Order AF 6030.33 Regional Engineering Steering Committee for Unassigned Engineering (RESCUE)
This document is cancelled. It may have been replaced. Check the official source before relying on it.
U.S. DEPARTMENT OF TRANSPORTATION
U.S. DEPARTMENT OF TRANSPORTATION
.FEDERAL AVIATION ADMINISTRATION IGL AF 6030. 33
Great Lakes Region
7/7/93
SUBJ: REGIONAL ENGINEERING STEERING COMMITTEE FOR UNASSIGNED ENGINEERING (RESCUE)
1. PURPOSE. This order establishes the Regional Engineering Steering Committee for Unassigned Engineering (RESCUE) to assign·engineering projects by balancing the Division goals and objectives with resource availability.
SUBJ: REGIONAL ENGINEERING STEERING COMMITTEE FOR UNASSIGNED ENGINEERING (RESCUE)
2. DISTRIBUTION. This order is distributed to branch levels and above in the Airway Facilities Division and to all Airway Facilities Field Offices, Great Lakes
Region.
3. SCOPE. RESCUE will consist of two GNAS, ~p.~d one ARTCC Assistant Sector Manager, AGL-460A, AGL-450A, AGL-450B, AGL-48P and AGL-420.1.
shall be AGL-460A. The Sector representative· shall rotate as with FY-93:
The chairperson follows beginning
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
MCH, ILL,
ILL, OHI, OHI, IND, IND, WIS, WIS, MIN, MIN, DAK,
DAK, CHI, CHI, MCH,
ZAU ZOB ZID ZMP ZAU ZOB ZID ZMP
ZAU ZOB ZID ZMP ZAU ZOB ZID ZMP
NOTE: Rotation repeats beginning at year one.
4. RESPONSIBILITIES. RESCUE shall maintain a prioritized list of engineering projects that the Engineering Branches/Sectors are unable to complete and assign items to the Sector Engineering Staff as follows:
a. A single prioritized list of all projects (including F&E and NAS plan projects) under consideration for assignment to operations engineering staff members shall be maintained. Each branch, AGL-450, AGL-460, and AGL-480 shall be responsible for providing a list of projects that cannot be accomplished within the resources allocated to the respective branch.
b. The projects will be consolidated and distributed quarterly.
c. New projects will be accepted or rejected as suitable engineering activities by RESCUE and placed in recommended priority. The consolidating official (AGL-460A) will then distribute copies to RESCUE members.
d. Assignment to the Sector Engineering Staff will be done by RESCUE promptly following distribution of the current list.
e. Each Sector Manager shall maintain and provide a list of his/her staff engineering members and their skills to RESCUE. The availability of staff members will have the approval of the Sector Manager prior to Project assignments. RESCUE will utilize the list to coordinate the assignment of projects.
Distribution: A-X(AF)-3; A-FAF-O(STD) Initiated By:AGL-460
GL AF 6030. 33 1/7/93
f. RESCUE will ensure fiscal resources for projects are available before the projects are assigned .
.g. The engineer assigned the project is responsible to track and close out the project in accordance with current orders.
h. RESCUE will (whenever possible) assign projects to Sectors that involve facilities within their own boundaries.
5. REPORTS. The chairpers.on of RESCUE will report project accomplishment and status monthly to AGL-450 and AGL-460.
Facilities Division, AGL-400