Radar Vectors
FAA OrderText changedNov 22, 2026

Order 6980.17 62.5 Kva Engine Generators, J. R. Hollingsworth Company Contract Fa-2614

Text re-read from the scan: 2 of 2 passages.

Date
Nov 22, 2026
Recorded
Nov 22, 2026
Passages
2 of 2 changed
Paragraphs
8 added or rewritten, 8 removed or rewritten

Read the current text Official source ↗

What changed in the text

Key: [removed: removed words] are struck through; [added: added words] are underlined. Each changed paragraph is labelled in the margin.

  1. Changed

    [added: ORDER ]DEPARTMENT OF TRANSPORTATION[added: FEDERAL AVIATION ADMINISTRATION]

  2. Removed

    [removed: fEDERAl AVIATION ADMINISTRATION GL 6980.17 GREAT IAKES BEGION]

  3. Added

    [added: GREAT LAKES REGION GL 6980.17]

  4. 8/15/73

  5. Changed

    62.5 KVA ENGINE [removed: .GENERATORS,][added: GENERATORS,] J. R. HOLLINGSWORTH SUBJ: COMPANY, CONTRACT [removed: FA..:2674][added: FA-2674]

  6. Changed

    1. PURPOSE. This[removed: .] Order is to advise the [removed: field.][added: field] offices of a discrepancy[removed: ··] in the instruction books and the fusing of the immersion heater circuits of the subject engine generators and to direct corrective action.[removed: ·]

  7. Changed

    2. DISTRIBUTION. This Order is distributed to the Airway Facilities Division, Branch level and above, and to all Airway Facilities field[added: offices.]

  8. Removed

    [removed: offices~]

  9. 3. CANCELLATION. Order CE SM 6980.14 is cancelled.

  10. Changed

    4. BACKGROUND. This office has information from Washington that during factory inspection it became [removed: apparent][added: apparent.] the 1500-watt immersion heaters being installed.on the subject [removed: pl&nts][added: plants] were inadequate. Therefore, [removed: 2180-wa.tt][added: 2180-watt] heaters were substituted and supplied with MDF-8 fuses. These [removed: fuse.s][added: fuses] proved to be inadequate during field operation.

  11. Changed

    5. ACTION. Sector Offices shall replace the MDF-8 fuses with a similar [removed: ty:pe][added: type] [removed: l5..ampere][added: 15-ampere] fuse and shall correct the instruction manuals to reflect the [removed: ty:pe][added: type] heater and [removed: fuses][added: fuses.] installed.[removed: ~~]

  12. Added

    [added: Aan H. Hlass ALAN H. GLASS]

  13. Chief, Airway Facilities Division

  14. Distribution: RAF-3; FAF-0 (Normal) Initiated By: AGL-445

Whole text before this change

DEPARTMENT OF TRANSPORTATION

fEDERAl AVIATION ADMINISTRATION GL 6980.17 GREAT IAKES BEGION

8/15/73

62.5 KVA ENGINE .GENERATORS, J. R. HOLLINGSWORTH SUBJ: COMPANY, CONTRACT FA..:2674

1. PURPOSE. This . Order is to advise the field. offices of a discrepancy ·· in the instruction books and the fusing of the immersion heater circuits of the subject engine generators and to direct corrective action. ·

2. DISTRIBUTION. This Order is distributed to the Airway Facilities Division, Branch level and above, and to all Airway Facilities field

offices~

3. CANCELLATION. Order CE SM 6980.14 is cancelled.

4. BACKGROUND. This office has information from Washington that during factory inspection it became apparent the 1500-watt immersion heaters being installed.on the subject pl&nts were inadequate. Therefore, 2180-wa.tt heaters were substituted and supplied with MDF-8 fuses. These fuse.s proved to be inadequate during field operation.

5. ACTION. Sector Offices shall replace the MDF-8 fuses with a similar ty:pe l5..ampere fuse and shall correct the instruction manuals to reflect the ty:pe heater and fuses installed. ~~

Chief, Airway Facilities Division

Distribution: RAF-3; FAF-0 (Normal) Initiated By: AGL-445

Whole text after this change

ORDER DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION

GREAT LAKES REGION GL 6980.17

8/15/73

62.5 KVA ENGINE GENERATORS, J. R. HOLLINGSWORTH SUBJ: COMPANY, CONTRACT FA-2674

1. PURPOSE. This Order is to advise the field offices of a discrepancy in the instruction books and the fusing of the immersion heater circuits of the subject engine generators and to direct corrective action.

2. DISTRIBUTION. This Order is distributed to the Airway Facilities Division, Branch level and above, and to all Airway Facilities field offices.

3. CANCELLATION. Order CE SM 6980.14 is cancelled.

4. BACKGROUND. This office has information from Washington that during factory inspection it became apparent. the 1500-watt immersion heaters being installed.on the subject plants were inadequate. Therefore, 2180-watt heaters were substituted and supplied with MDF-8 fuses. These fuses proved to be inadequate during field operation.

5. ACTION. Sector Offices shall replace the MDF-8 fuses with a similar type 15-ampere fuse and shall correct the instruction manuals to reflect the type heater and fuses. installed.

Aan H. Hlass ALAN H. GLASS

Chief, Airway Facilities Division

Distribution: RAF-3; FAF-0 (Normal) Initiated By: AGL-445