Order 6300.12 Project Implementation Plan (PIP) Fixed Ground Antenna Radome (FGAR) Including Tower Retrofit Mod
Text re-read from the scan: 1 of 1 passage.
- Date
- Nov 22, 2026
- Recorded
- Nov 22, 2026
- Passages
- 1 of 1 changed
- Paragraphs
- 3 added or rewritten, 8 removed or rewritten
Read the current text Official source ↗
What changed in the text
Key: [removed: removed words] are struck through; [added: added words] are underlined. Each changed paragraph is labelled in the margin.
Federal Aviation Administration
Memorandum
Date: JUL 2 3 2013 To: IT Business Enterprise Service Division, AES-200
- Changed
From:
[removed: Mic][added: Michael][removed: ,][added: Hufman,] Manager, Surveillance Systems & Sensor Programs, AJM-231[added: 7123117 Prepared by: Tev Hatčhér, Directives Management Ófficer, AJM-0 Subject: Cancellation of Directives for AJM-2] - Removed
[removed: Prepared by: Tev HatcherfDirectives Management Officer, AJM-0] - Removed
[removed: Subject: Cancellation of Directives for AJM-2] In meeting the FAA long-term goal of keeping directives current, the Program Management Organization's Surveillance Systems & Sensor Program is requesting to cancel the following orders because they are fully implemented plans or no longer in the National Air Space.
- Removed
[removed: Directive] - Added
[added: Directive Number Title Project Implementation Plan (PIP) Fixed Ground Antenna Radome 6300.12 (FGAR) Including Tower Retrofit Mod]
- Removed
[removed: Number Title] - Removed
[removed: Project Implementation Plan (PIP) Fixed Ground Antenna Radome 6300.12 (FGAR) Including Tower Retrofit Mod] 6340.20 Solid State Receive/Digital Moving Target Indicator PIP
- Changed
6360.15A Mode S Project Implementation Plan[added: Project Implementation Plan (PIP) Solid State Radar Beacon Decoder 6360.17 (SSRBD)]
- Removed
[removed: Project Implementation Plan (PIP) Solid State Radar Beacon Decoder 6360.17 (SSRBD)]
Whole text before this change
Federal Aviation Administration
Memorandum
Date: JUL 2 3 2013 To: IT Business Enterprise Service Division, AES-200
From: Mic , Manager, Surveillance Systems & Sensor Programs, AJM-231
Prepared by: Tev HatcherfDirectives Management Officer, AJM-0
Subject: Cancellation of Directives for AJM-2
In meeting the FAA long-term goal of keeping directives current, the Program Management Organization's Surveillance Systems & Sensor Program is requesting to cancel the following orders because they are fully implemented plans or no longer in the National Air Space.
Directive
Number Title
Project Implementation Plan (PIP) Fixed Ground Antenna Radome 6300.12 (FGAR) Including Tower Retrofit Mod
6340.20 Solid State Receive/Digital Moving Target Indicator PIP
6360.15A Mode S Project Implementation Plan
Project Implementation Plan (PIP) Solid State Radar Beacon Decoder 6360.17 (SSRBD)
Whole text after this change
Federal Aviation Administration
Memorandum
Date: JUL 2 3 2013 To: IT Business Enterprise Service Division, AES-200
From: Michael Hufman, Manager, Surveillance Systems & Sensor Programs, AJM-231 7123117 Prepared by: Tev Hatčhér, Directives Management Ófficer, AJM-0 Subject: Cancellation of Directives for AJM-2
In meeting the FAA long-term goal of keeping directives current, the Program Management Organization's Surveillance Systems & Sensor Program is requesting to cancel the following orders because they are fully implemented plans or no longer in the National Air Space.
Directive Number Title Project Implementation Plan (PIP) Fixed Ground Antenna Radome 6300.12 (FGAR) Including Tower Retrofit Mod
6340.20 Solid State Receive/Digital Moving Target Indicator PIP
6360.15A Mode S Project Implementation Plan Project Implementation Plan (PIP) Solid State Radar Beacon Decoder 6360.17 (SSRBD)