Order 6850.37 Visual Guidance Lighting Equipment Approval Program
Text changed: 36 of 49 passages.
- Date
- Nov 18, 2026
- Recorded
- Nov 18, 2026
- Passages
- 36 of 49 changed (was 14)
- Paragraphs
- 188 added or rewritten, 0 removed or rewritten
Read the current text Official source ↗
What changed in the text
Key: [removed: removed words] are struck through; [added: added words] are underlined. Each changed paragraph is labelled in the margin.
- 60 unchanged paragraphs
CHAPTER 2. PROGRAM IMPLEMENTATION
20. GENERAL. FAA approved third party verification bodies will implement this program. The FAA will use this program to acquire equipment under the FAA's F&E program. The purpose of the program is to assist the FAA in discharging its duty to ensure timely availability of visual guidance lighting equipment that meets the applicable FAA standards for safety, performance, quality, and standardization. Manufacturers are subject to a quality audit and twice yearly quality assurance inspections by the third party verification body. Manufacturers submitting products for approval must have a representative in North America to provide aftermarket services for the equipment. A simplified list of each party's responsibilities is given in Figure 1.
- Added
[added: 03-07-2006]
- Added
[added: FIGURE 1. SIMPLIFIED RESPONSIBILITIES CHART.]
- Added
[added: FAA]
- Added
[added: Establish Policy]
- Added
[added: Write Directives]
- Added
[added: Write Specifications]
- Added
[added: Coordinate Program]
- Added
[added: Issue Approval to Third Party Verifier]
- Added
[added: Provide Oversight]
- Added
[added: Maintain Third Party Verifier List]
- Added
[added: Maintain Approved Equipment List]
- Added
[added: Purchase Approved Equipment]
- Added
[added: Third Party Verifier]
- Added
[added: Submit a Request for Approval as a Third Party Verifier]
- Added
[added: Receive Approval as a Third Party Verifier]
- Added
[added: Negotiate Agreement with Manufacturer]
- Added
[added: Review and Authorize Test Procedures]
- Added
[added: Review Instruction Books]
- Added
[added: Test System]
- Added
[added: Analyze Test Data for Compliance with Specification]
- Added
[added: Issue Verification to Manufacturer]
- Added
[added: Manufacturer]
- Added
[added: Build Equipment to Specifications]
- Added
[added: Prepare Test Procedures]
- Added
[added: Prepare Instruction Book]
- Added
[added: Request Third Party Verification]
- Added
[added: Negotiate Agreement with Third Party Verifier]
- Added
[added: Receive Third PartyVerification]
- Added
[added: Maintain Configuration Management System]
- Added
[added: Receive Order for F&E Equipment]
- Added
[added: Deliver Equipment]
- Added
[added: 21. APPROVAL PROGRAM.]
- Added
[added: a. Procedures. Manufacturers of lighting and visual aid equipment that want to participate in the VGLEAP may select any third party verification body from the list in Appendix 1 to this order. The manufacturer will negotiate a licensing agreement (paragraph 22) that describes the relationship between the manufacturer and the third party verification body and specifies their respective responsibilities. A procedural guide (paragraph 23) supplements the license agreement and describes the operational aspects of the program. The third party verification body will evaluate the manufacturer's equipment using the procedures contained in this order. The third party verification body will issue the manufacturer a Certificate of Verification for each type of equipment that meets the applicable FAA standards. The third party verification body must submit a copy of each Certificate of Verification to the FAA. On a monthly basis, the FAA will add newly approved equipment to the list of Approved Visual Guidance Lighting Equipment. The FAA will update this list in the Appendix 1 and 2 to this order; and in the form of an addendum file to this order on the internet home page's identified in Appendix 2. Hard copies of this file may be obtained directly from Navigation Services at the address identified in Appendix 2.]
- Added
[added: b. Costs. The program is funded entirely by fees paid by participating manufacturers. The fee schedule may be obtained from the third party verification bodies listed in Appendix 1. The third party verification body determines the fee amounts and collects the fees.]
- Added
[added: 22. LICENSING AGREEMENT. The licensing agreement describes the relationship between the manufacturer and the third party verification body, and specifies their respective responsibilities. The licensing agreement will also include a schedule of fees for the manufacturer's participation in the program. These fees include a yearly administrative service fee and fees for quality control reviews and the witnessing of tests.]
- Added
[added: 23. PROCEDURAL GUIDE. The Procedural Guide describes the operational aspects of the third party verification body's program, and, as a minimum, must address the elements listed below. (See Appendix 3 for the Procedural Guide Outline.)]
- Added
[added: a. Scope. The scope of the Procedural Guide is to describe the general procedures for the Visual Guidance Lighting Equipment Approval Program. This section must discuss how the verifier will implement the equipment verification procedures contained in this order.]
- Added
[added: b. Quality Control Program. Describe the procedures for assuring manufacturer's compliance with the provisions of ISO 9000 (paragraph 41). A provision must be included to send copies ofall QA reports to Navigation Services.]
- Added
[added: c. Equipment Requirements. Describe the evaluation criteria for the equipment requirements.]
- Added
[added: d. Equipment Qualification Tests. Describes the procedures, with associated completion time frames, for the equipment qualification tests. The third party verification body may witness tests conducted by a manufacturer at the manufacturer's laboratory or witness tests conducted at an independent laboratory. All laboratories in which equipment is tested will be subject to inspection and audit to ensure conformance with ISO/IEC Guide 25.]
- Added
[added: e. Production Tests. Describes the procedures for ensuring that routine production tests, as required by FAA specifications, have been conducted. During the semiannual inspections (paragraph 23f), the third party verification body may request to witness some of the production testing.]
- Added
[added: f. Semiannual Inspections. Describes the procedures for conducting semiannual inspections at the manufacturing site of the participant to determine that the manufactured equipment is the same as the sample subjected to the qualification tests. The inspections may be scheduled or unannounced, at the option of the third party verification body. Samples of all verified equipment produced in a given year must be inspected at least once during these visits. The inspection will include configuration management of drawings, test procedures, and test fixtures. If equipment is not being produced during the semiannual visit, the third party verification body will review the production records and test data for that equipment. If production test records are not available, the verification must be suspended. Nonconformance to specifications found during these inspections will result in suspension of verification unless corrections are made within 72 hours. The third party verification body must notify the FAA within 24 hours of any suspension or withdrawal of equipment's Certification of Verification.]
- Added
[added: g. Appeals Procedure. Describes the procedures for conducting an appeals program. Under this procedure, a manufacturer who is affected by an adverse determination by the third party verification body with respect to its verified equipment or its participation in the program may appeal the determination to the third party verification body.]
- Added
[added: h. Challenge Procedure. Describes the procedures for conducting a challenge program. Under this program, if a manufacturer believes another manufacturer's equipment does not meet FAA specification requirements, it may challenge that manufacturer's verification by submitting to the third party verification body a written statement of reasons for the challenge. The statement shall specify the section(s) of the particular FAA specification being challenged. The third party verification body must follow the challenge procedures developed. The challenged manufacturer's equipment will remain on the Approved Visual Guidance Lighting Equipment list while the challenge is underway.]
- Added
[added: i. Latent Defects. Describes the procedures for correcting latent defects found in the manufacturer's verified equipment.]
- Added
[added: j. Forms. Describes the use and function of forms to be utilized in administering the program. The “Certificate of Verification" must follow the sample shown in Appendix 4.]
- Added
[added: 24. EQUIPMENT COVERED BY THE APPROVAL PROGRAM. The equipment covered by the approval program is included in the FAA specifications listed in Chapter 5 of this order. The FAA may periodically change the equipment covered by the program to reflect changes in the FAA's requirements.]
- Added
[added: 25. SUBMITTAL OF EQUIPMENT VERIFICATION REQUESTS. Requests for verification must be submitted in writing to a third party verification body listed in Appendix 1 of this order. This request must include the following:]
- Added
[added: a. A list of the types, classes, styles, and sizes of equipment, along with the manufacturer's catalog numbers. A list of equipment options must also be included when the individual FAAequipment specifications require.]
- Added
[added: b. Engineering assembly and schematic drawings of the equipment to permit determination of adherence to specification design requirements.]
- Added
[added: c. A copy of the proposed test procedures and test data sheets, and a statement as to whether the manufacturer proposes to conduct the tests at its own facility, or the name and location of an independent testing laboratory where the tests are to be conducted. Since the third party verification body reserves the right to witness any or all tests, the manufacturer should not commence the tests until after consulting with the third party verification body. The third party verification body must conduct initial inspections and audits of any new laboratories used for testing. The third party verification body may elect to witness or waive the option to witness the tests. The manufacturer must give the third party verification body at least 2 weeks notice prior to starting tests. The third party verifier's facility may be used as a laboratory for testing of the manufacturer's equipment.]
- Added
[added: d. A statement that the manufacturer agrees to provide the following minimum warranty for the equipment: "The equipment has been manufactured and will perform in accordance with applicable FAA specifications. Any defect in design, materials, (excluding lamps), or workmanship which may occur during proper and normal use during a period of one year from date of installation or a maximum of two years from date of shipment will be corrected by repair or replacement at the manufacturer's factory."]
- Added
[added: e. A statement that the manufacturer agrees to provide and maintain a quality control program in accordance with ISO 9000 quality standards. The manufacturer should provide a copy of the proposed quality control program.]
- Added
[added: f. A copy of the proposed instruction book conforming to specification FAA-D-2494b not including the appendix, for the equipment and a copy of each product's Listed Products Description Sheet (i.e., Parts List).]
- Added
[added: g. A plan for a configuration management program in accordance with FAA-STD-021a.]
- Added
[added: 26. REVIEW PROCEDURE FOR VERIFICATION REQUESTS. After receipt by the third party verification body of the request for verification, the manufacturer will be notified as to whether the proposed test procedures, test data sheets, and other documentation are acceptable. A mutually acceptable schedule for conducting tests should be agreed upon at that time. The manufacturer will be notified, in writing, after the last submittal of the required documentation or results of the equipment verification testing. If the equipment meets the requirements, the manufacturer will be issued a Certificate of Verification. The review procedure and associated time frames must be described by the third party verification body in the procedural guide.]
- Added
[added: 27. TESTS.]
- Added
[added: a. Quality Assurance Tests. The equipment must successfully pass all quality assurance tests described in the applicable FAA specification. The manufacturer will bear all associated costs. The testing may be witnessed by the third party verification body at the manufacturer's]
- Added
[added: laboratory or at an independent laboratory. Where the third party verification body waives the option to witness tests, the manufacturer must submit a certified copy of all test reports to the third party verification body.]
- Added
[added: b. Reverification. Each piece of equipment must be reverified every 4 years.]
- Added
[added: c. Equipment Requirements. The equipment must meet the requirements described in the applicable equipment FAA specification. The third party verification body may require additional testing of equipment or system components to demonstrate compliance to requirements, in areas where the specification quality assurance testing does not address a specific requirement.]
- Added
[added: d. Production Tests. In addition to quality assurance tests and FAA equipment requirements, each equipment specification requires some tests to be conducted on production units. The manufacturer must retain records of the production tests for 4 years, unless otherwise specified in the equipment specification, and permit the third party verification body, upon request, to witness these tests or inspect previous records.]
- Added
[added: 28. REMOVAL FROM APPROVED EQUIPMENT LIST. The Certificate of Verification will be subject to suspension if:]
- Added
[added: a. The manufacturer fails to provide the required documents.]
- Added
[added: b. The manufacturer fails to honor the warranty (paragraph 25d).]
- Added
[added: c. The manufacturer is found not in conformance with the quality control requirements or other program requirements (paragraph 25e).]
- Added
[added: d. The manufacturer does not maintain acceptable configuration management (paragraph 25g).]
- Added
[added: e. The equipment does not comply with the requirements for reverification (paragraph 27b).]
- Added
[added: f. The manufacturer fails to perform the required production tests (paragraph 27d).]
- Added
[added: g. The equipment has an unsatisfactory failure rate (paragraph 29).]
- Added
[added: h. Changes are made in the equipment without authorization from the third party verification body (paragraph 30).]
- Added
[added: i. The equipment specification is canceled or is revised and the manufacturer fails to requalify (paragraph 31). Once verification has been suspended, the manufacturer will be given a period of time to correct the problem, as specified by the documents of the suspension. While the equipment is suspended, it will remain on the approved list with notation that it has been suspended until a solution has been accepted by the third party verification body. If, after that period of time, the cause of the suspension has not been corrected, the verification will be withdrawn. After verification has been withdrawn, the equipment will be removed from the]
- Added
[added: approved equipment list and the manufacturer will have to resubmit the product for the full approvalprocess.]
- Added
[added: 29. UNACCEPTABLE FAILURE RATE. Since reliable equipment is of prime importance to the safety of airport operations, equipment that proves unreliable in use (as determined by the FAA) may be removed from the approved listing. The determination of unreliability will be based on judgment and experience with equipment of a like nature. Where any such equipment is deemed to have an unsatisfactory failure rate or is deficient in workmanship or materials, the manufacturer will be notified in writing by the FAA as to the basis for this determination. The manufacturer shall then notify the FAA in writing within 15 working days as to its plan of action for correcting the problem. If the manufacturer does not resolve the problem within a reasonable time (the time frame will, of necessity, be based on safety considerations and/or the nature of the problem), the manufacturer and third party verification body will be notified and the equipment will be removed from the approved listing. The FAA reserves the right to require the equipment to be subjected to any or all qualification tests when the equipment has been deemed unreliable.]
- Added
[added: 30. MODIFICATIONS TO EQUIPMENT. Once equipment has been verified, the manufacturer may not make any changes to the equipment without submitting the changes to the third party verification body for reverification. The verifier will maintain configuration management (CM) on the hardware and software configuration items (SWCIs) version numbers of the verified equipment. As a minimum, for SWCIs, the CM will include version number and checksum for each EPROM. The manufacturer will provide an equipment change notice to the verifier for Class I and II changes. If this process is not followed, the manufacturer's equipment will be removed from the approved list. Requests for design or component changes must be submitted in writing to the third party verification body and must be accompanied by supporting documentation plus (if applicable) copies of the revised instruction book pages that reflect the proposed change. The third party verification body will review the modification. If the change is acceptable and is required, the third party verification body will issue a revised Certificate of Verification. Substitution of stock electrical items such as resistors, capacitors, transistors, etc., which are identical in form, fit, and function and which are equal or better in quality and rating, is permissible. Such substitution may require reverification. The manufacturer must supply the third party verification body a list of the substituted items for filing with the inspection records. This requirement does not apply to lamps.]
- Added
[added: 31. REVISION OF SPECIFICATIONS. The FAA may, at times, revise the specification for particular equipment to reflect changing needs of aviation or of new technology. In such a case, the revised FAA equipment specification will contain an effective date, 6 months after which the prior verification automatically expires unless the manufacturer has been reverified to the revised FAA specification. Manufacturers will be informed by letter and supplied a copy of the revised specification within five days of its issuance. The procedure for reverification is the same as for the original verification (paragraph 25) with the following exceptions (not applicable to any equipment not tested under this program or a prior grand-fathered manufacturer):]
- Added
[added: a. The manufacturer does not have to resubmit the quality control plan unless it has changed.]
- Added
[added: b. Depending on the nature of the equipment modification, it may not be necessary to perform all verification tests. Exemption from certain tests may be granted by the third party]
- Added
[added: verification body when requested and justified by the manufacturer that the test is not applicable to the modified design.]
- Added
[added: 32. EXEMPTION FROM SPECIFICATION REQUIREMENTS. No exemptions from the specifications, except as previously stated (paragraph 30), will be granted. However, it is recognized that the FAA equipment specifications may not cover all specific design and operational applications and that equipment may be submitted for verification that does not meet all FAA specification requirements. If the proposed design is considered by the FAA to have merit, then the applicable equipment specification will be revised by the FAA to reflect the proposed design and submitted for comment through the normal coordination process with the aviation community. If no valid adverse comments are received by the FAA on the proposed revision, the proposed design may be given an interim approval before final approval and publication of the revised specification. In such cases, other manufacturers of similar equipment will be notified of the approval and of the forthcoming specification revision.]
- Added
[added: 33. PUBLICATION OF APPROVED EQUIPMENT. A listing of equipment that has been verified by third party verification bodies and approved by the FAA will be published on the internet home pages identified in Appendix 2, on a monthly basis as addendum file to this order. The list can also be obtained from:]
- Added
[added: Federal Aviation Administration Navigation Services 800 Independence Ave., SW Washington, DC 20591]
- Added
[added: 34. INTERNET ACCESS. This order and latest approved equipment list are available on the Internet on the FAA Regulatory and Guidance Library Web site. The direct Internet address is located in Appendix 2 of this order.]
- Added
[added: 35.-39.RESERVED.]
- Added
[added: CHAPTER 3. THIRD PARTY VERIFICATION BODIES]
- Added
[added: 40. ACCEPTANCE CRITERIA. Any entity may become an FAA accepted third party verification body if it demonstrates conformance with the American National Standards Institute (ANSI) Z34.1, Third Party Certification Programs, for Products, Processes, and Services, and:]
- Added
[added: a. Has been in operation as a third party testing facility for a minimum of 3 years;]
- Added
[added: b. Has a permanent assigned staff, knowledgeable in photometric testing and other disciplines related to testing and quality control;]
- Added
[added: c. Is under the supervision of a professional test director (Bachelor of Science Degree in related field; i.e., engineering, physics, physical science, etc.) with a minimum of 4 years experience in interpreting testing standards/specifications, test methods, evaluating test reports and quality assurance programs; and]
- Added
[added: d. All laboratory facilities conform to ISO/IEC Guide 25.]
- Added
[added: 41. DUTIES OF THIRD PARTY VERIFICATION BODY. In addition to administering the qualification program and issuing Certificates of Verification, a third party verification body must assure that the manufacturer provides and maintains a quality control system in accordance with ISO 9000 or Department of Defense quality standards. To ensure adherence, the third party verification body must perform an initial quality audit. It must also assure that testing laboratories which perform qualification testing conform to the requirements of the International Organization for Standardization/International Electrotechnical Commission (ISO/IEC) Guide 25, General Requirements for the Competence of Calibration and Testing Laboratories. Semiannual inspections of manufacturers must also be conducted (paragraph 23f).]
- Added
[added: 42. APPLICATION. In order to be listed as a Third Party Verification Body, the testing facility must agree to undergo an assessment to determine if it qualifies. The FAA will provide application information upon request. Requests should be submitted to:]
- Added
[added: Federal Aviation Administration Navigation Services 800 Independence Ave., SW Washington, DC 20591]
- Added
[added: a. The followinginformation must be submitted with the application:]
- Added
[added: (1). A summary of the entity's background as a third party testing facility.]
- Added
[added: (2). Resumes of permanent staff members who will be assigned to the verification program.]
- Added
[added: (3). A draft copy of procedural guide and licensing agreement for the Visual Guidance Lighting Equipment Approval Program. A schedule of fees does NOT have to be included in the licensing agreement.]
- Added
[added: (4). Scope of verification activities for which it is seeking FAA approval, if it is less than the total program.]
- Added
[added: b. If the FAA determines that the third party testing facility conforms to all criteria, a “Letter of Acceptance" will be issued to that body and they will be listed in Appendix 1, Third Party Verification Bodies.]
- Added
[added: 43. INSPECTION OF FACILITIES. Each participating third party verification body must agree to make facilities and program records available to the FAA or its representatives both initially and at all reasonable times thereafter for inspection. The FAA reserves the right to accompany the third party verification body to a manufacturer's facility or testing laboratory to witness qualification tests, quality control audits, site production tests, or inspections. The FAA also reserves the right to have staff or designated representatives visit the third party verification body to review its program.]
- Added
[added: 44. DURATION OF LETTER OF ACCEPTANCE. A FAA Letter of Acceptance is valid for a period of 2 years. However, a third party verification body that wishes to continue in the program may reapply by resubmitting the information called for above (paragraph 42), plus a statement covering any problems experienced that may relate to safety and reliability of products approved. However, should a third party verification body make any changes in the program prior to that time, they must notify the FAA and obtain FAA approval before implementing the changes. Any questions concerning this program or the operation of any of the accepted third party verification bodies should be sent to:]
- Added
[added: Federal Aviation Administration Navigation Services 800 Independence Ave., SW Washington, DC 20591]
- Added
[added: 45. WITHDRAWAL OF LETTER OF ACCEPTANCE. In the event the third party verification body ceases to meet the criteria of this order, the FAA reserves the right to withdraw the Letter of Acceptance.]
- Added
[added: 46. THIRD PARTY VERIFICATION BODY CHALLENGEPROCEDURE. If the FAA receives information that a third party verification body believes another third party verification body is not performing in accordance with the minimum criteria of this order, the FAA will notify the challenged party and investigate the charges. If the challenge is upheld, and the third party verification body is not performing in accordance with the criteria set forth in this order, the third party verification body will be notified of the deficiencies. If, at the end of 30 days, the third party verification body still does not meet the minimum criteria of this order, the FAA reserves the right to withdraw the Letter of Acceptance.]
- Added
[added: 47.-59. RESERVED.]
- Added
[added: CHAPTER 4. LIFE CYCLE SUPPORT]
- Added
[added: 60. LIFE CYCLE SUPPORT. When the FAA procures visual guidance lighting equipment under this F&E program, the life support requirements will be included in the solicitation's statement of work. The solicitation will include the spare parts and spare parts peculiar for the equipment as contract line items.]
- Added
[added: 61.-80. RESERVED.]
- Added
[added: CHAPTER 5. EQUIPMENT SPECIFICATIONS]
- Added
[added: 81. EQUIPMENT SPECIFICATIONS. This chapter provides a list of the FAA equipment specifications covered under the approval program. These specifications are available on the Internet at the FAA Navigation Services home page. They can also be obtained from FAA at:]
- Added
[added: Federal Aviation Administration Navigation Services Organization 800 Independence Ave., SW Washington, DC 20591.]
- Added
[added: FAA-E-982j PAR-56 Lampholder]
- Added
[added: FAA-E-2159e REIL]
- Added
[added: FAA-E-2325e MALSR]
- Added
[added: FAA-E-2408b PAR-56, 20A, Quartz Halogen Lamp]
- Added
[added: FAA-E-2491b Approach Light, Semiflush, Steady Burning]
- Added
[added: FAA-E-2628b Sequenced Flashing Lighting System, Elevated and Semiflush with Dimming and Monitoring]
- Added
[added: FAA-E-2651 ODALS]
- Added
[added: FAA-E-2663 Interface unit, MALSR Remote Control]
- Added
[added: FAA-E-2689a, Ch. 6 ALSF-2]
- Added
[added: FAA-E-2702 LIR Structures]
- Added
[added: FAA-E-2723 Amendement 1 RRCS]
- Added
[added: FAA-E-2756b PAPI]
- Added
[added: FAA-E-2891 MALSR,Semiflush Threshold Light Fixture]
- Added
[added: FAA-E-2952 ALSF-2,Semiflush Light Fixture]
- Added
[added: FAA-P-2965 PAR-56, Flashtube Lamp]
- Added
[added: FAA-E-2968 MALSR, Semiflush Light Fixture]
- Added
[added: FAA-P-2969 Red and Green Filters]
- Added
[added: DrawingC-6046 Frangible coupling Type 1 and Type 1A, Details]
- Added
[added: 81.-90. RESERVED.]
- Added
[added: APPENDIX 1. THIRD PARTY VERIFICATION BODIES]
- Added
[added: (As of issue date)]
- Added
[added: The third party testing facilities listed below have met the requirements contained in this order and have been accepted as Third Party Verification Bodies under the Visual Guidance Lighting Equipment Approval Program.]
- Added
[added: APPENDIX 2. ADDRESS LIST OF APPROVED VISUAL GUIDANCE LIGHTING EQUIPMENTMANUFACTURERS]
- Added
[added: This appendix is a list of the manufacturers with one or more pieces of approved equipment at the time of release of a change to this order. An addendum to this appendix, listing all currently approved equipment manufacturers' addresses, is updated monthly. Listing of a manufacturer in this appendix does not indicate that all of that manufacturer's products are approved; the addendum must be reviewed to assure approval of individual products. The addendum is available on the Internet at the FAA Regulatory and Guidance Library Web site (http://www.airweb.faa.gov\rgl) and/or Technical OperationsWeb site (http://atowdirectives.faa.gov). The addendum can also be obtained from the FAA at:]
- Added
[added: Federal AviationAdministration Navigation Services 800 Independence Ave., SW Washington, DC 20591]
- Added
[added: APPENDIX 3. PROCEDURAL GUIDE OUTLINE]
- Added
[added: 1. SCOPE. (§ 23a)]
- Added
[added: a. Basis of Program]
- Added
[added: b. Verifier's Role]
- Added
[added: c. Manufacturer's Role]
- Added
[added: d. FAA Role]
- Added
[added: 2. LICENSE AGREEMENTS. (§ 22)]
- Added
[added: 3. EQUIPMENT QUALIFICATION TEST PROCEDURES. (§ 23d)]
- Added
[added: (Use procedures in Chapter 2 as a guide.)]
- Added
[added: 4. SEMIANNUAL INSPECTIONS. (§ 23f)]
- Added
[added: a. Timing of Inspections]
- Added
[added: b. Production Records]
- Added
[added: c. Inspection Review Report]
- Added
[added: d. Configuration Management Program Compliance]
- Added
[added: e. Corrective Action]
- Added
[added: f. FAA Notification]
- Added
[added: 5. QUALITY CONTROL. (§ 23b)]
- Added
[added: a. Audit Visits]
- Added
[added: b. Rating System]
- Added
[added: 6. PRODUCTION TESTING. (§ 23e)]
- Added
[added: 7. APPEALS PROCEDURE. (§ 23g)]
- Added
[added: 8. CHALLENGE PROCEDURE. (§23h)]
- Added
[added: a. Written Challenge]
- Added
[added: b. Documentation]
- Added
[added: c. Costs]
- Added
[added: d. Sample Product 18]
- Added
[added: e. Testing f. Corrective Action]
- Added
[added: g. Payment 9. LATENT DEFECTS. (§ 23i) 10. USE AND FUNCTION OF FORMS. (§ 23j)]
- Added
[added: 11. FORMS]
- Added
[added: 03-07-2006]
- Added
[added: APPENDIX 4. SAMPLE VERIFICATION]
- Added
[added: Program Administrator]
- Added
[added: (Name and address of Third Party Verifier)]
- Added
[added: Visual Guidance Lighting Equipment Approval Program]
- Added
[added: Certification of Verification]
- Added
[added: Name and Address of Manufacturer]
- Added
[added: The equipment listed below is hereby verified in accordance with the procedures contained in Federal Aviation Administration (FAA) ORDER 6850.YY, Visual Guidance Lighting Equipment Approval Program (VGLEAP). The Verification is based on successful completion of test and conformance with requirements of the specifications listed in ORDER 6850.YY and the reporting to the Program Administrator the results of such test accompanied by related documents.]
- Added
[added: ITEM NUMBER – ITEM NAME]
- Added
[added: (FAA-E-2159) Mfgr's]
- Added
[added: Type Rating Class Style Size Watts Amps Lamps No. Cat No.]
- Added
[added: (NOTE: Use headings appropriate for the equipment tested.)]
- Added
[added: DATE:]
- Added
[added: (This is the date of the last issued verification based on complete test data.)]
- Added
[added: This equipment requires continuing validation in accordance with the requirements of ORDER 6850.YY.]
- Added
[added: Product tested and report issued by:]
- Added
[added: Report No.:]
- Added
[added: Date of Report:]
- Added
[added: FAA Specification No.:]
- Added
[added: VERIFIED BY:]
- Added
[added: Verifier's Signature]
- Added
[added: Verifier's Typed Name]
- Added
[added: Date Signed]
Whole text before this change
ORDER
VISUAL GUIDANCE LIGHTING EQUIPMENT
APPROVAL PROGRAM
March 7,2006
DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
Distribution: A-W (ND/OS/OP/S WNI/VN/FZWJ/GC)P; Initiated By: AJW-46 A-Y (DE/AY)-2; A-X (AF)-3
RECORD OF CHANGES DIRECTIVE NO.
OPTIONAL CHANGE
TO BASIC
OPTIONAL CHANGE
TO BASIC
SUPPLEMENTS SUPPLEMENTS
FOREWARD
This order establishes and describes the Visual Guidance Lighting Equipment Approval Program (VGLEAP) for equipment that is purchased and installed under the Facilities and Equipment (F&E) Program. This order introduces a new approach to providing visual guidance lighting systems and equipment into the National Airspace System (NAS). The goal of this program is to reduce the timeframe of the initial stages of the F&E procurement process for lighting systems.
Steve Zaidman vice President, Technical Operations Services
TABLE OF CONTENTS
… 1 . PURPOSE 1 … 2 . DISTR~M"T'ION 1 … 3 . BACKGROUND 1 … 4 . APPLICATION 1 … 5 . ACTION 1 … 6 . INTERNET ACCESS 2 … 7 . DELEGATION OF AUTHORITY 2 … 8-1 9 . RESERVED 2
20 . GENERAL … 3 … 2 1 . APPROVAL PROGRAM 5
22 . LICENSING AGREEMENT … 5
23 . PROCEDURAL GUIDE … 5
24 . EQUIPMENT COVERED BY THE APPROVAL PROGRAM … 6
25 . SUBMITTAL OF EQUIPMENT VERIFICATION REQUESTS … 6
26 . REVIEW PROCEDURE FOR VERIFICATION REQUESTS … 7
27 . TESTS … 7
28 . REMOVAL FROM APPROVED EQUIPMENT LIST … 8
29 . UNACCEPTABLE FAILURE RATE … 9
30 . MODIFICATIONS TO EQUIPMENT … 9 . 3 1 REVISION OF SPECIFICATIONS … 9
32 . EXEMPTION FROM SPECIFICATION REQUIREMENTS … 10
33 . PUBLICATION OF APPROVED EQUIPMENT … 10
34 . INTERNET ACCESS … 10
35.-39. RESERVED … 10
40 . ACCEPTANCE CRITERIA … 11
41 . DUTIES OF THIRD PARTY VERIFICATION BODY … 11
42 . APPLICATION … 11
43 . INSPECTION OF FACILITIES … 12
44 . DURATION OF LETTER OF ACCEPTANCE … 12
45 . WITHDRAWAL OF LETTER OF ACCEPTANCE … 12
46 . THIRD PARTY VERIFICATION BODY CHALLENGE PROCEDURE … 12
47..59. RESERVED … 12
60 . LIFE CYCLE SUPPORT … 13
6 1 .-8 0. RESERVED … 13 . 8 1 EQUIPMENT SPECIFICATIONS … 14
8 1 ..9 0. RESERVED … 15
APPENDIX 1 . THIRD PARTY VERIFICATION BODIES … 16
APPENDIX 2 . ADDRESS LIST OF APPROVED VISUAL GUIDANCE LIGHTINGEQUIPMENT MANUFACTURERS … 17
APPENDIX 3 . PROCEDURAL GUIDE OUTLINE … 18
APPENDIX 4 . SAMPLE VERIFICATION … 20
TABLE OF FIGURES
. FIGURE 1 SIMPLIFIED RESPONSIBILITIES CHART … 4
CHAPTER 1. GENERAL
1. PURPOSE. This order institutes, establishes, and describes the Visual Guidance Lighting Equipment Approval Program (VGLEAP). It provides information on the process for an organization to receive Federal Aviation Administration (FAA), Navigation Services acceptance as a third party verification body and how manufacturers may have their equipment verified and approved under the program. It lists FAA accepted verification bodies and approved products. This order imposes requirements on third party verification bodies and manufacturers who choose to participate in the VGLEAP. The order describes the criteria that the FAA will use to determine whether a verification body qualifies for participation and the verification procedure for equipment. This order also addresses the life cycle support items and configuration management requirements for the listed approved equipment. The FAA, Navigation Services, will use this order to acquire Facilities and Equipment (F&E) funded navigation and landing systems for use in the NAS. The list of approved equipment in this order should only be used for F&E procurements.
2. DISTRIBTUION. This order is distributed in headquarters to division level in Technical Operations, Acquisition and Business Services, and the Office of the Chief Counsel; to division level at the FAA Depot and the FAA Academy at the Mike Monroney Aeronautical Center; and to the branch level in the Technical Operations service areas.
3. BACKGROUND. The Airport Service Office established a similar equipment approval program on January 1, 1990. The program named a commercial testing laboratory, under the oversight of an Industry Technical Advisory Committee, as the program certification body for equipment to be provided under the Advisory Circulars. On May 15, 1995, the FAA, realizing that there were additional commercial laboratories that may want to participate as certification bodies, established and instituted the Airport Lighting Equipment Certification Program. This program allows any commercial laboratory meeting certain criteria to participate as a certification body and provides for FAA oversight and acceptance of certification bodies. The Airport Service program is further described in AC 15015345-53B. On November 13,1992, the FAA issued policy for using non-developmental items (NDI) in FAA acquisitions. FAA Order
181 0.6, Policy for Use of Nondevelopmental Items (NDI) in FAA Acquisitions, establishes the requirements for using NDI in all acquisitions to meet FAA requirements. To meet the policy, "Requirements shall be satisfied to the maximum extent through the use of NDI when such products will meet the user's need and are cost-effective over the entire life cycle of the item and are readily available without developmental cost." Navigation Services Organization has established the VGLEAP in response to this policy.
4. APPLICATION. This order applies to all visual guidance lighting equipment procured by Navigation Services with F&E funds.
5. ACTION. The FAA will establish and maintain a list of applicable specifications used by the VGLEAP. The FAA will issue an Advisory Circular detailing the responsibilities of the third party verification bodies and manufacturers who choose to participate in the program. The FAA will establish and maintain a list of accepted third party verification bodies (Appendix 1). The
third party verification bodies will evaluate and approve visual guidance lighting equipment and authorize suppliers to mark qualifying products. The FAA will establish and maintain lists of currently approved equipment and manufacturers' addresses (Appendix 2). When there are multiple providers listed in this order, Navigation Services will purchase visual guidance lighting equipment from the approved providers using a competitive bidding process. When there is only one listed approved provider, Navigation Services will purchase visual guidance lighting equipment using a negotiated acquisition process. Should the FAA determine to procure equipment from the approved vendor list, a Request for Proposal (RFP) will be issued and may include equipment and services required for the lifecycle support of the equipment requested. Life cycle support may include, but not be limited to training, spare parts peculiar, special tools and test equipment, Depot level support and site spares. Navigation Services will administer this program. The FAA will audit the approved equipment suppliers' configuration management programs in accordance with FAA-STD-02 1 a.
6. INTERNET ACCESS. This order, the latest approved equipment list, the address list of approved visual guidance lighting equipment manufacturers, and the list of third party verification bodies are available on the Internet at the FAA Regulatory and Guidance Library Web site and/or the Technical Operations Web site. The direct Internet addresses are located in Appendix 2 of this order.
7. DELAGATION OF AUTHORITY. The Director, Navigation Services, is authorized to issue changes to the Appendices in this order as needed.
8. - 19. RESERVED.
CHAPTER 2. PROGRAM IMPLEMENTATION
20. GENERAL. FAA approved third party verification bodies will implement this program. The FAA will use this program to acquire equipment under the FAA's F&E program. The purpose of the program is to assist the FAA in discharging its duty to ensure timely availability of visual guidance lighting equipment that meets the applicable FAA standards for safety, performance, quality, and standardization. Manufacturers are subject to a quality audit and twice yearly quality assurance inspections by the third party verification body. Manufacturers submitting products for approval must have a representative in North America to provide aftermarket services for the equipment. A simplified list of each party's responsibilities is given in Figure 1.
Whole text after this change
ORDER
VISUAL GUIDANCE LIGHTING EQUIPMENT
APPROVAL PROGRAM
March 7,2006
DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
Distribution: A-W (ND/OS/OP/S WNI/VN/FZWJ/GC)P; Initiated By: AJW-46 A-Y (DE/AY)-2; A-X (AF)-3
RECORD OF CHANGES DIRECTIVE NO.
OPTIONAL CHANGE
TO BASIC
OPTIONAL CHANGE
TO BASIC
SUPPLEMENTS SUPPLEMENTS
FOREWARD
This order establishes and describes the Visual Guidance Lighting Equipment Approval Program (VGLEAP) for equipment that is purchased and installed under the Facilities and Equipment (F&E) Program. This order introduces a new approach to providing visual guidance lighting systems and equipment into the National Airspace System (NAS). The goal of this program is to reduce the timeframe of the initial stages of the F&E procurement process for lighting systems.
Steve Zaidman vice President, Technical Operations Services
TABLE OF CONTENTS
… 1 . PURPOSE 1 … 2 . DISTR~M"T'ION 1 … 3 . BACKGROUND 1 … 4 . APPLICATION 1 … 5 . ACTION 1 … 6 . INTERNET ACCESS 2 … 7 . DELEGATION OF AUTHORITY 2 … 8-1 9 . RESERVED 2
20 . GENERAL … 3 … 2 1 . APPROVAL PROGRAM 5
22 . LICENSING AGREEMENT … 5
23 . PROCEDURAL GUIDE … 5
24 . EQUIPMENT COVERED BY THE APPROVAL PROGRAM … 6
25 . SUBMITTAL OF EQUIPMENT VERIFICATION REQUESTS … 6
26 . REVIEW PROCEDURE FOR VERIFICATION REQUESTS … 7
27 . TESTS … 7
28 . REMOVAL FROM APPROVED EQUIPMENT LIST … 8
29 . UNACCEPTABLE FAILURE RATE … 9
30 . MODIFICATIONS TO EQUIPMENT … 9 . 3 1 REVISION OF SPECIFICATIONS … 9
32 . EXEMPTION FROM SPECIFICATION REQUIREMENTS … 10
33 . PUBLICATION OF APPROVED EQUIPMENT … 10
34 . INTERNET ACCESS … 10
35.-39. RESERVED … 10
40 . ACCEPTANCE CRITERIA … 11
41 . DUTIES OF THIRD PARTY VERIFICATION BODY … 11
42 . APPLICATION … 11
43 . INSPECTION OF FACILITIES … 12
44 . DURATION OF LETTER OF ACCEPTANCE … 12
45 . WITHDRAWAL OF LETTER OF ACCEPTANCE … 12
46 . THIRD PARTY VERIFICATION BODY CHALLENGE PROCEDURE … 12
47..59. RESERVED … 12
60 . LIFE CYCLE SUPPORT … 13
6 1 .-8 0. RESERVED … 13 . 8 1 EQUIPMENT SPECIFICATIONS … 14
8 1 ..9 0. RESERVED … 15
APPENDIX 1 . THIRD PARTY VERIFICATION BODIES … 16
APPENDIX 2 . ADDRESS LIST OF APPROVED VISUAL GUIDANCE LIGHTINGEQUIPMENT MANUFACTURERS … 17
APPENDIX 3 . PROCEDURAL GUIDE OUTLINE … 18
APPENDIX 4 . SAMPLE VERIFICATION … 20
TABLE OF FIGURES
. FIGURE 1 SIMPLIFIED RESPONSIBILITIES CHART … 4
CHAPTER 1. GENERAL
1. PURPOSE. This order institutes, establishes, and describes the Visual Guidance Lighting Equipment Approval Program (VGLEAP). It provides information on the process for an organization to receive Federal Aviation Administration (FAA), Navigation Services acceptance as a third party verification body and how manufacturers may have their equipment verified and approved under the program. It lists FAA accepted verification bodies and approved products. This order imposes requirements on third party verification bodies and manufacturers who choose to participate in the VGLEAP. The order describes the criteria that the FAA will use to determine whether a verification body qualifies for participation and the verification procedure for equipment. This order also addresses the life cycle support items and configuration management requirements for the listed approved equipment. The FAA, Navigation Services, will use this order to acquire Facilities and Equipment (F&E) funded navigation and landing systems for use in the NAS. The list of approved equipment in this order should only be used for F&E procurements.
2. DISTRIBTUION. This order is distributed in headquarters to division level in Technical Operations, Acquisition and Business Services, and the Office of the Chief Counsel; to division level at the FAA Depot and the FAA Academy at the Mike Monroney Aeronautical Center; and to the branch level in the Technical Operations service areas.
3. BACKGROUND. The Airport Service Office established a similar equipment approval program on January 1, 1990. The program named a commercial testing laboratory, under the oversight of an Industry Technical Advisory Committee, as the program certification body for equipment to be provided under the Advisory Circulars. On May 15, 1995, the FAA, realizing that there were additional commercial laboratories that may want to participate as certification bodies, established and instituted the Airport Lighting Equipment Certification Program. This program allows any commercial laboratory meeting certain criteria to participate as a certification body and provides for FAA oversight and acceptance of certification bodies. The Airport Service program is further described in AC 15015345-53B. On November 13,1992, the FAA issued policy for using non-developmental items (NDI) in FAA acquisitions. FAA Order
181 0.6, Policy for Use of Nondevelopmental Items (NDI) in FAA Acquisitions, establishes the requirements for using NDI in all acquisitions to meet FAA requirements. To meet the policy, "Requirements shall be satisfied to the maximum extent through the use of NDI when such products will meet the user's need and are cost-effective over the entire life cycle of the item and are readily available without developmental cost." Navigation Services Organization has established the VGLEAP in response to this policy.
4. APPLICATION. This order applies to all visual guidance lighting equipment procured by Navigation Services with F&E funds.
5. ACTION. The FAA will establish and maintain a list of applicable specifications used by the VGLEAP. The FAA will issue an Advisory Circular detailing the responsibilities of the third party verification bodies and manufacturers who choose to participate in the program. The FAA will establish and maintain a list of accepted third party verification bodies (Appendix 1). The
third party verification bodies will evaluate and approve visual guidance lighting equipment and authorize suppliers to mark qualifying products. The FAA will establish and maintain lists of currently approved equipment and manufacturers' addresses (Appendix 2). When there are multiple providers listed in this order, Navigation Services will purchase visual guidance lighting equipment from the approved providers using a competitive bidding process. When there is only one listed approved provider, Navigation Services will purchase visual guidance lighting equipment using a negotiated acquisition process. Should the FAA determine to procure equipment from the approved vendor list, a Request for Proposal (RFP) will be issued and may include equipment and services required for the lifecycle support of the equipment requested. Life cycle support may include, but not be limited to training, spare parts peculiar, special tools and test equipment, Depot level support and site spares. Navigation Services will administer this program. The FAA will audit the approved equipment suppliers' configuration management programs in accordance with FAA-STD-02 1 a.
6. INTERNET ACCESS. This order, the latest approved equipment list, the address list of approved visual guidance lighting equipment manufacturers, and the list of third party verification bodies are available on the Internet at the FAA Regulatory and Guidance Library Web site and/or the Technical Operations Web site. The direct Internet addresses are located in Appendix 2 of this order.
7. DELAGATION OF AUTHORITY. The Director, Navigation Services, is authorized to issue changes to the Appendices in this order as needed.
8. - 19. RESERVED.
CHAPTER 2. PROGRAM IMPLEMENTATION
20. GENERAL. FAA approved third party verification bodies will implement this program. The FAA will use this program to acquire equipment under the FAA's F&E program. The purpose of the program is to assist the FAA in discharging its duty to ensure timely availability of visual guidance lighting equipment that meets the applicable FAA standards for safety, performance, quality, and standardization. Manufacturers are subject to a quality audit and twice yearly quality assurance inspections by the third party verification body. Manufacturers submitting products for approval must have a representative in North America to provide aftermarket services for the equipment. A simplified list of each party's responsibilities is given in Figure 1.
03-07-2006
FIGURE 1. SIMPLIFIED RESPONSIBILITIES CHART.
FAA
Establish Policy
Write Directives
Write Specifications
Coordinate Program
Issue Approval to Third Party Verifier
Provide Oversight
Maintain Third Party Verifier List
Maintain Approved Equipment List
Purchase Approved Equipment
Third Party Verifier
Submit a Request for Approval as a Third Party Verifier
Receive Approval as a Third Party Verifier
Negotiate Agreement with Manufacturer
Review and Authorize Test Procedures
Review Instruction Books
Test System
Analyze Test Data for Compliance with Specification
Issue Verification to Manufacturer
Manufacturer
Build Equipment to Specifications
Prepare Test Procedures
Prepare Instruction Book
Request Third Party Verification
Negotiate Agreement with Third Party Verifier
Receive Third PartyVerification
Maintain Configuration Management System
Receive Order for F&E Equipment
Deliver Equipment
21. APPROVAL PROGRAM.
a. Procedures. Manufacturers of lighting and visual aid equipment that want to participate in the VGLEAP may select any third party verification body from the list in Appendix 1 to this order. The manufacturer will negotiate a licensing agreement (paragraph 22) that describes the relationship between the manufacturer and the third party verification body and specifies their respective responsibilities. A procedural guide (paragraph 23) supplements the license agreement and describes the operational aspects of the program. The third party verification body will evaluate the manufacturer's equipment using the procedures contained in this order. The third party verification body will issue the manufacturer a Certificate of Verification for each type of equipment that meets the applicable FAA standards. The third party verification body must submit a copy of each Certificate of Verification to the FAA. On a monthly basis, the FAA will add newly approved equipment to the list of Approved Visual Guidance Lighting Equipment. The FAA will update this list in the Appendix 1 and 2 to this order; and in the form of an addendum file to this order on the internet home page's identified in Appendix 2. Hard copies of this file may be obtained directly from Navigation Services at the address identified in Appendix 2.
b. Costs. The program is funded entirely by fees paid by participating manufacturers. The fee schedule may be obtained from the third party verification bodies listed in Appendix 1. The third party verification body determines the fee amounts and collects the fees.
22. LICENSING AGREEMENT. The licensing agreement describes the relationship between the manufacturer and the third party verification body, and specifies their respective responsibilities. The licensing agreement will also include a schedule of fees for the manufacturer's participation in the program. These fees include a yearly administrative service fee and fees for quality control reviews and the witnessing of tests.
23. PROCEDURAL GUIDE. The Procedural Guide describes the operational aspects of the third party verification body's program, and, as a minimum, must address the elements listed below. (See Appendix 3 for the Procedural Guide Outline.)
a. Scope. The scope of the Procedural Guide is to describe the general procedures for the Visual Guidance Lighting Equipment Approval Program. This section must discuss how the verifier will implement the equipment verification procedures contained in this order.
b. Quality Control Program. Describe the procedures for assuring manufacturer's compliance with the provisions of ISO 9000 (paragraph 41). A provision must be included to send copies ofall QA reports to Navigation Services.
c. Equipment Requirements. Describe the evaluation criteria for the equipment requirements.
d. Equipment Qualification Tests. Describes the procedures, with associated completion time frames, for the equipment qualification tests. The third party verification body may witness tests conducted by a manufacturer at the manufacturer's laboratory or witness tests conducted at an independent laboratory. All laboratories in which equipment is tested will be subject to inspection and audit to ensure conformance with ISO/IEC Guide 25.
e. Production Tests. Describes the procedures for ensuring that routine production tests, as required by FAA specifications, have been conducted. During the semiannual inspections (paragraph 23f), the third party verification body may request to witness some of the production testing.
f. Semiannual Inspections. Describes the procedures for conducting semiannual inspections at the manufacturing site of the participant to determine that the manufactured equipment is the same as the sample subjected to the qualification tests. The inspections may be scheduled or unannounced, at the option of the third party verification body. Samples of all verified equipment produced in a given year must be inspected at least once during these visits. The inspection will include configuration management of drawings, test procedures, and test fixtures. If equipment is not being produced during the semiannual visit, the third party verification body will review the production records and test data for that equipment. If production test records are not available, the verification must be suspended. Nonconformance to specifications found during these inspections will result in suspension of verification unless corrections are made within 72 hours. The third party verification body must notify the FAA within 24 hours of any suspension or withdrawal of equipment's Certification of Verification.
g. Appeals Procedure. Describes the procedures for conducting an appeals program. Under this procedure, a manufacturer who is affected by an adverse determination by the third party verification body with respect to its verified equipment or its participation in the program may appeal the determination to the third party verification body.
h. Challenge Procedure. Describes the procedures for conducting a challenge program. Under this program, if a manufacturer believes another manufacturer's equipment does not meet FAA specification requirements, it may challenge that manufacturer's verification by submitting to the third party verification body a written statement of reasons for the challenge. The statement shall specify the section(s) of the particular FAA specification being challenged. The third party verification body must follow the challenge procedures developed. The challenged manufacturer's equipment will remain on the Approved Visual Guidance Lighting Equipment list while the challenge is underway.
i. Latent Defects. Describes the procedures for correcting latent defects found in the manufacturer's verified equipment.
j. Forms. Describes the use and function of forms to be utilized in administering the program. The “Certificate of Verification" must follow the sample shown in Appendix 4.
24. EQUIPMENT COVERED BY THE APPROVAL PROGRAM. The equipment covered by the approval program is included in the FAA specifications listed in Chapter 5 of this order. The FAA may periodically change the equipment covered by the program to reflect changes in the FAA's requirements.
25. SUBMITTAL OF EQUIPMENT VERIFICATION REQUESTS. Requests for verification must be submitted in writing to a third party verification body listed in Appendix 1 of this order. This request must include the following:
a. A list of the types, classes, styles, and sizes of equipment, along with the manufacturer's catalog numbers. A list of equipment options must also be included when the individual FAAequipment specifications require.
b. Engineering assembly and schematic drawings of the equipment to permit determination of adherence to specification design requirements.
c. A copy of the proposed test procedures and test data sheets, and a statement as to whether the manufacturer proposes to conduct the tests at its own facility, or the name and location of an independent testing laboratory where the tests are to be conducted. Since the third party verification body reserves the right to witness any or all tests, the manufacturer should not commence the tests until after consulting with the third party verification body. The third party verification body must conduct initial inspections and audits of any new laboratories used for testing. The third party verification body may elect to witness or waive the option to witness the tests. The manufacturer must give the third party verification body at least 2 weeks notice prior to starting tests. The third party verifier's facility may be used as a laboratory for testing of the manufacturer's equipment.
d. A statement that the manufacturer agrees to provide the following minimum warranty for the equipment: "The equipment has been manufactured and will perform in accordance with applicable FAA specifications. Any defect in design, materials, (excluding lamps), or workmanship which may occur during proper and normal use during a period of one year from date of installation or a maximum of two years from date of shipment will be corrected by repair or replacement at the manufacturer's factory."
e. A statement that the manufacturer agrees to provide and maintain a quality control program in accordance with ISO 9000 quality standards. The manufacturer should provide a copy of the proposed quality control program.
f. A copy of the proposed instruction book conforming to specification FAA-D-2494b not including the appendix, for the equipment and a copy of each product's Listed Products Description Sheet (i.e., Parts List).
g. A plan for a configuration management program in accordance with FAA-STD-021a.
26. REVIEW PROCEDURE FOR VERIFICATION REQUESTS. After receipt by the third party verification body of the request for verification, the manufacturer will be notified as to whether the proposed test procedures, test data sheets, and other documentation are acceptable. A mutually acceptable schedule for conducting tests should be agreed upon at that time. The manufacturer will be notified, in writing, after the last submittal of the required documentation or results of the equipment verification testing. If the equipment meets the requirements, the manufacturer will be issued a Certificate of Verification. The review procedure and associated time frames must be described by the third party verification body in the procedural guide.
27. TESTS.
a. Quality Assurance Tests. The equipment must successfully pass all quality assurance tests described in the applicable FAA specification. The manufacturer will bear all associated costs. The testing may be witnessed by the third party verification body at the manufacturer's
laboratory or at an independent laboratory. Where the third party verification body waives the option to witness tests, the manufacturer must submit a certified copy of all test reports to the third party verification body.
b. Reverification. Each piece of equipment must be reverified every 4 years.
c. Equipment Requirements. The equipment must meet the requirements described in the applicable equipment FAA specification. The third party verification body may require additional testing of equipment or system components to demonstrate compliance to requirements, in areas where the specification quality assurance testing does not address a specific requirement.
d. Production Tests. In addition to quality assurance tests and FAA equipment requirements, each equipment specification requires some tests to be conducted on production units. The manufacturer must retain records of the production tests for 4 years, unless otherwise specified in the equipment specification, and permit the third party verification body, upon request, to witness these tests or inspect previous records.
28. REMOVAL FROM APPROVED EQUIPMENT LIST. The Certificate of Verification will be subject to suspension if:
a. The manufacturer fails to provide the required documents.
b. The manufacturer fails to honor the warranty (paragraph 25d).
c. The manufacturer is found not in conformance with the quality control requirements or other program requirements (paragraph 25e).
d. The manufacturer does not maintain acceptable configuration management (paragraph 25g).
e. The equipment does not comply with the requirements for reverification (paragraph 27b).
f. The manufacturer fails to perform the required production tests (paragraph 27d).
g. The equipment has an unsatisfactory failure rate (paragraph 29).
h. Changes are made in the equipment without authorization from the third party verification body (paragraph 30).
i. The equipment specification is canceled or is revised and the manufacturer fails to requalify (paragraph 31). Once verification has been suspended, the manufacturer will be given a period of time to correct the problem, as specified by the documents of the suspension. While the equipment is suspended, it will remain on the approved list with notation that it has been suspended until a solution has been accepted by the third party verification body. If, after that period of time, the cause of the suspension has not been corrected, the verification will be withdrawn. After verification has been withdrawn, the equipment will be removed from the
approved equipment list and the manufacturer will have to resubmit the product for the full approvalprocess.
29. UNACCEPTABLE FAILURE RATE. Since reliable equipment is of prime importance to the safety of airport operations, equipment that proves unreliable in use (as determined by the FAA) may be removed from the approved listing. The determination of unreliability will be based on judgment and experience with equipment of a like nature. Where any such equipment is deemed to have an unsatisfactory failure rate or is deficient in workmanship or materials, the manufacturer will be notified in writing by the FAA as to the basis for this determination. The manufacturer shall then notify the FAA in writing within 15 working days as to its plan of action for correcting the problem. If the manufacturer does not resolve the problem within a reasonable time (the time frame will, of necessity, be based on safety considerations and/or the nature of the problem), the manufacturer and third party verification body will be notified and the equipment will be removed from the approved listing. The FAA reserves the right to require the equipment to be subjected to any or all qualification tests when the equipment has been deemed unreliable.
30. MODIFICATIONS TO EQUIPMENT. Once equipment has been verified, the manufacturer may not make any changes to the equipment without submitting the changes to the third party verification body for reverification. The verifier will maintain configuration management (CM) on the hardware and software configuration items (SWCIs) version numbers of the verified equipment. As a minimum, for SWCIs, the CM will include version number and checksum for each EPROM. The manufacturer will provide an equipment change notice to the verifier for Class I and II changes. If this process is not followed, the manufacturer's equipment will be removed from the approved list. Requests for design or component changes must be submitted in writing to the third party verification body and must be accompanied by supporting documentation plus (if applicable) copies of the revised instruction book pages that reflect the proposed change. The third party verification body will review the modification. If the change is acceptable and is required, the third party verification body will issue a revised Certificate of Verification. Substitution of stock electrical items such as resistors, capacitors, transistors, etc., which are identical in form, fit, and function and which are equal or better in quality and rating, is permissible. Such substitution may require reverification. The manufacturer must supply the third party verification body a list of the substituted items for filing with the inspection records. This requirement does not apply to lamps.
31. REVISION OF SPECIFICATIONS. The FAA may, at times, revise the specification for particular equipment to reflect changing needs of aviation or of new technology. In such a case, the revised FAA equipment specification will contain an effective date, 6 months after which the prior verification automatically expires unless the manufacturer has been reverified to the revised FAA specification. Manufacturers will be informed by letter and supplied a copy of the revised specification within five days of its issuance. The procedure for reverification is the same as for the original verification (paragraph 25) with the following exceptions (not applicable to any equipment not tested under this program or a prior grand-fathered manufacturer):
a. The manufacturer does not have to resubmit the quality control plan unless it has changed.
b. Depending on the nature of the equipment modification, it may not be necessary to perform all verification tests. Exemption from certain tests may be granted by the third party
verification body when requested and justified by the manufacturer that the test is not applicable to the modified design.
32. EXEMPTION FROM SPECIFICATION REQUIREMENTS. No exemptions from the specifications, except as previously stated (paragraph 30), will be granted. However, it is recognized that the FAA equipment specifications may not cover all specific design and operational applications and that equipment may be submitted for verification that does not meet all FAA specification requirements. If the proposed design is considered by the FAA to have merit, then the applicable equipment specification will be revised by the FAA to reflect the proposed design and submitted for comment through the normal coordination process with the aviation community. If no valid adverse comments are received by the FAA on the proposed revision, the proposed design may be given an interim approval before final approval and publication of the revised specification. In such cases, other manufacturers of similar equipment will be notified of the approval and of the forthcoming specification revision.
33. PUBLICATION OF APPROVED EQUIPMENT. A listing of equipment that has been verified by third party verification bodies and approved by the FAA will be published on the internet home pages identified in Appendix 2, on a monthly basis as addendum file to this order. The list can also be obtained from:
Federal Aviation Administration Navigation Services 800 Independence Ave., SW Washington, DC 20591
34. INTERNET ACCESS. This order and latest approved equipment list are available on the Internet on the FAA Regulatory and Guidance Library Web site. The direct Internet address is located in Appendix 2 of this order.
35.-39.RESERVED.
CHAPTER 3. THIRD PARTY VERIFICATION BODIES
40. ACCEPTANCE CRITERIA. Any entity may become an FAA accepted third party verification body if it demonstrates conformance with the American National Standards Institute (ANSI) Z34.1, Third Party Certification Programs, for Products, Processes, and Services, and:
a. Has been in operation as a third party testing facility for a minimum of 3 years;
b. Has a permanent assigned staff, knowledgeable in photometric testing and other disciplines related to testing and quality control;
c. Is under the supervision of a professional test director (Bachelor of Science Degree in related field; i.e., engineering, physics, physical science, etc.) with a minimum of 4 years experience in interpreting testing standards/specifications, test methods, evaluating test reports and quality assurance programs; and
d. All laboratory facilities conform to ISO/IEC Guide 25.
41. DUTIES OF THIRD PARTY VERIFICATION BODY. In addition to administering the qualification program and issuing Certificates of Verification, a third party verification body must assure that the manufacturer provides and maintains a quality control system in accordance with ISO 9000 or Department of Defense quality standards. To ensure adherence, the third party verification body must perform an initial quality audit. It must also assure that testing laboratories which perform qualification testing conform to the requirements of the International Organization for Standardization/International Electrotechnical Commission (ISO/IEC) Guide 25, General Requirements for the Competence of Calibration and Testing Laboratories. Semiannual inspections of manufacturers must also be conducted (paragraph 23f).
42. APPLICATION. In order to be listed as a Third Party Verification Body, the testing facility must agree to undergo an assessment to determine if it qualifies. The FAA will provide application information upon request. Requests should be submitted to:
Federal Aviation Administration Navigation Services 800 Independence Ave., SW Washington, DC 20591
a. The followinginformation must be submitted with the application:
(1). A summary of the entity's background as a third party testing facility.
(2). Resumes of permanent staff members who will be assigned to the verification program.
(3). A draft copy of procedural guide and licensing agreement for the Visual Guidance Lighting Equipment Approval Program. A schedule of fees does NOT have to be included in the licensing agreement.
(4). Scope of verification activities for which it is seeking FAA approval, if it is less than the total program.
b. If the FAA determines that the third party testing facility conforms to all criteria, a “Letter of Acceptance" will be issued to that body and they will be listed in Appendix 1, Third Party Verification Bodies.
43. INSPECTION OF FACILITIES. Each participating third party verification body must agree to make facilities and program records available to the FAA or its representatives both initially and at all reasonable times thereafter for inspection. The FAA reserves the right to accompany the third party verification body to a manufacturer's facility or testing laboratory to witness qualification tests, quality control audits, site production tests, or inspections. The FAA also reserves the right to have staff or designated representatives visit the third party verification body to review its program.
44. DURATION OF LETTER OF ACCEPTANCE. A FAA Letter of Acceptance is valid for a period of 2 years. However, a third party verification body that wishes to continue in the program may reapply by resubmitting the information called for above (paragraph 42), plus a statement covering any problems experienced that may relate to safety and reliability of products approved. However, should a third party verification body make any changes in the program prior to that time, they must notify the FAA and obtain FAA approval before implementing the changes. Any questions concerning this program or the operation of any of the accepted third party verification bodies should be sent to:
Federal Aviation Administration Navigation Services 800 Independence Ave., SW Washington, DC 20591
45. WITHDRAWAL OF LETTER OF ACCEPTANCE. In the event the third party verification body ceases to meet the criteria of this order, the FAA reserves the right to withdraw the Letter of Acceptance.
46. THIRD PARTY VERIFICATION BODY CHALLENGEPROCEDURE. If the FAA receives information that a third party verification body believes another third party verification body is not performing in accordance with the minimum criteria of this order, the FAA will notify the challenged party and investigate the charges. If the challenge is upheld, and the third party verification body is not performing in accordance with the criteria set forth in this order, the third party verification body will be notified of the deficiencies. If, at the end of 30 days, the third party verification body still does not meet the minimum criteria of this order, the FAA reserves the right to withdraw the Letter of Acceptance.
47.-59. RESERVED.
CHAPTER 4. LIFE CYCLE SUPPORT
60. LIFE CYCLE SUPPORT. When the FAA procures visual guidance lighting equipment under this F&E program, the life support requirements will be included in the solicitation's statement of work. The solicitation will include the spare parts and spare parts peculiar for the equipment as contract line items.
61.-80. RESERVED.
CHAPTER 5. EQUIPMENT SPECIFICATIONS
81. EQUIPMENT SPECIFICATIONS. This chapter provides a list of the FAA equipment specifications covered under the approval program. These specifications are available on the Internet at the FAA Navigation Services home page. They can also be obtained from FAA at:
Federal Aviation Administration Navigation Services Organization 800 Independence Ave., SW Washington, DC 20591.
FAA-E-982j PAR-56 Lampholder
FAA-E-2159e REIL
FAA-E-2325e MALSR
FAA-E-2408b PAR-56, 20A, Quartz Halogen Lamp
FAA-E-2491b Approach Light, Semiflush, Steady Burning
FAA-E-2628b Sequenced Flashing Lighting System, Elevated and Semiflush with Dimming and Monitoring
FAA-E-2651 ODALS
FAA-E-2663 Interface unit, MALSR Remote Control
FAA-E-2689a, Ch. 6 ALSF-2
FAA-E-2702 LIR Structures
FAA-E-2723 Amendement 1 RRCS
FAA-E-2756b PAPI
FAA-E-2891 MALSR,Semiflush Threshold Light Fixture
FAA-E-2952 ALSF-2,Semiflush Light Fixture
FAA-P-2965 PAR-56, Flashtube Lamp
FAA-E-2968 MALSR, Semiflush Light Fixture
FAA-P-2969 Red and Green Filters
DrawingC-6046 Frangible coupling Type 1 and Type 1A, Details
81.-90. RESERVED.
APPENDIX 1. THIRD PARTY VERIFICATION BODIES
(As of issue date)
The third party testing facilities listed below have met the requirements contained in this order and have been accepted as Third Party Verification Bodies under the Visual Guidance Lighting Equipment Approval Program.
APPENDIX 2. ADDRESS LIST OF APPROVED VISUAL GUIDANCE LIGHTING EQUIPMENTMANUFACTURERS
This appendix is a list of the manufacturers with one or more pieces of approved equipment at the time of release of a change to this order. An addendum to this appendix, listing all currently approved equipment manufacturers' addresses, is updated monthly. Listing of a manufacturer in this appendix does not indicate that all of that manufacturer's products are approved; the addendum must be reviewed to assure approval of individual products. The addendum is available on the Internet at the FAA Regulatory and Guidance Library Web site (http://www.airweb.faa.gov\rgl) and/or Technical OperationsWeb site (http://atowdirectives.faa.gov). The addendum can also be obtained from the FAA at:
Federal AviationAdministration Navigation Services 800 Independence Ave., SW Washington, DC 20591
APPENDIX 3. PROCEDURAL GUIDE OUTLINE
1. SCOPE. (§ 23a)
a. Basis of Program
b. Verifier's Role
c. Manufacturer's Role
d. FAA Role
2. LICENSE AGREEMENTS. (§ 22)
3. EQUIPMENT QUALIFICATION TEST PROCEDURES. (§ 23d)
(Use procedures in Chapter 2 as a guide.)
4. SEMIANNUAL INSPECTIONS. (§ 23f)
a. Timing of Inspections
b. Production Records
c. Inspection Review Report
d. Configuration Management Program Compliance
e. Corrective Action
f. FAA Notification
5. QUALITY CONTROL. (§ 23b)
a. Audit Visits
b. Rating System
6. PRODUCTION TESTING. (§ 23e)
7. APPEALS PROCEDURE. (§ 23g)
8. CHALLENGE PROCEDURE. (§23h)
a. Written Challenge
b. Documentation
c. Costs
d. Sample Product 18
e. Testing f. Corrective Action
g. Payment 9. LATENT DEFECTS. (§ 23i) 10. USE AND FUNCTION OF FORMS. (§ 23j)
11. FORMS
03-07-2006
APPENDIX 4. SAMPLE VERIFICATION
Program Administrator
(Name and address of Third Party Verifier)
Visual Guidance Lighting Equipment Approval Program
Certification of Verification
Name and Address of Manufacturer
The equipment listed below is hereby verified in accordance with the procedures contained in Federal Aviation Administration (FAA) ORDER 6850.YY, Visual Guidance Lighting Equipment Approval Program (VGLEAP). The Verification is based on successful completion of test and conformance with requirements of the specifications listed in ORDER 6850.YY and the reporting to the Program Administrator the results of such test accompanied by related documents.
ITEM NUMBER – ITEM NAME
(FAA-E-2159) Mfgr's
Type Rating Class Style Size Watts Amps Lamps No. Cat No.
(NOTE: Use headings appropriate for the equipment tested.)
DATE:
(This is the date of the last issued verification based on complete test data.)
This equipment requires continuing validation in accordance with the requirements of ORDER 6850.YY.
Product tested and report issued by:
Report No.:
Date of Report:
FAA Specification No.:
VERIFIED BY:
Verifier's Signature
Verifier's Typed Name
Date Signed