ORDER 6560.25A

PROJECT IMPLEMENTATION PLAN

FOR THE

METEOROLOGIST WEATHER PROCESSOR

July 27, !992

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

Distribution: A-W (NW/SM/SE/SU-3; A-W (TR/NS/FS/ Initiated By: ANW-300 BU/HT/TM-1; A-X (AF/AT)-3

RECORD OF CHANGES DIRECTIVE NO. 6560.25A

2

CHANGE

TO BASIC

SUPPLEMENT

OPTIONAL

CHANGE

TO BASIC

SUPPLEMENTS

,OPTIONAL

i r

-

! I

! ! !

I I I !

I I I

I

I

I

! !

I I I

;

I

I I I

!

I I '

l I I I

j

I I ! I !

FAA Form 1320-5 (6-80) USE PREVIOUS EDITION

FOREWORD

This order prescribes the Project Implementation Plan (PIP) for the acquisition, implementation, and support of the Meteorologist Weather Processor (MTJP).

3

~n-~,c.~ Jeanne Rush

Program Manager for Weather Processors, ANW-300

Page i (and ii)

CHAPTER 1.

1. 2. 3. 4. 5. 6. 7. 8.-19.

CHAPTER 2.

20. 21. 22.-29.

CHAPTER 3.

30. 31.

32.

33. 34.-39.

CHAPTER 4.

40. 41. 42. 43.-49.

CHAPTER 5.

SO.

51. 52. 53. 54.

55. 56. 57.

TABLE OF CONTENTS

GENERAL

5

Purpose Distribution cancellation Background Explanation Of Changes Definitions Authority to Change This Order

Reserved

PROJECT OVERVIEW

Synopsis Purpose

Reserved

PROJECT DESCRIPTION

Functional Description Physical Description Figure 3-1 MWP Generic Block Diagram System Requirements Figure 3-2 Front View of MWP Processor Racks Figure 3-3 Top View of MWP Processor Racks Figure 3-4 Top View of Meteorologist Work Station Figure 3-5 Top View of MWP Briefing Terminal Figure 3-6 Top View of MWP Color Printer Table Interfaces

Reserved

PROJECT SCHEDULE AND STATUS

Project Schedules and General Status Milestone Schedule Summary

Interdependencies and Sequence

Reserved

PROJECT MANAGEMENT

Project Management, General Figure S-1 MWP Organization Chart Project Contacts Project Coordination Project Responsibility Matrix Project Managerial Communications Figure S-2 MWP Responsibility Matrix Implementation Staffing Planning and Reports Applicable Documents

Page No.

1

1 1 1 1 1 1 1 1

3

3 3 3

5

5 5 6 7 9 10

12 13 14 16 17

19

19 19 19 19

21

21 22 25 25 32 32 33 34 34 34 58.-59. Reserved 35

Page iii

6

6560.25A 7/27/92

Page No. CHAPTER 6. PROJECT FUNDING 37

60. Project Funding Status, General 37 61. Special Funding Requirements 37 62. Regional Travel 37 63.-69. Reserved 37

CHAPTER 7. DEPLOYMENT 39

70. General Deployment Aspects 39 71. Site Preparation 40 72. Delivery 40 73. Installation Plan 40 74.-79. Reserved 40

CHAPTER 8. VERIFICATION 41

80. Factory Verification 41 81. Checkout 41 82. Contractor Integration Testing 41 83. Contractor Acceptance Inspection 41 84. FAA Integration Testing 41 85. Shakedown and Changeover 41 86. Joint Acceptance Inspection 43 87.-89. Reserved 43

CHAPTER 9. INTEGRATED LOGISTICS SUPPORT 45

90. Maintenance Concept 45 91. Training 45 92. Support Tools and Test Equipment 46 93. Supply Support 46 94. Vendor Data and Technical Manuals 46 95. Equipment Removal 47 96. Facilities 47 97.-99. Reserved 47

CHAPTER 10. ADDITIONAL PROJECT IMPLEMENTATION ASPECTS 49

100.-109. Reserved 49

APPENDIX 1. MILESTONES AND SCHEDULES (5 Pages) 1

APPENDIX 2. MWP PROJECT POINTS OF CONTACT (4 Pages) 1

APPENDIX 3. ISSUES AND CONCERNS (1 Page) 1

APPENDIX 4. ACRONYM LIST (3 Pages) 1

Page iv

7

CHAPTER 1. GENERAL

1. PURPOSE. This order identifies the activities and schedules of the Project Implementation Plan (PIP) required to implement the Meteorologist Weather Processor (MWP) and provides guidance and direction to all levels of the Federal Aviation Administration (FAA) responsible for the

implementation of the MWP. Project management information is presented in chapters 2 through 6 and project implementation guidance in chapters 7 through 10. The references provide further detailed technical information on the implementation of the MWP.

2. DISTRIBUTION. This order is being distributed to branch level in the office of the Program Director for Weather and Flight Service Systems, Systems Maintenance, NAS Systems Engineering, and Acquisition Support; director level in the Air Traffic Plans and Requirements, NAS Transition and Implementation, Flight Standards Services and the Offices of Budget, Training and Higher Education, and Air Traffic System Management; and branch level in the regional Airway Facilities and Air Traffic divisions.

3. CANCELLATION. This order cancels Order 6560.25, Project Implementation Plan for the Meteorologist Weather Processor, dated August 16, 1989.

4. BACKGROUND. The Central Weather Processor (CWP) is an important element of the overall National Airspace System (NAS) modernization effort and is intended to more expeditiously and more comprehensively provide aviation weather information to NAS users. The CWP will process weather data from a variety of sources (FAA, National Weather Service

(NWS), and Department of Defense) and provide tailored weather products to other NAS systems as defined in Order 1812.7, System Requirements Statement for the Central Weather Processor. As originally envisioned, the CWP was to be a single, integrated hardware and software system. In 1987, the CWP was divided into two systems to meet the project's NAS goals. These systems are the Real-Time Weather Processor (RWP) and the MWP. The RWP will be an automated data processing system that will provide hazardous and other operationally significant weather information that is specifically tailored for use by the air traffic control (ATC) controllers, pilots, and traffic management personnel. The MWP is described in paragraph 20.

5. EXPLANATION OF CHANGE. This revision updates the order with MWP contractor specific information and a revised implementation schedule.

6. DEFINITIONS. An acronym list is provided in appendix 4.

7. AUTHORITY TO CHANGE THIS ORDER. Updates, revisions, and/or changes to this order may be authorized by the Program Manager for Weather Processors, ANW-300.

8.-19. RESERVED.

Chap 1 Par 1 Page 1 (and 2)

9

CHAPTER 2. PROJECT OVERVIEW

20. SYNOPSIS. The MWP is an automated meteorological information processing system which will receive, process, and provide weather data and products to NWS meteorologists, assigned to Center Weather Service Units (CWSU) in the Air Route Traffic Control Centers (ARTCC) and the Central Flow Weather Service Unit (CFWSU) in the Air Traffic Control System Command Center (ATCSCC), traffic management (TM) personnel in the Traffic Management Units (TMU) and in the ATCSCC, and air traffic

supervisory personnel in the ARTCC's. The MWP has been acquired as an "interim service" for a lease period of 3 years with two one-year options.

21. PURPOSE. The purpose of the MWP is to automate an information gathering, processing, and distribution process that is today, for the most part, done manually. The MWP will receive, process, store, and display alphanumeric, radar, satellite imagery, and graphic weather products. The MWP will also provide the capability for the creation, storage, and display of meteorologist generated alphanumeric and graphic products.

22.-29. RESERVED.

Chap 2 Par 20 Page 3 (and 4)

11

CHAPTER 3. PROJECT DESCRIPTION

30. FUNCTIONAL DESCRIPTION. The detailed functional description of the MWP is contained in the MWP System Specification, FAA-S-2834. Figure 3-1 depicts the MWP system configuration. The following is a summary of the MWP's primary functions:

a. Simultaneous and continuous receipt of a specified set of weather products.

b. Processing and storage of a specified set of weather products.

c. The capability to display alphanumeric, radar, satellite, or graphic products for the meteorologist's use.

d. The capability to produce or acquire selected meteorological analyses.

e. The capability to supply alphanumeric, radar, satellite, and graphic products to the briefing terminals at the Traffic Management Unit

(TMU) and area supervisors in the ARTCC's, and Traffic Management (TM) specialists at the ATCSCC.

f. The capability for the meteorologist to compose alphanumeric weather products for display at briefing terminals located in the TMU

and/or at other locations within the ARTCC and ATCSCC.

g. The capability for the meteorologist to create graphics and/or annotations to existing graphics for display at briefing terminals located in the TMU and/or at other locations within the ARTCC or ATCSCC.

h. The capability for the meteorologist to disseminate alphanumeric products to the Weather Message Switching Center (WMSC) via the GS-200.

31. PHYSICAL DESCRIPTION. The detailed physical description of the MWP system is provided in figure 3-1 for all ARTCC configurations except for Anchorage (ZAN). The MWP equipment includes a receive-only satellite antenna for receipt of weather data, one MWP processor (consisting of two Concurrent Model 6450 computers), two Topaz Escort Micro Power Conditioners, modems to receive the dedicated Radar Remote Weather Display System (RRWDS) radars at each site, one MWP work station, two

color hardcopy devices, one alphanumeric printer, and up to nine briefing terminals at each ARTCC. The contractor will provide two MWP systems at the ATCSCC. There will be no dedicated radars at ATCSCC, but each MWP at the ATCSCC and ARTCC's will have the capability to dial up any RRWDS equipped radar available across the continental United States. There will be no need for the Power Conditioners at the ATCSCC as there is no Uninterrupted Power Supply (UPS) at the ATCSCC. There also will not be any dedicated radars at ZAN. neither ATCSCC nor ZAN will have a MAD installed.

Chap 3 Par 30 Page 5

12

FIGURE 3-1. MWP GENERIC BLOCK DIAGRAM

Chap 3 Page 6 Par 31

a. The physical characteristics of the MWP are given in detail in subparagraphs 3la(l)-(3).

(1) Processors. There will be two racks of processor equipment at the ARTCC's and four MWP racks at ATCSCC. (The dimensions of the equipment racks are defined in paragraphs 32a and b.)

13

(2) Work station Equipment. The MWP system will include a work station display console which will consist of the following:

(a) One full ASCII QWERTY keyboard with numeric keypad.

(b) One mouse.

(c) Two physical 19" color graphics displays.

(d) One color hard-copy printer.

(e) One alphanumeric printer.

(3) Briefing Terminals. The MWP will be capable of supporting up to nine (9) remote briefing terminals. Appendix 1 lists the number of briefing terminals that will be installed in each ARTCC TMU and the area supervisor positions, and in the ATCSCC. One color hard-copy printer will be provided at one of the TMU briefing terminals. Each briefing terminal will consist of:

(a) One 19" color graphics monitor.

(b) One ASCII QWERTY keyboard.

(c) One personal computer with a 40 megabyte hard drive and a 5.25 inch floppy disk drive.

(4) Communications. The MWP will include one ground, pole, or roof mounted satellite antenna for receipt of weather data products. The size of the antenna for each site is provided in appendix 1. The MWP will also include modems for receipt of radar data, and an interface to the Multiple Access Device (MAD) discussed in paragraph 33. The contractor will provide all required equipment. Impacts on facility communications installations will be determined during the site surveys. The MWP will transmit to the WMSC via the GS-200 in accordance with Attachment J-12 to the MWP contract.

32. SYSTEM REQUIREMENTS. The following MWP requirements that impact facility planning are measured values of the MWP system:

a. Weight limits.

(1) Floor loading. Average weight distribution not to exceed 125 lbfsq.ft.

Chap 3 Par 31 Page 7

14

6560.25A 7/27/92

(a) Equipment Rack 1. 22"W x 34"0 (5.19 sq. ft.) with a weight of 622 pounds. The weight distribution is 120 pounds per square foot.

(b) Equipment Rack 2. 22"W x 34"0 (5.19 sq.ft.) with a weight of 582 pounds. The weight distribution is 112 pounds per square foot.

(c) Work Station. 60"W x 30"0 (12.5 sq.ft.) with a weight of 337 pounds. The weight distribution is 27 pounds per square foot.

(d) Color Hardcopy Printer. 26"W x 26"0 (4.7 sq.ft.) with a weight of 75 pounds. The weight distribution is 16 pounds per square foot.

(e) Briefing Terminal. 24"W x 30"0 (5.0 sq. ft.) with a weight of 165 pounds. The weight distribution is 33 pounds per square foot.

(2) Point loads. No point load over 1,000 lbfsq.in. over a 4 square foot area for any single cabinet or rack.

(a) Equipment Rack 1. The floor contact surface is (0.5" x 20" x 2) plus (0.5" x 27" x 2) for an area (contact point) of 47 square

inches. The point load (662 lbs/47 sq.in.) is 14.09 pounds per square inch.

(b) Equipment Rack 2. The floor contact surface is identical to Equipment Rack 1, 47 square inches. The point load (582 lbs/47 sq.in.) is 12.38 pounds per square inch.

(c) Work Station. The point load equally distributed over four legs, each one-inch square, is (337 lbs/4 sq.in.) 84.25 pounds per square inch.

(d) Color Hardcopy Printer. The point load equally distributed over four legs, each 0.75 inch square (0.5625 sq.in.), is

(75 lbs/2.25 sq.in.) 33.33 pounds per square inch.

(e) Briefing Terminal. The point load equally distributed over four legs, each 0.75 inch square (0.5625 sq. in.), is (165 lbs/2.25 sq.in.) 73.33 pounds per square inch.

b. Dimensions. There will be two equipment cabinets/racks in each ARTCC and four equipment racks in ATCSCC. Each of the MWP racks are 22"W x 34"0 x 76"H. Figures 3-2 and 3-3 illustrate the two racks of equipment and the required front and rear clearance space for each rack.

c. Floor space.

(1) Processors. A space of 44"W x 118"0 (36.1 sq.ft.) for the ARTCC configuration and a space of 88"W x 118"0 (72.2 sq.ft.) for the

Chap 3 Page 8 Par 32

15

MONITOR

AlB SWITCH

I HIGH RATE MODEM I

Chap 3 Par 32 Page 9

6560.2SA 7/27/92

FIGURE 3-3. TOP VIEW OF MWP PROCESSOR RACKS

MWP MWP PROCESSOR PROCESSOR 3Z. RACK RACK

•• •

CHASSIS EXTENDED ON

SLIDES

44.

Chap 3 Par 32 Page 10

ATCSCC configuration is required. This includes front and rear access space.

17

(2) Work Stations. The MWP work station will include one desk, one table, and one chair. The MWP meteorologist desk will be approximately 60"W x 30"D x 26"H. The additional table is for the color printer and is approximately 26"W x 26"D x 26"H. The MWP meteorologist desk also includes two lockable drawers suspended under the left front corner of the desk top, a grommeted cable access hole near each rear corner, and a set of wire and cable holding clips to aid in cable management. The exact location of the MWP meteorologist desk will be determined at each of the MWP site surveys. In general, a maximum of 52.5 sq.ft. for the ARTCC and 105 sq.ft. for the ATCSCC will be required. This includes access and operator seating space. The chair has a molded, fabric-upholstered seat and back. Arms are foam-padded with resilient elastomer covering. Seat height is adjustable with a gas cylinder spring to raise the seat when a lever is pressed and the operator's weight is

lifted from the seat. Height and angle of the spring-loaded back is adjustable to provide lumbar support suited to individual operators. The chair swivels freely on a central column. The base of the chair has five legs for stability. Each leg has an independently swiveling dual caster. The seat and back fabric of the chair is grey leedsweave, a dense, soilresistant, 100-percent Nylon, medium blue-grey fabric. The chair upholstery fabric complies with the following performance standards:

(a) Flame resistance in accordance with National Fire Protection Association 260A, Class 1; Department of Commerce 191-53 Class 1; California Technical Bulletin 117.

(b) Wear resistance exceeds the requirements of GSA Specification CCC-C-00540, Amendments 1-4 for Type VIII fabric; ASTM Standard for Heavy Duty Upholstery - exceeds 80,000 double rubs.

(c) Non-upholstered surfaces are black elastomeric material finished in a fine haircell or pigskin texture. An example of the MWP meteorologist work station is provided in figure 3-4.

(3) Briefing Terminals. The briefing terminals will include one table. An additional table will be provided for the one color hardcopy printer. The briefing terminal table will be approximately 24"W x 30"D x 26"H (5 sq.ft. each). Figure 3-5 depicts the briefing terminal table. The color hard-copy printer table (26"W x 26"D x 26"H, 4.7 sq.ft.) is identical to the MWP work station printer table illustrated in figure 3-6. This space requirement does not include access or operator seating space. The ATCSCC will have eighteen (18) stations and the ARTCC's may have up to nine (9). The number of briefing terminals for each ARTCC is listed in appendix 1.

Chap 3 Par 32 Page 11

18

6560.2SA 7/27/92

FIGURE 3-4. TOP VIEW OF MWP METEOROLOGIST WORK STATION

.5 ~~~~-----~------~~~1

c: I

D

lllllllllllllllllliiii--J-1

I~~~-----;--------~~~~

(")

.5 0

Chap 3 Page 12 Par 32

FIGURE 3-5. TOP VIEW OF MWP BRIEFING TERMINAL

~o~~~~l~---------24 in ..--------1...~1

CPU

Monitor 30in. -

19

Keyboard ~D I I CCJ CJC

25-ln. High Tabl ''"'

Chap 3 Par 32 Page 13

6560.25A 7/27/92

FIGURE 3-6. TOP VIEW OF MWP COLOR PRINTER TABLE

I~~.--------------25in ..--------------~~~~

Seiko Video Copier 25in.

25-in. High Table

Chap 3 Par 32 Page 14

d. Cable runs. The maximum length of the cable run between the MWP processors and the last briefing terminal is limited to 640 feet, or 1,000 feet if a booster is utilized.

21

e. Electrical Power. The MWP has the following power requirements:

(1) Critical Power Requirements.

(a) Voltage and frequency.

120 VAC, +/- 10 percent, 1 phase, 60 Hz +/- 2 percent

(b) Current.

21 amps +/- 10 percent

(c) Power.

2.4 KW +/- 10 percent 2.8 KVA +/- 10 percent

(2) Essential Power Requirements.

(a) Table 3-1 gives the measured essential power requirements for the MWP based on antenna size. (The antenna size for each site is listed in appendix 1.)

TABLE 3-1. ESSENTIAL POWER REQUIREMENTS

Item Voltage Current Power Quantity Total Power

Color Printer 120 VAC 2.3 amps 163 Watts 2 326 Watts Briefing Terminal 120 VAC 2.4 amps 190 Watts 9 (max) 1710 Watts Work station 120 VAC 6.25 amps 460 Watts 1 460 Watts

Subtotal for Control Room Floor Equipment: 2496 Watts

Antenna Deicer (three types based on antenna size)

Control Box 120 VAC 6 amps 720 Watts 1 720 Watts 1.8 Meter Dish 120 VAC 11.5 amps 1390 Watts 1 1390 Watts 2.4 Meter Dish 120 VAC 23 amps 2760 Watts 2 5520 Watts 3.5 Meter Dish 3ph 208 VAC 23 amps 8132 Watts 1 8132 Watts Totals Control Room Floor Equipment With 1.8 Meter Dish: 4606 Watts Control Room Floor Equipment With 2.4 Meter Dish: 8736 Watts Control Room Floor Equipment With 3.5 Meter Dish: 11348 Watts

(3) Power sources.

(a) At the ARTCC, the MWP processor and the satellite

Chap 3 Par 32 Page 15

22

6560.25A 7/27/92

rece~v~ng equipment shall be connected to critical power after Site Acceptance Testing. Only one 30 amp breaker connection will be made to the critical power bus via the MWP power conditioning units. Power from the MWP power conditioning unit will be provided to the MWP processor and the satellite antenna. Power to the MWP work station and the briefing terminals will be supplied from the ARTCC essential power bus or the equivalent of the essential power bus. The connection to the critical power shall be in accordance with the provisions of Order 6950.158, ARTCC Critical Load Circuits and Configuration, the interim procedures for ARTCC space and power configuration management, and any approved regional Configuration Control Board (CCB) procedures. The project office has processed the National NAS Change Proposal (NCP) 13221 necessary for

critical power connection at the ARTCC's.

(b) The MWP processor shall be connected to essential power or the equivalent of essential power during site acceptance testing

(SAT) testing and critical power testing, if critical power testing is performed at the ARTCC's.

(c) The MWP shall present a load to the critical power bus that meets the requirements of FAA-G-2100e, Electronic Equipment, General Specification, sections 3.3.2, 3.3.4, and 3.3.7.

(d) The installation and testing at all FAA facilities shall comply with Order 6950.2C, Electrical Power Policy Implementation at National Airspace System Facilities.

(e) In the ATCSCC, the MWP shall be connected to the existing ATCSCC power bus.

(f) Except for Houston (ZHU), Miami (ZMA), Jacksonville (ZJX), and Oakland (ZOA), the satellite antenna will be supplied with deicing equipment. Power to the deicing need not be conditioned.

f. Environment. Indoor equipment environments are:

(1) Temperature: 60 to 90 degrees F.

(2) Relative humidity: 10 to 80 percent.

g. Electromagnetic Interference <EMil. The MWP will meet the requirements of MIL-STD-461C, Electromagnetic Emission and Susceptibility Requirements for the control of Electromagnetic Interference, Section 7.

33. INTERFACES. The MWP system will interface to RRWDS digitizers at the NWS and FAA radar sites, the MAD, and to the WMSC via the GS-200 at each site, except for Alaska, which will not have RRWDS or MAD interfaces

implemented.

a. RRWDS. The MWP system will interface to RRWDS digitizers at radar sites to obtain required real-time weather radar data. The contractor will coordinate between the NWS, the local ARTCC, and the

Chap 3 Page 16 Par 32

23

selected phone vendor on matters concerning the installation schedule, and all connectivity issues between RRWDS radars and the MWP. The contractor is responsible for distributing RRWDS data to multiple ARTCC's. The RRWDS interface will be in accordance with Attachment J-5 of the MWP contract.

b. MAD. The FAA has procured and will be installing a MAD in each ARTCC. The organization responsible for procuring MAD is En Route/Special Projects Program, ANR-110. The MAD will provide dial-up access to weather radar data from RRWDS equipped radars. This capability will allow up to eight users to simultaneously dial-in to the MAD and access radar signals for display from up to 16 radars. Additionally, some radars, which are not currently available on a dial-up basis at the radar site but are brought into ARTCC's via microwave communications, will be available on a dial-up basis through the MAD. The MWP contractor will provide RRWDS radar data to the MAD in each ARTCC on request. Radars required to support the mosaic radar product at each ARTCC will be continuously available. Questions concerning the MAD should be addressed to ANR-110.

c. WMSC. As part of the MWP contract, the MWP contractor shall develop, demonstrate, and implement an interface to the WMSC. This interface will allow the dissemination of meteorologist-created alphanumeric products. This interface shall be implemented via the Leased A/B Service (LABS) system's GS-200 located in or serving each of the ARTCC's and the ATCSCC. The GS-200 in Alaska is off-site and is connected via modem in a manner similar to the test configuration described below. The WMSC interface preliminary demonstration will be accomplished as part of the Factory Acceptance Test (FAT) and final testing at the site acceptance testing. As part of this development activity, the contractor has been provided with the capability to access the GS-200 at the GS-200 vendor's facility via a dial-up port. The GS­ 200 port to be-used for the WMSC interface development will be connected to the MWP contractor's facility via modem. The contractor will provide all communications back to his facility during the development and demonstration of the WMSC interface. Messages may be sent from the contractor's facility, via the modem to the GS-200 at the GS-200 vendor's facility. In this way the contractor can perform needed development tests of the WMSC interface. The MWP-WMSC interface via the GS-200 will be in accordance with Attachment J-12 of the MWP contract.

34.-39. RESERVED.

Chap 3 Par 33 Page 17 (and 18)

25

CHAPTER 4. PROJECT SCHEDULE AND STATUS

40. PROJECT SCHEDULES AND GENERAL STATUS. The MWP contract was awarded on September 29, 1989, to Harris Corporation, Government Information Systems Division, located in Melbourne, Florida. The current project milestones are provided in appendix 1. For planning purposes, the regions may obtain a Systems Engineering and Integration (SEI) developed and maintained ARTEMIS schedule from the SEI contractor regional representatives.

41. MILESTONE SCHEDULE SUMMARY. Milestones that pertain to implementation are listed in appendix 1. These milestones reflect key contract deliverables required by the Statement of Work and a site specific delivery schedule.

42. INTERDEPENDENCIES AND SEQUENCE. For the MWP/WMSC interface, the MWP will operate as a LABS (GS-200) terminal. There is a planned modification to the GS-200 that will enable the GS-200 to convert from ASCII to X3.28. This new protocol conversion capability of the GS-200 will be utilized by the MWP and other processors. The involvement of the GS-200 will be strictly limited to the allocation and use of one

Input/Output (I/O) port. When the MWP is installed at a site where the MAD device is operational:

a. The MWP contractor will supply the. RRWDS radar data to the MAD.

b. The dial-in telephone lines connected to the MAD are the responsibility of the FAA.

c. Maintenance of the MAD is an FAA responsibility.

43.-49. RESERVED.

Chap 4 Par 40 Page 19 (and 20)

27

CHAPTER 5. PROJECT MANAGEMENT

50. PROJECT MANAGEMENT, GENERAL.

a. FAA Project Manaaement. The overall management of the MWP project shall be the responsibility of the Program Manager for Weather Processors, ANW-300. This organization will accomplish management tasks within the guidelines provided by FAA policies, procedures, and directives. A member of ANW-300 has been designated the MWP Program Manager and is the single focal point fpr all MWP project activities. The technical and contract management of the MWP shall be the responsibility of ANW-130.

b. Contracting Officer. The Contracting Officer (CO) has been designated by the Office of Acquisition Support, Contracts Division, ASU­ 330. The CO performs the general contract management activities of monitoring contractor schedules, assessing problem reports and solutions,

attending meetings, conducting inspections, conducting in-progress reviews, and all other. activities concerned with assuring that the terms of the contract are met. The CO is the only person authorized to make changes that will affect prices, deliverables, or schedules.

c. Contracting Officer's Technical Representative. The Contracting Officer's Technical Representative (COTR) has been designated by the CO

and provides technical guidance and direction to the contractor within the scope of the contract. The COTR shall ensure that the contractor has access to technical documentation, appropriate data bases, and sources of information relative to Government Furnished Equipment (GFE). The COTR has overall responsibility for inspection and acceptance of the MWP service. The COTR may designate the ARTCC Air Traffic Technical Representative (ATTR) as the individual responsible for inspecting and

accepting the MWP.

d. Air Traffic Plans and Requirements Associate Program Manager. The Air Traffic Plans and Requirements Service shall appoint an Air Traffic Plans and Requirements Associate Program Manager (ATRAPM). The ATRAPM will coordinate proposed changes to Order 7210.38A, Center Weather Service Unit, and Chapter D-25 of the Weather Service Operations Manual

(WSOM) with the regional Air Traffic Associate Program Manager (ATAPM), the ARTCC ATTR, the NWS MWP Project Manager, and the MWP Project Manager

for changes to these documents.

e. FAA Airwav Facilities Regional Proaram Manaaement. Each region shall appoint an MWP Airway Facilities Associate Program Manager (AFAPM). The AFAPM shall ensure that facilities and engineering work is completed prior to the delivery of the MWP equipment. The AFAPM shall monitor the installation of the MWP equipment and coordinate requests for contractual or technical support with ANW-130. Each AFAPM shall designate an Airway Facilities Technical Representative (AFTR) at each ARTCC. The Eastern Region AFAPM shall also designate an AFTR for the ATCSCC. The AFAPM shall coordinate with the ARTCC and ATCSCC AFTR's to ensure that adequate staffing is maintained during scheduled Airway Facilities (AF) training.

Chap 5 Par 50 Page 21

28

6560.2SA 7/27/92

FIGURE 5-l. MWP ORGANIZATION CHART

ATR-130

ATRAPM

ACI-230 ASM-400

ACT AAF TECH REP TECH REP

AIW-300 ASIJ-330 - I FAA . . CONTRACTING PROGRAM MANAGER OFFICER I I I AXX...cooJSOO IWS

REGIONAL NWS PROGRAM MANAGERS PROJECT MANAGER

I I I AXX-4XXJ5XX I ARTCC TECHNICAL

CWSU/CFWSU

TECH REP REPRESENTATIVES I

COTR

~------­

Chap 5 Page 22 Par 50

29

The AFAPM shall be responsible for equipment removal and disposal in accordance with Order 4800.2A, Utilization and Disposal of Excess and Surplus Personal Property. (A suggested plan of action is provided in paragraph 85.)

f. FAA Air Traffic Regional Program Management. Each region shall appoint an MWP ATAPM. The ATAPM will designate the ATTR at each center. The ATAPM shall coordinate with the ARTCC and ATCSCC ATTR's to ensure that adequate staffing is maintained during scheduled Air Traffic (AT), TM, and NWS training. The ATAPM will also review ATTR recommended changes in operating procedures and coordinate comments with the ATRAPM.

g. ARTCC/ATCSCC Airway Facilities Technical Representative.

(1) The ARTCC/ATCSCC AFTR shall be appointed by the respective AFAPM's. They shall be responsible to the COTR for the management of site preparation, installation, and acceptance activities within their respective facilities. The AFTR shall be responsible for ensuring that the MWP site preparation activities are complete and acceptable before the MWP equipment arrives.

(2) The AFTR will be responsible for assisting the MWP contractor in conducting the site survey, coordinating through the AFAPM, ANW-130, and ASU, any site preparation work. The contractor and facility personnel will jointly determine the cable runs required during the site survey. The contractor shall then prepare the cables. For those facilities which prefer to install cables themselves, the contractor shall ship the cables a minimum of 45 days prior to equipment delivery so that the facilities personnel can install them prior to delivery of the MWP equipment. Where the cable route makes it possible, the contractor shall ship cables complete with connectors attached.

(3) The AFTR shall report any problems encountered during the contractor's installation of the MWP and the resolution of these problems with the help of the AFAPM and ANW-130, if required. The AFTR must ensure that all MWP hardware has been installed according to the MWP contractor's Installation and Checkout (I/CO) Plan, that acceptance testing has been completed, and that Initial Operational Capability (IOC) has been reached. The AFTR shall ensure that all contractor training for the AF personnel has been completed satisfactorily. The duties of the AFTR will be completed when the MWP is made available for service.

(4) The AFTR is to coordinate with the ATTR for AF training.

h. ARTCC/ATCSCC Air Traffic Technical Representative.

(1) The ATTR shall ensure that all contractor training for the NWS meteorologists, and the associated NWS training to TMU and supervisory personnel has been satisfactorily completed, and shall participate in the acceptance activities at their respective facilities.

Chap 5 Par 50 Page 23

30

6560.25A 7/27/92

(2) The ATTR shall make recommendations to change operational procedures.

(3) The ATTR shall coordinate these recommendations with the NWS CWSU/CFWSU technical representative and then forward them to the ATRAPM. The duties of the ATTR will be completed when the MWP is made available for service.

i. National Weather Service Project Management. The NWS has appointed a NWS MWP Project Manager. The NWS Project Manager will appoint technical representatives as needed to participate in selected MWP activities. The NWS Project Manager will receive recommended changes in the procedures to WSOM chapter D-25 from the NWS CWSU/CFWSU technical representatives and Regional Aviation Meteorologists (RAM) prior to the operational readiness date (ORD). The NWS Project Manager will coordinate with the FAA ATRAPM in revising WSOM Chapter D-25 procedures and the ATRAPM will coordinate with the NWS Program Manager in revising Order 7210.38A. The NWS Program Manager will monitor and coordinate requests for technical support with FAA MWP Project Manager.

j. NWS CWSU/CFWSU Technical Representative. The NWS CWSU/CFWSU technical representative shall be the Meteorologist-In-Charge (MIC) in each facility. The NWS CWSU/CFWSU technical representative shall coordinate training with the FAA ATTR for NWS personnel, aid in training the traffic management coordinators and area supervisors, and provide assistance as needed in other site activities. Problems encountered shall be coordinated with the FAA facility ATTR and ATAPM, NWS Project Manager, and ANW-130, if required. The NWS CWSU/CFWSU technical representative shall also be responsible for recommending changes in procedures to the RAM and the NWS Project Manager. These changes in procedures shall be coordinated with the ATTR. The implementation duties of the NWS CWSU/CFWSU technical representative shall be completed when the MWP is made available for service.

k. FAA Technical Center Project Manaoement. A test representative shall be appointed from the FAA Technical Center Communications/ Navigation/Surveillance Division (ACN-200) and Weather and Remote Maintenance Monitoring Systems Branch (ACN-250), to serve as lead for

integration testing. ACN-250 will review plans and procedures and monitor test activities for factory acceptance test (FAT), site

acceptance test (SAT), shakedown test and evaluation (ST&E), and operational test and evaluation (OT&E). ACN-250 will prepare test documentation and conduct any required integration tests. Test representative activities will be coordinated with the MWP Project Manager, ANW-130.

1. FAA Operational Suitability Testing Manager. ASM-400 will:

(1) Have overall responsibility for testing operational suitability of the MWP service.

Chap 5 Page 24 Par 50

31

(2) Name a representative who shall coordinate with the users and ANW-130 on all testing issues (FAT, SAT, ST&E, and OT&E) through the conclusion of Joint Acceptance Inspection (JAI).

(3) Review plans and procedures and monitor test activities for FAT, SAT, and integration testing.

(4) Prepare test documentation and conduct any required operational suitability tests.

(5) Coordinate with the users and ANW-130 to resolve any issues that may arise.

m. Associate Program Manager for Logistics CAPMLl. The NAILS Program Divison (ANS-400) shall appoint an APML who shall be responsible for ensuring that all National Airspace Integrated Logistics Support

(NAILS) requirements are identified and satisfied.

51. PROJECT CONTACTS. Appendix 2 has a listing of project management personnel designated as points of contact for respective organizations.

52. PROJECT COORDINATION.

a. General. The MWP COTR has the overall responsibility for the acceptance of the MWP service. Major organizational responsibilities are as follows:

ANW-130: Project management, service procurement, and configuration management.

ATM-110: AT requirements and acceptance testing.

ATR-130: AT requirements and certification.

NWS: Meteorologist requirements and procedures.

ACN-250: NAS integration testing.

ASM-400: System shakedown.

ASM-300: Interfacility communications.

ASU-300: Preparation and negotiation of contract and contract modifications.

AHT-400: Personnel and technical training.

ANS-200: Space Configuration Management, power connection, and configuration management.

ANS-420 National Airspace Integrated Logistics Support

Chap 5 Par 50 Page 25

32

6560.25A 7/27/92

ALG-300 Advise the regions on disposal of replaced equipment.

AXX-400: Assign AFAPM's and ARTCC/ATCSCC AFTR's.

AXX-500: Assign ATAPM's and ARTCC/ATCSCC ATTR's.

AAC-932d: Supply training materials to new FAA and NWS hires.

ARTCC/ATCSCC: Site configuration management, site preparation, site

survey support, and equipment installation support.

SEI contractor: Project management support and planning.

Support Contractors: Project management support.

Contractor: Provide MWP service which includes hardware, software, data stream, communications, maintenance, and initial training for the NWS meteorologists and AF personnel. A limited number of AT personnel will attend a module of the NWS meteorologist/AF courses.

b. Weather and Flight Service systems CANWl Responsibilities.

(1) Direct, guide, and coordinate overall project activities.

(2) Develop and baseline a system specification based on validated user requirements.

(3) Fund a contractor.

(4) Develop and maintain the project master schedule.

(5) Ensure adherence to Capital Investment Plan (CIP) and availability of funds.

(6) Develop and maintain the PIP.

(7) Develop an Integrated Logistics Support Plan.

(8) Coordinate the training program with Air Traffic Training Program Division, AHT-500.

(9) Develop and maintain the project Master Test Plan.

(10) Develop any appropriate national NCP for the MWP connection to critical power.

(11) Ensure vendor maintenance support is in-place.

(12) Accept the MWP services from the contractor.

Chap 5 Page 26 Par 52

33

(13) Task the SEI contractor and other support contractors as required for effective project management.

(14) Develop the draft JAI checklist in accordance with Order 6030.45, Facility Reference Data File.

c. Air Traffic Plans and Procedures !ATP> Responsibilities. ATP will prepare MWP operational procedures.

d. Air Traffic System Management !ATM> Responsibilities.

(1) Identify operational/functional concepts.

(2) Review and approve/disapprove operational cutover plans.

(3) Support ANW-130 in the acquisition of the service by participating in site acceptance testing.

(4) Support the MWP contractor development of a WMSC interface using the LABS system and the GS-200's.

e. Air Traffic Plans and Requirements Service !ATR> Responsibilities.

(1) Identify operational/functional reuirements.

(2) Coordinate the AT training requirements and training program.

(3) Provide advice and representation on technical training programs.

(4) Coordinate with the NWS Project Manager on related WSOM procedures and FAA order changes.

(5) Collect overall AT and NWS operational and functional requirements for the MWP and associated briefing terminals.

(6) Coordinate overall AT and NWS operational and functional requirements for the MWP and associated briefing terminals.

(7) Validate overall AT and NWS operational and functional requirements for the MWP and associated briefing terminals, as well as being involved in all phases of testing and evaluation, including

factory, site acceptance, and follow-on evaluations.

f. NWS Responsibilities.

(1) Identify operational/functional requirements.

(2) Update WSOM Chapter D-25 procedures and recommend changes

Chap 5 Par 52 Page 27

34

6560.25A 7/27/92

to FAA orders to reflect operational changes due to the MWP

implementation.

(3) Coordinate with FAA ARTCC AT and AF technical representatives to provide facility meteorologists, AT, and AF training, uninterrupted operational system planning, and coordinate cutover with the ATTR.

(4) Provide assistance in training the FAA traffic management coordinators and area supervisors in the use of briefing terminals.

g. FAA Technical Center, Engineering, Test, and Evaluation Service CACNl Responsibilities.

(1) Appoint a test manager for NAS integration test and evaluation (IT&E).

(2) Develop the NAS integration test plan (ITP) and test procedures.

(3) Conduct NAS IT&E at the first operational site.

(4) Report on NAS IT&E at the first operational site.

(5) Support ANW-130 in the review and acceptance of the FAT, SAT, ST&E, and OT&E plans and procedures.

(6) Support ANW-130 in monitoring FAT, SAT, ST&E, and OT&E tests for compliance with their respective plans and procedures.

h. Systems Maintenance Service CASMl Responsibilities.

(1) Appoint a test manager for ST&E.

(2) Develop the ST&E plans and procedures.

(3) Validate the ST&E plans and procedures at the ATCSCC and the first operational site.

(4) Conduct ST&E at the ATCSCC and first operational site.

(5) Report on the ST&E at the ATCSCC and the first operational site.

(6) Provide validated and updated ST&E plans and procedures to all other MWP sites for their ST&E.

(7) Support ANW-130, AF, and AT during ST&E and OT&E of other MWP sites.

(8) Process daily down time and maintenance action information.

Chap 5 Page 28 Par 52

35

(9) Support ANW-130 in the review of the FAT, SAT, and IT&E plans and procedures.

(10) Support ANW-130 in monitoring FAT, SAT, and IT&E tests for compliance to their respective plans and procedures.

(11) Identify a site and a GS-200 port for the WMSC interface development.

i. Acauisition Support CASU) Responsibilities. Prepare, negotiate, and administer a contract for MWP services.

j. Training and Higher Education <AHTl Responsibilities.

(1) Assure that project technical training requirements are identified.

(2) Assure that the contractor-provided technical training programs meet the training requirements and are administered according to the contract.

k. NAS Telecommunications Management and Operations Division (ASM-300) Responsibilities.

(1) Manage space, critical power, and intrafacility communications configuration.

(2) Assign specific ports on modems and statistical multiplexers for contractor access to microwave-relayed RRWDS data.

(3) Provide the contractor access to the MAD in order for the contractor to supply RRWDS data to the MAD.

(4) Coordinate with the contractor in order for the contractor to provide RRWDS data to the MAD.

(5) Provide a dedicated access port to each FAA RRWDS digitizer.

(6) Ensure that all NAILS requirements are identified and satisfied.

1. FAA Academy <AACl Responsibilities. The FAA Academy will provide training materials to NWS and FAA new hires.

m. Loaistic Services CALGl Responsibilities. Logistic Services will support AF regional personnel in the removal and disposal of obsolete CWSU equipment.

n. Airway Facilities Regional/ARTCC/ATCSCC Responsibilities.

Chap 5 Par 52 Page 29

36

6560.2SA 7/27/92

(1) Conduct initial site survey and support contractor's site survey to identify cable run paths, potential structural modifications to support potential satellite antenna installation, and establish a location for the contractor's leased line connections.

(2) Generate NCP's to establish configuration baselines for each site which satisfy floor space and critical power requirements.

(3) Perform site preparation including site engineering and planning, update facility documentation, drill holes through operations

floor and walls for cable routing, install signal and power cables.

(4) Provide assistance to the contractor during installation.

(S) Review the generic and site-specific site preparation requirements plan, SAT plans and procedures, site survey report, and I/CO plan prior to installation and ensure that all FAA activities are completed.

(6) Provide the contractor access to the installation site and coordinate with the contractor on installation and integration activities.

(7) Appoint a representative in each ARTCC to monitor, signoff, and report all MWP maintenance activities.

(8) Monitor and report, to ANW-130, contractual compliance with installation plan and site test procedures and ensure that all nonconformances have been documented.

(9) Support site acceptance testing.

(10) Conduct the JAI.

(11) Support the contractor in scheduling personnel for training.

(12) Update the facility drawings.

(13) Plan, coordinate, remove, and dispose of obsolete CWSU equipment in accordance with Order 4800.2A.

o. Air Traffic Regional/ARTCC/ATCSCC Responsibilities.

(1) Provide space for the contractor to conduct training.

(2) Coordinate with the NWS RAM's and the CWSU/CFWSU technical representatives to provide facility meteorologists and AT training, uninterrupted operational system planning, and coordinate cutover with ATTR.

(3) Coordinate the facility plans and procedures with AF

Chap 5 Page 30 Par 52

37

necessary to modify and/or relocate the current CWSU work area.

(4) Support site acceptance testing.

p. System Engineering and Integration <SEI> Contractor Responsibilities. The SEI contractor will support:

(1) Overall project activities.

(2) The development and baselining of a system specification based on validated user requirements.

(3) The development and maintenance of a project master schedule.

(4) Adherence to the CIP and availability of funds.

(5) The development and maintenance of a PIP.

(6) The development of an integrated logistics support plan.

(7) AT, AF, and NWS meteorologist training requirements and coordinate the training program with AHT-400 and AHT-500.

(8) Development of project Master Test Plan.

q. Other Support Contractors Responsibilities. Other support contractors will support:

(1) Overall project activities.

(2) The development and baselining of a system specification based on validated user requirements.

(3) Adherence to the CIP and availability of funds.

(4) The development and maintenance of a PIP.

(S) The development an Integrated Logistics Support Plan.

(6) AT, AF, and NWS meteorologist training requirements and coordinate the training program with AHT-400 and AHT-500.

(7) Development of the project Master Test Plan.

r. MWP Contractor Responsibilities.

(1) Prepare all contract specified plans:

(a) Site Preparation Requirements Plan.

Chap 5 Par 52 Page 31

38

6560.25A 7/27/92

(b) Installation and Checkout Plan.

(c) Operations and Maintenance Plan.

(d) Contractor Master Test Plan.

(e) FAT Plan and Procedures.

(f) SAT Plan and Procedures.

(g) Contract Training Plan.

(2) Conduct FAT at the contractor's facility.

(3) Conduct site surveys at each MWP site.

(4) Install MWP equipment.

(5) Conduct checkout and SAT of the MWP.

(6) Conduct NWS meteorologist and AF training in accordance with contract prov~s~ons. A limited number of AT personnel will attend a module of the NWS/AF training courses to gain indepth knowledge of the MWP system.

(7) Ensure contractor maintenance support is in accordance with contract provisions.

53. PROJECT RESPONSIBILITY MATRIX • The MWP responsibility matrix is provided in .figure 5-2.

54. PROJECT MANAGERIAL COMMUNICATIONS.

a. Meetings.

(1) The contractor has conducted a post-contract award kick-off meeting. Copies of the minutes may be obtained through the MWP Project Office.

(2) The contractor will schedule and conduct monthly progress meetings at the contractor's facility until the FAT is completed. Additional meetings will be scheduled, as required, until the last SAT is completed.

(3) The contractor's project manager will meet, as needed, with the COTR for discussions regarding MWP status.

(4) Meetings to discuss training issues will also be held, as needed, at the contractor's facility.

Chap 5 Page 32 Par 52

39

FIGURE S-2. MWP RESPONSIBILITY MATRIX

ACTIVITY ANW ATM ATR NWS ACN ASM ASU AHT ASE lAC Af AT sa ANS CONTRACTOR

OlHER= 1. PROJ. MAST<R SCHED SVSTEMSPECIACAllON p s s

2. DEVELOP MWP PIP p R R R R R R R R R R R M p R M

l DEVELOPMWP ILSP R R R R R s R s .. PROJECT MAST<R TEST PLAN R R R R s R R

~J~MASm A R R R p R

6. SIT!SUIMY M M D M c

7. SIT! PREPARAllON PLANS &PROCEDURES A R R R p

8. CONDUCT SIT! PREPARATION c s

9. SITE PREPARAllON REPORlS R R R R

10. FAT PLANS & PROCEDURES A R R R R p R

11. CONDUCTFAT M M M M M c M

12. fAT REPORlS A R R R R R R p R

13. ~0 PLANS & PROCEDURES A R R R p

1•. CONDUCT IICO M M M p c

15. IICOREPORlS A R R R p

16. SAT PLANS & PROCEDURES A R R R R R R p R

17. CONDUCTSAT M M M M M M M c M

18. SATREPORTS A R R R R R R p R

19. IT&E/SLT&E PLANS &PROCEDURES A R p R R R R

20. CONDUCT IT&E M M c M M M M M M

21. IT&E/SLT&E REPORTS A R p R R R R R R

22. OT&E /ST&E PLANS &PROCEDURES A R R R p R R R R

23. CONDUCT OT&E I ST&E M M M M c M M M

~. OT&E/ST&E REPORlS A R R R p R R R R

25. PROOUCEllWMNG MATERIAl A R R A R R p R

26. CONDUCTIWiS/AF TRAINING M M M M M R c

27. ASSIST AT JlM TRAINING c M M R

28. MAINTAINTlWNING MATERIAL c M

29. MWP MAINTENANCE REPORllNG M c M M

30. MWPMAINTENANCE M M M M c

lEGEND A~ p "'-­ ~ oaa- C CGrc1uc1 I Potlonn R --c:omo-r D DftCI s~ M-tot~....,. Chap 5 Par 54 Page 33

40

6560.25A 7/27/92

(5) ANW-130 will hold weekly staff meetings to discuss project progress and issues.

(6) Program Director Status Review (PDSR) meetings are held with ANW-1 bimonthly to review project status including cost and schedule

issues.

(7) Major System Acquisition review meetings are held with the Office of the Administrator (AOA-1) on a quarterly basis.

b. Reports.

(1) The contractor will prepare monthly progress, status, and management reports until the last SAT is complete.

(2) The contractor will prepare conference minutes.

(3) The regional AFAPM's will prepare monthly reports until the last ORO is completed synopsizing contractor progress, potential problem areas, and their potential resolutions.

55. IMPLEMENTATION STAFFING. There are no unique or peculiar staffing requirements associated with the implementation of this project. Offices with assigned responsibilities are expected to accomplish their tasks with existing resources.

56. PLANNING AND REPORTS. Successful implementation of the service described in this order will require the preparation and approval of several documents by the FAA and the contractor. Included in this are items such as the Master Test Plan, Configuration Management Plan, Installation and Checkout Plan, Training Plan, Maintenance Plan, Test Procedures, Test Reports, etc. A list of the applicable plans and reports required for implementation is included in appendix 1.

57. APPLICABLE DOCUMENTS.

a. FAA-S-2834 Meteorologist Weather Processor (MWP) System

Specification

b. FAA-G-2100e Electronic Equipment, General Requirements

c. Order FAA NAS Test and Evaluation Program 1810.4A

d. Order System Requirements Statement for the 1812.7 Central Weather Processor

e. Order Utilization and Disposal of Excess and Surplus 4800.2A Personal Property

f. Order Facility Reference Data File 6030.45

Chap 5 Page 34 Par 54

41

g.

h.

i.

j.

k.

1.

58.-59.

Order

6950.2C

Order 6950.158

Order

7210.38A

WSOM Chapter D-25

MIL-STD-461C

RESERVED

Electrical Power Policy Implementation at National Airspace System Facilities

ARTCC Critical Load Circuits and Configuration

Center Weather Service Unit

National Weather Service, Operations Manual Support to Air Traffic Facilities

Electromagnetic Emission and Susceptibility Requirements for the Control of Electromagnetic Interference

Uniform Building Code, May 1985

Chap 5 Par 57 Page 35 (and 36)

43

CHAPTER 6. PROJECT FUNDING

60. PROJECT FUNDING STATUS, GENERAL. The project is fully funded.

61. SPECIAL FUNDING REQUIREMENTS. The following items will be funded by the MWP Project Office:

a. Intrafacility equipment moves from initial locations to accommodate ongoing facility modernization.

b. Equipment removals for replaced equipments.

c. Site preparation subject to the review and approval of the Site Preparation Requirements Plan (SPRP) for each site.

62. REGIONAL TRAVEL. A lump sum was provided to the regions from the project office to provide for travel for field and regional personnel as required to support the MWP project implementation.

63.-69. RESERVED.

Chap 6 Par 60 Page 37 (and 38)

45

CHAPTER 7. DEPLOYMENT

70. GENERAL DEPLOYMENT ASPECTS. The general deployment aspects and the schedule for the Deployment Readiness Review (ORR) of the MWP are:

a. Deployment Aspects.

(1) FAA has provided generic site equipment location drawings to prospective bidders.

(2) Bidders have submitted generic site installation requirements and cost estimates as part of their proposals.

(3) Upon contract award, the FAA has provided additional details on site-specific equipment locations to the contractor. The data was based on responses to the ANW-130 letter of May 30, 1988, and any updates provided by the regions prior to contract award.

(4) Upon contract award, the FAA has provided the generic site installation requirements of the selected contractor to all regions and sites.

(5) Contractor will perform site surveys. The roles of FAA site personnel and the contractor concerning the physical installation of system cabling will be determined by each ARTCC AF Sector Manager based upon the results of the site survey.

(6) Contractor will deliver the SPRP which will include specific site preparation actions to be accomplished by FAA sites.

(7) Regions will accomplish required site preparation as defined in the SPRP and update the facility drawings.

(8) Contractor will prepare detailed I/CO plans for each site.

(9) Contractor will deliver the system to the site.

(10) The COTR, or his/her designated representative, along with the contractor and FAA site personnel will conduct pre-installation walkthrough. This will ensure that all site preparations activities have been successfully completed and that all equipment, tools, and personnel are onsite and ready for the I/CO.

(11) Contractor will install and checkout the system in accordance with the approved I/CO plan. The MWP processor will initially be connected to essential power during all phases of testing. The installation and testing shall comply with Order 6950.2C, Electrical Power Policy Implementation at National Airspace System Facilities.

(12) The contractor will perform the SAT in accordance with the contractor developed and FAA approved SAT plan and procedures. The FAA will monitor the conduct of the SAT and review/approve the SAT report.

Chap 7 Par 70 Page 39

46

6560.25A 7/27/92

(13) The contractor will provide required NWS and AF training in accordance with approved training plans and course documentation. A limited number of AT personnel will attend a module of the NWS/AF training courses to gain indepth knowledge of the MWP system.

(14) Each site will perform the Contract Acceptance Inspection (CAI) in accordance with the provisions of Order 6030.45.

(15) Each site will perform the integration testing in accordance with ACN-250 developed plans and procedures.

(16) Each site will declare IOC after successful completion of the integration tests along with the completion of the required training and receipt of all required documentati~n.

(17) Each site will perform the system shakedown in accordance with ASM-400 developed plans and procedures.

(18) Each site will perform the JAI and declare the ORD in accordance with the provisions of Order 6030.45.

(19) After successful SAT, the MWP power conditioning units shall be connected to critical power.

b. DRR Schedule. The milestones and dates for all DRR activities are contained in Appendix 1, Milestones and Schedules.

71. SITE PREPARATION. Site preparation will be performed in accordance with the contractor prepared and FAA approved SPRP. This plan will be based upon the results of each individual site survey. The regions are responsible for site preparation. Site preparation may be performed by AF personnel, the Technical Services Support Contractor (TSSC), or other contractors as determined on a site-by-site basis.

72. DELIVERY. Delivery dates are not specified in the contract. The completion of the FAT and SAT will be in accordance with the requirements of the MWP contract and Statement-of-Work. Estimated delivery dates are provided in Appendix 1, Milestones and Schedules.

73. INSTALLATION PLAN. The contractor will prepare I/CO plans to reflect site specific requirements and plans as agreed to during the site survey. The I/CO plans shall include the appropriate seismic requirements as specified in the Uniform Building Code, section 2312 and Table 23-J. Plans for ZLA, ZOA, and ZAN require zone 4 compliance. Sites ZSE, ZBW, ZME, and ZLC require zone 3 compliance. ZAB and ZTL require zone 2 compliance. All other sites are classified as zone 1 or zone 0, neither of which require special seismic consideration. AF personnel will ensure these sites are prepared as necessary to meet the

seismic requirements.

74.-79. RESERVED.

Chap 7 Page 40 Par 70

47

CHAPTER 8. VERIFICATION

80. FACTORY VERIFICATION. Factory verification will consist of a FAT. The FAT plan and procedures will be written by the contractor and approved by the FAA. The FAT will consist of system-level testing on the first system delivered only and will be performed at the contractor's facility. The FAT will verify all system requirements as defined in FAA­ S-2834 and verify the requirements necessary for the MWP to connect to critical power.

81. CHECKOUT. The I/CO of the MWP will be accomplished in accordance with the provisions of the I/CO plan. The I/CO plan will be written by the contractor and approved by the FAA.

82. CONTRACTOR INTEGRATION TESTING. There is currently no requirement for contractor integration testing of the MWP system with other NAS systems. SAT plans and procedures will be written by the contractor and approved by the FAA. The SAT will be performed by the contractor after completion of the I/CO. ACN-250 will accomplish part or all of the MWP integration testing by witnessing appropriate parts of the SAT. The SAT will demonstrate the functional performance of the MWP. The contractor will provide required NWS/AF training at the completion of the SAT. A limited number of AT personnel will attend a module of the NWS/AF training courses to gain indepth knowledge of the MWP system.

83. CONTRACTOR ACCEPTANCE INSPECTION. The CAI will be performed after the site acceptance testing and training is complete. Requirements will include the completion of the I/CO, SAT, and training. At the CAI the COTR, or his/her designated representative, will accept the system for use in the CWSU and/or CFWSU.

84. FAA INTEGRATION TESTING. Integration testing will be performed by ACN-250 in accordance with Order 1810.4. For the basic system the integration testing will be limited to the RRWDS, GS-200, and MAD interfaces. ACN-250 will accomplish part or all of the MWP integration testing by witnessing appropriate parts of the SAT. For the WMSC interface, ACN-250 will test the integration of the MWP with the WMSC via the GS-200. Upon successful completion of the integration testing, the IOC will be declared.

85. SHAKEDOWN AND CHANGEOVER. ASM-400 has been tasked to develop the shakedown plans and procedures as required by Order 1810.4. The system shakedown will exercise the MWP system in the real operational environment and assist in the development and refinement of operational procedures. These will be developed for the ARTCC with modifications for the ATCSCC environment. The system shakedown plans and procedures will be validated at the ATCSCC and first ARTCC site and provided to the remaining sites for their use in conducting the system shakedown. After shakedown is completed at the first site, the final ORR report will be briefed to AAF-1 and the ORR Executive Committee for a deployment decision. Following each field shakedown, the ARTCC's and the ATCSCC will be allowed a period of parallel operations between the MWP and

Chap 8 Par 80 Page 41

48

6560.25A 7/27/92

existing Geostationary Operational Environmental Satellite (GOES) facsimile (FAX), digital FAX (DIFAX), RRWDS displays and processors, and/or other unique CWSU equipment. Each ARTCC and the ATCSCC is responsible for providing the regional AFAPM a list of equipment to be disposed of at the particular site. The following guidelines are provided for the disposal of equipment.

a. The ATTR and the MIC should determine if any:

(1) Non-standard/special equipment purchased/leased by the region or ARTCC should be disposed.

(2) Other users (Flight Service Stations, NWS Weather Forecasting Offices) are supported by the current CWSU equipment (i.e., RRWDS leased lines and/or processors).

b. The suggested standard list of equipment to be removed at each site include the following:

(1) RRWDS displays.

(2) RRWDS processors and leased lines to the RRWDS processors with the exception of those sites with other users as described in subparagraph 85a(2).

(3) GOES FAX.

(4) DIFAX, only after the MWP begins to receive the high altitude AFOS graphics not currently available through the NWS's Family Of Services.

(5) Any other unique equipment that falls under subparagraph 85a(1) and is deemed unnecessary by the ATTR and the cwsu MIC.

c. ANW-130 recommends the following procedures for disposal of the RRWDS displays and processors.

(1) Coordinate with the FAA Logistics Center for disposal of the RRWDS displays and processors. The RRWDS displays and processors may be of some value since many flight service stations utilize similar equipment.

(2) Coordinate with the NWS weather forecasting offices since many of these offices utilize similar equipment.

(3) Salvage the equipment.

Chap 8 Page 42 Par 85

49

86. JOINT ACCEPTANCE INSPECTION. Each site will perform the JAI as defined in Order 6030.45 and declare the ORO. Harris Corporation will maintain both the MWP's hardware and software for the life of the system, therefore the software documentation, hardware documentation, and spares

logistics do not seem to be of concern during the JAI.

87.-89. RESERVED.

Chap 8 Par 86 Page 43 (and 44)

51

CHAPTER 9. INTEGRATED LOGISTICS SUPPORT

90. MAINTENANCE CONCEPT.

a. The MWP contract requires the contractor to perform all maintenance on the MWP for the life of the contract to meet the

availability requirements as stated in the system specification. Contractor maintenance includes contractor provided communications equipment and telecommunications circuits. The contractor is required to provide a maintenance plan which describes how the support of the MWP is to be accomplished.

b. The MWP System specification states that the MWP shall have a functional availability based upon 24 hour/day, 7 days/week operation, of 0.995. The MWP has a mean downtime of 4 hours with a maximum down time of 8 hours. The contractor must respond to meet the availability requirements or the Government will accrue downtime credit.

c. The contractor is required to provide the Government a primary point of contact with a telephone number and address and make arrangements to receive requests for service assistance 24 hours per day, 7 days a week. The contractor is also required to provide a secondary point of contact in the event the primary point of contact is not available.

d. The contractor will provide training to AF personnel in order for the AF personnel to determine if the MWP is operational as well as provide overall knowledge of the MWP system.

e. The contractor is required to provide an Operations and Maintenance Plan. The plan includes a list of equipment and techniques used to provide fault detection and isolation, a description of any other

fault reporting techniques or devices incorporated into the operation and maintenance devices, a schedule for contractor performed preventive maintenance activities, and a description of the procedures for reporting malfunctions.

91. TRAINING. MWP training will be provided at each site as follows:

a. National Weather Service. The NWS meteorologists at each site will be trained by the contractor in the complete operations of the MWP

system, work stations, and briefing stations. The contractor will provide a complete package of training materials to each site and the FAA Academy. Two of these courses will be conducted at each site.

b. Air Traffic. The contractor will develop an AT Operations Systems User's Guide. A limited number of AT personnel will attend a module of the NWS/AF training courses to gain indepth knowledge of the MWP system. Lectures/briefings for AT personnel will be given by the MWP contractor on the use and operation of the briefing terminals. Additionally, TMU and supervisory personnel will be trained in the operations of the briefing stations by the AT training specialist and

Chap 9 Par 90 Page 45

52

6560.25A 7/27/92

assisted by the contractor trained NWS meteorologists at each site. ATCSCC personnel will be trained by NWS meteorologists.

c. Airway Facilities. AF personnel will attend the NWS training courses to gain overall knowledge of the MWP system. In addition, the contractor is required to provide an Operations and Maintenance Plan, as described in paragraph 90, and an Operation and Program Manual. Two of these courses will be conducted at each site.

d. Training Materials. Training materials to be developed and delivered by the contractor are:

(1) Job task analysis.

(2) Contract training plan.

(3) Course design guide.

(4) Instructor lesson plans for training courses.

(5) Tests for measurement of student achievement.

(6) Students guide and documentation.

(7) Class schedule.

(8) Audiovisual aids, master reproducible&, and review copies for training equipment and training courses.

(9) Validation reports.

(10) AT operations systems user's guide.

e. Training Travel. Since all personnel cannot be trained at the same time, it may be necessary for some personnel to travel between centers to receive the required training. Detailed training plans will be available soon after contract award.

92. SUPPORT TOOLS AND TEST EQUIPMENT. The contractor will maintain the MWP. Therefore, there are no requirements for the FAA to have support tools and test equipment. The contractor is required to meet the operational availability re~irements as stated in the MWP system specification.

93. SUPPLY SUPPORT. There are no FAA supply support requirements for the MWP. The contractor must provide all supply support. This includes consumables such as printer paper, printer ribbons, printer ink, magne~ic tapes, etc.

94. VENDOR DATA AND TECHNICAL MANUALS. The schedule for delivery of contractor supplied data and manuals is provided in appendix 1.

Chap 9 Page 46 Par 91

53

95. EQUIPMENT REMOVAL. The MWP will replace existing FAX, non-LABS teletype, and RRWDS displays/processors in the CWSU's and the CFWSU. The MWP project office, working with NAS Transition and Implementation

Service (ANS) and Systems Maintenance Service (ASM), will fund and provide disposition instructions for these replaced systems after the period of parallel MWP/existing systems operations.

96. FACILITIES. Due to the "interim" nature of the MWP, the physical locations of the system components within the facilities are left to the discretion of the regional and site AF and AT representatives subject to the following restrictions:

a. The work station(s) should be installed in the CWSU/CFWSU.

b. Two briefing stations and a color printer are to be installed in the TMU at the ARTCC's.

c. Up to seven other briefing stations are to be installed at the area supervisor stations. In the ATCSCC, up to 18 stations will be installed for the traffic management specialists.

d. The processors should be installed in the automation wing basement in or near the area designated for the end-state weather processors. In any case they must be within 640 feet (or 1,000 feet when utilizing a booster) of the work/briefing stations.

e. The selected locations for the processors should provide for inlet of cooling air from under the floor of the facility or from above the floor at the rear of the MWP processor rack. Specific flooring and cooling requirements will be determined and resolved during the site surveys, and documented in the SPRP and I/CO Plan.

f. Provision should be made to allow for the installation of one satellite dish antenna of up to 11.5 feet in diameter. The antenna will be installed on the grounds of the facility. The ATCSCC MWP systems will require the installation of only one satellite dish on the roof of the FAA headquarters building. The exact size of the antenna required at each site is given in appendix 1.

g. Regions will submit cost estimates to ANW-130 for site preparation work as identified in the FAA approved SPRP for each site.

97.-99. RESERVED.

Chap 9 Par 95 Page 47 (and 48)

55

CHAPTER 10. ADDITIONAL PROJECT IMPLEMENTATION ASPECTS

100.-109. RESERVED.

Chap 10 Par 100 Page 49 (and 50)

7/27/92 6560.25A Appendix 1

APPENDIX 1. MILESTONES AND SCHEDULES

1. PROJECT SCHEDULES AND MILESTONES.

a. Estimated Delivery Dates. There are no contractual requirements as to the dates of delivery of equipment. The contract only specifies the schedule for acceptance of the "service," defined as the completion of the SAT. The following delivery schedule is based upon the contract required SAT completion schedule and an estimated period of 3 weeks from delivery to completion of the SAT:

57

SITE ACCEPTANCE # ANTENNA SITE SITE DELIVERY TEST (SAT) BRIEFING SIZE # (Weeks after COMPLETION TERMINALS AT EACH contract (Weeks after (TMU/ SITE award) contract award) SUPERVISOR) (meters)

1 Atlanta (ZTL) 55 56 2/7 1.8 2 ATCSCC (1 of 2) 59 61 9 2.4 3 Fort Worth (ZFW) 61 62 2/6 2.4 4 Kansas City (ZKC) 61 62 2/6 2.4 5 Leesburg (ZDC) 62 63 2/7 2.4 6 Indianapolis (ZID) 62 63 2/5 1.8 7 Seattle (ZSE) 63 64 2/4 3.5 8 Minneapolis (ZMP) 64 67 2/7 3.5 9 Salt Lake City (ZLC) 64 67 2/4 2.4 10 Miami (ZMA) 67 68 2/5 3.5 11 Oakland ( ZOA) 67 68 2/5 2.4 12 Boston (ZBW) 68 69 2/5 2.4 13 Cleveland (ZOB) 68 69 2/7 3.5 14 Memphis ( ZME) 69 70 2/5 1.8 15 Albuquerque (ZAB) 69 70 2/6 2.4 16 Los Angeles (ZLA) 70 71 2/5 2.4 17 Denver (ZDV) 70 71 2/5 2.4 18 Chicago (ZAU) 71 72 2/7 1.8 19 New York (ZNY) 71 72 2/7 2.4 20 Jacksonville (ZJX) 73 74 2/5 1.8 21 Houston (ZHU) 73 74 2/7 2.4 22 ATCSCC (2 of 2) 74 75 9 N/A 23 Anchorage (ZAN) 75 76 2/2 3.5

58

6560.25A 7/27/92 Appendix 1

b. Contract Deliverables. The following is a list of key contract deliverables that are related to the implementation of the MWP.

DELIVERABLE

Draft Operations and Maintenance Plan

Draft Contractor Master Test Plan

Operations and Maintenance Plan

Draft FAT Plan

Draft SAT Plan

Contractor Master Test Plan

FAT Plan (Final)

SAT Plan (Final)

FAT Report

Training Material

SAT Reports

Site Preparation Requirements Plan

Installation and Checkout Plan

DELIVERY DATE

2 Weeks after Contract Award

4 Weeks after Contract Award

8 Weeks after Contract Award

8 Weeks after Contract Award

10 Weeks after Contract Award

15 Weeks after Contract Award

15 Weeks after Contract Award

21 Weeks after Contract Award

3 Weeks after FAT

3 Weeks after equipment delivery

3 Weeks after each SAT

114 Calendar Days before SAT

28 Calendar Days after each Site Survey

59

7/27/92 6560.25A Appendix 1

c. Generic Site Implementation Schedules. This list provides a generic schedule of site implementation milestones relative to the completion of the SAT.

MILESTONE

Site Survey Start

SPRP Draft

Review Comments Due

SPRP Final

System Delivery

Site Walk-through

Installation and Checkout

SAT Start

SAT Complete

NWS/AF Training Start

CAI

Integration Testing Start

Shakedown Testing Start

JAI

ORO

WORKING DAYS REFERENCED TO SAT COMPLETION

- 111

- 102

- 87

- 81

- 19

- 18

- 16

- 5

REFERENCE

+ 5

+ 16

+ 17

+ 28

+ 37

+ 47

60

6560.25A 7/27/92 Appendix 1

d. Contractor Site Implementation Schedules. This list provides the contractor's schedule of site implementation milestones.

ACTUAL ACTUAL ACTUAL DAY OF WEEK OF SAT SITE SITE SITE SURVEY INSTALL START COMPLETION

1 Atlanta (ZTL) 11/14/89 10/15/90 11/09/90 2 ATCSCC (1 of 2) 11/08/89 11/13/90 11/30/90 3 Fort Worth (ZFW) 2/14/90 11/26/90 12/07/90 4 Kansas City (ZKC) 12/14/89 11/26/90 12/14/90 5 Leesburg (ZDC) 2/06/90 12/14/90 8/29/91 6 Indianapolis (ZID) 2/27/90 12/03/90 12/14/90 7 Seattle (ZSE) 3/21/90 12/14/90 8/29/91 8 Minneapolis (ZMP) 4/11/90 9/09/91 9/19/91 9 Miami ( ZMA) 4/25/90 9/09/91 9/19/91 10 Boston (ZBW) 5/22/90 9/16/91 9/26/91 11 Cleveland (ZOB) 5/31/90 9/16/91 9/26/91 12 Memphis ( ZME) 5/30/90 9/23/91 10/03/91 13 New York (ZNY) 7/21/90 9/23/91 10/03/91 14 Chicago (ZAU) 6/29/90 9/30/91 10/10/91 15 Jacksonville (ZJX) 8/02/90 9/30/91 10/10/91 16 Houston (ZHU) 9/06/90 10/07/91 10/17/91 17 ATCSCC (2 of 2) N/A 10/07/91 10/17/91 18 Anchorage (ZAN) 8/30/90 10/14/91 10/24/91 19 Oakland (ZOA) 5/16/90 10/14/91 10/24/91 20 Los Angeles (ZLA) 6/27/90 10/21/91 10/31/91 21 Albuquerque (ZAB) 6/21/90 10/21/91 10/31/91 22 Denver (ZDV) 7/12/90 10/28/91 11/07/91 23 Salt Lake City (ZLC) 4/18/90 10/28/91 11/07/91

61

7/27/92 6560.25A Appendix 1

2. DEPLOYMENT READINESS REVIEW SCHEDULE.

ACTUAL ACTION DATE

SEI Conducts Initial Review NOV 21 1989

Initiate DRR Process DEC 07 1989

First Test Site Delivery OCT 15 1990

DRR Report JUN 18 1991

AND-1 Approval JUN 19 1991

Conduct EXCOM Meeting JUN 28 1991

Deployment Memorandum JUL 03 1991

63

7/27/92 6560.25A Appendix 2

APPENDIX 2. MWP PROJECT POINTS OF CONTACT

Phone Organization Number

FAA HEADQUARTERS

Jeanne Rush ANW-300 Program Manager 267-5857 Kevin Young ANW-130 Associate Program Mgr. 267-8547 David Roth ANW-130 MWP TO/Proj Mgr.-COTR 267-8662 Don Espinosa AHT-400 Training 267-8030 Ron LaMarche ATM-120 ATCSCC AT Operations 267-7957 Mike Munro ATR-134 Associate MWP Proj Mgr 267-9170 Steve Manley ASU-330 contracting Officer FTS: 267-7539 Mike Cieslak ASU-330 Contract Specialist (202)724-0374 Ed Cabott ANS-420 Associate Program Manager

for Logistics (APML) 267-8806

FAA TECHNICAL CENTER

Frances MacKuse ACN-250 NAS IT&E FTS: 482-5415 Donald Shawver ASM-400 NAS OT&E FTS: 482-6503

NWS HEADQUARTERS

Mike Tomlinson W/OM13xl NWS Project Manager 427-7726

CENTRAL REGION CACEl

Jeff Yarnell ACE-452 AFAPM FTS: 867-5676 Charles Gray ACE-510.8 ATAPM FTS: 867-3400 Eric Markussen ZKC AFTR FTS: 753-1625 Joe Taber ZKC ATTR FTS: 753-1460 Gary Foltz W/CR1x3 NWS RAM FTS: 867-3239 Gary H. Ernst NWS MIC ( ZKC) FTS: 753-1456

EASTERN REGION CAEAl

Charles Gruner AEA-452.1 AFAPM FTS: 667-1890 Al Garcia FTS: 667-1198 Helen Krywka AEA-510 ATAPM FTS: 667-1223 John Kochis AFS-824 ZNY AFTR FTS: 663-3577 John Paeper ZNY-510 ZNY ATTR FTS: 663-3491 Dennis Freeman AFS-834 ZDC AFTR FTS: 925-4670 (703) 771-3670 James M. Morris ZDC-510 ZDC ATTR FTS: 925-4420 John E. Jones W/ER1x2 NWS RAM 649-5459 Pat Albanese NWS MIC (ZNY) FTS: 663-3454 Norbert Novacin NWS MIC (ZDC) FTS: 925-4480 Ray Stralka NWS MIC (CFWSU) FTS: 267-9390 Michael R. Chinn AFSF0-840.3 ATCSCC AFSFO ManagerFTS: 267-8200 Stan Lowrey AF/Sector FTS: 267-8016

64

6560.25A 7/27/92 Appendix 2

Name Organization

Phone Title Number

AFAPM FTS: 384-7422 FTS: 384-7559 ATAPM FTS: 384-7559 ZID AFTR FTS: 332-0280 ZID ATTR FTS: 332-0536 ZAU AFTR FTS: 388-9201 ZAU ATTR FTS: 388-9397 ZAU ATTR (alt.) FTS: 388-9239 ZOB AFTR FTS: 292-8241 ZOB ATTR FTS: 292-8127 ZMP AFTR FTS: 784-3226 ZMP ATTR FTS: 784-3370 NWS RAM (ZID,ZAU,ZMP) 867-3239 NWS RAM (ZOB) 649-5459 NWS MIC (ZID) FTS: 332-0469 NWS MIC (ZAU) FTS: 388-9291 NWS MIC (ZOB) FTS: 292-8164 NWS MIC (ZMP) FTS: 784-3189

AFAPM FTS: 836-7271 ATAPM FTS: 836-7147 ZBW AFTR FTS: 834-6792 ZBW ATTR FTS: 834-6801 NWS RAM 649-5459 NWS MIC (ZBW) FTS: 834-6698

AFAPM FTS: 392-2408 ATAPM FTS: 392-2516 ZSE AFTR FTS: 390-5306 ZSE ATTR FTS: 390-5230 ZLC AFTR FTS: 586-3144 ZLC ATTR FTS: 586-3244 ZDV AFTR FTS: 323-4434 ZDV ATTR FTS: 323-4205 NWS RAM (ZSE, ZLC) 588-4000 NWS RAM (ZDV) 867-3239 NWS MIC (ZSE) FTS: 390-5401 NWS MIC (ZLC) FTS: 586-3278 NWS MIC (ZDV) FTS: 323-4251

GREAT LAKES REGION

Gary St.Johns Russ Hazelite Lee Riley

Fred Heaviland William Frazier Danny Kaebla David Michalak Tom Berry Allen Johnson Tom Hutchcraft Jack Huber Gary Foltz

John E. Jones Mike Rosemark Allan H. Fisher Ernest Marion Dale Branch

NEW ENGLAND REGION

Bruce Ng Wendy Schoneberger Don Nevers Richard Chomitz John E. Jones Gregory Dietz

NORTHWEST MOUNTAIN REGION CANMl

CAGLl

AGL-422.1 AGL-420 AGL-510

W/CR1x3 W/ER1x2

CANE)

ANE-422N ANE-515 AFS-815

ZBW-540A W/ER1x2

Don Keen Dale Realph Rachel Ayers Cliff Wallace Milton R. Scholz Arno Bosley Terry Malleck Bobby Mullikin Larry Burch Gary Foltz John Machowski John A. Conlin Frederick J. Foss

ANM-422E3 ANM-516

W/WR1x2 W/CR1x3

65

7/27/92 6560.25A Appendix 2

Phone Name Organization Title Number

SOUTHERN REGION (ASO)

Richard Williams AS0-422 AFAPM FTS: 246-7371 Deborah Dennis AS0-514 ATAPM FTS: 246-7488 Fred Terrible AS0-402 ZJX AFTR FTS: 965-1662 Gene Wygal ZJX ATTR FTS: 965-1578 Jim Harris AS0-402 ZMA AFTR FTS: 820-1370 Glen Rivera ZMA ATTR FTS: 820-1241 David Howell AS0-402 ZME AFTR FTS: 222-3181

x207 Dan Carrington ZME ATTR FTS: 222-3181

x216 Richard Farell AS0-402 ZTL AFTR FTS: 249-7971 John s. Davis ZTL ATTR FTS: 249-7960 Armando Garza W/SRlx2 NWS RAM 334-2652 Curtis Morton NWS MIC (ZJX) FTS: 965-1544 David McLaughlin NWS MIC (ZMA) FTS: 820-1274 John D. White NWS MIC (ZME) FTS: 222-3181

x250 Arthur Ayers NWS MIC (ZTL) FTS: 249-7693

SOUTHWEST REGION <ASW) Russ Lenz/SEI ASW-4222.2 AFAPM FTS: 734-5426 Doug Felix ASW-511F ATAPM FTS: 734-5519 Randy Simpson ZFW-TSO ZFW AFTR FTS: 334-7430 Phil Harris, Jr. ZFW-510 ZFW AMNI FTS: 334-1303 James Tabor ZHU-OSC ZHU TSS FTS: 527-5350 Max Tindell ZHU-510 ZHU AMNI FTS: 527-5503 Dave Roop ZAB-RDPS ZAB TSS FTS: 476-0451 Dan Kerr ZAB-510 ZAB ATTR FTS: 476-0510 Armando Garza W/SR1x2 NWS RAM FTS: 334-2652 Jack Paup NWS MIC (ZFW) FTS: 334-1538 Roger Smith NWS MIC (ZHU) FTS: 527-5676 Serge Rivard NWS MIC (ZAB) FTS: 476-0690

66

6560.25A 7/27/92 Appendix 2

Name Organization

WESTERN PACIFIC REGION (AWPl

Lee Richards AWP-422.41 John Maloney AWP-512.4 Robert Durben Ward Billings John Skudmore Lewis Hawkins Donald Chapman Elisabeth Morse W/WR1x2 Walter Rodgers Kenneth Parker

ALASKAN REGION lAALl

Leonard Grau AAL-421A Terry Alexander AAL-510 Karla Schommer ZAN AF MNI John R. Cline Mgr Tech Supt Joe Boswell Maint. Man. Office Bill Hampton ZAN-560 Dale Eubanks W/AR1x1 Paul McCloud Bruce Benson AAL-403Z Leon Chesler AAL-480 Dave Palmer ZAN AT AMNI Stewart Mee MMC-SEI

Phone Title Number

AFAPM FTS: 984-1494 ATAPM FTS: 984-0053 ZLA AFTR FTS: 968-8416 ZLA AFTR (alt.) FTS: 968-8456 ZLA ATTR FTS: 968-8251 ZOA AFTR FTS: 449-6382 ZOA ATTR FTS: 449-6308 NWS RAM 588-4000 NWS MIC (ZLA) FTS: 968-8258 NWS MIC (ZOA) FTS: 449-6457

AFAPM (907) 271-3840 ATAPM (907) 271-5881 AF NAS IMPL (907) 269-1239 ZAN MTS (907) 269-1191 (907) 269-1157 ZAN ATTR (907) 269-1108 NWS RAM (907) 271-5132 NWS MIC (ZAN) (907) 338-1010 NAS Coordinator (907) 269-1131 TM&O Mgr (907) 271-5563 AMNI (907) 269-1118 ZAN Center Lead (907) 269-1127

67

7/27/92 6560.25A Appendix 3

APPENDIX 3. ISSUES AND CONCERNS

1. COMMUNICATIONS. Two issues concerning communications support for the MWP are:

a. The capability and space requirements for the MAD.

b. The organizational responsibilities needed to ensure complete implementation.

2. PARALLEL OPERATIONS/TRANSITION.

a. Space for the MWP work station during parallel operations.

b. Radar data to MWP and RRWDS processor during parallel operations.

69

AAC AAL ACE ACN ACT AEA AF AFAPM AFSFO AFTR AGL ALG AHT AND ANE ANM ANS ANW AOA ARTCC ASCII ASE ASM ASO ASU ASW AT ATAPM ATC ATCSCC ATM ATR ATRAPM ATTR AWP

CAI CCB CFWSU co COTR CWP cwsu

DIFAX DRR

EMI EXCOM

FAA

Appendix 4

APPENDIX 4. ACRONYM LIST

Aeronautical Center Alaskan Region Central Region Engineering, Test, and Evaluation Service FAA Technical Center Eastern Region Airway Facilities Airway Facilities Associate Program Manager Airway Facilities Sector Field Office Airway Facilities Technical Representative Great Lakes Region Logistic Services Office of Training and Higher Education Associate Administrator for NAS Development

New England Region Northwest Mountain Region NAS Transition and Implementation Service Weather and Flight Service Systems Office of the Administrator Air Route Traffic Control Center American Standard Code for Information Interchange NAS Systems Engineering Service Systems Maintenance Service Southern Region Office of Acquisition Support Southwest Region Air Traffic Air Traffic Associate Program Manager Air Traffic Control Air Traffic Control System Command Center Air Traffic Management Air Traffic Plans and Requirements Division ATC Plans and Requirements Associate Program Manager Air Traffic Technical Representative Western-Pacific Region

Contractor Acceptance Inspection Configuration Control Board Central Flow Weather Service Unit Contracting Officer Contracting Officer's Technical Representative Central Weather Processor Center Weather Service Unit

Digital Facsimile Machine Deployment Readiness Review

Electromagnetic Interference Executive Committee

Federal Aviation Administration

71

6560.25A 7/27/92 Appendix 4

FAT FAX

GOES

I/CO I/0 IOC IT&E ITP

JAI

KVA KW

LABS

MAD MIC MWP

NAFAX NAILS NAS NATCOM NCP NWS

ORD OT&E

PDSR PIP

RAM RRWDS RWP

SAT SEI SPRP ST&E STD

TM TMU TO TSSC

UPS

Factory Acceptance Test Facsimile Machine

Geostationary Operational Environmental Satellite

Installation and Checkout Input/Output Initial Operational Capability Integration Test and Evaluation Integration Test Plan

Joint Acceptance Inspection

Kilo-volts amperes Kilowatts

Leased A & B Service

Multiple Access Device Meteorologist In Charge Meteorologist Weather Processor

National Facsimile Machine National Airspace Integrated Logistics Support National Airspace System National Communications Center NAS Change Proposal National Weather Service

Operational Readiness Date Operational Test and Evaluation

Program Director Status Review Project Implementation Plan

Regional Aviation Meteorologist Radar Remote Weather Display System Real-time Weather Processor

Site Acceptance Test Systems Engineering and Integration Site Preparation Requirements Plan Shakedown Test and Evaluation Standard

Traffic Management Traffic Management Unit Technical Officer Technical Services Support Contractor

Uninterrupted Power Supply

72

7/27/92 6560.25A Appendix 4

VAC Volts Alternating Current

WMSC Weather Message Switching Center WSOM Weather Service Operations Manual