Order 6980.17 62.5 Kva Engine Generators, J. R. Hollingsworth Company Contract Fa-2614
Text re-read from the scan: 2 of 2 passages.
- Date
- Nov 22, 2026
- Recorded
- Nov 22, 2026
- Passages
- 2 of 2 changed
- Paragraphs
- 8 added or rewritten, 8 removed or rewritten
Read the current text Official source ↗
What changed in the text
Key: [removed: removed words] are struck through; [added: added words] are underlined. Each changed paragraph is labelled in the margin.
- Changed
[added: ORDER ]DEPARTMENT OF TRANSPORTATION[added: FEDERAL AVIATION ADMINISTRATION]
- Removed
[removed: fEDERAl AVIATION ADMINISTRATION GL 6980.17 GREAT IAKES BEGION] - Added
[added: GREAT LAKES REGION GL 6980.17]
8/15/73
- Changed
62.5 KVA ENGINE
[removed: .GENERATORS,][added: GENERATORS,] J. R. HOLLINGSWORTH SUBJ: COMPANY, CONTRACT[removed: FA..:2674][added: FA-2674] - Changed
1. PURPOSE. This
[removed: .]Order is to advise the[removed: field.][added: field] offices of a discrepancy[removed: ··]in the instruction books and the fusing of the immersion heater circuits of the subject engine generators and to direct corrective action.[removed: ·] - Changed
2. DISTRIBUTION. This Order is distributed to the Airway Facilities Division, Branch level and above, and to all Airway Facilities field[added: offices.]
- Removed
[removed: offices~] 3. CANCELLATION. Order CE SM 6980.14 is cancelled.
- Changed
4. BACKGROUND. This office has information from Washington that during factory inspection it became
[removed: apparent][added: apparent.] the 1500-watt immersion heaters being installed.on the subject[removed: pl&nts][added: plants] were inadequate. Therefore,[removed: 2180-wa.tt][added: 2180-watt] heaters were substituted and supplied with MDF-8 fuses. These[removed: fuse.s][added: fuses] proved to be inadequate during field operation. - Changed
5. ACTION. Sector Offices shall replace the MDF-8 fuses with a similar
[removed: ty:pe][added: type][removed: l5..ampere][added: 15-ampere] fuse and shall correct the instruction manuals to reflect the[removed: ty:pe][added: type] heater and[removed: fuses][added: fuses.] installed.[removed: ~~] - Added
[added: Aan H. Hlass ALAN H. GLASS]
Chief, Airway Facilities Division
Distribution: RAF-3; FAF-0 (Normal) Initiated By: AGL-445
Whole text before this change
DEPARTMENT OF TRANSPORTATION
fEDERAl AVIATION ADMINISTRATION GL 6980.17 GREAT IAKES BEGION
8/15/73
62.5 KVA ENGINE .GENERATORS, J. R. HOLLINGSWORTH SUBJ: COMPANY, CONTRACT FA..:2674
1. PURPOSE. This . Order is to advise the field. offices of a discrepancy ·· in the instruction books and the fusing of the immersion heater circuits of the subject engine generators and to direct corrective action. ·
2. DISTRIBUTION. This Order is distributed to the Airway Facilities Division, Branch level and above, and to all Airway Facilities field
offices~
3. CANCELLATION. Order CE SM 6980.14 is cancelled.
4. BACKGROUND. This office has information from Washington that during factory inspection it became apparent the 1500-watt immersion heaters being installed.on the subject pl&nts were inadequate. Therefore, 2180-wa.tt heaters were substituted and supplied with MDF-8 fuses. These fuse.s proved to be inadequate during field operation.
5. ACTION. Sector Offices shall replace the MDF-8 fuses with a similar ty:pe l5..ampere fuse and shall correct the instruction manuals to reflect the ty:pe heater and fuses installed. ~~
Chief, Airway Facilities Division
Distribution: RAF-3; FAF-0 (Normal) Initiated By: AGL-445
Whole text after this change
ORDER DEPARTMENT OF TRANSPORTATION FEDERAL AVIATION ADMINISTRATION
GREAT LAKES REGION GL 6980.17
8/15/73
62.5 KVA ENGINE GENERATORS, J. R. HOLLINGSWORTH SUBJ: COMPANY, CONTRACT FA-2674
1. PURPOSE. This Order is to advise the field offices of a discrepancy in the instruction books and the fusing of the immersion heater circuits of the subject engine generators and to direct corrective action.
2. DISTRIBUTION. This Order is distributed to the Airway Facilities Division, Branch level and above, and to all Airway Facilities field offices.
3. CANCELLATION. Order CE SM 6980.14 is cancelled.
4. BACKGROUND. This office has information from Washington that during factory inspection it became apparent. the 1500-watt immersion heaters being installed.on the subject plants were inadequate. Therefore, 2180-watt heaters were substituted and supplied with MDF-8 fuses. These fuses proved to be inadequate during field operation.
5. ACTION. Sector Offices shall replace the MDF-8 fuses with a similar type 15-ampere fuse and shall correct the instruction manuals to reflect the type heater and fuses. installed.
Aan H. Hlass ALAN H. GLASS
Chief, Airway Facilities Division
Distribution: RAF-3; FAF-0 (Normal) Initiated By: AGL-445