGHT MAGNESIUM SHEETS AND FORGINGS .... 6-35 6-150. REPAIR OF MAGNESIUM SHEET METAL AFTER EXTENSIVE CORROSION REMOVAL … 6-35 6-151. IN-PLACE TREATMENT OF MAGNESIUM CASTINGS … 6-36 6-152. EXAMPLE OF REMOVING CORROSION FROM MAGNESIUM … 6-36 6-153.–6-163. [RESERVED.] … 6-40
SECTION 10. FERROUS METALS … 6-41
6-164. GENERAL … 6-41 6-165. SPECIAL TREATMENT OF HIGH-STRENGTH STEEL … 6-41 6-166. SPECIAL TREATMENT OF STAINLESS STEEL … 6-41 6-167. EXAMPLE OF REMOVING CORROSION FROM FERROUS METALS … 6-42 6-168.–6-178. [RESERVED.] … 6-42
SECTION 11. OTHER METALS AND ALLOYS … 6-43
6-179. NOBLE METAL COATINGS CLEANUP AND RESTORATION … 6-43 6-180. COPPER AND COPPER ALLOYS … 6-43 6-181. TITANIUM AND TITANIUM ALLOYS … 6-43 6-182.–6-192. [RESERVED.] … 6-44
Page xiii
SECTION 12. PLATED PARTS … 6-45
6-193. CHROMIUM AND NICKEL-PLATED PARTS … 6-45 6-194. CADMIUM AND ZINC-PLATED PARTS … 6-45 6-195.–6-205. [RESERVED.] … 6-45
SECTION 13. CORROSION PROOFING OF LAND PLANES CONVERTED TO
SEAPLANES … 6-46
6-206. GENERAL … 6-46 6-207. NECESSARY MINIMUM PRECAUTIONS … 6-46 6-208. RECOMMENDED PRECAUTIONS … 6-46 6-209.–6-219. [RESERVED.] … 6-47
SECTION 14. HANDLING AND CARE OF AIRCRAFT RECOVERED FROM WATER
IMMERSION … 6-48
6-220. GENERAL … 6-48 6-221. INITIAL FRESHWATER OR DETERGENT WASH … 6-48 6-222. RECIPROCATING ENGINES AND PROPELLERS … 6-48 6-223. AIRFRAME … 6-49 6-224.–6-234. [RESERVED.] … 6-49
CHAPTER 7. AIRCRAFT HARDWARE, CONTROL CABLES, AND TURNBUCKLES .... 7-1
SECTION 1. RIVETS … 7-1
7-1. GENERAL … 7-1 7-2. MATERIAL APPLICATIONS … 7-1 7-3.–7-13. [RESERVED.] … 7-2
SECTION 2. SCREWS … 7-3
7-14. GENERAL … 7-3 7-15. STRUCTURAL SCREWS … 7-3 7-16. MACHINE SCREWS … 7-3 7-17. PAN HEAD SCREWS (NAS600 THROUGH NAS606, NAS610 THROUGH NAS616, NAS623, AND NAS1402 THROUGH NAS1406) … 7-3 7-18. SELF-TAPPING SCREWS … 7-4 7-19. WOOD SCREWS … 7-4 7-20.–7-33. [RESERVED.] … 7-4
SECTION 3. BOLTS … 7-5
7-34. GENERAL … 7-5 7-35. BOLTS … 7-5 7-36. IDENTIFICATION … 7-5 7-37. GRIP LENGTH … 7-6
Page xiv
7-38. LOCKING OR SAFETYING OF BOLTS … 7-6 7-39. BOLT FIT … 7-6 7-40. TORQUES … 7-7 7-41. STANDARD AIRCRAFT HEX HEAD BOLTS (AN3 THROUGH AN20) … 7-10 7-42. DRILLED HEAD BOLTS (AN73 THROUGH AN81) … 7-10 7-43. ENGINE BOLTS … 7-10 7-44. CLOSE-TOLERANCE BOLTS … 7-10 7-45. INTERNAL WRENCHING BOLTS (NAS144 THROUGH NAS158 AND NAS172 THROUGH NAS176) … 7-10 7-46. INTERNAL WRENCHING BOLTS (MS20004 THROUGH MS20024) AND SIX HOLE, DRILLED SOCKET HEAD BOLTS (AN148551 THROUGH AN149350) … 7-11 7-47. TWELVE-POINT, EXTERNAL WRENCHING BOLTS (NAS624 THROUGH NAS644) … 7-11 7-48. CLOSE-TOLERANCE SHEAR BOLTS (NAS464) … 7-11 7-49. NAS6200 SERIES BOLTS … 7-11 7-50. CLEVIS BOLTS (AN21 THROUGH AN36) … 7-11 7-51. EYEBOLTS (AN42 THROUGH AN49) … 7-11 7-52.–7-62. [RESERVED.] … 7-11
SECTION 4. NUTS … 7-12
7-63. GENERAL … 7-12 7-64. SELF-LOCKING NUTS … 7-12 7-65. NUT IDENTIFICATION FINISHES … 7-13 7-66. CASTLE NUT (AN310) … 7-14 7-67. CASTELLATED SHEAR NUT (AN320) … 7-14 7-68. PLAIN NUT (AN315 AND AN335) … 7-14 7-69. LIGHT HEX NUTS (AN340 AND AN345) … 7-14 7-70. CHECKNUT (AN316) … 7-15 7-71. WINGNUTS (AN350) … 7-15 7-72. SHEET SPRING NUTS (AN365) … 7-15 7-73.–7-84. RESERVED … 7-15
SECTION 5. WASHERS … 7-16
7-85. GENERAL … 7-16 7-86. PLAIN WASHERS (AN960 AND AN970) … 7-16 7-87. LOCK WASHERS (AN935 AND AN936) … 7-16 7-88. BALL SOCKET AND SEAT WASHERS (AN950 AND AN955) … 7-16 7-89. TAPER PIN WASHERS (AN975) … 7-16 7-90.–7-100. [RESERVED.] … 7-16
SECTION 6. PINS … 7-17
7-101. TAPER PINS … 7-17 7-102. FLATHEAD PINS (AN392 THROUGH AN406) … 7-17
Page xv
7-103. COTTER PINS (AN380) … 7-17 7-104. SPRING PINS … 7-17 7-105. QUICK-RELEASE PINS … 7-17 7-106.–7-121. [RESERVED.] … 7-17
SECTION 7. SAFETYING … 7-18
7-122. GENERAL … 7-18 7-123. SAFETY WIRE … 7-18 7-124. SAFETY-WIRING PROCEDURES … 7-20 7-125. TWISTING WITH SPECIAL TOOLS … 7-21 7-126. SECURING OIL CAPS, DRAIN COCKS, AND VALVES … 7-21 7-127. SECURING WITH COTTER PINS … 7-25 7-128.–7-139. [RESERVED.] … 7-26
SECTION 8. INSPECTION AND REPAIR OF CONTROL CABLES AND
TURNBUCKLES … 7-27
7-140. GENERAL … 7-27 7-141. CABLE DEFINITIONS … 7-27 7-142. FLEXIBLE CABLES … 7-27 7-143. NYLON-COATED CABLES … 7-29 7-144. NONFLEXIBLE CABLES … 7-30 7-145. CABLE SPECIFICATIONS … 7-31 7-146. CABLE PROOF LOADS … 7-31 7-147. REPLACEMENT OF CABLES … 7-31 7-148. MECHANICALLY-FABRICATED CABLE ASSEMBLIES … 7-32 7-149. CABLE SYSTEM INSPECTION … 7-39 7-150. CORROSION AND RUST PREVENTION … 7-44 7-151. WIRE SPLICES … 7-45 7-152. CABLE MAINTENANCE … 7-45 7-153. CABLE TENSION ADJUSTMENT … 7-45 7-154.–7-164. [RESERVED.] … 7-46
SECTION 9. TURNBUCKLES … 7-47
7-165. GENERAL … 7-47 7-166. TURNBUCKLE INSTALLATION … 7-47 7-167. WITNESS HOLE … 7-48 7-168.–7-178. [RESERVED.] … 7-48
SECTION 10. SAFETY METHODS FOR TURNBUCKLES … 7-49
7-179. GENERAL … 7-49 7-180. DOUBLE-WRAP METHOD … 7-49 7-181. SINGLE-WRAP METHOD … 7-50 7-182. SAFETY WIRE SECURED TURNBUCKLES … 7-50 7-183. SPECIAL LOCKING DEVICES … 7-52
Page xvi
7-184. ASSEMBLING AND SECURING CLIP-LOCKING TURNBUCKLES … 7-52 7-185.–7-195. [RESERVED.] … 7-53
SECTION 11. HARDWARE IDENTIFICATION TABLES … 7-54
7-196.–7-206. [RESERVED.] … 7-83
CHAPTER 8. ENGINES, FUEL, EXHAUST, AND PROPELLERS … 8-1
SECTION 1. ENGINES … 8-1
8-1. GENERAL … 8-1 8-2. SPECIAL INSPECTION … 8-1 8-3. CRANKSHAFT INSPECTION AND REPAIR REQUIREMENTS … 8-3 8-4. REPLACEMENT PARTS IN CERTIFICATED ENGINES … 8-4 8-5. OIL SYSTEM LINES INSPECTION … 8-4 8-6. OIL FILTER INSPECTION … 8-4 8-7. CYLINDER HOLD-DOWN NUTS AND CAP SCREWS … 8-4 8-8. REUSE OF SAFETYING DEVICES … 8-5 8-9. SELF-LOCKING NUTS FOR AIRCRAFT ENGINES AND ACCESSORIES … 8-5 8-10. METALLIZING … 8-5 8-11. PLATING … 8-5 8-12. CORROSION … 8-7 8-13. ENGINE RUN-IN … 8-7 8-14. COMPRESSION TESTING OF AIRCRAFT ENGINE CYLINDERS … 8-7 8-15. SPARK PLUGS … 8-10 8-16. OPERATIONAL PROBLEMS … 8-14 8-17. SPARK PLUG PRE-RECONDITIONING INSPECTION … 8-19 8-18. IGNITION HARNESSES INSPECTION … 8-19 8-19. MAGNETO INSPECTION … 8-20 8-20. MAGNETO-TO-ENGINE TIMING … 8-22 8-21.–8-29. [RESERVED.] … 8-22
SECTION 2. FUEL SYSTEMS … 8-23
8-30. GENERAL … 8-23 8-31. FUEL LINES AND FITTINGS … 8-23 8-32. FUEL TANKS AND CELLS … 8-24 8-33. FUEL TANK CAPS, VENTS, AND OVERFLOW LINES … 8-25 8-34. FUEL CROSS-FEED, FIREWALL SHUTOFF, AND TANK SELECTOR VALVES … 8-25 8-35. FUEL PUMPS … 8-26 8-36. FUEL FILTERS, STRAINERS, AND DRAINS … 8-26 8-37. INDICATOR SYSTEMS … 8-26 8-38. FUEL SYSTEM PRECAUTIONS … 8-26 8-39.–8-44. [RESERVED.] … 8-27
Page xvii
SECTION 3. EXHAUST SYSTEMS … 8-28
8-45. GENERAL … 8-28 8-46. MUFFLER/HEAT EXCHANGER FAILURES … 8-28 8-47. MANIFOLD/STACK FAILURES … 8-30 8-48. INTERNAL MUFFLER FAILURES … 8-31 8-49. INSPECTION … 8-33 8-50. REPAIRS … 8-35 8-51. TURBOSUPERCHARGER … 8-36 8-52. AUGMENTER SYSTEMS … 8-36 8-53.–8-70. [RESERVED.] … 8-36
SECTION 4. REPAIR OF METAL PROPELLERS … 8-37
8-71. GENERAL … 8-37 8-72. STEEL BLADES … 8-37 8-73. ALUMINUM PROPELLER REPAIRS … 8-37 8-74. REPAIR LIMITS … 8-40 8-75. STEEL HUBS AND HUB PARTS … 8-42 8-76. PROPELLER HUB AND FLANGE REPAIR … 8-42 8-77. CONTROL SYSTEMS … 8-43 8-78. DEICING SYSTEMS … 8-44 8-79.–8-90. [RESERVED.] … 8-44
SECTION 5. INSPECTION OF PROPELLERS … 8-45
8-91. GENERAL … 8-45 8-92. WOOD OR COMPOSITION PROPELLERS AND BLADES … 8-45 8-93. METAL PROPELLERS AND BLADES … 8-47 8-94. PROPELLER HUB … 8-48 8-95. TACHOMETER INSPECTION … 8-49 8-96.–8-106. [RESERVED.] … 8-49
SECTION 6. PROPELLER TRACKING AND VIBRATION … 8-50
8-107. GENERAL … 8-50 8-108. PROPELLER TRACKING CHECK … 8-50 8-109. VIBRATION … 8-51 8-110.–8-129. [RESERVED.] … 8-51
CHAPTER 9. AIRCRAFT SYSTEMS AND COMPONENTS … 9-1
SECTION 1. INSPECTION AND MAINTENANCE OF LANDING GEAR … 9-1
9-1. GENERAL … 9-1 9-2. GENERAL INSPECTION … 9-1 9-3. CLEANING AND LUBRICATING … 9-1 9-4. FIXED-GEAR INSPECTION … 9-2
Page xviii
9-5. INSPECTION OF RETRACTABLE LANDING GEAR … 9-3 9-6. EMERGENCY SYSTEMS … 9-4 9-7. LANDING-GEAR COMPONENTS … 9-4 9-8. FLOATS AND SKIS … 9-6 9-9. INSPECTION AND REPAIR OF FLOATS AND SKIS … 9-8 9-10. TYPES OF LANDING-GEAR PROBLEMS … 9-9 9-11. SPECIAL INSPECTIONS … 9-11 9-12. RETRACTION TESTS … 9-11 9-13. TIRE AND TUBE MAINTENANCE … 9-11 9-14. TIRE INSPECTION AND REPAIR … 9-12 9-15. INFLATION OF TIRES … 9-13 9-16. PERSONAL SAFETY … 9-14 9-17. DISASSEMBLE THE WHEEL … 9-14 9-18. REASSEMBLING THE WHEEL … 9-15 9-19. SLIPPAGE … 9-15 9-20. WHEEL INSPECTION … 9-15 9-21. WHEEL INSTALLATION … 9-15 9-22.–9-24. [RESERVED.] … 9-16
SECTION 2. HYDRAULIC SYSTEMS … 9-17
9-25. GENERAL … 9-17 9-26. PURPOSES OF HYDRAULIC SYSTEMS … 9-17 9-27. TYPES OF HYDRAULIC FLUID … 9-17 9-28. HANDLING HYDRAULIC FLUID … 9-18 9-29. HYDRAULIC SYSTEM MAINTENANCE PRACTICES … 9-19 9-30. HYDRAULIC LINES AND FITTINGS … 9-22 9-31.–9-36. [RESERVED.] … 9-34
SECTION 3. EMERGENCY EQUIPMENT … 9-35
9-37. LIFE RAFTS … 9-35 9-38. LIFE RAFT INSPECTIONS … 9-35 9-39. SURVIVAL KIT INSPECTION … 9-37 9-40. SPECIAL INSPECTIONS … 9-41 9-41. INSPECTION RECORD … 9-41 9-42. RAFT REPAIRS … 9-41 9-43. LIFE PRESERVERS … 9-44 9-44. LIFE PRESERVER INSPECTION … 9-45 9-45. REPAIR OF LIFE PRESERVERS … 9-46 9-46. MISCELLANEOUS EQUIPMENT … 9-46 9-47. OXYGEN SYSTEMS … 9-47 9-48. INSPECTION … 9-48 9-49. MAINTENANCE … 9-49 9-50. FUNCTIONAL TESTING AFTER REPAIR … 9-51 9-51. REQUIREMENTS FOR REQUALIFICATION OF OXYGEN CYLINDERS .... 9-52 9-52.–9-59. [RESERVED.] … 9-55
Page xix
SECTION 4. CABIN INTERIOR … 9-56
9-60. GENERAL … 9-56 9-61. CAR 3 AIRCRAFT INTERIOR … 9-56 9-62. PART 23 AIRCRAFT INTERIOR … 9-56 9-63. SOURCE OF INFORMATION … 9-57 9-64. UPHOLSTERY AND/OR BELTS … 9-57 9-65.–9-70. [RESERVED.] … 9-57
CHAPTER 10. WEIGHT AND BALANCE … 10-1
SECTION 1. TERMINOLOGY … 10-1
10-1. GENERAL … 10-1 10-2. TERMINOLOGY … 10-1 10-3.–10-13. [RESERVED.] … 10-9
SECTION 2. WEIGHING PROCEDURES … 10-10
10-14. GENERAL … 10-10 10-15. PROCEDURES … 10-10 10-16. REPAIRS AND ALTERATIONS … 10-11 10-17. ANNUAL OR 100-HOUR INSPECTION … 10-11 10-18. W&B COMPUTATIONS … 10-12 10-19. W&B EXTREME CONDITIONS … 10-13 10-20. LOADING CONDITIONS AND/OR PLACARDS … 10-16 10-21. EQUIPMENT LIST … 10-19 10-22. EQUIPMENT CHANGE … 10-20 10-23. SAMPLE W&B REPORT … 10-21 10-24. INSTALLATION OF BALLAST … 10-24 10-25. LOADING SCHEDULE … 10-25 10-26.–10-34. [RESERVED.] … 10-25
CHAPTER 11. AIRCRAFT ELECTRICAL SYSTEMS … 11-1
SECTION 1. INSPECTION AND CARE OF ELECTRICAL SYSTEMS … 11-1
11-1. GENERAL … 11-1 11-2. INSPECTION AND OPERATION CHECKS … 11-1 11-3. FUNCTIONAL CHECK OF STAND-BY OR EMERGENCY EQUIPMENT .... 11-2 11-4. CLEANING AND PRESERVATION … 11-2 11-5. BATTERY ELECTROLYTE CORROSION … 11-2 11-6. ADJUSTMENT AND REPAIR … 11-2 11-7. INSULATION OF ELECTRICAL EQUIPMENT … 11-3 11-8. BUS BARS … 11-3 11-9. ASTM INTERNATIONAL … 11-3 11-10.–11-14. [RESERVED.] … 11-4
Page xx
SECTION 2. STORAGE BATTERIES … 11-5
11-15. GENERAL … 11-5 11-16. BATTERY CHARGING … 11-5 11-17. BATTERY FREEZING … 11-5 11-18. TEMPERATURE CORRECTION … 11-6 11-19. BATTERY MAINTENANCE … 11-7 11-20. ELECTROLYTE SPILLAGE … 11-10 11-21. NOXIOUS FUMES … 11-10 11-22. INSTALLATION PRACTICES … 11-10 11-23.–11-29. [RESERVED.] … 11-12
SECTION 3. INSPECTION OF EQUIPMENT INSTALLATION … 11-13
11-30. GENERAL … 11-13 11-31. INSTALLATION CLEARANCE PROVISIONS … 11-13 11-32. WIRES, WIRE BUNDLES, AND CIRCUIT PROTECTIVE DEVICES … 11-13 11-33. ALTERNATOR DIODES … 11-13 11-34. STATIC ELECTRICAL POWER CONVERTERS … 11-13 11-35. ACCEPTABLE MEANS OF CONTROLLING OR MONITORING THE ELECTRICAL LOAD … 11-14 11-36. ELECTRICAL LOAD DETERMINATION … 11-14 11-37. JUNCTION BOX CONSTRUCTION … 11-15 11-38.–11-46. [RESERVED.] … 11-15
SECTION 4. INSPECTION OF CIRCUIT-PROTECTION DEVICES … 11-16
11-47. GENERAL … 11-16 11-48. DETERMINATION OF CIRCUIT BREAKER RATINGS … 11-16 11-49. DC CIRCUIT PROTECTOR CHART … 11-16 11-50. RESETTABLE CIRCUIT PROTECTION DEVICES … 11-17 11-51. CIRCUIT BREAKER USAGE … 11-17 11-52. CIRCUIT BREAKER MAINTENANCE … 11-18 11-53. SWITCHES … 11-18 11-54. RELAYS … 11-22 11-55. LOAD CONSIDERATIONS … 11-23 11-56. OPERATING CONDITIONS FOR SWITCHES AND RELAYS … 11-23 11-57.–11-65. [RESERVED.] … 11-23
SECTION 5. ELECTRICAL WIRE RATING … 11-24
11-66. GENERAL … 11-24 11-67. METHODS FOR DETERMINING CURRENT CARRYING CAPACITY OF WIRES … 11-28 11-68. INSTRUCTIONS FOR USE OF ELECTRICAL WIRE CHART … 11-29 11-69. COMPUTING CURRENT CARRYING CAPACITY … 11-33 11-70.–11-75. [RESERVED.] … 11-40
Page xxi
SECTION 6. AIRCRAFT ELECTRICAL WIRE SELECTION … 11-41
11-76. GENERAL … 11-41 11-77. AIRCRAFT WIRE MATERIALS … 11-41 11-78. SUBSTITUTIONS … 11-43 11-79.–11-84. [RESERVED.] … 11-43
SECTION 7. TABLE OF ACCEPTABLE WIRES … 11-44
11-85. AIRCRAFT WIRE TABLE … 11-44 11-86. OPEN AIRFRAME INTERCONNECTING WIRE … 11-47 11-87. PROTECTED WIRE … 11-47 11-88. SEVERE WIND AND MOISTURE PROBLEMS (SWAMP) … 11-47 11-89. SHIELDED WIRE … 11-47 11-90.–11-95. [RESERVED.] … 11-48
SECTION 8. WIRING INSTALLATION INSPECTION REQUIREMENTS … 11-49
11-96. GENERAL … 11-49 11-97. WIRING REPLACEMENT … 11-52 11-98. TERMINALS AND TERMINAL BLOCKS … 11-53 11-99. FUSES AND FUSE HOLDERS … 11-53 11-100. CONNECTORS … 11-54 11-101. JUNCTION BOXES, PANELS, SHIELDS, AND MICRO-SWITCH HOUSINGS … 11-55 11-102. RIGID METALLIC, FLEXIBLE METALLIC AND RIGID NONMETALLIC CONDUIT … 11-55 11-103. JUNCTIONS … 11-55 11-104. CIRCUIT BREAKERS … 11-56 11-105. SYSTEM SEPARATION … 11-56 11-106. ELECTROMAGNETIC INTERFERENCE (EMI) … 11-56 11-107. INTERFERENCE TESTS … 11-56 11-108. IDENTIFICATION STENCILS AND PLACARDS ON ELECTRICAL EQUIPMENT … 11-57 11-109.–11-114. [RESERVED.] … 11-57
SECTION 9. ENVIRONMENTAL PROTECTION AND INSPECTION … 11-58
11-115. MAINTENANCE AND OPERATIONS … 11-58 11-116. GROUP AND BUNDLE TIES … 11-58 11-117. MINIMUM WIRE BEND RADII … 11-59 11-118. SLACK … 11-59 11-119. DRIP LOOP IN WIRE BUNDLE … 11-60 11-120. POWER FEEDERS … 11-61 11-121. RF CABLE … 11-61 11-122. PRECAUTIONS … 11-61
Page xxii
11-123. MOISTURE PROTECTION, WHEEL WELLS, AND LANDING GEAR AREAS … 11-62 11-124. PROTECTION AGAINST PERSONNEL AND CARGO … 11-62 11-125. HEAT PRECAUTIONS … 11-62 11-126. MOVABLE CONTROLS WIRING PRECAUTIONS … 11-62 11-127. FLAMMABLE FLUIDS AND GASES … 11-62 11-128.–11-134. [RESERVED.] … 11-63
SECTION 10. SERVICE LOOP HARNESSES (PLASTIC TIE STRIPS) … 11-64
11-135. GENERAL … 11-64 11-136. SUPPORT … 11-64 11-137. ANTI-CHAFING MATERIAL … 11-64 11-138. STRAIN RELIEF … 11-64 11-139. “SERVICE LOOP” … 11-64 11-140.–11-145. [RESERVED.] … 11-65
SECTION 11. CLAMPING … 11-66
11-146. GENERAL … 11-66 11-147. WIRE AND CABLE CLAMPS INSPECTION … 11-66 11-148.–11-154. [RESERVED.] … 11-69
SECTION 12. WIRE INSULATION AND LACING STRING TIE … 11-70
11-155. GENERAL … 11-70 11-156. INSULATION MATERIALS … 11-70 11-157. STRIPPING INSULATION … 11-70 11-158. LACING AND TIES … 11-71 11-159. INSULATION TAPE … 11-74 11-160.–11-166. [RESERVED.] … 11-74
SECTION 13. SPLICING … 11-75
11-167. GENERAL … 11-75 11-168.–11-173. [RESERVED.] … 11-75
SECTION 14. TERMINAL REPAIRS … 11-76
11-174. GENERAL … 11-76 11-175. ATTACHMENT OF TERMINALS TO STUDS … 11-77 11-176. STUDS AND INSULATORS … 11-77 11-177. WIRE TERMINALS AND BINDING POSTS … 11-78 11-178. CRIMP ON TERMINAL LUGS AND SPLICES (pre-insulated crimp type) … 11-78 11-179. LOCK WASHERS FOR TERMINALS ON EQUIPMENT … 11-79 11-180.–11-184. [RESERVED.] … 11-79
Page xxiii
SECTION 15. GROUNDING AND BONDING … 11-80
11-185. GENERAL … 11-80 11-186. GROUNDING … 11-80 11-187. BONDING … 11-82 11-188. BONDING INSPECTION … 11-82 11-189. BONDING JUMPER INSTALLATIONS … 11-84 11-190. CREEPAGE DISTANCE … 11-89 11-191. FUEL SYSTEMS … 11-89 11-192. ELECTRIC SHOCK PREVENTION BONDING … 11-89 11-193. LIGHTNING PROTECTION BONDING … 11-89 11-194. LIGHTNING PROTECTION FOR ANTENNAS AND AIR DATA PROBES . 11-90 11-195. STATIC-DISCHARGE DEVICE … 11-90 11-196. CLEANING … 11-90 11-197. HARDWARE ASSEMBLY … 11-90 11-198.–11-204. [RESERVED.] … 11-91
SECTION 16. WIRE MARKING … 11-92
11-205. GENERAL … 11-92 11-206. WIRE IDENTIFICATION … 11-92 11-207. IDENTIFICATION AND INFORMATION RELATED TO THE WIRE AND WIRING DIAGRAMS … 11-92 11-208. PLACEMENT OF IDENTIFICATION MARKINGS … 11-92 11-209. TYPES OF WIRE MARKINGS … 11-93 11-210. HOT STAMP MARKING … 11-94 11-211. DOT MATRIX MARKING … 11-94 11-212. INK JET MARKING … 11-94 11-213. LASER MARKING … 11-95 11-214. IDENTIFICATION SLEEVES … 11-95 11-215. IDENTIFICATION TAPE … 11-95 11-216. OPERATING CONDITIONS … 11-96 11-217. INSTALLATION OF PRINTED SLEEVES … 11-96 11-218. IDENTIFICATION OF WIRE BUNDLES AND HARNESSES … 11-96 11-219. TERMINAL MARKING SLEEVE AND TAGS … 11-97 11-220. SLEEVES AND CABLE MARKERS SELECTION … 11-98 11-221. TEMPORARY WIRE AND CABLE MARKING PROCEDURE … 11-103 11-222. MARKER SLEEVE INSTALLATION AFTER PRINTING … 11-103 11-223.–11-229. [RESERVED.] … 11-104
SECTION 17. CONNECTORS … 11-105
11-230. GENERAL … 11-105 11-231. SELECTION … 11-105 11-232. TYPES OF CONNECTORS … 11-105 11-233. VOLTAGE AND CURRENT RATING … 11-111 11-234. SPARE CONTACTS (FUTURE WIRING) … 11-111
Page xxiv
11-235. INSTALLATION … 11-112 11-236. FEED-THROUGH BULKHEAD WIRE PROTECTION … 11-113 11-237. SPECIAL PURPOSE CONNECTOR … 11-113 11-238. POTTING COMPOUNDS … 11-113 11-239. POTTING CONNECTORS … 11-113 11-240. THROUGH BOLTS … 11-114 11-241.–11-247. [RESERVED.] … 11-114
SECTION 18. CONDUITS … 11-115
11-248. GENERAL … 11-115 11-249. SIZE OF CONDUIT … 11-115 11-250. CONDUIT FITTINGS … 11-115 11-251. CONDUIT INSTALLATION … 11-115 11-252. RIGID CONDUIT … 11-115 11-253. FLEXIBLE CONDUIT … 11-116 11-254.–11-259. [RESERVED.] … 11-117
SECTION 19. UNUSED CONNECTORS AND UNUSED WIRES … 11-118
11-260. GENERAL … 11-118 11-261. QUICK REFERENCE CHART … 11-118 11-262. UNPRESSURIZED AREA CONNECTORS … 11-118 11-263. PRESSURIZED AREAS … 11-120 11-264.–11-270. [RESERVED.] … 11-120
SECTION 20. ELECTRICAL AND ELECTRONIC SYMBOLS … 11-121
11-271. GENERAL … 11-121 11-272. SYMBOLS … 11-121 11-273.–11-283. [RESERVED.] … 11-134
CHAPTER 12. AIRCRAFT AVIONICS SYSTEMS … 12-1
SECTION 1. AVIONICS EQUIPMENT MAINTENANCE … 12-1
12-1. GENERAL … 12-1 12-2. HANDLING OF COMPONENTS … 12-1 12-3.–12-7. [RESERVED.] … 12-1
SECTION 2. GROUND OPERATIONAL CHECKS FOR AVIONICS EQUIPMENT
(ELECTRICAL) … 12-2
12-8. GENERAL … 12-2 12-9. INSPECTION OF AVIONICS SYSTEMS … 12-2 12-10. COMMUNICATION SYSTEMS … 12-4 12-11. VHF OMNI-DIRECTIONAL RANGE (VOR) … 12-4 12-12. DISTANCE MEASURING EQUIPMENT (DME) … 12-4
Page xxv
12-13. AUTOMATIC DIRECTION FINDER (ADF) … 12-5 12-14. INSTRUMENT LANDING SYSTEMS (ILS) … 12-5 12-15. MARKER BEACON … 12-6 12-16. LONG RANGE NAVIGATION (LORAN) … 12-6 12-17. GLOBAL POSITIONING SYSTEM (GPS) … 12-6 12-18. AUTOPILOT SYSTEMS … 12-6 12-19. ALTIMETERS … 12-7 12-20. TRANSPONDERS … 12-7 12-21. AUTOMATIC DEPENDENT SURVEILLANCE-BROADCAST (ADS-B) … 12-8 12-22. EMERGENCY LOCATOR TRANSMITTERS (ELT) … 12-8 12-23. INSPECTION OF ELT … 12-8 12-24. FLIGHT DATA RECORDER (FDR) … 12-9 12-25. COCKPIT VOICE RECORDERS (CVR) … 12-10 12-26. WEATHER RADAR … 12-11 12-27. RADOME INSPECTION … 12-11 12-28. DATABUS … 12-11 12-29. ELECTRIC COMPATIBILITY … 12-11 12-30.–12-36. [RESERVED.] … 12-12
SECTION 3. GROUND OPERATIONAL CHECKS FOR AVIONICS EQUIPMENT
(NON-ELECTRICAL) … 12-13
12-37. COMPASS SWING … 12-13 12-38. PNEUMATIC GYROS … 12-15 12-39.–12-50. [RESERVED.] … 12-18
SECTION 4. PITOT/STATIC SYSTEMS … 12-19
12-51. GENERAL … 12-19 12-52. SYSTEM COMPONENTS … 12-19 12-53. PITOT/STATIC TUBES AND LINES … 12-19 12-54. STATIC PORTS AND VENTS … 12-20 12-55. HEATER ELEMENTS … 12-20 12-56. SYSTEM INSPECTION … 12-21 12-57. SYSTEM LEAK TEST … 12-21 12-58. STATIC SYSTEM TESTS … 12-21 12-59. TEST PITOT SYSTEM … 12-22 12-60. MAINTENANCE PRECAUTIONS … 12-22 12-61. REPLACING LINES … 12-23 12-62. RELOCATION OF PITOT TUBE … 12-23 12-63. TROUBLESHOOTING THE PITOT/STATIC PRESSURE SYSTEM … 12-23 12-64.–12-69. [RESERVED.] … 12-24
SECTION 5. AVIONICS TEST EQUIPMENT … 12-25
12-70. GENERAL … 12-25 12-71. TEST EQUIPMENT CALIBRATION STANDARDS … 12-25
Page xxvi
12-72.–12-83. [RESERVED.] … 12-26
CHAPTER 13. HUMAN FACTORS … 13-1
13-1. HUMAN FACTORS INFLUENCE ON MECHANIC’S PERFORMANCE … 13-1 13-2. THE FAA AVIATION SAFETY PROGRAM … 13-1
APPENDIX 1. GLOSSARY … 1 APPENDIX 2. ACRONYMS AND ABBREVIATIONS … 1 APPENDIX 3. METRIC-BASED PREFIXES AND POWERS OF 10 … 1
LIST OF FIGURES
Figure 1-1. Relative shrinkage of wood members due to drying … 1-5 Figure 1-2. Tapering of faceplate … 1-5 Figure 1-3. Likely areas to incur structural damage … 1-15 Figure 1-4. Consideration of grain direction when making scarf joints … 1-17 Figure 1-5. Method of splicing solid or laminated rectangular spars … 1-18 Figure 1-6. Method of splicing solid “I” spars … 1-19 Figure 1-7. Repairs to built-up “I” spar … 1-20 Figure 1-8. Method of splicing box spar flanges (plate method) … 1-21 Figure 1-9. Method of splicing box spar webs … 1-22 Figure 1-10. Method of reinforcing a longitudinal crack and/or local damage in a solid spar … 1-24 Figure 1-11. Repair of wood ribs … 1-26 Figure 1-12. Typical wing compression rib repairs … 1-28 Figure 1-13. Splayed patch … 1-30 Figure 1-14. Surface patches … 1-32 Figure 1-15. Scarf patches (back of skin accessible) … 1-33 Figure 1-16. Scarf patches (back of skin not accessible) … 1-34 Figure 1-17. Oval plug patch assembly … 1-36 Figure 1-18. Round plug patch assembly … 1-37 Figure 2-1. Fabric seams … 2-7 Figure 2-2.
Figure 1-1 · page 26Picture of the page from the copy saved here
Typical methods of attaching fabric … 2-8 Figure 2-3. Exploded side view of rib … 2-11 Figure 2-4. Standard external modified seine knot used for single and double rib lacing … 2-12 Figure 2-5. Starting stitch for rib lacing … 2-13 Figure 2-6. Standard single-loop lacing … 2-14 Figure 2-7. Standard knot for double-loop lacing … 2-15 Figure 2-8. Standard double-loop lacing (optional) … 2-16 Figure 2-9a. Alternate sequence to tie a modified seine knot for rib lacing … 2-17 Figure 2-9b. Alternate sequence to tie a modified seine knot for rib lacing … 2-18 Figure 2-9c. Alternate sequence to tie a modified seine knot for rib lacing … 2-19 Figure 2-10. Splice knot … 2-20 Figure 2-11. Blindstitch lacing square knot secured with half hitches … 2-21 Figure 2-12. Fabric attachment spacing … 2-23
Page xxvii
Figure 2-3 · page 26Picture of the page from the copy saved here
Figure 2-13. Repair of tears in fabric … 2-39 Figure 2-14. Hand-stitch detail … 2-40 Figure 3-1. Typical laminate (facing) repair … 3-2 Figure 3-2. Typical core and facing repair … 3-3 Figure 3-3. Typical stepped joint repair … 3-3 Figure 3-4. Preparing the fiberglass sandwich … 3-5 Figure 3-5. Scarfed repair to a nonstructural laminated fiberglass component … 3-6 Figure 3-6. Symmetrical layup same as original number of plies, plus one extra ply … 3-7 Figure 3-7. Typical scarf joint repair … 3-8 Figure 3-8. Carefully cut through each layer of fiberglass cloth and remove it from the damaged area … 3-9 Figure 3-9. Sample bagging layup cross-section … 3-10 Figure 3-10. Typical types of core replacement … 3-14 Figure 3-11. Typical undercut core material cavity … 3-15 Figure 3-12. Cross-section of bonded and bolted overlap repairs … 3-15 Figure 3-13. Honeycomb core removal … 3-16 Figure 3-14 Removing honeycomb core from a tapered control surface … 3-16 Figure 3-15. Removal of core with core knife … 3-17 Figure 3-16. Details of core repair … 3-18 Figure 3-17.
Figure 2-13 · page 27Picture of the page from the copy saved here
Hanging of acrylic sheets … 3-21 Figure 3-18. Drill having an included angle of approximately 150º, used to drill acrylic plastics … 3-24 Figure 3-19. Unibit drill for drilling acrylic plastics … 3-24 Figure 3-20. Applying pressure to acrylic plastics … 3-25 Figure 3-21. Stop-drilling cracks … 3-26 Figure 3-22. Surface patches … 3-27 Figure 3-23. Plug patch repair … 3-28 Figure 3-24. Temporary repairs to cracked windshields or windows … 3-31 Figure 4-1. Comparison of indentation made by Knoop and Vickers indenters in the same work metal and at the same loads … 4-10 Figure 4-2. Setback for a 90-degree bend … 4-17 Figure 4-3. Methods of determining setback for bends other than 90 degrees … 4-19 Figure 4-4. Rivet identification and part number breakdown … 4-21 Figure 4-5. Rivet hole spacing and edge distance for single-lap sheet splices … 4-25 Figure 4-6. Riveting practice and rivet imperfections … 4-26 Figure 4-7. Self-plugging friction-lock cherry rivets … 4-27 Figure 4-8. Mechanical-lock (Bulbed CherryLOCK) cherry rivet … 4-29 Figure 4-9. CherryMAX rivet … 4-30 Figure 4-10.
Figure 3-18 · page 27Picture of the page from the copy saved here
Olympic-Lok rivet … 4-31 Figure 4-11. Huck rivet … 4-32 Figure 4-12. Typical repair method for tubular members of aluminum alloy … 4-34 Figure 4-13. Typical repair for buckled or cracked metal wing rib cap strips … 4-36 Figure 4-14. Typical metal rib repairs … 4-37 Figure 4-15. Typical repairs of trailing edges … 4-38 Figure 4-16. Typical repairs of stressed sheet metal coverings … 4-39 Figure 4-17. Typical stringer and flange splices … 4-44
Page xxviii
Figure 4-11 · page 27Picture of the page from the copy saved here
Figure 4-18. Example of stringer splice (material: 2017 alloy) … 4-45 Figure 4-19. Application of typical flange splices and reinforcement … 4-46 Figure 4-20. Example of intermediate frame stringer splice (material: 2017-T3 AL alloy) … 4-50 Figure 4-21. Typical methods of repairing cracked leading and trailing edges and rib intersections … 4-51 Figure 4-22. Typical methods of replacing cracked members at fittings … 4-52 Figure 4-23. Typical methods of repairing cracked frame and stiffener combination … 4-53 Figure 4-24. Typical repairs to rudder and to fuselage at tail post … 4-54 Figure 4-25. Typical methods of repairing elongated or worn bolt holes … 4-56 Figure 4-26. Common defects to avoid when fitting and welding aircraft certification cluster … 4-66 Figure 4-27. Lap weld strength calculation … 4-67 Figure 4-28. Basic gas-welding flames: each has a distinctive shape, color, and sound; neutral flame is the most used … 4-68 Figure 4-29. Set TIG welder to DC current, straight polarity for welding mild steel, stainless steel, and titanium … 4-69 Figure 4-30.
Figure 4-18 · page 28Picture of the page from the copy saved here
Set TIG to AC current for welding aluminum and magnesium … 4-70 Figure 4-31. In spot welding, heat is produced by electrical resistance between copper electrodes; pressure is simultaneously applied to electrode tips to force metal together to complete fusing process; spot-weld nugget size is directly related to tip size … 4-71 Figure 4-32. Silver brazing joints … 4-73 Figure 4-33. Electric soldering iron … 4-74 Figure 4-34. Finger patch repairs for members dented at a cluster … 4-77 Figure 4-35. Members dented in a bay (repairs by welded sleeve) … 4-78 Figure 4-36. Welded-patch repair … 4-79 Figure 4-37. Splicing by inner-sleeve method … 4-81 Figure 4-38. Splicing by outer-sleeve method (replacement by welded outside sleeve) .... 4-82 Figure 4-39. Tube replacement at a station by welded outer sleeves … 4-83 Figure 4-40. Splicing using larger diameter replacement tube … 4-84 Figure 4-41. Repairs at built-in fuselage fittings … 4-85 Figure 4-42. Streamline tube splice using round tube (applicable to landing gear) … 4-87 Figure 4-43.
Figure 4-31 · page 28Picture of the page from the copy saved here
Streamline tube splice using split sleeve (applicable to wing and tail surface brace struts and other members) … 4-88 Figure 4-44. Streamline tube splice using split insert (applicable to landing gear) … 4-89 Figure 4-45. Streamline tube splice using plates (applicable to landing gear) … 4-90 Figure 4-46. Representative types of repairable axle assemblies … 4-91 Figure 4-47. Landing gear assemblies that cannot be repaired by welding … 4-92 Figure 5-1. Typical borescope designs … 5-11 Figure 5-2. Using a flashlight to inspect for cracks … 5-13 Figure 5-3. Generating an eddy current … 5-14 Figure 5-4. Detecting an eddy current … 5-15 Figure 5-5. Typical instrument displays … 5-15 Figure 5-6. Typical surface cracks … 5-16 Figure 5-7. Typical subsurface cracks … 5-17
Page xxix
Figure 4-44 · page 28Picture of the page from the copy saved here
Figure 5-8. Typical structural corrosion … 5-18 Figure 5-9. Magnetic field disrupted … 5-20 Figure 5-10. Crack detection by magnetic particle inspection … 5-20 Figure 5-11. Circular magnetization … 5-26 Figure 5-12. Longitudinal magnetization … 5-27 Figure 5-13. Penetrant and developer action … 5-33 Figure 5-14. Radiography … 5-40 Figure 5-15. Ultrasound … 5-43 Figure 5-16. Pulse-echo and through-transmission ultrasonic inspection techniques … 5-44 Figure 5-17. Typical portable ultrasonic inspection instrument … 5-45 Figure 5-18. Example of position fixture and shoe … 5-46 Figure 5-19. Example of the use of a transducer positioning fixture … 5-46 Figure 5-20. Example of a typical reference standard … 5-47 Figure 5-21. Examples of bonded structure configurations and suggested inspection coverage … 5-50 Figure 5-22. Sample of special tap hammer … 5-55 Figure 6-1. Simplified corrosion cell showing conditions which must exist for electrochemical corrosion … 6-1 Figure 6-2. Elimination of corrosion by application of an organic film to metal surface … 6-2 Figure 6-3.
Figure 5-8 · page 29Picture of the page from the copy saved here
Corrosion attack … 6-5 Figure 6-4. General surface corrosion … 6-5 Figure 6-5a. Pitting corrosion (external view) … 6-6 Figure 6-5b. Pitting corrosion (magnified cross-section) … 6-6 Figure 6-6. Concentration cell corrosion … 6-7 Figure 6-7. Active-passive cell … 6-8 Figure 6-8. Filiform corrosion … 6-8 Figure 6-9. Intergranular corrosion of 7075-T6 aluminum adjacent to steel fastener … 6-9 Figure 6-10. Exfoliation corrosion … 6-10 Figure 6-11. Galvanic corrosion of magnesium adjacent to steel fastener … 6-10 Figure 6-12. Stress corrosion cracking … 6-11 Figure 6-13. Fretting corrosion … 6-13 Figure 6-14. Typical example of acceptable cleanup of corrosion pits … 6-26 Figure 6-15. Blendout of corrosion as a single depression … 6-27 Figure 6-16. Blendout of multiple pits in a corroded area … 6-28 Figure 7-1. Typical aircraft bolt markings … 7-6 Figure 7-2. Torque wrench with various adapters … 7-8 Figure 7-3. Securing screws, nuts, bolts, and snaprings … 7-19 Figure 7-3a. Wire twisting by hand … 7-19 Figure 7-4. Use of a typical wire twister … 7-21 Figure 7-4a.
Figure 6-4 · page 29Picture of the page from the copy saved here
Securing oil caps, drain cocks, and valves … 7-22 Figure 7-5. Safety-wiring procedures … 7-23 Figure 7-5a. Safety-wiring procedures … 7-24 Figure 7-5b. Safety-wiring procedures … 7-25 Figure 7-6. Securing with cotter pins … 7-26
Page xxx
Figure 7-7. Alternate method for securing with cotter pins … 7-26 Figure 7-8. Flexible cable cross-section … 7-29 Figure 7-9. Nonflexible cable cross-section … 7-31 Figure 7-10. Insertion of cable into terminal … 7-33 Figure 7-11. Gauging terminal shank after swaging … 7-34 Figure 7-12. Typical cable splices … 7-34 Figure 7-13. Typical terminal gauge … 7-35 Figure 7-14. Typical thimble-eye splice … 7-38 Figure 7-15. Typical terminal gauge … 7-38 Figure 7-16. Cable inspection technique … 7-40 Figure 7-17. Cable wear patterns … 7-41 Figure 7-18. Worn cable (replacement necessary) … 7-42 Figure 7-19. Internal end view of cable wear … 7-42 Figure 7-20. Pulley wear patterns … 7-44 Figure 7-21. Corrosion … 7-45 Figure 7-22. Manufacturer’s wire splice … 7-45 Figure 7-23. Turnbuckle thread tolerance … 7-47 Figure 7-24. Safetying turnbuckles … 7-49 Figure 7-25. Securing turnbuckles … 7-51 Figure 7-26. Clip-type locking device … 7-52 Figure 7-27. Assembling and securing clip-locking turnbuckles … 7-53 Figure 8-1. Schematic of differential pressure compression tester … 8-9 Figure 8-2.
Figure 7-5 · page 29Picture of the page from the copy saved here
Chart of spark plug temperature ranges … 8-11 Figure 8-3. Hot and cold spark plugs … 8-12 Figure 8-4. Spark plug reach … 8-13 Figure 8-5. Method of checking spark plug gap … 8-13 Figure 8-6. Typical carbon-fouled spark plug … 8-15 Figure 8-6a. Typical lead-fouled spark plug … 8-15 Figure 8-6b. Typical oil-fouled spark plug … 8-16 Figure 8-6c. Typical spark plug with cracked core nose … 8-17 Figure 8-6d. Typical worn out spark plug … 8-17 Figure 8-6e. Typical spark plug with bridged electrodes … 8-18 Figure 8-7. Spark plug well flashover … 8-19 Figure 8-8. Typical method of clamping leads … 8-20 Figure 8-9. Normal contact point … 8-21 Figure 8-10. Point with minor irregularities … 8-21 Figure 8-11. Point with well-defined mound … 8-21 Figure 8-12. Location of clamps at tube bends … 8-24 Figure 8-13. Typical muffler wall fatigue failure at exhaust outlet. (A. Complete muffler assembly with heat shroud removed; B. Detail view of failure) … 8-28 Figure 8-14. Typical muffler wall failure.
Figure 8-3 · page 30Picture of the page from the copy saved here
(A. Complete muffler assembly with heat shroud removed; B. Detail view of failure; C. Cross-section of failed muffler) … 8-29 Figure 8-15. Typical muffler wall fatigue failure. (A. Complete muffler assembly with heat shroud partially removed; B. Detailed view of failure) … 8-30 Figure 8-16. Typical fatigue failure of muffler end plate at stack inlet … 8-30
Page xxxi
Figure 8-15 · page 30Picture of the page from the copy saved here
Figure 8-17. Section of a muffler showing typical internal baffle failure … 8-31 Figure 8-18. Loose pieces of a failed internal baffle … 8-31 Figure 8-19. Failed internal baffle partially obstructing the muffler outlet … 8-32 Figure 8-20 Failed internal baffle completely obstructing the muffler outlet … 8-32 Figure 8-21a. Example of exhaust outlet guard … 8-33 Figure 8-21b. Example of exhaust outlet guard installed … 8-33 Figure 8-22. Effect of improperly positioned exhaust pipe/muffler clamp … 8-34 Figure 8-23. Primary inspection areas … 8-35 Figure 8-24. Method of repairing surface scratches, nicks, etc., on aluminum-alloy propellers … 8-38 Figure 8-25. Correct and incorrect method of reworking leading edge of aluminum-alloy propellers … 8-38 Figure 8-26. Method of repairing damaged tip of aluminum-alloy propellers … 8-39 Figure 8-27. Example 1: Determine the repair width limits … 8-40 Figure 8-28. Example 2: Determine the repair thickness limits … 8-41 Figure 8-29. Repair of fixed-pitch hub and propeller with elongated or damaged bolt holes … 8-43 Figure 8-30.
Figure 8-17 · page 31Picture of the page from the copy saved here
Propeller tracking (wood block or cowling fixture shown) … 8-50 Figure 9-1. A typical ski installation … 9-7 Figure 9-2. Typical bolt cracks … 9-9 Figure 9-3. Typical cracks near bolt holes … 9-10 Figure 9-4. Typical bolt hole cracks … 9-10 Figure 9-5. Typical rod-end cracks … 9-10 Figure 9-6. Typical torque tube bolt hole elongation … 9-11 Figure 9-7. Examples of tread wear indicating overinflation and underinflation … 9-13 Figure 9-8. Hose assembly instructions (can be used for low-pressure hydraulic fluid, and oil line applications) … 9-25 Figure 9-9. Proper hose installations … 9-28 Figure 9-10. Minimum bend radii … 9-29 Figure 9-11. Suggested handling of preformed hose … 9-31 Figure 9-12. Minimum bend radii–Teflon hose … 9-32 Figure 9-13. Inflation valve … 9-37 Figure 9-14. Repair dimensions … 9-43 Figure 9-15. Oxygen cylinder damage … 9-49 Figure 9-16. Cylinder brackets and clamps … 9-50 Figure 10-1. Typical datum locations … 10-2 Figure 10-2. Illustration of arm (or moment arm) … 10-3 Figure 10-3. Example of moment computation … 10-3 Figure 10-4.
Figure 9-1 · page 31Picture of the page from the copy saved here
Empty weight center of gravity formulas … 10-4 Figure 10-5. Empty weight and empty weight center of gravity tailwheel type aircraft … 10-5 Figure 10-6. Empty weight and empty weight center of gravity nosewheel type aircraft … 10-6 Figure 10-7. Operating center of gravity range … 10-7 Figure 10-8. Weighing point center line … 10-8 Figure 10-9. Empty weight and empty weight center of gravity when aircraft is weighed with oil … 10-11
Page xxxii
Figure 10-5 · page 31Picture of the page from the copy saved here
Figure 10-10. Example of check of most forward weight and balance extreme … 10-14 Figure 10-11. Example of check of most rearward weight and balance extreme … 10-15 Figure 10-12. Loading conditions: determination of the number of passengers and baggage permissible with full fuel … 10-17 Figure 10-13. Loading conditions: determination of the fuel and baggage permissible with maximum passengers … 10-18 Figure 10-14. Loading conditions: determination of the fuel and the number and location of passengers permissible with maximum baggage … 10-19 Figure 10-15. Effects of the addition of equipment items on balance … 10-20 Figure 10-16. Example of moment and weight changes resulting from equipment changes … 10-21 Figure 10-17. Sample weight and balance report to determine empty weight center of gravity … 10-22 Figure 10-18. Sample weight and balance report including an equipment change for aircraft fully loaded … 10-23 Figure 10-19. Permanent ballast computation formula … 10-24 Figure 11-1. Battery ventilating systems … 11-11 Figure 11-2. Conductor chart, continuous flow … 11-35 Figure 11-3.
Figure 10-10 · page 32Picture of the page from the copy saved here
Conductor chart, intermittent flow … 11-36 Figure 11-4a. Single copper wire in free air … 11-37 Figure 11-4b. Single copper wire in free air … 11-38 Figure 11-5. Bundle derating curves … 11-39 Figure 11-6. Altitude derating curve … 11-40 Figure 11-7. Group and bundle ties … 11-58 Figure 11-8. Comb for straightening wires in bundles … 11-59 Figure 11-9a. Slack between supports … 11-60 Figure 11-9b. Drainage hole in low point of tubing … 11-61 Figure 11-10. Separation of wires from plumbing lines … 11-63 Figure 11-11. Safe angle for cable clamps … 11-67 Figure 11-12. Typical mounting hardware for AS21919 cable clamps … 11-67 Figure 11-13. Installing cable clamp to structure … 11-68 Figure 11-14. Clamping at a bulkhead hole … 11-69 Figure 11-15. Single cord lacing … 11-72 Figure 11-16. Double cord lacing … 11-73 Figure 11-17. Making ties … 11-74 Figure 11-18. Staggered splices in wire bundle … 11-75 Figure 11-19. Millivolt drop test … 11-83 Figure 11-20. Copper jumper connector to tubular structure … 11-88 Figure 11-21. Bonding conduit to structure … 11-88 Figure 11-22.
Figure 11-4a · page 32Picture of the page from the copy saved here
Aluminum jumper connection to tubular structure … 11-88 Figure 11-23. Spacing of printed identification marks (direct marking) … 11-93 Figure 11-24. Spacing of printed identification marks (indirect marking) … 11-93 Figure 11-25. Identification of wire bundles and harnesses … 11-97 Figure 11-26. Standard sleeves (135 ºC) … 11-97 Figure 11-27. Installation of heat-shrinkable insulation sleeves … 11-98 Figure 11-28. Cable markers … 11-99
Page xxxiii
Figure 11-23 · page 32Picture of the page from the copy saved here
Figure 11-29. Tie-down strap installation … 11-99 Figure 11-30. Tie-down strap installation tool … 11-102 Figure 11-31. Completed installation … 11-103 Figure 11-32. Temporary wire identification marker … 11-103 Figure 11-33. Inserting wire into marker … 11-104 Figure 11-34. Shrinking marker on wire … 11-104 Figure 11-35. Connector information example … 11-107 Figure 11-36. Different types of connectors … 11-108 Figure 11-37. Coax cable connectors … 11-109 Figure 11-38. Spare wires for potting connector … 11-114 Figure 11-39. Stub wire installation … 11-119 Figure 11-40. Sealing unused contact cavities—unpressurized areas (cut-away view) .... 11-120 Figure 12-1. Venturi system for providing airflow through gyro instruments … 12-15 Figure 12-2. Instrument vacuum system using a wet-type vacuum pump … 12-16 Figure 12-3. Instrument vacuum system using a dry-type air pump … 12-18 Figure 12-4. Instrument pressure system using a dry-type air pump … 12-18 Figure 12-5. Pitot/static system for a small aircraft … 12-19 Figure 12-6. Pitot/static tube head … 12-20 Figure 13-1. Personal minimums checklist … 13-2
Figure 11-29 · page 33Picture of the page from the copy saved here
LIST OF TABLES
Table 1-1. Selection and properties of aircraft wood … 1-2 Table 1-2. Minimum recommended bend radii for aircraft plywood … 1-29 Table 2-1. Cotton and linen fabrics … 2-2 Table 2-2. Cotton and linen, tapes and threads … 2-4 Table 2-3. Safety tips for dope/paint … 2-28 Table 2-4. Tips for doping … 2-28 Table 3-1. Typical temperatures for forming acrylic sheets … 3-23 Table 4-1. Ferrous (iron) alloy materials … 4-1 Table 4-2. Numerical system for steel identification … 4-2 Table 4-3. Examples of stainless and heat-resistant steels nominal composition (percent) … 4-3 Table 4-4. Basic temper designations and subdivisions from aluminum alloys … 4-4 Table 4-5. Hardness values for aluminum alloys … 4-7 Table 4-6. Recommended radii for 90-degree bends in aluminum alloys … 4-17 Table 4-7. K-chart for determining setback for bends other than 90 degrees … 4-18 Table 4-8. Aircraft rivet identification … 4-22 Table 4-9. Number of rivets required for splices (single-lap joint) in bare 2014-T6, 2024-T3, 2024-T36, and 7075-T6 sheet, clad 2014-T6, 2024-T3, 2024-T36, and 7075-T6 sheet, 2024-T4, and 7075-T6 plate, bar, rod, tube, and extrusions, 2014-T6 extrusions … 4-41 Table 4-10. Number of rivets required for splices (single-lap joint) in 2017, 1017 alclad, 2024-T3 alclad sheet, plate, bar, rod, tube, and extrusions … 4-42 Table 4-11. Number of rivets required for splices (single-lap joint) in 5052 (all hardnesses) sheet … 4-48 Table 4-12. Current and polarity selection for inert gas welding … 4-64
Page xxxiv
Table 4-13. Torch tip sizes … 4-66 Table 4-14. Calculated allowable strength of base metal … 4-72 Table 4-15. Chart showing welding filler rod selection … 4-76 Table 5-1. Advantages and disadvantages of NDI methods … 5-7 Table 5-2. Listing of commonly accepted standards and specifications for magnetic particle inspection … 5-23 Table 5-3. Classification of penetrant inspection materials covered by MIL-I-25135E … 5-34 Table 5-4. Fluorescent and visible penetrant inspection general processing procedures flowsheet … 5-35 Table 5-5. Pre-cleaning methods for penetrant inspection … 5-36 Table 5-6. Listing of commonly accepted standards and specifications for penetrant inspection … 5-38 Table 5-7. Acceptable ultrasonic inspection methods associated with the example bonded structure configurations shown in Figure 5-21 … 5-51 Table 5-8. Ultrasonic inspection methods for bonded structures … 5-52 Table 6-1. Abrasives for corrosion removal … 6-25 Table 7-1. Recommended torque values (inch-pounds) … 7-9 Table 7-2. Minimum prevailing torque values for reused self-locking nuts … 7-13 Table 7-3.
Flexible cable construction and physical properties … 7-27 Table 7-4. Nonflexible cable construction and physical properties … 7-30 Table 7-5. Straight-shank terminal dimensions … 7-32 Table 7-6. Copper oval sleeve data … 7-36 Table 7-7. Copper stop sleeve data … 7-37 Table 7-8. Turnbuckle safetying guide … 7-51 Table 7-9. Locking-clip application … 7-53 Table 7-10. Table of rivets … 7-54 Table 7-11. Table of screws … 7-56 Table 7-12. Table of bolts … 7-64 Table 7-13. Table of nuts … 7-71 Table 7-14. Table of washers … 7-78 Table 7-15. Table of pins … 7-81 Table 8-1. Current engine and maximum permissible cylinder barrel oversize … 8-6 Table 8-2. Sample manufacturer’s propeller inspection checklist … 8-45 Table 9-1. Bungee cord color codes … 9-2 Table 9-2. Tube data … 9-23 Table 9-3. Aircraft hose specifications … 9-26 Table 9-4. Ball diameters for testing hose restrictions or kinking … 9-30 Table 9-5. Table of filling pressures … 9-55 Table 11-1. ASTM consensus standards … 11-3 Table 11-2. Lead-acid battery electrolyte freezing points … 11-6 Table 11-3.
Sulfuric acid temperature correction … 11-7 Table 11-4. DC wire and circuit protector chart … 11-17 Table 11-5. Switch derating factors … 11-19 Table 11-6. Selection of contact material … 11-20
Page xxxv
Table 11-7. Tabulation chart (allowable voltage drop between bus and utilization equipment ground) … 11-24 Table 11-8. Examples of determining required tin-plated copper wire size and checking voltage drop using Figure 11-2 … 11-25 Table 11-9. Examples of determining maximum tin-plated copper wire length and checking voltage drop using Figure 11-2 … 11-25 Table 11-10. Current carrying capacity and resistance of copper wire … 11-27 Table 11-11. Current carrying capacity and resistance of aluminum wire … 11-28 Table 11-12. Comparable properties of wire insulation systems … 11-43 Table 11-13. Open wiring … 11-44 Table 11-14. Protected wiring … 11-46 Table 11-15. Allowable nicked or broken strands … 11-71 Table 11-16. Stud bonding or grounding to flat surface … 11-85 Table 11-17. Plate nut bonding or grounding to flat surface … 11-86 Table 11-18. Bolt and nut bonding or grounding to flat surface … 11-87 Table 11-19. Recommended size of identification sleeving … 11-96 Table 11-20. Selection table for standard sleeves … 11-100 Table 11-21. Selection table for thin-wall sleeves … 11-100 Table 11-22. Selection table for high-temperature sleeves … 11-101 Table 11-23. Selection table for cable markers … 11-101 Table 11-24. Plastic tie-down straps (MS3367, Type I, Class 1) … 11-102 Table 11-25. Bend radii for rigid conduit … 11-116 Table 11-26. Minimum bending radii for flexible aluminum or brass conduit … 11-117 Table 11-27. Contact cavity sealing-quick reference … 11-118 Table 11-28. Sealing rod dimensions … 11-120 Table 11-29. Electronic/electrical symbols … 11-121 Table 12-1. Color codes for pitot-static systems … 12-24
Figure 11-2 · page 32Picture of the page from the copy saved here
1-2. WOODS. › b. Substitution of Original Wood. The wood species used to repair a…
CHAPTER 1. WOOD STRUCTURE
SECTION 1. MATERIALS AND PRACTICES
1-1. GENERAL. Wood aircraft construction dates back to the early days of certificated aircraft. Today only a limited number of wood aircraft structures are produced. However, many of the older airframes remain in service. With proper care, airframes from the 1930s through the 1950s have held up remarkably well considering the state of technology and long-term experience available at that time. It is the responsibility of the mechanic to carefully inspect such structures for deterioration and continuing airworthiness.
1-2. WOODS.
a. Quality of Wood. All wood and plywood used in the repair of aircraft structures should be of aircraft quality (refer to Air Force Navy Commerce Department Bulletin ANC-19, Wood Aircraft Inspection and Fabrication). Table 1-1 lists some permissible variations in characteristics and properties of aircraft wood. However, selection and approval of woodstock for aircraft structural use are specialized skills and should be done by personnel who are thoroughly familiar with inspection criteria and methods.
b. Substitution of Original Wood. The wood species used to repair a part should be the same as that of the original whenever possible; however, some permissible substitutes are given in Table 1-1. Obtain approval from the airframe manufacturer or the Federal Aviation Administration (FAA) for the replacement of modified woods or other nonwood products with a substitute material.
TABLE 1-1. SELECTION AND PROPERTIES OF AIRCRAFT WOOD
(See notes following table)
Species of Wood
Strength properties
as compared to
spruce
Maximum permissible grain
deviation (slope of grain)
Remarks
1. 2. 3. 4.
Spruce (Picea) Sitka (P. Sitchensis)
Red (P. Rubra) White (P. Glauca).
100% 1:15
Excellent for all uses. Considered as standard for this table.
Douglas Fir (Pseudotsuga Taxifolia). Exceeds spruce. 1:15
May be used as substitute for spruce in same sizes or in slightly reduced sizes providing reductions are substantiated. Difficult to work with hand tools. Some tendency to split and splinter during fabrication and considerable more care in manufacture is necessary. Large solid pieces should be avoided due to inspection difficulties. Gluing satisfactory.
Noble Fir (Abies Nobiles).
Slightly exceeds
spruce except 8% deficient in shear.
1:15
Satisfactory characteristics with respect to workability, warping, and splitting. May be used as direct substitute for spruce in same sizes providing shear does not become critical. Hardness somewhat less than spruce. Gluing satisfactory.
Western Hemlock (Tsuga Heterpphylla).
Slightly exceeds
spruce. 1:15
Less uniform in texture than spruce. May be used as direct substitute for spruce. Upland growth superior to lowland growth. Gluing satisfactory.
Pine, Northern White
(Pinus Strobus).
Properties between 85% and 96% those of spruce.
1:15
Excellent working qualities and uniform in properties, but somewhat low in hardness and shock-resisting capacity. Cannot be used as substitute for spruce without increase in sizes to compensate for lesser strength. Gluing satisfactory.
Species of Wood
Strength properties
as compared to
spruce
Maximum permissible grain
deviation (slope of grain)
Remarks
White Cedar, Port
Orford (Charaecyparis
Lawsoniana).
Exceeds spruce. 1:15
May be used as substitute for spruce in same sizes or in slightly reduced sizes providing reductions are substantiated. Easy to work with hand tools. Gluing difficult, but satisfactory joints can be obtained if suitable precautions are taken.
Poplar, Yellow
(Liriodendrow
Tulipifera).
Slightly less than
spruce except in
compression (crushing) and shear.
1:15
Excellent working qualities. Should not be used as a direct substitute for spruce without carefully accounting for slightly reduced strength properties. Somewhat low in shock-resisting capacity. Gluing satisfactory. Notes for Table 1-1 1. Defects Permitted. a. Cross grain. Spiral grain, diagonal grain, or a combination of the two is acceptable providing the grain does not diverge from the longitudinal axis of the material more than specified in column 3. A check of all four faces of the board is necessary to determine the amount of divergence. The direction of free-flowing ink will frequently assist in determining grain direction. b. Wavy, curly, and interlocked grain. Acceptable, if local irregularities do not exceed limitations specified for spiral and diagonal grain. c. Hard knots.
Sound, hard knots up to 3/8 inch in maximum diameter are acceptable providing: (1) they are not projecting portions of I-beams, along the edges of rectangular or beveled unrouted beams, or along the edges of flanges of box beams (except in lowly stressed portions); (2) they do not cause grain divergence at the edges of the board or in the flanges of a beam more than specified in column 3; and (3) they are in the center third of the beam and are not closer than 20 inches to another knot or other defect (pertains to 3/8 inch knots—smaller knots may be proportionately closer). Knots greater than 1/4 inch must be used with caution. d. Pin knot clusters. Small clusters are acceptable providing they produce only a small effect on grain direction. e. Pitch pockets.
Acceptable in center portion of a beam providing they are at least 14 inches apart when they lie in the same growth ring and do not exceed 1-1/2 inches length by 1/8 inch width by 1/8 inch depth, and providing they are not along the projecting portions of I-beams, along the edges of rectangular or beveled unrouted beams, or along the edges of the flanges of box beams. f. Mineral streaks. Acceptable, providing careful inspection fails to reveal any decay. 2. Defects Not Permitted. a. Cross grain. Not acceptable, unless within limitations noted in 1a. b. Wavy, curly, and interlocked grain. Not acceptable, unless within limitations noted in 1b. c. Hard knots. Not acceptable, unless within limitations noted in 1c. d. Pin knot clusters. Not acceptable, if they produce large effect on grain direction. e. Spike knots. These are knots running completely through the depth of a beam perpendicular to the annual rings and appear most frequently in quarter-sawed lumber. Reject wood containing this defect.
c. Effects of Shrinkage. When the moisture content of a wooden part is… › (3) Thoroughly seal all wood surfaces, particularly end grain and bolt…
f. Pitch pockets. Not acceptable, unless within limitations noted in 1e. g. Mineral streaks. Not acceptable, if accompanied by decay (see 1f). h. Checks, shakes, and splits. Checks are longitudinal cracks extending, in general, across the annual rings. Shakes are longitudinal cracks usually between two annual rings. Splits are longitudinal cracks induced by artificially induced stress. Reject wood containing these defects. i. Compression wood. This defect is very detrimental to strength and is difficult to recognize readily. It is characterized by high specific gravity, has the appearance of an excessive growth of summer wood, and in most species shows little contrast in color between spring wood and summer wood. In doubtful cases reject the material, or subject samples to toughness machine test to establish the quality of the wood. Reject all material containing compression wood. j. Compression failures.
This defect is caused from the wood being overstressed in compression due to natural forces during the growth of the tree, felling trees on rough or irregular ground, or rough handling of logs or lumber. Compression failures are characterized by a buckling of the fibers that appear as streaks on the surface of the piece substantially at right angles to the grain, and vary from pronounced failures to very fine hairlines that require close inspection to detect. Reject wood containing obvious failures. In doubtful cases reject the wood, or make a further inspection in the form of microscopic examination or toughness test, the latter means being the more reliable. k. Decay. Examine all stains and discoloration carefully to determine whether or not they are harmless, or in a stage of preliminary or advanced decay. All pieces must be free from rot, dote, red heart, purple heart, and all other forms of decay.
c. Effects of Shrinkage. When the moisture content of a wooden part is lowered, the part shrinks. Since the shrinkage is not equal in all directions, the mechanic should consider the effect that the repair may have on the completed structure. The shrinkage is greatest in a tangential direction (across the fibers and parallel to the growth rings), somewhat less in a radial direction (across the fibers and perpendicular to the growth rings), and is negligible in a longitudinal direction (parallel to the fibers). Figure 1-1 illustrates the different grain directions and the effects of shrinkage on the shape of a part. These dimensional changes can have several detrimental effects upon a wood structure, such as loosening of fittings and wire bracing and checking or splitting of wood members. A few suggestions for minimizing these shrinkage effects are:
(1) Use bushings that are slightly short so that when the wood member shrinks the bushings do not protrude and the fittings may be tightened firmly against the member.
(2) Gradually drop off plywood faceplates by feathering as shown in Figure 1-2.
(3) Thoroughly seal all wood surfaces, particularly end grain and bolt holes, with varnish, epoxy, or other acceptable sealer to slow or prevent moisture changes in the member. (See Section 5, Finishing Wood Structures.)
a. Adhesives acceptable to the FAA can be identified in the following… › (2) Adhesives meeting the requirements of a Military Specification…
FIGURE 1-1. RELATIVE SHRINKAGE OF WOOD MEMBERS DUE TO DRYING
FIGURE 1-2. TAPERING OF FACEPLATE
1-3. MODIFIED WOOD PRODUCTS. The most common forms of modified woods found in aircraft construction are plywood. Although not a wood product, Phenolic parts are sometimes incorporated into structures. These products are used whenever the manufacturer requires specialized strength or durability characteristics.
1-4. ADHESIVES. Because of the critical role played by adhesives in aircraft structure, the mechanic must employ only those types of adhesives that meet all of the performance requirements necessary for use in certificated civil aircraft. Use each product strictly in accordance with the aircraft and adhesive manufacturer’s instructions.
a. Adhesives acceptable to the FAA can be identified in the following ways:
(1) Refer to the aircraft maintenance or repair manual for specific instructions on acceptable adhesive selection for use on that type aircraft.
(2) Adhesives meeting the requirements of a Military Specification (MIL-SPEC), Aerospace Material Specification (AMS), or Technical Standard Order (TSO) for wooden aircraft structures are satisfactory providing they are found to be compatible with existing structural materials in the aircraft and the fabrication methods to be used in the repair.
b. Common types of adhesives that are or have been used in aircraft… › (6) Epoxy adhesives are a two-part synthetic resin product and are…
b. Common types of adhesives that are or have been used in aircraft structure fall into two general groups: casein and synthetic-resins. Adhesive technology continues to evolve, and new types (meeting the requirements of paragraph 1-4a) may become available in the future.
(1) Casein adhesive performance is generally considered inferior to other products available today; modern adhesives should be considered first.
CAUTION: Casein adhesive deteriorates over the years after exposure to moisture in the air and temperature variations. Some modern adhesives are incompatible with casein adhesive. If a joint that has previously been bonded with casein is to be rebonded with another type of adhesive, all traces of the casein must be scraped off before the new adhesive is applied. If any casein adhesive is left, residual alkalinity may cause the new adhesive to fail to cure properly.
(2) Synthetic-resin adhesives comprise a broad family which includes plastic resin glue, resorcinol, hot-pressed Phenol, and epoxy.
(3) Plastic resin glue (urea-formaldehyde resin glue) has been used in wood aircraft for many years. Caution should be used due to possible rapid deterioration (more rapidly than wood) of plastic resin glue in hot, moist environments and under cyclic swell-shrink stress. For these reasons, urea-formaldehyde should be considered obsolete for all repairs. Any proposed use of this type adhesive should be discussed with the appropriate FAA office prior to using on certificated aircraft.
(4) Federal Specification MMM-A-181D and Military Specification MIL-A-22397 both describe a required series of tests that verify the chemical and mechanical properties of resorcinol. Resorcinol is the only known adhesive recommended and approved for use in wooden aircraft structure and fully meets necessary strength and durability requirements. Resorcinol adhesive (resorcinol-formaldehyde resin) is a two-part synthetic resin adhesive consisting of resin and a hardener. The appropriate amount of hardener (per manufacturer’s instruction) is added to the resin, and it is stirred until it is uniformly mixed; the adhesive is now ready for immediate use. Quality of fit and proper clamping pressure are both critical to the achievement of full joint strength. The adhesive bond lines must be very thin and uniform in order to achieve full joint strength.
CAUTION: Read and observe material safety data. Be sure to follow the manufacturer’s instructions regarding mixing, open assembly and close assembly times, and usable temperature ranges.
(5) Phenol-formaldehyde adhesive is commonly used in the manufacturing of aircraft grade plywood. This product is cured at elevated temperature and pressure; therefore, it is not practical for use in structural repair.
(6) Epoxy adhesives are a two-part synthetic resin product and are acceptable providing they meet the requirements of paragraph 1-4a. Many new epoxy resin systems appear to have excellent working properties. They have been found to be much less critical of joint quality and clamping pressure. They penetrate well into wood and plywood. However, joint durability in the
1-6. PREPARATION OF WOOD SURFACES FOR BONDING. › a. Roughening smooth, well-planed surfaces of normal wood before…
presence of elevated temperature or moisture is inadequate in many epoxies. The epoxy adhesives generally consist of a resin and a hardener that are mixed together in the proportions specified by the manufacturer. Depending on the type of epoxy, pot life may vary from a few minutes to an hour. Cure times vary between products.
CAUTION: Some epoxies may have unacceptable thermal or other hidden characteristics not obvious in a shop test. It is essential that only those products meeting the requirements of paragraph 1-4a be used in aircraft repair. Do not vary the resin-to-hardener ratio in an attempt to alter the cure time. Strength, thermal, and chemical resistance will be adversely affected. Read and observe material safety data. Be sure to follow the adhesive manufacturer’s instructions regarding mixing, open and closed curing time, and usable temperature ranges.
1-5. BONDING PRECAUTIONS. Satisfactory bond joints in aircraft will develop the full strength of wood under all conditions of stress. To produce this result, the bonding operation must be carefully controlled to obtain a continuous thin and uniform film of solid adhesive in the joint with adequate adhesion and penetration to both surfaces of the wood. Some of the more important conditions involve:
a. Properly prepared wood surfaces.
b. Adhesive of good quality, properly prepared, and properly selected for the task at hand.
c. Good bonding technique, consistent with the adhesive manufacturer’s instructions for the specific application.
1-6. PREPARATION OF WOOD SURFACES FOR BONDING. It is recommended that no more time than necessary be permitted to elapse between final surfacing and bonding. Keep prepared surfaces covered with a clean plastic sheet or other material to maintain cleanliness prior to the bonding operation. The mating surfaces should be machined smooth and true with planers, joiners, or special miter saws. Planer marks, chipped or loosened grain, and other surface irregularities are not permitted. Sandpaper must never be used to smooth softwood surfaces that are to be bonded. Sawn surfaces must approach well-planed surfaces in uniformity, smoothness, and freedom from crushed fibers. It is advisable to clean both joint surfaces with a vacuum cleaner just prior to adhesive application. Wood surfaces ready for bonding must be free from oil, wax, varnish, shellac, lacquer, enamel, dope, sealers, paint, dust, dirt, adhesive, crayon marks, and other extraneous materials.
a. Roughening smooth, well-planed surfaces of normal wood before bonding is not recommended. Such treatment of well-planed wood surfaces may result in local irregularities and objectionable rounding of edges. When surfaces cannot be freshly machined before bonding, such as plywood or inaccessible members, very slight sanding of the surface with a fine grit such as 220, greatly improves penetration by the adhesive of aged or polished surfaces. Sanding should never be continued to the extent that it alters the flatness of the surface. Very light sanding may also improve the wetting of the adhesive to very hard or resinous materials.
1-8. ASSEMBLY TIME IN BONDING. › d. Pressing (or clamping) time is the period during which the parts are…
b. Wetting tests are useful as a means of detecting the presence of wax, old adhesive, and finish. A drop of water placed on a surface that is difficult to wet and thus difficult to bond will not spread or wet the wood rapidly (in seconds or minutes). The surface may be difficult to wet due to the presence of wax, exposure of the surface to heat and pressure as in the manufacture of hot press bonded plywood, the presence of synthetic resins or wood extractives, or simply chemical or physical changes in the wood surface with time. Good wettability is only an indication that a surface can be bonded satisfactorily. After performing wetting tests, allow adequate time for wood to dry before bonding. Preliminary bonding tests and tests for bond strength are the only positive means of actually determining the bonding characteristics of the adhesive and material combinations. (See paragraph 1-29h.)
1-7. APPLYING THE ADHESIVE. To make a satisfactory bonded joint, spread the adhesive in a thin, even layer on both surfaces to be joined. It is recommended that a clean brush be used and care taken to see that all surfaces are covered. Spreading of adhesive on only one of the two surfaces is not recommended. Be sure to read and follow the adhesive manufacturer’s application instructions.
1-8. ASSEMBLY TIME IN BONDING. Resorcinol, epoxy, and other adhesives cure as a result of a chemical reaction. Time is an important consideration in the bonding process. Specific time constraints are as follows:
a. Pot life is the usable life of the adhesive from the time that it is mixed until it must be spread onto the wood surface. Once pot life has expired, the remaining adhesive must be discarded. Do not add thinning agents to the adhesive to extend the life of the batch.
b. Open assembly time is the period from the moment the adhesive is spread until the parts are clamped together. Where surfaces are coated and exposed freely to the air, some adhesives experience a much more rapid change in consistency than when the parts are laid together as soon as the spreading has been completed.
c. Closed assembly time is the period from the moment that the structure parts are placed together until clamping pressure is applied. The consistency of the adhesive does not change as rapidly when the parts are laid together.
d. Pressing (or clamping) time is the period during which the parts are pressed tightly together and the adhesive cures. The pressing time must be sufficient to ensure that joint strength is adequate before handling or machining the bonded structure.
NOTE: Follow the adhesive manufacturer’s instructions for all time limits in the bonding process. If the recommended open or closed assembly periods are exceeded, the bond process should not be continued. Discard the parts if feasible. If the parts cannot be discarded, remove the partially cured adhesive and clean the bond line per adhesive manufacturer’s instructions before application of new adhesive.
1-11. METHOD OF APPLYING PRESSURE. › c. The size of the nails must vary with the size of the members. If…
1-9. BONDING TEMPERATURE. Temperature of the bond line affects the cure rate of the adhesive. Some adhesive types, such as resorcinol, require a minimum temperature which must be maintained throughout the curing process. Each type of adhesive requires a specific temperature during the cure cycle, and the manufacturer’s recommendations should be followed.
1-10. CLAMPING PRESSURE.
a. Use the recommended pressure to squeeze adhesive out into a thin, continuous film between the wood layers. This forces air from the joint and brings the wood surfaces into intimate contact. Pressure should be applied to the joint before the adhesive becomes too thick to flow and is accomplished by means of clamps, presses, or other mechanical devices.
b. Nonuniform clamping pressure commonly results in weak and strong areas in the same joint. The amount of pressure required to produce strong joints in aircraft assembly operations varies with the type of adhesive used and the type of wood to be bonded. Typical pressures when using resorcinol may vary from 125 to 150 pounds per square inch for softwoods and 150 to 200 pounds per square inch for hardwoods. Insufficient pressure or poorly machined wood surfaces usually result in thick bond lines, which indicate a weak joint, and should be carefully guarded against. Some epoxy adhesives require much less clamping pressure to produce acceptable joint strength. Be sure to read and follow the manufacturer’s instructions in all cases.
1-11. METHOD OF APPLYING PRESSURE. The methods of applying pressure to joints in aircraft bonding operations range from the use of brads, nails, small screws, and clamps; to the use of hydraulic and electrical power presses. The selection of appropriate clamping means is important to achieving sound bond joints.
a. Hand nailing is used rather extensively in the bonding of ribs and in the application of plywood skins to the wing, control surfaces, and fuselage frames. Small brass screws may also be used advantageously when the particular parts to be bonded are relatively small and do not allow application of pressure by means of clamps. Both nails and screws produce adverse after effects. There is considerable risk of splitting small parts when installing nails or screws. Metal fasteners also provide vulnerable points for moisture to enter during service.
b. On small joints using thin plywood for gussets or where plywood is used as an outer skin, the pressure is usually applied by nailing or stapling. Thin plywood nailing strips are often used to spread the nailing pressure over a larger area and to facilitate removal of the nails after the adhesive has cured.
c. The size of the nails must vary with the size of the members. If multiple rows of nails are required, the nails should be 1 inch apart in rows spaced 1/2 inch apart. The nails in adjacent rows should be staggered. In no case should the nails in adjacent rows be more than 3/4 inch from the nearest nail. The length of the nails should be such that they penetrate the wood below the joint at least 3/8 inch. In the case of small members, the end of the nail should not protrude through the member below the joint. Hit the nails with several light strokes, just seating the head into the surface of the gusset. Be careful not to crush the wood with a heavy hammer blow.
SECTION 1. MATERIALS AND PRACTICES › 1-12.–1-17. [RESERVED.]
d. In some cases the nails are removed after adhesive cure, while in others the nails are left in place. The nails are employed for clamping pressure during adhesive cure and must not be expected to hold members together in service. In deciding whether to remove nails after assembly, the mechanic should examine adjacent structure to see whether nails remain from original manufacture.
e. On larger members (spar repairs for example), apply pressure by means of screw clamps, such as a cabinet-maker’s bar or “C-clamps.” Strips or blocks should be used to distribute clamping pressure and protect members from local crushing due to the limited pressure area of the clamps, especially when one member is thin (such as plywood). The strip or block should be at least twice as thick as the thinner member being bonded.
f. Immediately after clamping or nailing a member, the mechanic must examine the entire joint to assure uniform part contact and adhesive squeeze-out. Wipe away excess adhesive.
1-12.–1-17. [RESERVED.]
SECTION 2. HEALTH AND SAFETY › 1-21.–1-26. [RESERVED.]
SECTION 2. HEALTH AND SAFETY
1-18. GENERAL. The possibility of an injury is an important consideration when working with wooden aircraft structures. The tools and machines used to shape wooden members can be very dangerous. In addition, there are potential health hazards in working with adhesives and finishes. The mechanic should follow manufacturer’s instructions wherever applicable to prevent injury. Federal law mandates that individual chemical manufacturers are to provide material safety data sheets (MSDS) with health hazard data to all consumers. First aid information and handling precautions must also be identified. Most of the products used in wooden aircraft construction are flammable. Some, such as dope and paint, may be highly flammable.
1-19. SANDING IN AREAS OF EXISTING BOND JOINTS AND FINISHES. Some adhesives used in wooden aircraft construction contain biocides. A common-sense precaution when machining or sanding existing structure is to wear a respirator to avoid inhaling dust products. To lower potential fire hazards avoid using electric sanders around dope, paints, and adhesives.
1-20. HANDLING OF ADHESIVES AND FINISHES. Most adhesives and finish products present at least some toxic potential to users. Injury may occur from skin or eye contact, inhalation, or accidental ingestion. Users should be aware of the manufacturer’s instructions and MSDS.
a. Appropriate skin, eye, ear, and respiratory protection should be worn whenever indicated.
b. Shop cleanliness is essential for health and fire safety.
c. Shop personnel should maintain awareness of others in the work area to assure that bystanders are not injured.
d. Proper shop ventilation is essential to disperse fumes emitted from adhesives such as resorcinol and epoxy.
1-21.–1-26. [RESERVED.]
1-29. INSPECTION METHODS. › a. Likely locations for wood structure deterioration should be given…
SECTION 3. INSPECTION
1-27. GENERAL. Inspection of wooden structure includes some methods, equipment, and awareness of failure modes which are unique to wooden aircraft.
1-28. TYPES OF DETERIORATION AND DAMAGE.
a. Wood Decay. Wood is an organic product which is subject to attack by fungi. Fungi are plants that grow on and in wood. The moisture content of the wood nominally will have to be 20 percent or greater to sustain fungus growth. The result of this growth is called decay. Decayed wood exhibits softness, swelling if still wet, excessive shrinkage when dry, cracking, and discoloration. Repair or replace wood if any amount or form of decay is found.
b. Splitting. Splits or cracks in wooden members occur along grain lines. When the moisture content of wood is lowered, its dimensions decrease. The dimensional change is greatest in a tangential direction (across the fibers and parallel to the growth rings), somewhat less in a radial direction (across the fibers and perpendicular to the growth rings), and is negligible in a longitudinal direction (parallel to the fibers). These dimensional changes can have detrimental effects upon a wood structure, particularly when two parts are bonded together with grains in different directions. This effect can often be seen where a plywood doubler is bonded to a spruce member. As the spruce member dries, it attempts to shrink, but is restrained by the plywood, which shrinks less. The resulting stress in the spruce member exceeds its cross-grain strength, and a split occurs.
c. Bond Failure. Bond joint failure is generally due to improper fabrication technique or prolonged exposure to moisture in service. Although none of the older adhesives have been specifically found to fail by simple aging, the mechanic is advised to inspect all accessible joints carefully.
d. Finish Failure. The finish coat on wood structure (usually varnish) is the last line of defense to prevent water entry into wood and the resulting decay. Finish failure can be the result of prolonged water exposure, wood splitting, ultraviolet light exposure, or surface abrasion.
e. Damage. Stress, impact, or mechanical damage to a wood structure is caused by excessive aerodynamic loads or impact loads occurring while the aircraft is on the ground. Overtightening of fittings can also cause crushing of the underlying wood member and possible bending of the metal fitting.
1-29. INSPECTION METHODS. Whenever possible, the aircraft should be kept in a dry, well-ventilated hangar, with all inspection covers, access panels, etc., removed for as long as possible before final inspection. The aircraft should be given a preliminary inspection when first removing the inspection covers and access panels and inspected with a moisture meter at this time. If the moisture content is high, the aircraft should be thoroughly dried. If the aircraft is dry, this will facilitate later inspection, especially when determining the condition of bonded joints.
a. Likely locations for wood structure deterioration should be given special attention. Most damage is caused by external influence such as moisture, temperature extremes, or sunlight. Care should be taken to note all possible entry points for moisture (i.e., cracks or breaks
(2) Highly suspected structurally damaged areas are shown in Figure… › (b) Check all metal fittings which attach to wooden structure for…
in the finish, fastener holes, inspection/access openings, control system openings, drain holes, and the interfaces of metal fittings and the wood structure). The mechanic should also look for evidence of swelling or warpage of the aircraft’s wood structure, which would indicate underlying damage or decay. Particular attention should be paid to the wood structure immediately beneath the upper surfaces, especially under areas that are finished in dark colors, for signs of deteriorating adhesives. Cracks in wood spars are often hidden under metal fittings or metal rib flanges and leading edge skins. Any time a reinforcement plate exists that is not feathered out on its ends, a stress riser exists at the ends of the plate. A failure of the primary structure can be expected to occur at this point.
b. Tapping the wood structure with a light plastic hammer or screwdriver handle should produce a sharp solid report. If the suspect area sounds hollow and soft, further inspection is warranted by the following methods.
c. Probe the area in question, if accessible, with a sharp metal tool. The wood structure should be solid and firm. If the suspect area feels soft and mushy the mechanic should assume that the area is rotted. Disassembly of the structure is warranted at this point.
d. Prying the area of a bond joint will reveal any mechanical separation of the joint. If the mechanic detects any relative movement between two adjacent wood members, a failure of the bond is evident. Any loose fittings should arouse the mechanic’s suspicion, and the fittings should be removed to check for elongated bolt holes. Disassembly is warranted for further inspection.
e. Odor is an important indicator of possible deterioration. During the initial inspection, as the access panels are being removed from the structure, the mechanic should be aware of any areas that smell musty or moldy. These odors are indicative of the presence of moisture and associated fungal growth and decay.
f. Visual inspection requires looking at the wood structure both externally and internally for visual signs of decay or physical damage. Any accumulations of dirt, bird nests, or rodent nests are likely places to hold moisture and promote decay.
(1) The mechanic should remove any such accumulations that are found and inspect the area for signs of decay. Decay will appear as a dark discoloration or gray stains running along the grain and often a swelling of the wood member if still wet. Fittings will be imbedded in the wood instead of flush.
(2) Highly suspected structurally damaged areas are shown in Figure 1-3. A list of most likely areas to incur structural damage include the following:
(a) Check front and rear spars for compression cracks adjacent to the plywood reinforcing plates, where the lift struts attach, and at the rib attach points on either side of the strut attach points. Triple-check these areas and the spar to fuselage attach points for cracks if the wingtip has contacted the ground, a hangar wall, etc.
(b) Check all metal fittings which attach to wooden structure for looseness, corrosion, cracks, or warps. Areas of particular interest are strut attach fittings, spar butt fittings,
aileron and flap hinges, jury strut fittings, compression struts, pulley brackets, and any landing gear fittings.
(2) Highly suspected structurally damaged areas are shown in Figure… › (m) The two areas where it is possible to identify a compression crack…
(c) Check front and rear spars for longitudinal cracks at the ends of the plywood reinforcement plates where the lift struts attach. Triple-check this area if the wing has encountered any kind of ground strike.
(d) Check ribs on either side of strut attach points for missing or loose rib-to-spar attach nails.
(e) Check ribs on either side of strut attach points for cracks where the cap strips pass over and under the spars.
(f) Check for cracked leading edge skin and/or failed nose ribs in the area directly in front of the jury strut.
(g) Check the brackets which attach the struts to the spars for cracks.
(h) Check the aileron, flap hinge, and hinge brackets for cracks and loose or missing rivets.
(i) Check all exposed end grain wood, particularly the spar butts, for cracking or checking. Checking, or splitting, of wood spar butts is common on aircraft based in arid areas.
(j) Also check for any cracks that indicate a bond line failure or structural failure of the wood member. Any evidence of movement of fittings, bushings, or fasteners should be cause for concern, and further inspection is warranted. Splits in fabric covering the plywood, especially on upper surfaces exposed to ultraviolet light and water, dictate that the mechanic remove the fabric around the split so the underlying plywood may be inspected for physical damage or decay. When removing metal fasteners from wood, check for evidence of corrosion. Any corrosion present indicates the presence of moisture and the strong probability of decay in the adjoining wood structure.
(k) Any wooden member that has been overstressed is subject to compression failure (e.g., ground loop). Compression cracking and failure of the wood spars in certain aircraft are a continuing problem. Compression failures are defined as failure of wood fibers on a plane perpendicular to the wood fiber’s longitudinal axis. If undetected, compression failures may result in structural failure of the wing during flight. Compression cracks have been found emanating from the upper surfaces of the wing spars and progressing downward.
(l) The usual locations for cracks have been the front spar at both ends of the reinforcement plate for the lift strut and the front spar rib attach points, both inboard and outboard of the spar reinforcement plate; and the rear spar lift strut and rib attach points. An inspection of both the front and rear spars for compression cracks is recommended.
(m)The two areas where it is possible to identify a compression crack are on the face and top surface of the spar. Using a borescope through existing inspection holes is one method of inspection. An alternate method is to cut inspection holes in the skin. If inspection
holes are cut, they should be made on the aft side of the front spar and the forward side of the rear spar. This will allow the fabric to be peeled away from the spar. Longitudinal cracks may also be detected during this inspection. Loose or missing rib nails may indicate further damage and should be thoroughly investigated. The mechanic may shine a light, at a low angle and parallel with the grain, in the area of the member subjected to the compression load. An area of grain waviness would indicate a potential compression failure. In all cases the manufacturer’s inspection data should be followed.
SECTION 3. INSPECTION › 1-30.–1-35. [RESERVED.]
FIGURE 1-3. LIKELY AREAS TO INCUR STRUCTURAL DAMAGE
g. Moisture meters are effective tools for detection of excessive moisture content in wood members. An instrument such as this allows the mechanic to insert a probe into the wood member and read its moisture content directly off the meter. A correction chart usually accompanies the instrument to correct for temperature and species of wood. Any reading over 20 percent indicates the probability of fungus growth in the member. Moisture content of the wood should be 8–16 percent, preferably in the 10–12 percent range (this range is during inspection). Where plywood skin covers the spar and the spar would be inaccessible without removing the skin, the moisture meter probe can be inserted through the plywood skin and into the spar to check the moisture content of the spar. The small holes made by the probe are easily sealed.
h. Destructive testing of sample bonded joints whenever a new bond joint is made, a sample joint should be made with the adhesive from the same batch used on the repair and scraps of wood left over from the repair. After curing, the sample joint should be destructively tested to ensure proper bonding of the two wood pieces. Any failure in the bond line indicates a cohesive failure of the adhesive. Any failure along the bond line indicates an adhesive failure, which is indicative of poor bonding. The ideal situation is when wood fibers are observed on both sides of the fracture surface. This indicates a failure in the wood, and indicates the bond joint is actually stronger than the wood.
1-30.–1-35. [RESERVED.]
SECTION 4. REPAIRS › 1-39. SCARF JOINTS.
SECTION 4. REPAIRS
1-36. GENERAL. The basic standard for any aircraft repair is that the repaired structure must be as strong as the original structure and be equivalent to the original in rigidity and aerodynamic shape. Repairs should be made in accordance with manufacturer specifications whenever such data is available.
1-37. REPLACEMENT OF DRAIN HOLES AND SKIN STIFFENERS. Whenever repairs are made that require replacing a portion that includes drain holes, skin stiffeners, or any other items, the repaired portion must be provided with similar drain holes, skin stiffeners, or items of the same dimensions in the same location. Additional drain holes may be required if reinforcement under a skin repair interferes with water flow to existing drain holes. Make any additional drain holes the same diameter as originals, usually 1/4 inch.
1-38. CONTROL SURFACE FLUTTER PRECAUTIONS. When repairing or refinishing control surfaces, especially on high performance airplanes, care must be exercised that the repairs do not involve the addition of weight aft of the hinge line. Such a procedure may adversely affect the balance of the surface to a degree that could induce flutter. As a general rule, it will be necessary to repair control surfaces in such a manner that the structure is identical to the original, and that the stiffness, weight distribution, and mass balance are not affected in any way. Consult the aircraft maintenance manual or seek manufacturer’s direction for specific requirements on checking control surface balance after repair and refinishing of any control surface.
1-39. SCARF JOINTS. The scarf joint is the most satisfactory method of making an end joint between two solid wood members. Cut both parts accurately. The strength of the joints depends upon good joint design and a thin, uniform bond line. Make the scarf cut in the general direction of the grain slope as shown in Figure 1-4.
1-40. SPLICING OF SPARS. › b. The reinforcement plate may overlap drag wire, antidrag wire, or…
FIGURE 1-4. CONSIDERATION OF GRAIN DIRECTION WHEN MAKING
SCARF JOINTS
1-40. SPLICING OF SPARS. Unless otherwise specified by the manufacturer, a spar may be spliced at any point except under the wing attachment fittings, landing gear fittings, engine mount fittings, or lift and interplane strut fittings. These fittings may not overlap any part of the splice. A spar splice repair should not be made adjacent to a previous splice or adjacent to a reinforcing plate. Spacing between two splices or between a splice and a reinforcing plate should be no less than three times the length of the longer splice. Splicing under minor fittings such as drag wire, antidrag wire, or compression strut fittings is acceptable under the following conditions:
a. The reinforcement plates of the splice should not interfere with the proper attachment or alignment of the fittings. Do not alter the locations of pulley support brackets, bellcrank support brackets, or control surface support brackets. Plates are to be tapered off, as depicted in Figure 1-2.
b. The reinforcement plate may overlap drag wire, antidrag wire, or compression strut fittings, if the reinforcement plates are on the rear face of the rear spar or the front face of the front spar. In such cases, it will be necessary to install slightly longer bolts. The front face
reinforcement plate should not overlap drag strut fittings, except when it does not require sufficient shortening of compression struts or changes in drag-truss geometry, to prevent adjustment for proper rigging. Even though take up is sufficient, it may be necessary to change the angles on the fittings. (Acceptable methods for splicing the various types of spars are shown in Figure 1-4 through Figure 1-9.) Reinforcement plates must be used as indicated on all scarf repairs to spars and the slopes of scarves shown are minimum slopes.
FIGURE 1-5. METHOD OF SPLICING SOLID OR LAMINATED
RECTANGULAR SPARS
FIGURE 1-6. METHOD OF SPLICING SOLID “I” SPARS
FIGURE 1-7. REPAIRS TO BUILT-UP “I” SPAR
FIGURE 1-8. METHOD OF SPLICING BOX SPAR FLANGES (PLATE METHOD)
SECTION 4. REPAIRS › 1-41. SPAR REPLACEMENT.
FIGURE 1-9. METHOD OF SPLICING BOX SPAR WEBS
1-41. SPAR REPLACEMENT. Replacement of spars is a major repair. Spars may be replaced by new parts made by the manufacturer or the holder of a Parts Manufacturer Approval (PMA) for that part. Owner-produced spars may be installed providing they are made from a manufacturer-approved drawing. Also, a spar may be made by reference to an existing spar providing sufficient evidence is presented to verify that the existing spar is an original part, and that all materials and dimensions can be determined. The dimensions and type of wood used are
SECTION 4. REPAIRS › 1-44. SPAR LONGITUDINAL CRACKS AND LOCAL DAMAGE.
critical to the structural strength of the aircraft. Care should be taken that any replacement spars accurately match the manufacturer’s original design.
1-42. SPLICING OF BOX SPAR WEBS. Always splice and reinforce plywood webs with the same type of plywood as found on the original part. Do not use solid wood to replace plywood webs. Plywood is stronger in shear than solid wood of the same thickness due to the grain direction of the individual plies. The face-grain of plywood replacement webs and reinforcement plates must be in the same direction as the original member to ensure that the new web will have the required strength. (The method of splicing plywood webs is shown in Figure 1-9.)
1-43. REPLACING SOLID-TYPE SPARS WITH LAMINATED-TYPE SPARS. Solid spars may be replaced with laminated spars or vice versa, provided the material is of the same high quality. External reinforcements (plywood or solid) must always be replaced as on the original member.
1-44. SPAR LONGITUDINAL CRACKS AND LOCAL DAMAGE. Cracked spars (except box spars) may be repaired by bonding plates of spruce or plywood of sufficient thickness to develop the longitudinal shear on both sides of the spar. Extend the plates well beyond the termination of the cracks, as shown in Figure 1-10. A method of repairing small local damage to either the top or bottom side of a spar is also shown in Figure 1-10.
1-44. SPAR LONGITUDINAL CRACKS AND LOCAL DAMAGE. › b. Repairing Cracks Versus Installing a New Spar. The presence of…
FIGURE 1-10. METHOD OF REINFORCING A LONGITUDINAL CRACK AND/OR
LOCAL DAMAGE IN A SOLID SPAR
a. Longitudinal Cracking of Wood Wing Spars of Aircraft Operating in Arid Regions. Aircraft having wood spars and operating in arid regions may develop longitudinal spar cracks in the vicinity of the plywood reinforcement plates. These cracks result from the tendency of the spar to shrink when drying takes place. Plywood resists this tendency to shrink and causes the basic spar stock to split (see paragraph 1-2c). Cracks start under the plywood plates, usually (but not necessarily) at a bolt hole or cutout, and usually spread in each direction until they extend a short distance beyond the ends of the plates where the resistance to spar shrinkage disappears. Cracks have also been found in the butt end of spars. Other factors, which have been found conducive to the formation of cracks are poor protective finishes, large cutouts, and metal fittings that utilize two lines of large diameter bolts.
b. Repairing Cracks Versus Installing a New Spar. The presence of cracks does not necessarily mean that the spar must be discarded. If the crack is not too long or too close to either edge and can be reinforced properly, it will probably be more economical and satisfactory to perform repair rather than install a new spar or section. However, a generally acceptable procedure suitable for all airplane models is not available. Because of the possibility of strength deficiencies contact the manufacturer. In absence of the manufacturer, the FAA should be
1-46. RIB REPAIRS. › a. Rib Repair Methods. Acceptable methods of repairing damaged ribs are…
contacted for approval before making repairs not in accordance with the manufacturer-approved instructions or the recommendations of this AC. Longitudinal cracking or the recurrence of cracking can be minimized by ensuring that the moisture content of the solid wood portion is within the proper range before bonding. In arid desert areas, during bonding the moisture content should be in the range of 6–8 percent before bonding, but in other areas 10–12 percent is satisfactory. If solid or plywood repair stock is procured from another climatic region, it should be allowed to season, in the same storage area as the part to be repaired, for no less than 2 weeks.
c. Preventing Cracks. An important step in the prevention of longitudinal cracking, particularly in spar butts, is to ensure that the wood is thoroughly sealed with a penetrating and highly moisture-resistant finish. Application of a thin, slow-curing epoxy adhesive or sealer can be very effective in slowing or preventing moisture changes in spar butts.