U.S. DEPARTMENT OF TRANSPORTATION ORDER FEDERAL AVIATION ADMINISTRATION 8120.2E National Policy

Effective Date: 5/29/07

SUBJ: Production Approval and Certificate Management Procedures

FOREWORD

This order was prepared to provide guidance for Aircraft Certification Service personnel in the accomplishment of certain agency responsibilities. These include the evaluation, approval, and certificate management of the production activities of manufacturers and their suppliers producing products or parts thereof in accordance with Title 14, Code of Federal Regulations.

The guidance in this order relates to the following four types of production approvals issued by the Federal Aviation Administration:

1. Production Certificate.

2. Approved Production Inspection System.

3. Parts Manufacturer Approval.

4. Technical Standard Order authorization.

This order has been organized into two functional areas: procedures for the evaluation and issuance of a production approval and procedures for certificate management of a production approval.

Frank P. Paskiewiez Manager, Production and Airworthiness Division, AIR-200

Distribution: A-W (IR/FS/VN) -3; A-X (CD/FS) -3; Initiated By: AIR-200 A-FFS-0 (LTD); A-FAC-0 (ALL); AMA-220 (10 copies); AMA-250 (10 copies); AFS-600 (10 copies); AVS-20 (ALL); AEU-100

TABLE OF CONTENTS

CHAPTER 1. INTRODUCTION

CHAPTER 1. INTRODUCTION

Paragraph

1. Purpose … 2. Distribution. 3. Cancellation. 4. Explanation of Major Changes. 5. Acronyms. 6. Definitions. 7. Forms. 8. Relation to Other Directives. 9. Requests for Information. 10. Authority To Change This Order. 11. Deviations. 12. Electronic Signature. 13. Records Management. 14.-19. Reserved.

Page

1 1

I 2 3 6 6 7 7 7 7 7 7

CHAPTER 2. PROCEDURES FOR ISSUING A PRODUCTION APPROVAL

CHAPTER 2. PROCEDURES FOR ISSUING A PRODUCTION APPROVAL

SECTION 1. INTRODUCTION

20. General.

9

SECTION 2. PRODUCTION UNDER A TYPE CERTIFICATE ONLY

(PART 21, SUBPART F)

PART 1. GENERAL

21. Applicability. 22. Privileges. 23. Advising the Applicant.

9 9 9

PART 2. FAA ACTIONS DURING THE SIX-MONTH PERIOD

PART 2. FAA ACTIONS DURING THE SIX-MONTH PERIOD

24. FAA Conformity Determinations. 25. Assessing the Applicant's Progress. 26. Extension of Six-Month Period. 27. APIS or PC Not Established Within Six-Month Period.

12 12 12 12 13

Figure 1. Sample FAA Form 8100-1, Conformity Inspection Record. Figure 2. Sample Letter of Authorization for Extension of § 21.123(c) Six-Month

Limitation.

iii

15

8120.2E 5/29/07

PART 3. PROCESSING AN APPLICATION FOR AN APIS

PART 3. PROCESSING AN APPLICATION FOR AN APIS

Paragraph Page

28. Application. 12 Figure 3. Sample FAA Form 8110-12, Application for Type Certificate, Production Certificate, or Supplemental Type Certificate. 16 29. Review of Production Inspection System Data. 17 30. Provisional Approval Procedures. 17 31. Preliminary DO Audit. 17 32. APIS Board. 18

PART 4. ISSUANCE OF AN APIS

PART 4. ISSUANCE OF AN APIS

33. APIS Approval Letter. 18 34. Initial Risk Management Assessment. 18 35.-40. Reserved. 18 Figure 4. Sample Letter for Approving a Manufacturer's Production Inspection System. 19

SECTION 3. PRODUCTION CERTIFICATE (PART 21, SUBPART G)

PART 1. GENERAL

PART 1. GENERAL

41. Applicability. 22 42. Privileges. 22 43. Advising the Applicant. 23

PART 2. PROCESSING AN APPLICATION FOR A PC

44. Application. 26 45. Preliminary DO Audit. 26 Figure 5. Sample PC Application Acknowledgement Letter. 27

PART 3. PRODUCTION CERTIFICATION BOARD

46. General. 28 47. PCB Member Responsibilities. 28 48. Conduct of the Board. 29 49. PCB Minutes. 30 50. PCB Adjourmment. 31

PART 4. ISSUANCE OF PRODUCTION CERTIFICATE AND PRODUCTION LIMITATION RECORD

PART 4. ISSUANCE OF PRODUCTION CERTIFICATE AND PRODUCTION LIMITATION RECORD

51. Preparation and Delivery of PC and PLR. 31 Figure 6. Sample FAA Form 8120-4, Production Certificate. 32 Figure 7. Sample FAA Form 8120-3, Production Limitation Record. 33 Figure 8. Sample PC Transmittal Letter. 34 52. Initial Risk Management Assessment. 35 53.-55. Reserved. 35 iv

SECTION 4. TECHNICAL STANDARD ORDER AUTHORIZATION

SECTION 4. TECHNICAL STANDARD ORDER AUTHORIZATION

(PART 21, SUBPART O)

PART 1. GENERAL

Paragraph

56. Applicability. 57. Privileges. 58. Advising the Applicant.

Page

36 36 36

PART 2. PROCESSING AN APPLICATION FOR A TSO AUTHORIZATION

59. Application. 60. Design Approval. 61. Preliminary DO Audit.

PART 2. PROCESSING AN APPLICATION FOR A TSO AUTHORIZATION

39 39 39

PART 3. ISSUANCE OF A TSO AUTHORIZATION OR LETTER OF

TSO DESIGN APPROVAL

62. TSO Letter of Authorization. 63. Letter of TSO Design Approval. 64. Initial Risk Management Assessment. 65.-67. Reserved.

40 40 40 40

SECTION 5. PARTS MANUFACTURER APPROVAL (PART 21, SUBPART K)

PART 1. GENERAL

PART 1. GENERAL

68. Applicability. 69. Privileges. 70. Advising the Applicant.

PART 2. PROCESSING AN APPLICATION FOR A PMA

71. Applicant Responsibilities. Figure 9. Sample PMA Letter of Application. 72. MIDO Responsibility.

41 42 42

45 46 47

Figure 10. Sample TC, STC, or TSO Authorization Holder's

PART 2. PROCESSING AN APPLICATION FOR A PMA

PMA Assist Letter.

48

Figure 11. Sample PMA Supplement for Licensing Agreement and STC.

PART 3. ISSUANCE OF A PMA

73. Assignment of the PMA Number. 74. PMA Letter. Figure 12. Sample PMA Letter.

50

49 51 52

Figure 13. Sample Transmittal Letter of Subsequent PMA Supplement.

75. Initial Risk Management Assessment.

PART 3. ISSUANCE OF A PMA

V

55 51

PART 4. POST-PMA ACTIVITIES

Paragraph

76. Change in Location of the Manufacturing Facility. 77. Transferability. 78. Reuse of PMA Design Data. 79. Changes to the FIS. 80. Export Considerations. 81.-84. Reserved.

Page

51 51 51 51 56 56

SECTION 6. EXTENSION OF A PRODUCTION APPROVAL WITHIN THE

UNITED STATES

UNITED STATES

PART 1. GENERAL

85. Applicability. 86. Privileges. 87. Advising the Original PAH and the Associate Facility.

56 56 56

PART 2. PROCESSING A REQUEST FOR EXTENSION OF A PRODUCTION

APPROVAL

88. Request for Extension of a Production Approval. 89. Evaluating the Reque … 90. Coordination With the Geographic District Office.

PART 2. PROCESSING A REQUEST FOR EXTENSION OF A PRODUCTION

57 57 58 59

Figure 14. Sample Hand-Off Memo for Requesting a DO Audit and CM.

PART 3. APPROVAL OF THE REQUEST FOR EXTENSION OF A PRODUCTION

APPROVAL

91. Approval of the Request.

58 58

Geographic MIDO Responsibility After Approval of the Request for Extension.

92.

SECTION 7. NON-U.S. MANUFACTURING FACILITIES—DETERMINATION OF

UNDUE BURDEN AND NO UNDUE BURDEN

UNDUE BURDEN AND NO UNDUE BURDEN

93. Undue Burden and No Undue Burden. 94.-95. Reserved.

CHAPTER3. CERTIFICATE MANAGEMENT PROCEDURES

SECTION 1. INTRODUCTION

96. General. Figure 15. Certificate Management Life Cycle Process. 97. Assignment of CM Coordinator. 98. Status of a PAH. 99.-102. Reserved.

SECTION 1. INTRODUCTION

vi

62 62

63 64 65 65 65

SECTION 2. ONGOING CM RESPONSIBILITIES

PART 1. INTRODUCTION

Paragraph

103. General.

Page

66

Figure 16. Certificate Management Responsibilities (Ongoing) - Minimum

Requirements. 104. Certificate Management Plan. 105. Coordination of Audit Activities With Other CAAs. 106. Recording Noncompliances. 107. Reserved.

PART 2. RISK MANAGEMENT

PART 2. RISK MANAGEMENT

108. Risk Management Model. 109. Scope. 110. Risk Management Groups. 111. Risk Management Categories. 112. Risk Management Assessment of Facilities. Figure 17. Sample AIR Form 8120-9. 113. Identification of Risk Management Groups. 114. Modification of Risk Management Groups. 115. Risk Management Model Validation Plan. 116. Modification of the Risk Management Model. 117.-122. Reserved.

PART 3. SUPPLIER CONTROL

PART 3. SUPPLIER CONTROL

66 67 67 68 68

68 68 68 69 69 70 72 72 72 73 73

SUBPART A. DETERMINING SUPPLIER CONTROL BY A PAH

OR ASSOCIATE FACILITY

123. General. 124. Certificate Management Activity. 125. Determination of Supplier Control. 126.-128. Reserved.

SUBPART B. SUPPLIER CONTROL AUDIT

SUBPART B. SUPPLIER CONTROL AUDIT

129. General. 130. Supplier Selection. 131. Directorate Supplier Control Audit List. 132. Coordination of Supplier Control Audits Between Directorates. 133. Domestic Hand-Off Procedures. 134. Notifying a PAH or Associate Facility. 135. Conducting and Recording a Supplier Control Audit. Figure 18. Sample Supplier Control Audit Notification Letter. 136.-138. Reserved.

vii

73 75 75 75

75 76 77 78 78 80 80 81 82

PART 4. PRINCIPAL INSPECTOR EVALUATION

PART 4. PRINCIPAL INSPECTOR EVALUATION

Paragraph

139. General. 140. Recording a PI Evaluation. 141.-143. Reserved.

Page

82 84 84

PART 5. AIRCRAFT CERTIFICATION SYSTEMS EVALUATION PROGRAM

EVALUATION

144. General. 145.-147. Reserved.

PART 6. PRODUCT AUDIT

148. General. 149. Selection of Product Audit Characteristics. 150. Product Audit Areas. 151. Product Audit Criteria.

PART 6. PRODUCT AUDIT

84 85

85 86 86 86

Figure 19. Applicability of Product Audit Criteria to Product Audit Areas

(Minimum). 152. Recording Product Audit Results. 153. Recording Completion of a Product Audit. 154.-156. Reserved.

SECTION 3. RANDOM CM RESPONSIBILITIES

PART 1. INTRODUCTION

157. General. 158.-159. Reserved.

PART 1. INTRODUCTION

87 87 88 88

88 88

PART 2. EVALUATION OF CHANGES TO A PAH'S OR ASSOCIATE FACILITY'S

QUALITY OR INSPECTION SYSTEM

160. General. 161. Prioritization of Review. 162. Review of Changes. 163. Post-Review Actions. 164.-167. Reserved.

88 88 88 89 89

Figure 20. Sample Letter of Approval for Quality System Changes by a

QUALITY OR INSPECTION SYSTEM

PC or TSO Authorization Holder.

90

Figure 21. Sample Letter of Acknowledgement for Inspection System Changes

by an APIS or PMA Holder.

viii

91

PART 3. INVESTIGATION OF SERVICE DIFFICULTIES

Paragraph

168. General. 169. Investigation. 170. Corrective Action. 171. Reporting a Service Difficulty Investigation. 172. Foreign Manufacturers. 173.-175. Reserved.

PART 3. INVESTIGATION OF SERVICE DIFFICULTIES

Page

89 92 92 92 93 93

PART 4. INVESTIGATION OF REGULATORY VIOLATIONS

176. Enforcement Actions on Safety-Related or Systemic Noncompliances.

177. Enforcement Procedures. 178. Multiple Enforcement Actions. 179. Timeliness. 180. Invalid Alleged Violations. 181. Voluntary Disclosure Procedures. 182.-184. Reserved.

PART 5. CORRECTIVE ACTION

PART 5. CORRECTIVE ACTION

185. General. 186. Corrective Action Procedures. Figure 22. Corrective Action Flowchart. 187. Corrective Action Response. 188. Corrective Action Validation. 189.-191. Reserved.

93 94 94 94 94 94 95

95 95 96 98 99 99

PART 6. UNSCHEDULED AUDITS, EVALUATIONS, OR INVESTIGATIONS

PART 6. UNSCHEDULED AUDITS, EVALUATIONS, OR INVESTIGATIONS

192. General. 193. Non-Scheduled CM Audits/Evaluations. 194. Other Random Investigations. 195.-197. Reserved.

99 99 100 100

PART 7. PROVIDING GUIDANCE TO A PAH OR ASSOCIATE FACILITY

198. General.

101

APPENDIX 1. EVALUATION OF A PAH'S QUALITY OR INSPECTION SYSTEM

1. Purpose. 2. Data Review. 3. Data Approval/Acceptance Standards.

APPENDIX 1. EVALUATION OF A PAH'S QUALITY OR INSPECTION SYSTEM

ix

1 1 3

8120.2E 5/29/07

APPENDIX 2. FABRICATION INSPECTION SYSTEM

Paragraph Page

1. Establishment of the Fabrication Inspection System (FIS). 1 2. Section 21.303(h)(1). 1 3. Section 21.303(h)(2). 2 4. Section 21.303(h)(3). 2 5. Section 21.303(h)(4). 2 6. Section 21.303(h)(5). 3 7. Section 21.303(h)(6). 4 8. Section 21.303(h)(7). 5 9. Section 21.303(h)(8). 5 10. Section 21.303(h)(9). 5

APPENDIX 3. RISK MANAGEMENT INDICATOR ASSESSMENT CRITERIA

APPENDIX 3. RISK MANAGEMENT INDICATOR ASSESSMENT CRITERIA

1. Purpose. 1 2. Specific Guidance. 1 Figure 1. Risk Management Indicators 1

APPENDIX 4. CATEGORY PARTS LIST

1. Purpose. 1 2. Category Parts List. 1 3. Structure of the CPL. 1 4. CPL Revision Process. Figure 1. Sample Category Parts List. 2 Figure 2. CPL Revision Process Flowchart. 4 Figure 3. Sample Part Categorization Memo for Requesting an Addition to the CPL. 5 Figure 4. Sample Part Categorization Memo for Requesting a Change to the CPL. 6 Figure 5. Sample Part Categorization Memo for Requesting Removal of an Assembly/Part From the CPL. 7

APPENDIX 5. RISK MANAGEMENT REPORTS

APPENDIX 5. RISK MANAGEMENT REPORTS

1. Purpose. 1 2. Types of Reports. 1

APPENDIX 6. RISK MANAGEMENT MODEL VALIDATION PLAN

1. Purpose. 2. Risk Management Validations. 1

x

5/29/07 8120.2E

APPENDIX 7. PREPARATION INSTRUCTIONS FOR FAA FORM 8100-6, NONCOMPLIANCE RECORD

Paragraph Page

APPENDIX 7. PREPARATION INSTRUCTIONS FOR FAA FORM 8100-6, NONCOMPLIANCE RECORD

1. Purpose. 1 2. Specific Guidance. 1 Figure 1. Sample FAA Form 8100-6. 4

APPENDIX 8. PREPARATION INSTRUCTIONS FOR FAA FORM 8120-14, PRODUCTION APPROVAL/CERTIFICATE MANAGEMENT ACTIVITY REPORT

1. Purpose … 1 2. Specific Guidance. 1 Figure 1. Sample FAA Form 8120-14. 3

APPENDIX 9. FORMS LISTING

APPENDIX 9. FORMS LISTING

1. Purpose. Figure 1. Forms Available From FAA Logistics Center... 1 Figure 2. Forms Available Within CMIS. 1

xi (and xii)