ORDER SO 6000.14A

ORDER SO 6000.14A

F&E Construction and Electronics Handbook

FEDERAL

December 21, 1990

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

Distribution: FAF-2/3/7; ASO-450 CAT IV; AAF-1 (2 cys); Initiated By: AS0-450 A-X(AF)-4; ASO-60 (1 cy)

12/21/90 SO 6000.14A

FOREWARD

FEDERAL AVIATION ADMINISTRATION

This Directive contains specific guidelines, information, and examples of activities associated with the Southern Region's Facilities and Equipment (F&E) program. This handbook instructs FAA F&E engineers and technicians of the administrative and technical aspects of their activities within the Establishment Engineering Branch, ASO-450.

C. R. Pinkerton Manager, Airway Facilities Division

Page i (and ii)

TABLE OF CONTENTS

TABLE OF CONTENTS

CHAPTER 1. GENERAL INFORMATION

SECTION 1. INTRODUCTION, EMPLOYMENT, AND SAFETY

1. Purpose 2. Distribution 3. Cancellation 4. Introduction 5. Employment 6. Training Program 7. Safety/Injury On the Job 8. Telephone 9. Transportation by POV 9-1. Personal Mail

SECTION 2. ADMINISTRATIVE INFORMATION AND FORMS

SECTION 2. ADMINISTRATIVE INFORMATION AND FORMS

10. FAA Directives System 11. Work Order and Engineering Package Figure 1-1. FAA Form 6030-4 12. The Weekly Report of Expenditures Figure 1-2. PCB&T Figure 1-3. Reimbursables 13. Weekly Construction Report and Diary Figure 1-4. Weekly Construction Report

SO 6000.14A CHG 1

Page No.

SO 6000.14A CHG 1

1

1

1 1 1 1 2 2 3 4 4 5

6

6 10 11 12 13 14 16 17

Figure 1-5. Construction Diary Daily Entry Data Format

14. Periodical Estimate, FAA Form 3669 Figure 1-6. FAA Form 3669 15. Approval or Disapproval of Contractor's Materials or Shop Drawings, SO Form 4445-1 Figure 1-7. SO Form 4445-1 16. Excess Property Report, FAA Form 4800-1 Figure 1-8. FAA Form 4800-1 17. Time Reporting 18. Travel Reimbursement Figure 1-9. Computation Examples 19. F&E Coding and Purchases 20. Field Purchases 21. Paying for purchases Figure 1-10. SO Form 4406-2

CHAPTER 2. INSTALLATION OF FACILITIES

CHAPTER 2. INSTALLATION OF FACILITIES

SECTION 1. DESCRIPTION OF FACILITIES

22. Air Route Traffic Control Center (ARTCC) 23. Air Traffic Control Tower (ATCT)

20 21 22

23 24 25 26 27 27 34 36 37 37 39

44

44

44 44

Page iii

SO 6000.14A, Chg. 1

34. VOR and DME, VOR/DME 35. Radar

53 53

36. Air Traffic Control Beacon Interrogator (ATCBI)

36. Air Traffic Control Beacon Interrogator (ATCBI)

37. Digital Bright Radar Indicator Tower Equipment (DBRITE) 38. Radio Communications Link (RCL) 39. Backup Emergency Communications (BUEC) 40. Automated Radar Terminal System (ARTS) 41. Runway Visual Range (RVR) 42. Approach Lighting System with Sequenced Flashers, CAT II (ALSF-2) 43.

54

54 54 55 55 56

56

Medium Intensity Approach Lighting System with

Runway Alignment Indicator Lights (MALS/RAIL) 44. Runway End Identifier Lights (REIL) 45. Precision Approach Path Indicator (PAPI)

SECTION 2. INSTALLATION PROCEDURES

SECTION 2. INSTALLATION PROCEDURES

46. Project Work Assignments 47. Preliminary Project Activity 48. Electronic Cabinet Placement 49. Anchoring Electronic Cabinets 50. Electrical Wiring 51. Mounting Electronic Components 52. System Wiring 53. Grounding of Equipment 54. Antenna and Coaxial Cables 55. Tune-up 56. Flight Check 57. Facility Reference Data File (FRDF) 58. As-builts 59. Joint Acceptance Inspection (JAI) 60. Final Project Work 61. Notice to Airmen (NOTAM) 62. Soldering

SECTION 3. CONSTRUCTION PROCEDURES

SECTION 3. CONSTRUCTION PROCEDURES

63. General 64. Duties 65. Familiarization 66. Coordination 67. Locator 68. Construction Schedule 69. Construction Materials 70. Access and Security 71. Utilities 72. Layout and Surveys 73. Contract Drawings and Specifications

Page iv

56 56 57

56

57 57 57 58 58 59 60 61 62 63 64 64 64 64 64 65 65

68

69 69 70 70 70 70 71 72 72 73 73

12/21/90

SECTION 3. CONSTRUCTION PROCEDURES

63. General 64. Duties 65. Familiarization 66. Coordination 67. Locator 68. Construction Schedule 69. Construction Materials 70. Access and Security 71. Utilities 72. Layout and Surveys 73. Contract Drawings and Specifications 74. Construction Contract Administration 75. Construction Inspection 76. Reports and Records 77. Photographic Records 78. "As-built Drawings" 79. Acceptance Inspection, 6030.45 80. Design Improvements and Recommendations 81. Documentation of Claims 82. Construction at Operating Facilities 83. Construction on Airports 84. Installation of Underground Cables 85. Installation of Engine Generators (SO 6980.1) 86. Ground Resistance and Lightning Protection

APPENDIX 1. SYMBOLS, CHARTS, AND ILLUSTRATIONS Figure 1 - International Morse Code Figure 2 - Binary Numbers Figure 3 - Electronics Symbols Figure 4 - Electronics Formulas Figure 5 - Electrical/Mathematical Relationship Figure 6 - Electronics Color Coding Figure 7 - Transistor Outlines Figure 8 - Color Coding for Multiconductor Cable Figure 9 - Cable Color Codes

SO 6000.14A

Page No.

67

67 67 67 68 68 68 68 69 70 70 71 71 71 72 72 72 73 74 74 74 75 76 79 79

1 2 3 4 7 9 15 18 19

Figure 10 - Attenuator (Pad) Networks, Formulas, and

Tables Figure ll - Characteristics of Commonly-used Transmission Lines Figure 12 - R.F. Cable and Waveguide Data

25

29 30 38

Figure 13 - Coaxial Connector/Cable Cross-reference

Figure 14 - Coaxial Connector Data Figure 15 - Series N Adapters Figure 16 - BNC Connectors Figure 17 - BNC Adapters Figure 18 - TNC Connectors

40 45 46 48 49

Page v

SO 6000.14A

Figure 19 - TNC Adapters Figure 20 - Adapters Between Series Figure 21 - Crimp-on Connectors Figure 22 - Semi-rigid Coax and Connectors Figure 23 - Assembly Instructions Figure 24 - Duct, Lay-in Figure 25 - Conduit Fittings Figure 26 - Wire Terminal Connectors (Lugs)

12/21/90

Page No.

51 52 53 54 55 68 71 78

Figure 27 - Cable Ties, Tie Mounts, and Spiral Wrap

Figure 28 - Machine Screws, Head Styles Figure 29 - Sheet-metal Gauges Figure 30 - Wire (Stranding and Other Data) Figure 31 - Drill Sizes Figure 32 - Demarcations Figure 33 - Cable Illustrations

80 82 84 85 86 87 90

Page vi

12/21/90 SO 6000.14A

CHAPTER 1. GENERAL INFORMATION

CHAPTER 1. GENERAL INFORMATION

SECTION 1. INTRODUCTION, EMPLOYMENT, AND SAFETY

1. PURPOSE. This order provides technical information useful to electronic and construction field personnel. Installation of complete facilities are accomplished by the Establishment Engineering Branch. However, each "sub-branch" has duties which are unique to them. Therefore, as you use this handbook, remember to refer to your appropriate work area when the information is split "construction" and "installation" information.

SECTION 1. INTRODUCTION, EMPLOYMENT, AND SAFETY

a. Field employees, administrative duties, training opportunities, telephone policy, and safety practices are defined in this section of the order.

b. Section 2 covers a brief description of the following: FAA Directives System, work orders, engineering packages, weekly reports, construction reports, time reporting, travel, F&E coding, and purchases.

c. A description of FAA facilities and systems is briefly contained in Chapter 2, Section 1, of this order.

d. Electronic installation standards and procedures are outlined in Chapter 2, Section 2, of this order.

e. A description of construction standards and procedures is contained in Chapter 2, Section 3.

f. Electronic symbols, charts, technical installation reference, electronic formulas, and materials most commonly used are contained in Appendix I of this order.

2. DISTRIBUTION. This order is distributed to the regional Airway Facilities Division, section level; all Establishment Engineering Branch, ASO-450, Category IV employees; and to all Airway Facility sectors and sector field offices.

3. CANCELLATION. This order cancels Southern Region Orders SO 6000.14, dated February 24, 1977, and SO 6900.5, dated July 28, 1980.

4. INTRODUCTION. This handbook is issued to all field employees so that they may better understand the construction/installation work activity and the duties and responsibilities of Construction and Installation Units. This publication should be carried to all project assignments, thereby being available as a ready reference in performance of construction and installation work.

Chap 1 Par 1 Page 1

SO 6000.14A 12/21/90

5. EMPLOYMENT. Employment as a field engineer/technician is governed by the FAA policies and regulations contained in Agency orders and directives. Each employee is bound by these regulations as management is in providing employee benefits and career opportunities.

a. Conduct and Discipline. Each employee must conduct himself, both on and off duty, in such a manner that reflects credit on the Federal Government and the FAA. Rules of conduct are contained in Handbook 3750.4 and DOT Regulations, Part 99 - Employee Responsibilities and Conduct. Each year a copy of DOT Regulations, Part 99, is circulated to all employees for reading and signature.

b. Recognition and Awards. The FAA Award Program gives recognition to employees for superior achicvenents by offering honorary recognition through letters of commendation or appreciation and cash awards such as Quality Step Pay Increase or Sustained Performance Awards. An award may be given to an individual or to several employees as a Group Award (Reference Handbook 3450.7).

c. Suggestion Award. Suggestion awards are given to employees who recognize problems in the agency operation and propose solutions to that problem. Suggestions on how to improve the construction/installation effort, such as use of tools which make the job safer and more efficient, are encouraged by management. Awards for suggestions are usually cash, based on the cost vs. benefits. Suggestions should be submitted on FAA Form 2333.

d. Career Development. The Establishment Engineering Branch offers an employee the opportunity to develop technical skills on many types of FAA systems. His abilities may be developed on one or more of the following specialities: navigational aids, radar systems, communication systens, or data processing equipment. The combination of these technical skills, along with the training programs offered by FAA, give the employee an opportunity for career progression.

6. TRAINING PROGRAM. The objective of the FAA Training Program is to develop, improve, and increase the knowledge and skills of its employccs in order to increase economy and effectiveness of the agency's operation and to raise the quality of performance by its employees to the maximum possible level of proficiency. The program design encourages employee self-development. The types of training offered are:

a. Directed study. The Directed Study Program is a series of correspondence courses administered by the FAA Academy. Enrollment in this program can be voluntary or may be mandatory to fulfill prerequisite training requirements prior to academy resident training.

b. Resident Training. Resident training is the formal training conducted by the FAA Academy. Selection of courses and employees to

Chap 1 Page 2 Par 5

12/21/90 SO 6000.14A

attend is made by the Installation Unit Supervisor. Early notification (three weeks or more) of scheduled training is normally given so that an employee can plan his personal affairs. F&E Training is given a lower priority by the FAA. Maintenance personnel requiring equipment certification credentials to perform their job are given training priority over F&E personnel. On occasion a training slot will become available on short notice because maintenance personnel cannot fill the quota, and this quota is offered to F&E.

c. On-the-job Training. Most of the knowledge and skills necessary for installation work are developed while actually working on F&E projects and observing the techniques of other installers. As stated earlier, installation projects are diversified in several areas which aid employee development.

d. Out-of-agency Training. This is training offered by private industries, other government agencies, or the military. These courses are. primarily equipment or civil engineering and construction in nature. Very little academy training is offered for construction or civil engineering training.

7. SAFETY/INJURY ON THE JOB.

a. Each employee has a responsibility for safety of himself as well as others. In this regard, employees are expected to report all unsafe conditions to the work order carrier and/or to their supervisor. All employees are expected to observe all safety regulations. If an accident does occur, the employee should immediately seek first aid and report the accident to his supervisor as soon as practical. Employees should recognize that even when on TDY, injuries off the job and/or after duty hours should be reported.

b. Accident Reporting. Details for reporting of all accidents are contained in Orders 3900.24, Accident and Fire Reporting, and 4670.2, Motor Vehicle Management. General information only wili be provided here, so every one should become familiar with the above-mentioned orders. Some orders specify certain forms be prepared by the employee's supervisor. However, due to the remoteness of the supervisor in our organization, it is necessary that all the required forms be completed to whatever degree possible by the employee, then forwarded to his supervisor. The supervisor will then complete the forms and forward them to the appropriate officials. Accidents occurring in POv's used on official business should be reported the same as accidents occurring in Gov's.

c. If you are injured, you must fill out form CA-l and CA-2, Federal Employees Notice of Injury or Occupational Disease. Items 1 through 16 of this form must be completed by the injured employee or some one acting for him whenever an injury is sustained in the performance of duty. It will also be the responsibility of the employee or some one acting in his behalf to obtain the information required by iters 17, l8, and 19. The

Chap 1 Page 3 Par 6

SO 6000.14A 12/21/90

completed form is to be forwarded to the employee's supervisor within 48 hours following the injury. The supervisor will complete the "Receipt of Notice of Injury" portion of the form and return that portion to the employee. The back of the form will be completed by the employee's supervisor.

d. A Form CA-l6 is completed by the supervisor, work order carrier, or local sector field office manager when it has been determined that an injury has occurred in the performance of duty and the supervisor is authorizing the payment of medical bills by the Government. In this instance, Item 6, Block A, would be checked. However, if there is doubt that the injury was sustained in the performance of duty, then Item 6, Block B, would be completed.

e. When, after returning to work, you stop work as a result of the original injury, a Form CA-2a, "Notice of Recurrence of Disability" must be completed and forwarded to your supervisor.

8. TELEPHONE.

a. The FAA Southern Region Office operates the Regional Communications Control Center 24 hours a day. Telephone numbers of all supervisors are on file at the Communications Control Center. In case of emergency after hours, during weekends, and holidays, the center will provide the employee with telephone numbers and switch telephone calls to a supervisor. The Regional Communications Control Center telephone numbers are 246-7541 (FTS) and (404) 763-7541 (commercial).

b. When an F&E employee is in a travel status for two or more consecutive nights, other than academy training, that individual will be authorized one brief call to his/her residence each day during nonduty periods on FTS service if available. If FTS is not available, each employee will be reimbursed on his travel voucher for no more than two calls to his/her residence over commercial long distance network per week (or each seven (7) day period).

c. Brief. Brief telephone calls should be interpreted to be calls that do not exceed $3 on commercial lines or five minutes if on FTS lines.

d. F&E personnel are encouraged to use the Government-provided telephone service to report their arrival and departures to their respective office when changing job assignments, i.e., departing Mobile, AL, and arriving Jackson, TN.

e. Calls must be between places within the United States (the 50 states and the District of Columbia). See Order DOT 1500.6.

9. TRANSPORTATION BY POV. The majority of field employees use their own automobile on project assignments due to the restrictions on use of

Chap 1 Page 4 Par 7

10/4/91 SO 6000.14A CHG 1

10/4/91 SO 6000.14A CHG 1

Government vehicles after duty hours. An employee electing to use his POV must keep the vehicle in good mechanical condition and otherwise use the vehicle under the same conditions he would a Government car.

9-1. PERSONAL MAIL

a. Personal mail will not be received in the regional office for employees of this Division. The only exception to this will be mail for F&E Category IV (field) employees who are in a continuous travel status and do not have a permanent home address. The correct address to be used by these employees is: John J. Doe, FAA, ASO-450A or ASO-450B (as appropriate), P. 0. Box 20636, Atlanta, Georgia 30320.

9-1. PERSONAL MAIL

(1) The majority of mail being received in the regional office for F&E Category IV (field) employees has the correct address with the appropriate routing symbol; however, some are still being received without this information. This creates an additional workload on employees in the Mail Room and in the branch offices. All F&E Category IV (field) employees receiving personal mail in the regional office are responsible for reviewing all mail received to insure that the correct address, as outlined above, is being used. Action will be taken immediately to change incomplete and/or incorrect addresses with all companies, personnel, etc., to conform to the above.

(2) All first-, second-, and fourth-class mail, and thirdclass mail of obvious value, addressed to F&E Category IV (field) employees will be forwarded to addressee by ASO-450A or ASO-450B as appropriate. This mail so forwarded will be endorsed by the forwarding office, "Change of Address Due to Official Orders." Third-class mail that is not of obvious value cannot be reforwarded without additional postage. Therefore, this type mail, received in this office, will be held until it is personally picked up or appropriate arrangements are made to furnish postage for reforwarding.

Chap 1 Par 9 Page 5

12/21/90 SO 6000.14A (l16) 6500 Communications and Flight Assistance Facilities.

(17) 6600 Communication Equipment.

(18) 6700 Navigational Aids.

(19) 6900 Plants and Structures.

(20) 8200 Flight Inspections and Procedures. c. FAA Directives. Some specific directives which list procedures, standards, tolerances, and other information, some of which is directive in nature, are listed below. These directives (handbooks) contain information which installation personnel will find very useful. All personnel should become familiar with these handbooks. These directives are available for your reference at the airways facilities sectors and sector field offices throughout the region. It is common practice for the region to supplement FAA (Washington) directives. The supplements normally provide more details and reflect the Southern Region's operating guidelines. The supplements are just as directive as the basic orders and must be followed. Always check the current edition of the Southern Region Directives Checklist for the latest version of a supplement or order.

d. General.

(1) 1500.14, Travel (transmits DOT 1500.6)

(2) SO 6000.10, Preparation of Weekly Report of Expenditures, SO Form 6000-2.

(3) 6000.15, General Maintenance Handbook for Airway Facilities.

(4) 6000.20, Waiver of Criteria for Establishment and Maintenance of Airway Facilities.

(5) 6030.45, Facility Reference Data File.

(6) OAP 8200.1, United States Standard Flight Inspection Manual.

e. Communications.

(1) 6000.22, Maintenance of Two-Point Private Lines.

(2) 6550.2, Maintenance of Weather Broadcast and Information Service Equipment.

(3) 6560.13, Maintenance of Aviation Meteorological Systems and Miscellaneous Aids (LLWAS).

Chap 1 Par 10 Page 7

SO 6000.14A 12/21/90

(4) 6580.5, Maintenance of Remote Communication Facility (RCF) Equipments.

(5) 6600.2l, Maintenance of Communications Transceivers.

(6) 6640.2, Maintenance of Audio and Speech Equipment.

(7) 6670.4, Maintenance of Multichannel Recorder Equipment.

f. Radar.

(1) 6300.6, Five-Channel Video Mapper, FA-8970

(2) AF P 63l0.l, Radar Facilities and Equipment Modification Handbook - ASR.

(3) 6310.2, Maintenance of Airport Surveillance Radar (ASR) Facilities.

(4) 6310.3, ASR-8/ATCBI-5 Implementation.

(5) SO 63l0.5, Operating Policy for Airport Surveillance Radar (ASR) Systems.

(6) SM P 6330.1, Maintenance of Airport Surface Detection Equipment Facilities.

(7) AF P 6340.l, Radar Facilities and Equipment Modification Handbook Long Range Surveillance.

(8) 6340.8, Maintenance of Air Route Surveillance Radar (ARSR) Facilities.

(9) SO 6340.4, Cable Testing by Time Domain Reflectometry.

(10) 6360.l, Maintenance of Air Traffic Control Beacon Interrogator Equipment.

(ll) AF P 6360.l, Radar Facilities and Equipment Modification Handbook - Radar. (12) SO 6360.1, SECRA Power Reduction Procedures.

(13) 6360.2, Air Traffic Control Radar Beacon System Interrogator Usage and Power Reduction Procedures. (14) IM P 6360.2, Installation Instructions for ATC Radar Beacon, Type ATCBI.

(15) IM P 6360.3, Installation Instructions for Radar Beacon Equipment Used with FAA, ADC, and Navy Radars. Chap 1 Page 8 Par 10

12/21/90 SO 6000.14A

(16) T.I. 6410.18, DBrite Operations and Maintenance Instructions.

(17) T.I. 6410.19, DBrite Systems Circuit Diagrams.

(18) T.I. 6130.6, Flight Data Input/Output (FDIO) System.

(19) T.I. 6130.7, Flight Data Input/Output (FDIO) System.

g. Navaids.

(1) 6560.8, Maintenance of Runway Visual Range (RVR) Equipment.

(2) 6730.2, Maintenance of Distance Measuring Equipment (DME) Facilities.

(3) 6740.2, Maintenance of Nondirectional Beacons.

(4) 6740.4, Nondirectional Beacon (NDB) Installation Standards Handbook.

(5) AF P 6750.l, Navigational Aids Facilities and Equipment Modification - ILS.

(6) 6750.6B, Installation Instructions For Category I and Category II ILS Glide Slopes.

(7) 6750.16, Siting Criteria for Instrument Landing Systems.

(8) 6750.35, Installation Instructions for Category I Localizer, Marker Beacon, and Compass Locator Facilities.

(9) 6750.47, End-Fire Glide Slope Antenna Installation Drawings.

(10) 6750.49, Maintenance of Instrument Landing System (ILS) Facilities.

(1l) SO 6750.9, Vector Voltmeter Applications for ILS Technicians.

(12) TI 6820.2, Instruction Book VORTAC, VOR/DME, VOR, DVOR Equipment.

(13) 6820.7, Maintenance of Navigational Aids Facilities and Equipment VOR, VOR/DME, VORTAC.

(14) 6820.10, VOR, VOR/DME, and VORTAC Siting Criteria.

Chap 1 Par 10 Page 9

SO 6000.14A 12/21/90

h. Automation.

(1) 6l00.l, Maintenance of NAS Enroute Stage A - Air Traffic Control Systen.

(2) 6190.1, EEM Handbook - ARTS System Equipment.

(3) 6l90.6, Maintenance of Automated Radar Terminal and Tracking System.

11. WORK ORDER AND ENGINEERING PACKAGE.

a. Installation Unit work order, FAA Form 6030-4, (figure 1-1, following page) will be issued for all projects. In almost all cases, the work order will be part of an engineering package. The engineering package is a set of documents consisting of the work order, which is the authorization for work, the plans and specifications that provide the installation details necessary for the accomplishment of F&E and maintenance projects, and the supplementary work order instructions. The work order provides a brief description of work, the local coordination contacts, an estimated completion date, the authorized mandays/dollars, and the appropriation codes for the project. The plans and specifications include detaiied scope of the project, suggested installation procedures, parts lists, drawings, and other information pertinent to the completion of the project. The supplementary work order instruction provides guidance for the completion of documentation required during the course of the project. The engineering package should be adhered to as xuch as possible.

If a change is necessary which conflicts with the engineering package, prior approval from an installation unit supervisor must be obtained and the change documented on the appropriate drawing. Though the engineering package is issued to the work order carrier, the other members of the installation crew should read it to be familiar with the total project. Detailed guidance on the content of the engineering package is provided in Branch Operational Procedure No. 2. Work orders are usually prepared by the responsible project engineer, assigned by the installation unit supervisor, requested by the engineering unit supervisor, and authorized by the section supervisor.

b. Construction Unit Work Order, FAA Form 6030-4, makes the specific job assignment and provides local contacts, estimated completion date, authorized mandays/dollars, and the appropriation code. Generally attached to the work order are several sets of plans and specifications, a copy of the contract, and the coordination designation letter.

c. The amount of mandays authorized in the work order shall not be exceeded. The unit supervisor should be advised as soon as it becomes apparent the authorized amount is insufficient. The unit supervisor is required to increase the mandays by written amendment to the work order or request the field engineer/technician be reassigned to another job when the xandays authorized by the work order are depleted. Within one week

Page 10 Chap 1 Par 10

12/21/90 SO 6000.14A

FIGURE 1-1. FAA FORM 6030-4 O. 60861 WORK ORDER- COST DATA WORK ORDER NO. AS0-453-90-013

TO: FROM: SUTTLEWENT NO. 4 DATE John Q. Cat, IV Supervisor, Installation Unit 1/19/90 You resuthorizedto proceed to Huntsville, AL, on or about I/30/90 tor the purpose ot changing the insulators on the DvoR. Detailed instructions are provided in the attached plans and specifications.

LOCAL PROJECT COORDINAIION. You shall coordinate yout work schedule and other important aspects of this project with the following personnel prior to starting and, as necessary, during implementation of this project.

Manager, Airuay Facilities Sector, Memphis, TN Manager, Airway Facilities Sector Field Office, Huntsville, IN

The Sector Manager or Sector Field Office Manager (as appropriate) will be kept informed of project progress throughout the duration of the project.

JOINT ACCEPTANCE INSPECTION. The JAI is tentatively scheduled for 2/2/9Ó.

ESTIMATED OELIVERY SCHEDULE PREVIOUS AOQITIONAL PIRSTOR TOPAL OATE FIRST UNIT HOURS REQUIRED IN FIELD NO.UNITS THERE. ct AFTER FISCALPROGRAMMING SINAL CORTIP.US IST OTA. INOGTA. OTHOTA.

WITHORAWFROU ALLOCATE TO AMOUNT NOTE TO BUOGET 7/482.0/8093/810/442/60861/2112 (Trave1) 7/082.0/8093/440/60861/2630 (Pμrchases) S200 Funding 20 Mandays

REQUESTEO OV (SL) AUTHORIZEOOTISI)

REQUESTEO OV (SL) AUTHORIZEOOTISI)

Jane Doe John Doe

TITU Supervisot, Engineering Unit ASO-453.10 TITLE Supervisor. Elec. NAVAIDS Sectioh NEF. NO ASO-453

FAA FOrm 6030 -L I7-n rOReLT FAA rO 9

Page 11 Chap 1 Par 1l

SO 6000.14A 12/21/90

after completion of an assignment, the work order carrier should fill out the final charges (candays and funds) on the work order and so note on the weekly report of expenditures that it is the final report.

d. The amount of funds authorized are to be used for local purchases and are not to be exceeded without prior approval of an installation supervisor.

12. THE WEEKLY REPORT OF EXPENDITURES. SO ForM 6O0O-2 is to be prepared by the work order carrier (Woc) in accordance with the current Order So 6000.l0. The report is to be prepared and mailed each Friday and at the completion of the project. Although it is the Woc's responsibility for preparation, all personnel assigned to the project should become familiar with the contents of the weekly report.

a. On the following pages are examples of the proper format to use in the preparation of the weekly report. Examples vary as to how the Eront pages are completed. The back of the form should be coxpleted as instructed on the fors.

b. Example One is the format to be used when the project is covered by PCB&T/Activity 8 (personnel copensation, benefits, and travel) funding (see Eigure l-2, PCB&T, following paye). This example is for the vast majority of our jobs.

c. Exarple T:o is the format to be used on a reimbursable project where our costs are being paid by an airport authority. military, etc., and a strict accounting of funds spent is needed for proper payment to the FAA. A quick ethod to determine if a project is reimbursable is to check the job number (see Eigure l-3, Reimbursables, following page).

(l) If the fifth digit of the appropriation code is a 9, this denotes reimbursable funding.

(2). If the second digit of the five digit job number is a 7 or 8, this denotes reimbursable funding also.

Example: x/xxx.9/xxxx/xxxx8xxx/xxx

(3) Example One preparation:

(a) Routing block: Check for appropriate section supervisor.

(b) Week Ending: Saturday's date. Week runs from Sunday to Saturday.

(c) Report Number: Starting at 1, number sequentially until end of project where the last leport should have, in addition to the

nurber, the xord "Final." Chap 1

Page 12 Par 11

12/21/90 SO 6000.14A

FIGURE 1-2. PCB&T WEEKLY REPORT OF EXPENDITURES

FIGURE 1-2. PCB&T WEEKLY REPORT OF EXPENDITURES

TO Chief, Environmental Engineering Br. Chlef, Electronic Engineering Br. DEE CCINS J0● NO. P 01/25/90 01 7/482.0/8095/810/330/C0603 AS0-455-90-3 Construction of MALSR, Rwy 34, Ashevllle Reglonal Airport, Asheville, NC DARE POOJECT STARTED 01/18/90 EOCEVT COWPLETED TO ONTE 22z by cost ESTIWATED COMPLETION OATE 03/18/90 1. PROJECT EXPENDITURES PERSONNEL I TEMIZED DATA (+40%) PURCHASE CONTRnCP VEWICLE CHARGES TOTAL

Total this week 76.5 17.23 Total previous week 0 0 Total to date 76.5 17.23 TOTAL WORK ORDER AMOUNT $1,000.00 TOTAL WORK ORDER BALANCE $982.77 11. NARRATIVE REPORT See Constructlon Report fl for narrative report. Percent complete to date was figured by Including structural steel onsite In a cnst analysis, so it may be misleadingly high. Any other method is Just as questionable this early in the job.

The pictoral record attached Is prlmarlly of road conditions at start of Job to allow enforcement of Note 8, SO-D-100810-C01.

Joe P. Cat, IV, RE, ASO-455

Supplemental: Contract purchases were for fllm and develnping. etc. Can expect cost of $6nn (approxImate) by SF-44 through SFO For components to build landline control unlt and panel.

SO FORH 6000-2 (03-88) (Supersedes prcvlous edItlon)

Chap 1 Par 12 Page 13

SO 6000.14A 12/21/90

FIGURE 1-3. REIMBURSABLES

FIGURE 1-3. REIMBURSABLES

WEEKLY REPORT OF EXPENDITURES

TO Chlef, Environmental Engineering Br. Chief, Electronic Englneering Br.

9 Hay 81 5 88353 AS0-453-87-016

Relncate vOR nnd convert to DvOR, Augustn. (A COWPLCPION OATE 6 Apr11 87 402 26 June 87 1. PROJECT EXPENDITURES PERSONNEL

LIEWIZED DATA 1O1AL (140%)

LIEWIZED DATA 1O1AL (140%)

Total thls ueek 120 2,029.38 762.23 383.80 41.94 3,217.43

lotal prevlous ueek 340 5,761.38 2.159.00 362.11 276.48 8.558.97

Total to date 460 7,790.76 2.921.2 745.99 318.42 11.776.40

TOTAL WORR ORNER AMOINT 11,000.00 TOTAL WORR OANER BALANCE 5,223.60 11. Mandnye Alloted 30 HARRATIVE REPORT HandnyS Used S7.S

111. Fersommel Asslgned llours thils week llours tolal 1. Doe 200 T. Fugineer 40 111 R. Techulcian 40 112 S. Anybody 11

IV. Work Thls Week 1. Bolted doun Sn antenna rereatals. 2. Hounted antennn braces. 3. Lustalled equlpment drauers in racks. 4. Began Interconnect ulrlng nf vORTAc: equlpment. S. lounted carrler antenna.

V. Work Next Heek 1. Alisu pedestnls, carrier autenna, aul vor monttor antennn. 2. Hount S0 antennns and radlomes. 3. Trnnsport neu TACAN antenna to neu site. 4. Continue Interconnect ulring or voRTAC equipment.

VI. Remarks llal to purchinse ney hardware Sor autenna brnces hecause the boits that vere shipred vere tno long.

S0 F0R 6000-2 (03-88) (Supnrele prr,1s cllt1nn) Chap 1 Page 14 Par 12

12/21/90 SO 6000.14A

(d) Job Number: Fro the work order accounting block (withdraw Ero=). x/xxx.x/xxxx/xxx/xxx/93904/xxxx.

(e) Work order number: Fro: the work order job number block (example: ASO-453-90-10).

(f) Project name: Short description of job and location. Example: Install LLWAS, Bristol, TN.

(g) Date project started: Date of departure for the project.

(h) Estimate of work completed on project: Quick check of progress vs. andays used: Divide mandays used by total mandays allotted, and compare to your estizate of percentage of work completed.

(i) Estizated completed date: As titled.

(j) Man Hrs.: Weekly total of manhours for all personnel assigned to project. Regular, overtize, and comp. all count the same.

(k) Total Previous Week: If this is weekly report one, then there would be no entry; for later reports, it would have the data fro "Total to Date" of the previous week's report.

(1) Total to Date: Running total of manhours used.

(m) Total Work Order Amount: Total number of manhours allocated for project (Mandays X 8).

(n) Contract Purchase This Week: Amount of funds spent during the week for local purchase itens (nuts, bolts, wire, etc.).

(o) Contract Purchase Total Previous Week: Running total of local purchases.

(p) Contract Purchases Total to Date: As stated.

(q) Total Work Order Balance: Total amount of Eunds allotted for project.

(r) Personnel Assigned: A listing of all F&E personnel assigned to project, with their weekly hours charged to project, and total hours charged to project. If several people have been reassigned to other projects, instead of listing their names and total manhours each "eek, a statement such as "Personnel from previous reports" and their total manhours as a group will be sufficient.

(s) Mandays Allotted: Total Mandays allotted fron work order.

Chap 1 Page 15 Par 12

SO 6000.14A 12/21/90

(t) Mandays Used: Tize charged to project in mandays.

(u) Work Performed This Week: A brief suxnary of work performed during the week. Any problens concerning the project such as missing material, etc., should be noted.

(v) Work To Be Perforzed Next Week: Brief outline of work planned to be performed during the next week.

(w) Remarks: As stated.

(4) Exanple Two preparation:

(a) Preparation of a Weekly Report for a reimbursable project varies only in the reporting of expenditures. All charges to the project must be accounted for. In addition to keeping track of manhours and contract purchases, the salary for each individuai assigned to the project must be figured, along with per diem and vehicle charges.

(b) Salary: Salary charts showing overhead charges added to base rates are distributed each January fron the branch. These charts breakdown the costs to a hourly, daily, and weekly rate.

(c) Per Diem: A dollar amount of all per diem charges being charged to the project.

(d) Vehicle Charges: All POV mileage charges must be accounted for.

13. WEEKLY CONSTRUCTION REPORT AND DIARY (CONStrUCtiOn Unit OnlY).

a. Weekly Construction Report, SO Forn 6900-5 (Figure 1-4, following pages). This report should be prepared at the end of every work week. The report serves as communications between the resident engineer, the project engineer, and the contracting officer. The report should indicate progress nade, conditions encountered, and construction planned for the following week.

b. The weekly construction report i's used to monitor construction progress, provide inforiation for coordination with other organizational elements in the agency, and, when necessary, by the contracting officer to initiate corrective action to avoid or reduce delays in completion of construction. This report :ay also be used to resolve disputes and claims arising fron the construction contracts. Therefore, it is important that the report be a coxplete and accurate synopsis of the daily construction diary entries.

c. Three copies of the report should be made by the resident engineer. The original should be addressed in the top right hand corner to Aso-55. One copy should be arked to the attention of the project

Page 16 Chap 1 Par 12

12/21/90 SO 6000.14A

FIGURE 1-4. WEEKLY CONSTRUCTION REPORT

FIGURE 1-4. WEEKLY CONSTRUCTION REPORT

REPORT NO. 2. WEEK ENDING (FRIDAV) 01 01/17-25/90 WEEKLY CONSTRUCTION REPORT 3. CONTRACT NO. 4. WORK ORDER NO. DTFA06-89-30049 N/A DATE TO: Chief, Environmental Establishment Engineering Branch, ASO-440 01/26/90 5. JOS NAME 6. JOB LOCATION Construction of MALSR, Rwy 34 Asheville, North Carolina 7. CONTRACTOR B. WEATHER Home Menders, Inc. Clear and warm at first, then rain began. 9. CONTRACTOR'S SUPERINTENOENT 10. GROUND CONDITIONS A. B. Foreman Frozen crust in a.m., slightly muddy in p.m.

11. CONTRACT T:ME USED 13 12. WORK COMPLETED 22% by cost 13. CONTRACT TIME (DAVS) 60 14. CONTRACT TIME USED (DAYS) 08

15. ITEMS OF WORK BEHINO SCHEDULE 18. REASON FOR DELAY

15. ITEMS OF WORK BEHINO SCHEDULE 18. REASON FOR DELAY

Based on schedule provided by contractor, Contractor's work force is not as large as

the fabrication of the towers is slightly expected. Rain on 01/20 and 01/25

behind schedule but not by much. The hampered progress.

foundation work is progressing slowly though. 17. SHORTAGE OF GOVERNMENT FURNISHED MATERIALS BY ITEM IB. ACTION TAKEN REGARDING DELAYED MATERIALS NUMBER 1g, 3, 4, 5, 6, 10, 16, 18, 19, 20, 22, Informed project engineer, ASO-455. He 26, 31, 32, 33, 34, 35, 36, 39, 40, 42 is arranging acquisition.

(11 is available from SFO) 19. TIME LOST THIS WEEK 20. REASONS FOR TIME LOST (DAYS & HOURS) 1 day, 5 hours 01/20 - rain 1:00 to 6:00 p.m. 01/15 - Rain all day ITEM REVERSE) YES NO

21. ARE THE CONTRACTOR - FURNISHED MATERIALS ON ORDER OR PRESENTLY ON SITE: OR OTHERWISE OUICKLY AVAILABLE FOR USE WHEN SCHEDULED? X

22. ARE THE WORKING FORCE AND EOUIPMENT ADEOUATE TO ACCOMPLISH SCHEDULED COMPLETION? Questionable at this time.

23. ARE YOU POSTING AND MAINTAINING THE CONSTRUCTION PROGRESS SCHEDULE? X 24. ARE THERE ENOUGH OIFFERENT ITEMS WORK BEING ACCOMPLISHED SIMULTANEOUSLY TO ASSURE Difficult to SCHEDULED COMPLETION? evaluate this early in job.

25. IS CONTRACTOR'S SUPERVISION ADEOUATE? X

25. IS CONTRACTOR'S SUPERVISION ADEOUATE? X

26. 1S CONTRACTOR'S SUPERVISION CONTINUOUST X 27. IS THE CONTRACTOR INITIATING AND ACCOMPLISHING WORK ITEMS IN CONFORMANCE WITH THE CONSTRUCTION PROGRESS SCHEDULE? (EXPLAIN) X 28. ITEMS OF WORK SUSPENDED BY REASON OF WEATHER OR GROUND CONDITIONS. (EXPLAIN) Contractor intended to layout, excavate, form, and place concrete at all stations with GP-l towers and MG towers first. To date, he has only 2 complete compared to 4 or 5 expected. Rain and work force has contributed to the slower productivity. 29. VISITORS. OFFICIAL. AND CONTRACTOR'S PRINCIPAL Onsite: Bob Technician (AVL SFO), R. C. Watts (CP&L) plus PRECON Attendants. 30. SPECIAL INSTRUCTIONS GIVEN OR RECEIVED Jane Doe will pay invoice for structural steel onsite per inspection after PRECON. Special provisions to Aiport Road Easement revised to reflect installation of 4-inch dia. conduit at 48 inches depth. RE instructed to obtain price for extra 23 feet of duct required by same. Suzy Secretary. (Real Estate) to handle expired application for service by CP&L. SO FORM 6900-5 (3-82) (Superseaes previous edition) (See reverse)

Chap 1 Par 13 Page 17

SO 6000.14A 12/21/90

FIGURE 1-4. WEEKLY CONSTRUCTION REPORT (CONT'D)

FIGURE 1-4. WEEKLY CONSTRUCTION REPORT (CONT'D)

31. PRINCIPAL ITEMS OF WORK THIS WEEK (CHECK YES OR NO) 32. THIS WEEKS ROLL OF FILM UNDER CONSTRUCTION COMPLETED IS ENCLOSED to ASO-455 ITEM YES NO YES NO X X X X 33. HAVE YOU RECEIVED CURRENT PAYROLLS?

MECHANICAL Not applicable X X XNO (NOTE DISCREPANCIES) X Should receive next Monday, will Not applicable include in next report. REQUISITION FOR FORMS - FORM FAA-192.I ENCLOSED YES NO x 35. REOUISITION FOR OFFICE SUPPLIES - FORM FAA-542 ENCLOSED 3B. LIST BY NAMES SUB-CONTRACTORS ON PROJECT DURING THE WEEK Big and Small (Land Surveyors)

37. REMARKS Attached: GEM Transfer List with status of missing items. (2 pages) Digest of Meeting with NC DOT Representative--changes Special Provisions of Airport Road cable crossing agreement. (1 page)

Daily Notes: 01/17 PRECON held. Site inspected, structural steel acknowledged as onsite, new cable betweem P&C Station and Localizer 16 was suggested.

01/18 Coordinated and accomplished layout survey of base line and elevation off of runway centerline. RE inventoried GFM.

01/19 Surveyor continued layout, RE reported GFM status and transferred material on hand to contractor. Contractor began tying reinforcement steel for tower

foundations. 01/20 Contractor built temporary rain shelter, repaired trencher. Rain in afternoon lost 5 hours work time. 0l/21 Contractor continued work on rain shelter and reinforcement steel.

01/22 Contractor built forms for Sta. 4, 6, 8 foundations, continued rein. steel work, lost rain shelter to wind. RE coordinated efforts for landline units, GFM, reinf.

steel inspection, etc. 01/23 Contractor excavated, formed, and placed concrete at Sta. 8. RE arranged meeting with NC DOT, witnessed concrete placement.

01/24 Contractor excavated, formed, and placed concrete at Sta. 6. RE witnessed it. Slow mist/drizzle did not stop work but did slow productivity.

01/25 RE met with NC DOT. Contractor did piddly work, all-day rain stopped progress. IDATE NAME OF FAA REPRESENTAT SIGN) TITLE Joe P. CAT IV Qve P. Cat IV Resident Engineer, ASO-455 01/26/90

Chap 1 Page 18 Par 13

12/21/90 SO 6000.14A

engineer, and the third copy should be retained by the resident engineer until final payment is made to the construction contractor.

d. Construction Diary.

(l) Accurate and factual entries shall be made in the construction diary as events occur, but no later than the end of each working.day. The construction diary is an official record and may be used to resolve disputes and claims arising out of the construction project. It is most ixportant that the entries be complete so as to permit reconstruction of all events and conditions Eron this written record.

(2) Preprinted, bound construction diaries (figure 1-5, following page) are usually furnished to the resident engineer at the beginning of each construction job. In the event the preprinted diaries are not available, a bound notebook shall be used and the information shown in the following sample, "Construction Diary Daily Entry Data Format" used as an outline and checkoff sheet. Loose leaf notes or binders are not acceptable for construction diaries.

(3) At the completion of the construction job, the construction diary or diaries shall be given to the project engineer for review and transxittal to the contracting officer.

Chap 1 Par 13 Page 19

SO 6000.14A 12/21/90

FIGURE L-5. CONSTRUCTION DIARY DAILY ENTRY DATA FORMAT

FIGURE L-5. CONSTRUCTION DIARY DAILY ENTRY DATA FORMAT

a. Day/Date:

b. Work Started: Work Stopped: (Tine)

c. Contract tize used: days.

d. Weather:

(1) Tesperature: High °°F LOW °°F

(2) Rainfall measured for the 24 hours: inches.

(3) Tize of rainfall

e. Conditions affecting work.

E. Nu:ber and type of ajor equipment that the contractor has on project site. Indicate if equipment is in use or not.

g. Nuzber and classification of employees the contractor or subcontractors have on project site and hours worked at job site for payroll review purposes.

h. Brief description of work accomplished this date.

i. Description of any accidents and injuries.

j. Special instructions or decisions given to contractor, interpretations of drawings, and specifications.

k. List of visitors to project site and purpose of visit.

1. Governzent-Furnished materials (GFM) received.

List of xajor construction materials received by contractor.

n. Materials or shop drawings received, approved or disapproved.

0. Contract correspondence (issued and received).

p. Telephone calls (time, person, title, subject matter.

q. Instructions received fro: regional office.

List of subcontractors.

s. Supplezental record. Chap 1 Page 20 Par 13

S0 6000.14A 12/21/90

14. PERIODICAL ESTIMATE. EAA FORM 3669 (Eigure L-6, Eollowing page). Periodical estizates usually are prepared by the cesident engineer on the the 25th of each Ionth and at the coipletion of the construction job. The twenty-fifth (2sth) day of each zonth or on the last working day before

original of the periodic estizate should be sent to the responsible project engineer Eor review and a copy retained in the job Eiles at the site. The certification on the estizate shall be signed and dated by the resident engineer. The tesident engineer shall discuss the periodic estizate with the contractor's representative before submitting it. a. The contractor can be given credit Eor materials that are at the job site but not installed if invoices are furnished. This azount should be included in the "Work pertorzed or zaterials installed to date . axount, Coluin 8," in the appropriate line itet. Planned change orders or contract azendzents should not be included in the periodical estizate.

b. A copy of the Einal constructlon acceptance inspection report should be enclosed with the Elnal periodical estimate subaitted through the project engineer to the construction contracting section for payzent.

Chap 1 Page 21 Par14

SO 6000.14A

FIGURE 1-6. PERIODICAL ESTIMATE

FIGURE 1-6. PERIODICAL ESTIMATE

PERIODICAL ESTIMATE

PROJECT YAME: YZ Facility LOCATION: STATE: Anytown (Fliers Field) Gaorgia PROJECT NO.: ALLOTMENT: APPROPRIATION:

12/21/90

PAGE 1 OF 1 ESTIMATE No.: 2 PERIOD ENDING: November 25, 1975 OATE PREPARED: November 25, 1975

PROPOSAL YO.:

PERIODICAL ESTIMATE

027.0/08061/330/54321

DESCRIPTION OF WORK: Construct XYZ facilicy building, antenna tower, and access road.

CONTRACTOR (NAME AND AOORESS): ACE Construction Company 1234 N. Main Street Atlanta, GA 30301 WORK COMMENCED: DUB DATE: October 3, 1975

ESTIMATEDOR.CTUALCOIPCETIOR DATE: January 13, 1976 5 DAYS BEHINDI

CONTRACT NO.: DOT-FA76SO-9598 CONTRACT AMOUNT: $46,400 LUMP SUM: UNIT PRICE: FORCE ACC'T.

CONTRACT TIME PHOCEED NOTICE 90 DAYS 169975

CONTRACT TIME PHOCEED NOTICE 90 DAYS 169975

ESTIMATED PERCENTAGE OF PHYSICAL COMPLETION 62%

SCIIEDULE.

CONTRACTOR YOW

TORK PERFORVED OR Per WATEHALS INSTILLED

LATEST REVISED DETAILED ESTMATE

ITEM CODE No. UESC:RIPTION OF ITEM QUANTITY UNIT UNIT PRICE (1) (2) (3) (5)

1. SCHEDULE I

1. SCHEDULE I

Building, antenna 1. JOB towers, and access. road

2. SCHEDULE II

Concrete piling 800 LE 8.00

3. CHANGE ORDER #1

Additional culvert 1 JOB

CERTIFICATE

come TO DATE co AMOUNT QUANTITY! AMOUNT pleto (6) (7) 11

40,000 24,000 60

6,400 600 4,800 75

Subtotal 28,000

600 600 100

total 29,400

3. CHANGE ORDER #1

e the materiels inetalled te date. ss shewn hereen, were secempissned in secordance un pians.

(HEREBY CERTIFY he ne Otmd

spectficsttene, end contreet provistone. and thes the quareuies wore decermined (res olfisias fieid measurements and are correet.

(Signature) Engineep in Charge REMARKS:

IPPROVED DATE SIGNATURE OF CONTRACTING OPFICER

IPPROVED DATE SIGNATURE OF CONTRACTING OPFICER

FAA FOrm 366911-64 OSSOLETE PHEVIOUs COTION

0052-637.:003 1552

Chap 1 Par 14

SO 6000.14A 12/21/90

15. APPROVAL OR DISAPPROVAL OF CONTRACTOR'S MATERIALS OR SHOP DRAWINGS. SO EoRM ttt5-L (Eigure 1-7, folloving page). Once the resident engineer is on the job site. all submittals and shop drawings should be subritted

to hi Eor approval or disapproval. Whether the resident engineer reviews the subzittals depends on inforzation available for proper review, his experience, and other Eactors such as availability of engineering assistance. The project engineer and the resident engineer should establish procedure Eor handling the subcittals prior to the start of the

construction job.

a. Usually, all subzittals the resident engineer is capable of reviexing are approved or disapproved by hin. Some exceptions will be made on hiyh cost facilities and where more than one facility of the saze type is being built. Subzittals the resident engineer considers controversial. technically coplex, or highly specialized are forwarded to the project engineer and reviewed by appropriate specialists at the regional office. All subzittals reviexed in the regional office will be returned to the contractor through the resident engineer to assure proper coordination and project anagezent.

b. The resident engineer shall conpile and taintain a log on sub:ittals required, subzitted, approved, or disapproved. He shall routinely review this log to assure that all required subxittals are sub:itted and processed in a tirely manner. Tize allowed for subsittals and the review, as well as the nu=ber of coples and the forxat of subzittals, is usually noted in the construction contract. It is critical that subzittals be reviewed and ceturned to the contractor within the contract tize allowed.

c. Review and comzent on the subaittals shall refer to specific contract drawings and/or specifications which apply Care should be exercised in the review of shop drawings to assure compliance with the contract conditions, compatibility with related iteus, physical space, raintainability, etc.

Chap 1 Page 23 Apr 15

SO 6000.14A 12/21/90

FIGURE 1-7. SO FORM 4445-1

FIGURE 1-7. SO FORM 4445-1

DEPARTMENT UF TRANSPORTATION APPROVAL OR DISAPPROVAL OF CONTRACTOR'S FEDERAL AVIATION ADMINISTRATION MATERIALS OR SHOP DRAWINGS SOUTHERN REGION

1. TO: 2. DATE January 16, 1990 3. COV'T TRANS. NO. 4. CONTRACTOR'S TRANS.NO. ACE Construction Company RE-03 #5 1234 N. Main Street S. DATE CONTRACTOR'S TRANSMITTAL RECEIVED Atlanta, GA 30301 January 15, 1990 6. PROJECT NAME XYZ Facility, Anytown, Georgia 7. CONTRACT, NUMBER DOT-FA91S0-9598 8. TRANSMITTAL REFERENCE TO CONTRACT DRAWINGS GAd/OF SHOP DRAWINGS

SO-D-9876-SI through S3 9. TRANSMITTAL REFERENCE TO CONTRACT SPECIFICATIONS AND PARAGRAPH NUMBER GAd/OF CHANCE CADEA

FAA-SO-789, Divisions 3 and 5

10. FACTS: Gestlesess We ire retursisg berewth the following Subalttal Datas 1. c. 0. E. APPROVAL F.

ITEM NO. COPIES NO. NANE OF SUPPLIER TYPE OF MATERIAL OR EQUIPMENT SUB'TO AS NOTED AS MFGR. AS TO APP4OVEE NOT ONLY 1 1 Atlas Steel Building reinforcing steel x(1) Atlas Steel Tower toundation reintorcing steel Strong Bolt Co. Tower anchor bolts x(2)

G. SUBMITTED MATERIAL OR EQUIPMENT FOR USE AS reinforcing steel for building and tower foundation. Tower anchor bolts.

H. AEMARKS (l) Reinforcing steel for pile caps showu on Atlas Steel shop drawing No. l23sheer 2. derail C. is incorrect size. see drawing S0-D-9876-S2, detail 3/S2; $6 x 4'- cabars caquired (2) Anchor bolts not correct material and galvanized coating: see specification FAA-S0-789, 0aragraphs 5.2.3. and 5.4.0.

1. STIPULATIONS

1. STIPULATIONS

Date doee set obivate Costrsetor Respossibility for correct quuatity take-ot? or isstallatios cleasaaces. or sotatioss, und is secepted dees sot reqeire re-subeittal. Date marked "Approved ss to ufer. Oniy wiil be accoptable, provtded re-sabaittal is nede with revised seleetios, sccerdiag te specificatioss. Data sarked "Not Appraved" deee set seet jos requireseats, ud coatractor seat remssbait os proper basia. Approval of

Siaceroly. Carbaa Copies Traassitted To:

Conrracting Officer. ASO-j5A Project Engineer, ASO-44l SO Form 4445-l (1-73)(Supersedes SO-Form 460) Chap 1 Par 15 Page 24

12/21/90 SO 6000.14A

16. EXCESS PROPERTY REPORT, FAA FORM 4800-1 (Elgure 1-8, Eollowing page). The resident engineer and the electronic installation work order carrier

should be aware at all tizes of the availability, usage, and excess of governzent-furnished saterials. especially cable. He is responsible for preparing a list of excess property. The list of excess property is given to the property custodian for proper action.

Chap 1 Par 16 Page 25

Page

22

REPORT OF EXCESS PROPERTY

REPORT OF EXCESS PROPERTY

1. PHEPAMING OFFICE 2. SUPPLY SUPPOHT/AUUHESS CUUE AfSFO, Auytown, Georkla 4251 - Anytown, CA, XY2 Fac1l1ty 4. NEPUNI APPHOVLD DT (N N) SILNAIUNE Leave blank Leave blank ACQUISITION COST UNIT ITEM NO. FEDERAL STOCK NUMBER (F SN) NOMENCLATURE CONDITION COUE ISSUE OF QUANIITI UNII PHILE IOIAL VALUE

171 (0) (0) (10) (11) (12) (1)) (114)

1. 6145-00-765-6736 Cable, 25 pr /19A N-1 FT 200 .39 78.00 I reel contlnuous length

2. 6145-00-867-462B Cable 2/c 18, 2 each N-1 FT 100 .89 89.00 50' length, colled

Excfss to Job N. 54367. xYZ Facllity, Anytown, Ceorgt

Ch1f, AFSFO, Anytown, Ceorgta Cus Ceuter Code - 0857β locptlon Identifier - AHT

Par 16 Chap 1

SO 6000.14A

PACE 1 Of 3. DOCUMENT NO. To be filled in by ASO-52C L.WAIE UI ARYHUVAL l.eave blank

UAIEAVAHABLI APPROVED ACTION

UAIEAVAHABLI APPROVED ACTION

(15) (10) FIGURE 1-8.

FAA FORM 4800-1

12/21/90

12/21/90 SO 6000.14A

17. TIME REPORTING: Tize and attendance reports (T&A's) are subzitted to the Payroll Branch electronically via the Electronic Tize and Attendance Manageient System (ETAMS). All F&E field personnel shall submit the following information to their TiA clerks once each week (tize to be designated by each section and/or unit): Daily hours of work, job number to charge those hours to, and all leave taken. This should be the first order of business to insure proper subsission of the T&A's. When there are several members of an installation crew, this should be done as a group effort with only one phone call, not several individual calls throughout the day. An example of how it should be called in follows:

FAA FORM 4800-1

"On the first Monday of the first week, I worked fron 8:00 a.i. to 4:30 p.. regular hours; ard froa 4:30 p.m. to 6:00 p.., overtime. These hours are charged to job number 87444."

a. Leave. All leave taken, regardless of type (annual, sick, or cop.) or azount, must be documented by subxission of an Application for Leave Forn (SE-71).

b. Annual Leave. Your supervisor should be notified as soon as possible when you need to take tize off; however, eight hours or less can be approved by your work order carrier, who in turn will notify the supervisor at the earliest possible moment. Annual leave in excess of three days requires that an SF-71 be coxpleted and subxitted to your supervisor for his signature/approval. Application for annual leave (submittal of SF-7l) should be made as far in advance of the start of the leave period as practical to allox for tevision of wotk schedules.

c. Sick Leave. Sick leave up to four days can be taken without having an Sf-7l signed by a doctor. Sick leave in excess of four days, however, requires submission of a completed SF-7l, signed by a doctor, to your supervisor. At the supervisor's discretion, a completed SF-71, signed by a doctor, can be required for sick leave of less than four days. In all cases of sick leave, you should notify your supervisor or work order carrier as soon as practical. If the work order carrier is notified, he in turn is to notify the supervisor.

18. TRAVEL REIMBURSEMENT. Employees traveling on official business away froz their headquarters are paid a daily.allowance to compensate them for expenses incurred for meals, lodging, tips, laundry, and dry cleaning. A standard mileage rate is also paid to employees for their vehicles on official business. The Travel Manual, 1500.14, appendix l, establishes basic travel policies and procedures for all DOT employees. This xanual is not always readily available to field personnel; therefore, the following information from the manual may be used in preparation of the employee's travel voucher.

Chap 1 Par 17 Page 27

SO 6000.14A 12/21/90

a. Glossary of travel terms:

(l) Constructive cost. Cost of travel by comron carrier which would have been incurred had travel been perforzed as authorized by the travel authorizing official and the travel manual.

(2) Government Quarters. Sleeping accomrodations in a facility (other -than that provided by carriers) operated under United States Government control or supervision, or furnished under the terms of a Government contract, or on a complimentary basis. Government quarters include hozes owned by the Governzent and permanently occupied by Government employees, guest houses, clubs, hotels, bachelor quarters, visiting officers' quarters, or similar facilities.

(3) Local Travel. Official travel (not involving per dien) perforzed by bus, streetcar, taxi, or other conveyance within the local travel area as defined by the official delegated authority to define local. travel.

(4) Mileage Allowance. The rate allowed per mile in lieu of actual expenses for operation of a privately-owned conveyance or in connection with towing a mobile hoxe.

(5) Mobile Home. All types of house trailers and dwellings constructed for use as residences and designed to be xoved overland, either self-propelled or towed.

(6) Per Diem. A daily allowance for employees or other persons while traveling or while on temporary duty assignments on official business. It is intended to compensate for the necessary subsistence costs of travel not otherwise reimburseable. It is intended to compensate for all subsistence expense, including zeals, lodging, personal use of a room during daytime, baths, all fees and tips to waiters, porters, baggage men, bellboys, hotel xaids, dining room stewards, and others on vessels, hotel servants in foreign countries, telegrams, and telephone calls reserving hotel accoamodations, laundry, cleaning and pressing of clothing, fans and fires in rooms, and transportation between places of lodging or business and places where meals are taken. The term "lodging" does not include accommodations on airplanes, trains, or steamers; and these expenses are not subsistence expenses.

(7) Permanent Change of Station (PCs) or Official Change of Station Travel. Travel of an employee in connection with a transfer to a different duty station on other than a texporary basis.

(8) Privately-owned Conveyance. A privately-owned aircraft, autoxobile, or xotorcycle used by a traveler other than on a for-hire or rental basis. Actual ownership ay or may not exist.

Chap 1 Page 28 Par 18

12/21/90 SO6000.14A

(9) Privately-owned Conveyance (POC) or Vehicle (PoV). Any self-propelled wheeled motor conveyance that is primarily for use as a passenger-carrying vehicle, jeeps, motorcycles and notor scooters, pickup and panel trucks and such trucks when converted to "campers," small autobuses of the Volkswagen, Micro, and similar types (not to exceed ninepassenger capacity) and other passenger-carrying or multipurpose motor vehicles designed for overland ground transportation which, while not specifiçally mentioned herein, may be found to qualify as privately owned otor vehicles on the basis of the employee's written certification that the vehicle is for his personal use as a passenger-carrying vehicle.

(10) Temporary Duty Travel (TDY). Travel to one or more places aiway Eron an official station to perform temporary assignments and, upon completion thereof, return to the official station or assignment to another teporary assignment.

(ll) Training. A formally planned and systeratically conducted routine of instruction and practice as distinguished Erom a meeting which is for the purpose of exchanging information and discussing problems with others inside official station.

(12) Travel, Official. Authorized travel solely in connection with business of the DoT. Official travel may be performed within the vicinity of a permanent duty station; to or from place of actual residence; to. fron, or between permanent duty stations; and to, from, at, and between places of temporary assignment. The term "travel" relates not only to movement from place to place but also includes entitlement to the use of quarters facilities, allowances, and certain transportation and reirbursable expenses incident to travel, subject to conditions and limitations in the travel manual.

(13) Travel Advance. A travel advance is intended to provide the traveler with funds before and during the period his travel voucher is being processed. A Government-issued Diners Club Card is available, and all travelers are encouraged to use the card. If the traveler is a member of the PASS BARGAINING UNIT, that individual may obtain a $3,600 advance; however, if he elects to use the Diners Club Card, he will be limited to an advance of only $2,500. All travelers who are not members of the bargaining unit are limited to the S2,500 advance. A cash advance of up to $600 may be obtained from an imprest fund.

b. Travel Order. Authorization in writing for official travel by a designated travel authorizing official. Travel orders include authorizations, approvals, limitations, instructions, and special conditions relating to travel and assignment.

c. Travel Status. The elapsed period of tine from the beginning to the ending of official travel in compliance with the authority in a travel order. This includes incidental waiting time enroute for transportation connections and delays enroute beyond the control of the traveler.

Chap 1 Page 29 Par 18

SO 6000.14A 12/21/90

d. Coposition of Per Dien Allowance.

(l) Per Dies Allowance at Official Station. Per dien will not be allowed an employee either at his official duty station or at his placeof abode fron which he comzutes daily to his official or texporary duty station.

(2) Lodging With Friends or Relatives. When an employee obtains lodging fron friends or relatives (including menbers of the immediate family) with or without charge, no part of the per diem allowance will be allowed for lodging unless the host actually incurs additional costs in accommodating the traveler and these costs are substantiated. Costs may include rental of a bed or sleep sofa and increased utility expenses. These costs need to be supported by rental receipts and, if appropriate, copies of utility bills for periods before, during, and after a visit which docuzent the increased costs. The additional documented costs may be allowed as a lodging expense when determined to be reasonable by approving officials. Neither costs based on room rates for comparable conventional lodging in the area nor flat "token" azounts will be considered reasonable.

(3) For Situations Involving Double Occupancy. If the lodging receipt shows a charge for double occupancy, such fact shall be shown on the travel voucher with the name and employing agency or office of the person sharing the roon if such person is a Government employee on official travel. One-half of the double occupancy charge will be allovable for each exployee. If the person sharing the room is not another Governient erployee on official travel, identification of the petson shating the room is not required; and the exployee may be allowed the singie roo. rate.

(4) Lodging Not Available at Te:porary Duty Location. In certain circunstances, lodging accommodations may not be available at the teiporary duty location, and the exployee zust obtain lodging in an adjacent locality where the prescribed maxinum per diem rate is higher than the maximum per diem rate for the location of the texporary duty point. In such instances, the authorizing official zay make an adzinistrative determination on an individual case basis to authorize or approve the higher maxiaum per diem rate. If the higher maximum rate is not justified and authorized in advance, the exployee must furnish a statezent with the travel voucher satisfactorily explaining the circuistances which required the use of lodging in an area other than that of the temporary duty point designated in the travel authorization.

e. Lodging Receipt Requirerents. Receipts shall be required to support all lodging costs for which an allowance is claized under the lodgings-plus per diem systex except that a written statement instead of a receipt xay be accepted for the fee or service charge incurred for the use of Government quarters. Receipts uie not required when a specific or reduced tate has been authorized iil advance of the travel.

Page 30 Chap 1 Par 18

12/21/90 SO6000.14A

f. Beginning and Ending of Entitlezent. For computing per dien alloxances, otficial travel begins at the tire an exployee leaves home, office, or other authorized point of departure and ends shen the exployee concludes travel at hoze, office, or other authorized point. Travel fro the regional office to a tesporary duty station shall not corence after 2 p.. except in emergency situations. Emergency cases :ust have the verbal. approval of the section supervisor.

g. Rules For Corputing Nuiber oE Days of Per Dier.

(1) TDY Travel of 24 hours or Less. In computing the amount ol per dien for periods of TDy of 24 hours or less, the actual nuzber of hours of the trip are counted and computed as if they fell entirely within one calendar day. For exaple, TDY status frox 4 p.. of one day to 2 p.. of the following day is counted as falling within one calendar day for the purpose of computing per dien. For each six hours or fractional part of a six hour period, per diem is allowed at the rate of one-fourth of the daily rate. In the example, the 22-hour terporary duty would be considered as one full day. No per dier xill be allowed when the travel period is l0 hours or less during the same calendar day, except when the travel period is six hours or more and begins before 6 a.. or terminates after 8 p..

(2) Travel of More than 24 Hours. The calendar day (midnight to idnight) will be the unit for a full day's per dien in cozputing per dien Eor continuous travel of nore than 24 hours. Fractional days of travel status will be cozputed at the rate of one-fourth of the per die: allowance for each period of six hours or fractional period based on the standard six-hour quarters of the calendar day.

n. Interruptions of Per Die Entitlement, Leave and Nonworkdays.

(l) Ceneral. Except as otherwise provided, if the time that ieave of absence begins or terminates. is within the traveler's prescribed hours of duty, per diem in lieu of subsistence expenses xill terminate at the beginning of the next quarter day or begins with the quarter day during which the leave of absence terzinates. If leave of absence does not Legin or terminate within the traveler's prescribed hours of duty, the tlaveler will be entitled to per dien in lieu of subsistence expenses until zidnight of the last day preceding the leave of absence and from 12:0l a.. of the day Eollowing the leave of absence.

(2) Nonworkdays. A traveler will be considered to be in a subsistence status on nonworkdays unless he returns to his official station or place of abode fron xhich he commutes daily to his official station, or unless he is in a leave status at the end of the workday preceding the nonworkday(s) and at the beginning of the workday following the nonworkday(s) and the period i leave on either of those days exceeds one-hale of the prescribed workin; hours for that day: Provided that

Chap 1 Par 18 Page 31

SO 6000.14A 12/21/90

subsistence ay not be paid for zore than two nonworkdays where the leave of absence is izzediately preceded and followed by nonworkday(s).

(3) Leave Within One Day. Leave of absence for part of a workday not extending into the next workday, where for one-half of the prescribed working hours or less, will be disregarded for subsistence purposes; shere leave for part of a workday exceeds one-half of the prescribed working hours, one half of the subsistence for that day may be allowed.

i. Part-day Leave Extending Between Successive workdays. Leave of absence for the last part of one workday, which extends into leave of absence the beginning of the next workday and there are no intervening nonworkdays, will be disregarded for subsistence purposes if the leave of absence on both days coubined does not exceed one-half of the prescribed working hours for one day.

j. Annual Leave on Friday Followed by Sick Leave on Monday. If, while in a travel status, an enployee takes annual leave on Friday afternoon and sick leave on the following Monday, he is not entitled to per diem after 6 p.m. on Friday unless a certification is included on the voucher stating when the illness began and indicating that it continued through Monday. Paynent of per dien is then authorized from the quarter of the day in which the illness began.

k. Per Diem for Indirect-Route or Interrupted Travel. Where, for the traveler's personal convenience or through the taking of leave, there is interruption of travel or deviation from the direct route, the per diem allowance zay not exceed that which would have been incurred for interrupted travel by a usually traveled route.

1. Sick Leave While in Travel Status. Whenever a traveler takes leave of absence because of being incapacitated due to his illness or injury, not due to his own misconduct, the prescribed per diem in lieu of subsistence will be continued for periods not to exceed l4 days (including fractional days) in any one period of absence unless, under the circuzstances in a particular case, a longer period is approved. The exployee sust certify on the travel voucher that the illness or injury was not due to isconduct and that no hospitalization or reimbursement was received under federal statute (other than Government Health Insurance). Reimbursement of per diex while on sick leave must be approved by an official authorized to approve travel. If, while in travel status, the traveler receives hospitalization (or is reimbursed for hospital expenses) under any federal statute, other than the Federal Employees Health Benefits Act, he is not entitled to a travel allowance for the period involved.

Chap 1 Par 18 Page 32

12/21/90 SO 6000.14A

Use of Mobile Drelling During Te-porary Duty.

(l) Per die: allowances are authorized for ezployee's privately owned trailers, carpers, and mobile homes during periods of travel and tezporary duty. The allowances will consist of a flat rate of S55 per day. This per dies rate is specifically lizited to facilities and equipzent (F&E) field personnel and zust be indicated specifically on the applicable travel order covering the individual's travel.

(2) Authorization Eor Elat rate per diem xust be approved by the division manager in writing.

n. Cost comparison - Lodging - Plus Per Diem System (see figure 1-9 for computation samples).

(1) Voluntary return to peranent duty station or place of abode is shown in figure 1-9.

(2) Saiple request for cost coparison - enroute travel is found in figure 1-9.

(3) Constructive cost forrulas are shown in figure 1.9.

Chap 1 Page 33 Par 18

SO 6000.14A 12/21/90

FIGURE 1-9. COMPUTATION EXAMPLES

FIGURE 1-9. COMPUTATION EXAMPLES

(1) Voluntary return to permanent duty station or place of abode.

7/3 Thursday - Depart TDY @ 4:30 p..

7/4 Eriday - Holiday.

7/5 Saturday - RDO.

7/6 Sunday - RDO arrive TDY @ 4 p.m.

TDY location is the standard CoNUS rate, maximun lodging of S40 plus S26 for M&IE.

Per Diem up to Point of Deviation Cost to Go Cost to Stay

7/3 3/4 M&IE 1/4 M&IE + transportation 1/4 M&IE lodging

7/40 0 M&IE + lodging

7/5 0 M&IE + lodging

7/6 1/2 M&IE + 1/2 M&IE + transportation 1/2 M&IE lodging

Lodging costs for constructive cost purposes will be determined by the cost of the previous night's lodging.

Chap 1 Par 18 Page 34

SO 6000.14A

12/21/90

FIGURE L-9. COMPUTATION EXAMPLES (CONT D)

FIGURE L-9. COMPUTATION EXAMPLES (CONT D)

(2) Cost Co:parison - Enroute Travel.

Actual Enroute Travel

8/2 8:30 a.. Dep Orlando, EL, via POV 5:15 p.=. Arr Atlanta, GA

POV MILEAGE 431 MILES @ .24 3/4 DAY @ $34 = S24.75 LODGING $55.29

8/3 At TDY location, Atlanta, GA 1 day @ $34 plus lodging, $55.29. Attended meeting beginning at 2 p..

8/14 10:30 a.. Dep Atlanta, GA 7:45 p.. Arr residence, Orlando, FL

1 day @ $34 POV ileage 431 miles @ .21 TOTAL ACTUAL TRAVEL

(3) Constructive Cost

3/3 7 a.. Dep residence for office - Pov 22 miles @ .24 Dep office for airport - POV 5 miles @ .24 12.05 ρ.. Dep Orlando via EA 336 1:35 p.i. Arr Atlanta, GA Round trip airEare Taxi to regional office 3/4 day @ $34 Lodging - $55.29

S103.44 25.50 55.29

89.29

34.00 103.44 $410.96

5.28

1.20

156.00 5.00 25.50 55.29

Attending meeting beginning at 2 p.m.

8/14 10:30 p.. Dep. regional office by taxi 12:30 p.=. Dep Atlanta via EA 337 2:06 p.. Arr Orlando, FL 3 p.. Arr office via POV 5 xiles @ .24 Parking, Orlando Airport

5.00

1.20 24.00

Mileage, office to residence - PoV

22 miles .24 3/4 day @ S34 TOTAL CONSTRUCTIVE COST

LESSER AMOUNT CLAIMED

LESSER AMOUNT CLAIMED

Chap 1 Par 18

5.28 25.50 $309.25

$309.25

SO 6000.14A 12/21/90

NOTES.

The lesser anount should be placed in Colunn M.

Transportation to and frox carrier terzinals, office, tesidence, and parking zust be the usual zethods based on traveier's prior trips.

Parking at carrier terinals rust be reasonable hen claied in constructive cost. Rule of thuib: Parking and ileage can not exceed round trip taxi fare.

19. F&E CODING AND PURCHASES. All documents where funds are deducted Ero the general ledger account ust be coded with a sequence of nuzbers hich the agency's data processing equipzent will identify. Some of the documents which are coded are travel vouchers, LDR's, For? 44's, and iprest fund purchase receipts.

a. Coding Eor at. The cozplete code is made up of several nuber groups which identify the appropriation, cegion, cost class, job order nu-ber, and object of the charge. The code sequence is:

x/xxx.x/xxxx/xxx xxxxx/xxxx

Region

Appropriation

Region cost center

Cost class, asset code, function

Job order nuzber

Object class

b. Coding Exaaples.

Hardware purchased for use on a specific project.

Example:7/182.0/3093/440/71427/2630 c. Object class Codes. The last four nuxbers of the code ake up the object class. This identifies the nature of the goods or services purchased. Order SO 2700.1 lists description and illustrations of purchases and specifies the object class to use. A few codes shich field personnel use are given below: (1) 2li2 Subsistence (per diem) clain and reirbursement for use of Pov on travel voucher. Chap 1 Par 18 Page 36

12/21/90 SO 6000.14A

(2) 2630 Includes all hardware items, hand tools, power tools, paint, lumber, electrical goods, and electrical parts.

(3) 2541 Rental, miscellaneous equiprent, with operator.

(4) 2543 Repair of equipment.

(5) 2391 Rental, miscellaneous equiprent, without operator.

(6) 2231 Rental, truck, GSA or commercial.

(7) 22ll Transportation of governzent supplies/material by commercial carrier.

(8) 2639 Film, photographic supplies, developing.

(9) 2370 Waste disposal, continuous service contract.

20. FIELD PURCHASES. Supervisors and project engineers are to insure that all local purchases are limited to the needs of the project or are required to perform day-to-day installation/construction activities. Purchase of logistics center stocked items is to be limited to the immediate needs of the project, with further procurement through F&ε Engineering Support Services, ASO-454.

21. PAYING FOR PURCHASES. Four payment options may be used in purchasing supplies in the field.

a. Visa Card. GSA has contracted with Rocky Mountain Bank Card System to provide a Government Visa Card to be used for small purchases. Employees who have been authorized small purchase authority are eligible for a Visa Card. The card is issued in the employee's name. An approving official is identified for each card holder. A card holder may purchase up to Slo00 for a single purchase. The FAA is then billed once a month for all purchases made by its card holders. The card holder receives a statement monthly of his/her purchases. He/she then attaches all the sales slips for the month, annotating the accounting classification for each purchase, and forwards it to the approving official. The approving official then certifies that the purchases were for official business and forwards to Accounting for payment. Accounting then pays Visa once a month as opposed to each individual vendor. The result is that the vendor gets his money anytime he turns the purchases over to Visa, daily if he wants. The Visa Card specifically states that the purchase is tax exempt. Vendors who previously did not want to sell to the Government due to delays in payment will be more willing to do business with us.

b. Imprest Fund. Cash purchases using ixprest fund money is another method of paying for field purchases. Imprest funds are usually established at all facility sector and sub-sector offices. Except for purchases made by credit card, all szall purchases shall be supported by

Chap 1 Page 37 Par 19

SO 6000.14A 12/21/90

an authorized procurement request (PR). A Standard Form (SF) ll64 completed by hand and signed by the ArS or SFO manager may be used as a PR for purchases reimbursed from the imprest fund. The original coppleted SF-ll64 will be retained by the imprest fund cashier. For small purchases of less than fifteen dollars, a cash register receipt is required for proof of purchase. Larger purchases require an original invoice marked "paid" and the seller's full signature. All receipts xust be F&E coded before payment by the imprest fund cashier. The region issues small purchase authority on an individual basis and issues a Small Purchase Authority Card, FAA Form 4405-2, (figure 1-l0, following page) to be presented to imprest fund cashiers when payment is requested.

c. Travel Voucher Reimbursement. Local purchases can be claimed on the employee's monthly travel voucher. This method of reimbursement can be used when working at locations where ixprest funds are small or not available. SF-ll64 should be used for miscellaneous purchases that total more than fifty dollars. Less than fifty dollars will be paid on your regular voucher.

d. SF-44, Purchase Order. Another method for paying billsis with a Standard Forn 44 (SF-44). This method has many restrictions. One of the essential criteria that must be met before a SF-44 can be used to make a purchase is that only one delivery and one payment will be made. It is not appropriate to split what should be a single purchase into smaller purchases in order to avoid competition or other limitations or restrictions. Do not ake monthly payments to avoid exceeding your Sf-44 limit authority. When issuing a SF-44 to an individual, include his/her tax ID nuzber or social security number on the SF-44.

Rectricted Purchase Itens (excerpted fron So Order 4402.3, Chg. 3).

(1) Unauthorized Acquisition of Expendable Supplies. All offices shall refrain from purchasing expendable supplies for personal consunption.

(2) Restrictions. The following items nay not be purchased using imprest fund, SF-44's, or blank purchase authorities (BPA) except as noted.

(a) Advertising in newspapers or trade journals.

(b) Annual agreements for maintenance, repair and reconditioning of typewriters, office machines, or other office equipment. However, one time repair of typewriters, office machines and other office equipment may be accomplished, provided that the cost of repair does not exceed the mandatory use threshold in any applicable GSA Supply Schedule contract. Contact Aso-55 for contract information on repairs not specifically identified in Paragraph "Y."

Chap 1 Par 21 Page 38

12/21/90 SO 6000.14A

FIGURE 1-10. SO FORM 4406-2

FIGURE 1-10. SO FORM 4406-2

LAST NAME FIRST NAME MIODLE INITIAL OFFICE & ROUTING SYMBOL

Cat, IV, John Q. ASO-453

SMALL PURCHASE AUTHORITY SOUTHERN REGION U.3. Depertment of Transportation Federnd Aviation No. Administratlon John Q. Cat, IV

Whose signature eppeare below le delegaled emalt purchase suthartty es descrtbed on the reverse of the larm.

LAST NAME FIRST NAME MIODLE INITIAL OFFICE & ROUTING SYMBOL

mhn Cat, IV Signature of Designee 10-1-90 Expiretion Dete

Signature ol Contracting Otficer Delo 3O Form 4406-2 (12/80)

INSTRUCTIONS: Designee shall slgn and return ALL copies lo the Procurement Branch, ASO-55

7

TYPE:FullRestricted

Suppllee not to exceed $ 500 Non-pereonadl eorvicee not to exceed $ Rentel of aircraft not to exceed Emergency Repake to agency alrcraft not to exceed $ other

Chap 1 Par 21 Page 39

SO 6000.14A 12/21/90

(c) Automated data processing hardware, software, and services. Prior approval must be obtained from the Regional Information Resource Manager, ASO-60.

(d) Books, xagazines, periodicals and publications.

(e) Carpets, rugs, linoleum, tile and other floor coverings.

(f) Clothing (or personal apparel of any description). Requirements for special type clothing are to be coordinated with the Procurement Branch, AS0-55.

(g) Commercial or short-term rental of motor vehicles - See Handbook 4670.2A, with SO Supplements, for more information.

(h) Covers, seat, truck and/or passenger cars.

(i) FAA Logistics Center support items, except as authorized by paragraphs 7 and 8 of Order 4650.12B, Local Purchases. SHOw BASIS FOR PURCHASE ON INVOICE OR SF-44.

(j) GSA Stores Stock Catalog except that purchases not exceeding Slo0 may be made if the item customarily obtained from GSA stock is not readilY available. A STATEMENT THAT THE ITEM PURCHASED WAS NOT AVAILABLE FROM GSA STOCK MUST ACCOMPANY THE WHITE AND GREEN COPIES OF THE SF-44 OR IMPREST FUND SUBVOUCHER.

(k) Handling employee's household effects. Specific instructions covering packing, crating, drayage, wharfage, handling, and storage of employee's personal effects shali be obtained from the Materiel Management Branch, AS0-52.

(1) Office furniture and equipment. This restriction includes all items in Federal Supply Classification Code Group 71, regardless of cost.

(m) Payment of salaries or wages.

(n) Personal services. Descriptive elements that should be used in assessing whether or not a proposed contract is personal in nature are listed in the Federal Acquisition Regulations (FAR), Subpart 37.l04(d) and include (1) performance onsite; (2) principal tools and equipment furnished by the Government; (3) services are applied directly to the integral effort of agencies or an organization subpart in furtherance of assigned function or mission; (4) comparable services, meeting comparable needs, are performed in the same or similar agencies using civil service personnel; (5) the need for the type of service provided can reasonably be expected to last beyond one year; (6) the inherent nature of the service,

Chap 1 Page 40 Par 21

12/21/90 SO 6000.14A

or the manner in which it is provided reasonably requires directly or indirectly, Government direction or supervision of contractor employees.

(o) Printing and binding. Requirements for printing or binding must be coordinated in advance with the Regional Printing Specialist, Materiel Management Branch, ASO-52. WHEN THE PRINTING SPECIALIST AUTHORIZES OUT-OF-AGENCY PURCHASING OR PRINTING SERVICES, THE PURCHASÉ DOCUMENT SHALL MAKE REFERENCE TO SUCH AUTHORIZATION.

(p) Purchases from DOT employees.

(q) Rental of real property (including storage space, buildings, land, easements, right-of-ways, etc.). This does not preclude the use of the small purchase method to obtain temporary storage of equipment and materials received at a site prior to the time actual installation can begin. HOWEVER, THE CIRCUMSTANCES SHALL BE EXPLAINED ON THE ORIGINAL AND GREEN COPIES OF THE SF-44 OR INVOICE.

(r) Repairs or alterations to leased premises. Approval of the Real Estate and Utilities Branch, ASo-56, is required prior to the. repair or alteration of leased premises.

(s) Space (including short-term use of conference and meeting facilities) without prior approval of the Real Estate and Utilities Branch, ASo-56.

(t) Transportation charges when services are ordered on a Government bill of lading or a commercial bill of lading to be converted to a Government bill of lading.

(u) Transportation of personnel or a combination of personnel and freight. A transportation request must be used in these instances.

(v) Utility services such as electrical energy, water, gas, etc., except by special authorization from the Real Estate and Utilities Branch, ASO-56.

(w) Water for drinking and coolers except at locations where there is no water available at the site. Show this fact on invoices or SF-44's.

(x) Purchase of automotive repair parts and maintenance or repair of FAA vehicles in excess of $300 must have prior approval of the Motor Fleet Manager, ASo-52C5. In no event shall purchases for automotive repair parts exceed any limitation that may be listed in Paragraph "z."

(y) The purchase of telephones is restricted. Contact the Telecommunications Operations and Administration Section, ASO-48l, FTS

Chap 1 Par 21 Page 41

SO 6000.14A 12/21/90

246-7387 or Commercial 763-7387, to obtain approvals for purchase of telephones.

(z) Other supplies or services as follows: Appliances, all types Batteries, all types over $300 Brooms, brushes over $l00 Calculators, desk top and handheld, over S50 Cameras, projectors, and accessories Canvas articles Chains, tires over $300 Drinking cups Drugs, medicinal (except as authorized under current labor agreement) Duck, cotton Envelopes, all types Equipment (test and facility administrative and other equiprent) Explosives and caps over $l00 Food preparation and serving equipment Ladders over $100 Lamps, electric and photographic, over $300 Modifications to contracts Padlocks for personal use Recreation and athletic equipment Repair of typewriters over $300 Repair of copiers over $500 Shelving, steel Spark plugs (more than one set) Tires and tubes over $100 Water coolers and dispensers

£. Emergencies. When the need for supplies or services is of such an unusual or compelling urgency that the delay in award would result in serious injury, financial or other, to the Government, the foregoing restrictions may be waived. In such cases, the purchaser shall attach to the original and green copies of the SF-44 or to the invoice a signed statement, in memorandum form, giving full details of the events leading to the emergency situation. "Emergency purchase" or other nonexplanatory words or phrases will not be acceptable. The original copy of the SF-44 or invoice shall be routed through the Procurement Branch for review and approval prior to being submitted to the Accounting Division for payment. This paragraph shall not relieve the purchaser from seeking prior approval from the Procurement Branch if time permits.

g. Preparation of SF-44's. Suppliers will be paid with a minimum of delay if SF-44's are prepared in the following manner:

(1) All copies are legible.

Chap 1 Page 42 Par 21

12/21/90 SO 6000.14A

(2) Monetary limitations are not to exceed Sl,000 without bids.

(3) No purchase of restricted items is made.

(4) The complete name, address, and zip code of seller is shown.

(5) A description of each item, the unit price, and total amount appears for each line item. A seller's invoice may be attached but not in lieu of the above description.

(6) The seller signs the white copy of the SF-44 in the seller's signature block.

(7) Competitive quotations are shown on the back side of the pink and green copies for purchases that exceed $l,00o.

(8) The purchase order number appears on the top of the SF-44.

(9) Agency nane and billing address block is indicated as follows:

Federal Aviation Administration ASO-22 P.0. Box 20636 Atlanta, Georgia 30320

Chap 1 Par 21 Page 43

SO 6000.14A 12/21/90

CHAPTER 2. INSTALLATION OF FACILITIES

CHAPTER 2. INSTALLATION OF FACILITIES

SECTION 1. DESCRIPTION OF FACILITIES

22. AIR ROUTE TRAFEIC CONTROL CENTER (ARTCC) (See figUre 2-1). The ARTCC is the agency's largest facility, both in physical size and magnitude of operation. Its primary duty is to provide separation of aircraft passing through its geographic boundaries. The center building is very large and contains a number of special purpose rooms. The equipment rooms for radar, communication, telco, and data equipxent are in the basement. The control room is directly above the equipment rooms. The control room can contain as many as 60 positions (sectors), each having radar, communications, and data equipment. Most of the center's communications is conducted over telephone lines to remote RCAG sites, and radar data fron remote ARSR sites is received on telephone lines. The amount of wiring within a center building is larger than many city telephone exchanges.

SECTION 1. DESCRIPTION OF FACILITIES

23. AIR TRAFFIC CONTROL TOWER (ATCT) (See figUre 2-2). The ATCT directs movement of aircraft in the vicinity of the airport, including all ground traffic on the runways and taxiways. Aircraft under the control of the ARTCC are directed to the airport control zone where they are "handed off" to the ATCT for landing directions. Aircraft taking off are directed to the airport zone linits where the ARTCC assumes responsibility. The ATCT uses radio and radar for directing aircraft. The complexity of equipment and nurber of controller positions at ATCT's vary with the amount of airport traffic. Many small towers are established without radar facilities and with all radio equipment located in the tower structure.

24. AUTOMATED FLIGHT SERVICE STATIONS (AESS) (See figUre 2-3). The AFSS's, 6l nationwide, primary functions are: pilot briefings, weather observations, search and rescue procedures, emergency services mainly through direction finder equipment, processing flight plans, hazardous inflight weather advisory services (HIWAS), enroute flight advisory service (EFAS), and inflight services, primarily to VFR aircraft. The AfSS functions depend on maintaining a complete nationwide weather gathering system and monitoring the operation of navigational aids (VORTAC's and NDB's) used for enroute air traffic movement in order to provide these services.

25. REMOTE COMMUNICATIONS AIR/GROUND (RCAG). RCAG'S are remOtelY operated air/ground radio facilities providing coverage for a specific sector of air space. RCAG facilities have a varying number of channels, with each channel consisting of a UHF frequency, a VHF frequency, or both. The UHF and VHF transmitters may be configured through the digital radio control equipment (RcE) as paired (keyed simultaneously) or split (keyed individually). The RCE provides the interface to the specially engineered 4-Wire telephone circuit that connects each RCAG channel to the ARTCC. At selected RCAG facilities, an AC generator provides emergency power for the continued operation of environmental/lighting systens while the RCE

Page 44 Chap 2 Par 22

Par 23 Cha? 2

RADAR HNO BEACON

RADAR HNO BEACON

CONNON 01G1TIZER

AFSS IERMINALS HNO MILITARY UTHER CENIERS REMOTE STRIP PRINSING UN LINE WX NNO NOIANS

FRON VX

PRIMARY RADAR

CDENTETY HND ALIITUDE UATA

000 FACILITIES

DAIA VOICE RECEIVER SWITCHING GROUP SYSIEN

7

CENTRAL COMPUTER WEATHER COMPUTER COMPLEX SUB- OISPLAY

YORTAC OR YOR/OME

YORTAC OR YOR/OME

COMPUTER UPOATE EQUIPMENT

12/21/90

ACA6 SITE

FIGURE 2-1.

MAINTENANCE MON TOR

AIR ROUTE TRAFFIC CONTROL CENTER

OIGITEZEA

RAOAA

Paze

SYSIEN CHANNEL

VEHTHER NAICH R POSETION POSITIONS

SUPERYISORY POSETIONS

A POSITIONS

0 POSCTIONS

SO 6000.14A

AIR ROUTE TRAFFIC CONTROL CENTER (ARTCC)

AIR ROUTE TRAFFIC CONTROL CENTER (ARTCC)

Paze

5

RIR ASOE

HRICC RIR

10 AP HU

PAR AIRPORI CONTROL TRACON TONER

AFSS

ASR NINPORT SUAVELLHNCE AADAR RVR ROR BCN AIR IRAFFIC RADAR DEACON ARICC PAR PRECISION APPROACH RADAA AFSS ASDE AIAPORT SUNFACE DEIECTION EQULPNENT TVOR

Par 25 Chap 2 RIR ILS RENOIE TRANSAITTER-PECEIVER INSIAUMENI LANDING SISIEN TRACON RCO

LOC ILS

LOC ILS

TVOR

-RUMMAT VESUAL. RANGE -NIR ROUTE IAAFFIC COMIROL CENIER -AUTOMAIED FLIONT SERVICE SIAIION TERNINAL VHF QMOL-RANGE TERNINAL. ROAA APPRBACH COMIROL HENOIE CONMUNICATIONS OUILET

SO

6S 6000.14A

ASA FIGURE ?-2.

RDA BCH

1 APPROACH LIGHIS 11 AIR TPAFFIC CONTROL TOWER

12/21/90

1 APPROACH LIGHIS 11 AIR TPAFFIC CONTROL TOWER

SO 6000.14A

AUTOMATED FLIGHT SERVICE STATIONS

FIGURE 2-3.

5.SS

100

11-0/000/ 03001

W3ISIS

Chap 2 Par 25

SOSS

EREH

SURUS

(WM)

CEIE NIIUIS

SO 6000.14A 12/21/90

systes provides zaintenance and environental conitoring and provides DC back-up poxer to the radio transmitters and receivers. These systezs. coupled with a zain and standby radio transmitter and receiver for each frequency, ensure controller to aircraft counication.

CEIE NIIUIS

26. REMOTE TRANSMITTER/RECEIVER (RTR). Remote transmitter/receiver sites serve the air/ground cozmunications needs of the ATCT's. In many cases, the receivers are located in the tower equipment roon with transzitters only at remote sites. Keying and audio signals are transmitted over buried cables fro the ATCT to the rexote site. In most cases, coplete one-for-one backup equipment is provided, with changeover to standby equipment accoxplished by a control panel in the tower cab. An RTR site may contain as rany as l2 air/ground channels. An RTR site can be located soze distance frox the controlling facility with keying and audio signals transzitted over telephone lines.

27. REMOTE CONTROL OUTLET (RCO). An RCO is an RTR lOCated SOme distance from the controlling Eacility. The control of the equipxent is siailar tó an RCAG with keying and audio siynals being transmitted over telephone lines. RCo's are installed in areas lacking reliable communications due to terrain or obstructions. A RCo provides communication coverage controlled by an AFSS.

28. LIMITED REMOTE CONTROL OUTLET (LRCO). LRCO equipment consists of One or t:o receivers installed at a voR. They share the saze telco line with the VOR onitor.tones to the controlling AFSs. Two-way communication to an aircraft is provided when the AFsS operator transmits on the VOR transmitter.

29. INSTRUMENT LANDING SYSTEM (ILS). The ILS helps pilots to safely land an aircraft at an airport under conditions of low ceilings and linited visibility. The use of the system reduces interruptions of service at airports resulting Erox bad weather by allowing operations to continue at loxer :eather xinizuns. The ILS also increases the traffic capacity of the airport under all weather conditions. The ILS consists of a localizer, glide slope, and fron one to three marker beacons plus necessary monitor and control equipment. Other radio facilities installed for use in conjunction with an ILs may include coxpass locators and distance measuring equipnent (DME).

a. Localizer. The localizer provides a course directed along the center line of the runway toward the direction of the approaching aircraft. The localizer provides right and left guidance of the aircraft by horizontal deflection of a needle in the cross pointer instruzent of the aircraft. The localizer channel frequencies (l08 MHz to ll2 MHz) are in the VHE Erequency range.

b. Glide Slope. The glide ilope transaits a signal pattern that provides a glide path along the approach course (defined by the localizer). This facility provides above and below path guidance to the

Page 48 Chap 2 Par 25

12/21/90 SO 6000.14A

pilot by vertical deflection of another needle in the cross pointer instruzent of the aircraft. The glide slope channel frequencies (329 MHz to 335 MHz) are in the UHE frequency band.

c. Marker Beacons. The 75 MHz ILS xarker beacons are located along the approach course at distances from the runway identified on the pilot's approach procedure charts. Indication is provided to the pilot via appropriate tone and lights when the aircraft passes over the marker beacon. The marker indication is received only when the aircraft is over the arker.

d. Compass Locator. The compass locator (non-directional beacon NDB), is usually collocated with the 75 MHz outer marker beacon. The pilot "homes-in-on" the nondirectional NDB signals in order to find the localizer course. The compass locator operates in the 200 to 415 KHz frequency band.

30. MICROWAVE LANDING SYSTEM (MLS). The MLS provides precision navigation guidance for exact alignnent and descent of aircraft.on approach to a runway. It provides azimuth, elevation, and distance. MLS has inproved signal accuracy over ILS. During flight testing, MLS has been proven to consistently satisfy the high accuracy standards set for Category III operations. The MLS has the capability to fulfill a variety of needs in the departure, landing, issed approach, and transition phases of flight. Other features of the.MLS are the ability to provide curved and segmented approaches, selective glide path angles, accurate 3-D positioning of the aircraft in space, and the establishment of boundaries to insure clearance from obstructions in the terminal area. MLS will eventually replace ILS as the standard landing system in the United States for civil, military, and international aviation.

31. VHE OMNI-DIRECTION RANGE (VOR). The conventional VOR sYstem and the doppler voR system provide properly equipped aircraft with azimuth information for enroute navigation. Both types of voR's provide aircraft with compatible azimuth information but in different ways. Conventional vOR stations transmit two rf signals. The first, a constant phase 30 Hz reference signal, is transmitted as frequency modulation (EM) of a 9960- Hz subcarrier, which in turn amplitude rodulates the conventional vOR transiitter. The second, a 30 Hz'variable phase signal, is produced in space by amplitude nodulation (AM) of the radiated rf carrier. In the aircraft receiver, the EM signal is detected and output as a 30-Hz reference signal, which has a constant phase at all azimuths around the VOR station. The AM signal is also detected and output as a 30 Hz variable signal with a phase angle that changes one degree for each degree change in azimuth around the conventional voR station. Conventional voR stations are designed so that at 0 degree magnetic or north bearing from the VOR the detected 30-Hz reference and the 30-Hz variable signals are in phase. As the receiver moves clockwise around the conventional vOR station, the detected 30-Hz variable phase signal lags the detected 30-Hz reference signal one degree for every degree of clockwise rovement.