Order 6930.15 Control and Reduction of Noise Levels Caused by Construction Activity at ATC Facilities

Text re-read from the scan: 3 of 3 passages.

Date
Nov 22, 2026
Recorded
Nov 22, 2026
Passages
3 of 3 changed
Paragraphs
18 added or rewritten, 32 removed or rewritten

Read the current text Official source ↗

What changed in the text

Key: [removed: removed words] are struck through; [added: added words] are underlined. Each changed paragraph is labelled in the margin.

  1. Changed

    DEPARTMENT OF [removed: TRANSPORfAtlON][added: TRANSPORTATOONN] ORDER FEDERAL AVIATION ADMINISTRATION[added: 6930.15]

  2. Changed

    [removed: 4/2/69][added: 4/2/669]

  3. Changed

    CONTROL AND REDUCTION OF NOISE LEVELS CAUSED BY CONSTRUCTION ACTIVITY [added: SI3BJ: ]AT AIR TRAFFIC CONTROL FACILITIES.[removed: WI3.7 :]

  4. Changed

    [removed: 1.][added: 1..] [removed: PTURPOSE.][added: PTRPOSE..] This Order establishes policy for the control and reduction of construction noise levels in the vicinity of ground/air and [removed: airjground][added: airjgrowmd] communications.

  5. Changed

    [removed: Le 7][added: 2e] BACKGROUND. Experiences have shown that noises resulting from construction activity in the vicinity of air traffic control communications operations areas have resulted in garbled transmissions received by aircraft. The garbling of transmission creates a [removed: hazardto][added: hazamddtt] flight safety si:lce flight data instructions may not be heard or may be misinterpreted.

  6. Changed

    [removed: l 3][added: 3.] POLICY. Prior to commencing any facility construction activity in the vicinity of the air traffic control communication operations, suitable measures shall be taken to ensure that the noise level of subsequent[added: construction activity will not be of such magnitude as to constitute a hazard to flight safety. Noises resulting from construction activities in the proximity of communications operating positions, shall be controlled or suitably dampened to ensure that the noises are not transmitted and do not interfere with other transmission or reception.]

  7. Removed

    [removed: construction activity will not be of such magnitude as to constitute a hazard to flight safety. Noises resulting from construction activities in the proximity of communications operating positions, shall be controlled or suitably dampened to ensure that the. noises are not transmitted and do not interfere with other transmission or reception.]

  8. 4. RESPONSIBILITY. Organizational elements responsible for facility design, construction, installation and maintenance shall take the necessary action to implement the policy established by this Order.

  9. Changed

    [removed: 5 0][added: 5!] GUIDELINES. Due to the diversification in types of construction noises and the variables in air/ground communications environments and operations, the solutions to the noise problems must be determined on an[added: individual basis. To aid in the solutions to these problems, the following listed items are suggested for guidance:]

  10. Removed

    [removed: individual basis. To aid in the solutions to these problems, the following listed items are suggested for guidance:]

  11. Added

    [added: a. Schedule construction operations at periods of low or non-existing air traffic activity.]

  12. Removed

    [removed: Schedule construction operations at periods of low or non-existing air traffic activity.]

  13. Added

    [added: b. Use acoustical drapes or curtains to isolate construction areas.]

  14. Removed

    [removed: Use acoustical drapes or curtains to isolate construction areas.]

  15. Added

    [added: Distribution: WRD/SW/AT/IG22; RATT/A&-3; MAT/AF-2; FAT/FAF-0 (1-5) Initiated by: RD:444]

  16. Removed

    [removed: a.]

  17. Added

    [added: Page 2 693015 412169]

  18. Removed

    [removed: rr]

  19. Added

    [added: 89q c. Isolate construction areas bycmsttructimg temporary acoustical walls; ceilings, and floors to reauce sound transmission.]

  20. Removed

    [removed: b.]

  21. Added

    [added: Limit construction operations. in air/ground communication areas to the installation function only. Perform fabrication, assembly etc., functions elsewhere.]

  22. Removed

    [removed: Distribution: WRD/SM/AT/LG-2; RAT/A&3; MAT/AF-2; FAT/FAF-0 (l-5) Initiated by:]

  23. Removed

    [removed: I RD.444 . .]

  24. Removed

    [removed: Page 2 6g3o.u 412169 ']

  25. Removed

    [removed: c.]

  26. Removed

    [removed: . j?,.89q, --*. i]

  27. Removed

    [removed: . . wal&s y]

  28. Removed

    [removed: .]

  29. Removed

    [removed: * Isolate construction areas i3yconstructing temporary acoustical]

  30. Removed

    [removed: ceilings, and floors to rkauce sound transmission.]

  31. Removed

    [removed: d . Limit construction operations. in air/ground communication areas to the installation function only. Perform fabrication, assembly etc., functions elsewhere.]

  32. e. Utilize construction methods that result in minimum noise levels.

  33. Changed

    f. Utilize noise canceling microphones and headsets and "muff-type"[added: earphones.]

  34. Removed

    [removed: . earphones.]

  35. Added

    [added: . Use alternate operating positions located away from the construction area if they are available.]

  36. Removed

    [removed: g. Use alternate operating positions located away from the construction]

  37. Added

    [added: 6. COST. The cost of controlling and reducing construction noises shall included as part of the overall cost of individual maintenance, repair or new construction projects. No special fumds or funding procedures for these costs are established by this Order.]

  38. Removed

    [removed: area if they are available.]

  39. Added

    [added: reiph Blito.]

  40. Removed

    [removed: COST. The cost of controlling and reducing construction noises shall eincluded as part of the overall cost of individual maintenance, repair]

  41. Added

    [added: Joseph D. Blatt Associate Administrator for Development]

  42. Removed

    [removed: or new construction projects. No special fmds or funding procedures for these costs are established by this Order.]

  43. Removed

    [removed: 6.]

  44. Removed

    [removed: ,’ 5]

Whole text before this change

DEPARTMENT OF TRANSPORfAtlON ORDER FEDERAL AVIATION ADMINISTRATION

4/2/69

CONTROL AND REDUCTION OF NOISE LEVELS CAUSED BY CONSTRUCTION ACTIVITY AT AIR TRAFFIC CONTROL FACILITIES. WI3.7 :

1. PTURPOSE. This Order establishes policy for the control and reduction of construction noise levels in the vicinity of ground/air and airjground communications.

Le 7 BACKGROUND. Experiences have shown that noises resulting from construction activity in the vicinity of air traffic control communications operations areas have resulted in garbled transmissions received by aircraft. The garbling of transmission creates a hazardto flight safety si:lce flight data instructions may not be heard or may be misinterpreted.

l 3 POLICY. Prior to commencing any facility construction activity in the vicinity of the air traffic control communication operations, suitable measures shall be taken to ensure that the noise level of subsequent

construction activity will not be of such magnitude as to constitute a hazard to flight safety. Noises resulting from construction activities in the proximity of communications operating positions, shall be controlled or suitably dampened to ensure that the. noises are not transmitted and do not interfere with other transmission or reception.

4. RESPONSIBILITY. Organizational elements responsible for facility design, construction, installation and maintenance shall take the necessary action to implement the policy established by this Order.

5 0 GUIDELINES. Due to the diversification in types of construction noises and the variables in air/ground communications environments and operations, the solutions to the noise problems must be determined on an

individual basis. To aid in the solutions to these problems, the following listed items are suggested for guidance:

Schedule construction operations at periods of low or non-existing air traffic activity.

Use acoustical drapes or curtains to isolate construction areas.

a.

rr

b.

Distribution: WRD/SM/AT/LG-2; RAT/A&3; MAT/AF-2; FAT/FAF-0 (l-5) Initiated by:

I RD.444 . .

Page 2 6g3o.u 412169 '

c.

. j?,.89q, --*. i

. . wal&s y

.

* Isolate construction areas i3yconstructing temporary acoustical

ceilings, and floors to rkauce sound transmission.

d . Limit construction operations. in air/ground communication areas to the installation function only. Perform fabrication, assembly etc., functions elsewhere.

e. Utilize construction methods that result in minimum noise levels.

f. Utilize noise canceling microphones and headsets and "muff-type"

. earphones.

g. Use alternate operating positions located away from the construction

area if they are available.

COST. The cost of controlling and reducing construction noises shall eincluded as part of the overall cost of individual maintenance, repair

or new construction projects. No special fmds or funding procedures for these costs are established by this Order.

6.

,’ 5

Whole text after this change

DEPARTMENT OF TRANSPORTATOONN ORDER FEDERAL AVIATION ADMINISTRATION 6930.15

4/2/669

CONTROL AND REDUCTION OF NOISE LEVELS CAUSED BY CONSTRUCTION ACTIVITY SI3BJ: AT AIR TRAFFIC CONTROL FACILITIES.

1.. PTRPOSE.. This Order establishes policy for the control and reduction of construction noise levels in the vicinity of ground/air and airjgrowmd communications.

2e BACKGROUND. Experiences have shown that noises resulting from construction activity in the vicinity of air traffic control communications operations areas have resulted in garbled transmissions received by aircraft. The garbling of transmission creates a hazamddtt flight safety si:lce flight data instructions may not be heard or may be misinterpreted.

3. POLICY. Prior to commencing any facility construction activity in the vicinity of the air traffic control communication operations, suitable measures shall be taken to ensure that the noise level of subsequent construction activity will not be of such magnitude as to constitute a hazard to flight safety. Noises resulting from construction activities in the proximity of communications operating positions, shall be controlled or suitably dampened to ensure that the noises are not transmitted and do not interfere with other transmission or reception.

4. RESPONSIBILITY. Organizational elements responsible for facility design, construction, installation and maintenance shall take the necessary action to implement the policy established by this Order.

5! GUIDELINES. Due to the diversification in types of construction noises and the variables in air/ground communications environments and operations, the solutions to the noise problems must be determined on an individual basis. To aid in the solutions to these problems, the following listed items are suggested for guidance:

a. Schedule construction operations at periods of low or non-existing air traffic activity.

b. Use acoustical drapes or curtains to isolate construction areas.

Distribution: WRD/SW/AT/IG22; RATT/A&-3; MAT/AF-2; FAT/FAF-0 (1-5) Initiated by: RD:444

Page 2 693015 412169

89q c. Isolate construction areas bycmsttructimg temporary acoustical walls; ceilings, and floors to reauce sound transmission.

Limit construction operations. in air/ground communication areas to the installation function only. Perform fabrication, assembly etc., functions elsewhere.

e. Utilize construction methods that result in minimum noise levels.

f. Utilize noise canceling microphones and headsets and "muff-type" earphones.

. Use alternate operating positions located away from the construction area if they are available.

6. COST. The cost of controlling and reducing construction noises shall included as part of the overall cost of individual maintenance, repair or new construction projects. No special fumds or funding procedures for these costs are established by this Order.

reiph Blito.

Joseph D. Blatt Associate Administrator for Development